Date of

Concrete
Sample Test Reports Submitted to CSC Document Number Refer of Page Reference in Test Report
S.L Concrete Supplier Location Grade Quantity No of Cubes RFI No Durability Testing Done
taken during / WBG by MDG Test Reports Document
(M3)
the Pour

Aerobic Digester tank-10


1 Smeet Ready Mix (DTL) C40/20 OPC+PFA 3-Sep-19 435 24 RFI-0296 REV-01 Yes Yes To be Submitted To be Submitted
Zone-1 Raft Slab

Aerobic Digester tank-10


2 Aamal Ready mix (DTL) C40/20 OPC+PFA 8-Sep-19 432 24 RFI-0460 Yes Yes To be Submitted To be Submitted
Zone-3 Raft Slab

Aerobic Digester Tank - 10,


3 Aamal Ready mix (DTL) Zone-2 Raft Slab Including Slope C40/20 OPC+PFA 12-Sep-19 416 24 RFI-0492 Yes Yes To be Submitted To be Submitted
Area

Aerobic Digester Tank-8


4 Aamal Ready mix (DTL) Zone-6 Including Slope Area C40/20 OPC+PFA 15-Sep-19 548 24 RFI-0524 Yes Yes To be Submitted To be Submitted
Raft Slab

Aerobic Digester Tank-8 & 9,


5 Aamal Ready mix (DTL) C40/20 OPC+PFA 18-Sep-19 568 24 RFI-0545 Yes Yes To be Submitted To be Submitted
Zone-5 Raft Slab

Aerobic Digester Tank-9 , Zone-4


6 Aamal Ready mix (DTL) C40/20 OPC+PFA 21-Sep-19 544 24 RFI-0571 Yes Yes To be Submitted To be Submitted
Raft Slab concrete

Aerobic Digester Tank-8 , Zone-9


7 Smeet Ready Mix (DTL) C40/20 OPC+PFA 3-Oct-19 553 24 RFI-0604 Rev-01 Yes Yes CP837-REP-CIV-0106 Rev 0 Pg 106 to 119
Raft Slab concrete

Aerobic Digester Tank-9 , Zone-7 Pg 124-130, 138,139,142,146-


8 Aamal Ready mix (DTL) C40/20 OPC+PFA 5-Oct-19 544 24 RFI-0649 Yes Yes CP837-REP-CIV-0106 Rev 0
Raft Slab concrete 151

Aerobic Digester Tank-8 & 9, Zone-


9 Aamal Ready mix (DTL) 8 C40/20 OPC+PFA 9-Oct-19 592 24 RFI-0659 Yes Yes CP837-REP-CIV-0106 Rev 0 Pg 152 - 163
Raft Slab concrete

Aerobic Digester Tank-8,Zon-


16 Aamal Ready mix (DTL) C40/20 OPC+PFA30% 28-Nov-19 100 24 RFI-1060 Yes Yes CP837-REP-CIV-0110 Rev 0 Pg 139-145
6{Pour-5} Retaining Wall Concrete

SSF Thickened Sludge Sump Wall


42 Aamal Ready mix (DTL) C40/20 OPC+PFA30% 17-Feb-20 144 24 RFI-1775 Yes No No Not Available
Concrete
54 Aamal Ready mix (DTL) SSF Feed Tank Wall Concrete C40/20 OPC+PFA30% 18-Mar-20 224 36 RFI-2136 Yes No No Not Available
DeWatering Centrifuge Bulilding
55 Aamal Ready mix (DTL) C40/20 OPC+PFA30% 25-Mar-20 13 24 RFI-2147 Yes No No Not Available
Ground Beam
57 Aamal Ready mix (DTL) SSF Supernant Wall C40/20 OPC+PFA30% 31-Mar-20 72 7 RFI-2250 Yes No No Not Available
Due to the unavailability of radial bars at site & NCR #17 (NCR Ref: CP837-QM-PIL-NCR-0017) , the concreting was rescheduled to on or before 13-May-2020 on which sampling for durability testing shall be
taken.
58 Aamal Ready mix (DTL) Lamella Clarifier Base Slab (Radial) C40/20 OPC+PFA30%
Test Reports shall be submitted separately within 2 Weeks from the date of testing (i.e. 56 days from the date of sampling). Pouring Card/ DTL Requisition form/ Confirmation Email from DTL Regarding
Sampling shall be submitted as an evidence for NCR Closure

Note:

3 7704
Total Concrete Quantity (M )
QCS 2014 Required Tests (Nos) 15
Actual Conducted Tests (Nos) 14
Pending No of Tests (Nos) 1