You are on page 1of 176

EDRAAK

QUEENRANIAFOUNDATI
ON
VOL
UME3
METHODOFMEAS
UREMENT
ANDBI
LLOFQUANTI
TI
ES

CONTRACTORCOPY

J
ANUARY2016

WWW.
HANNAS
ALAMEH.
COM +96265933396 CONNECT HANNAS
ALAMEH.
COM
METHOD OF MEASUREMENT
METHODS OF MEASUREMENT

TABLE OF CONTENTS

Division 1 General Requirements

Division 2 Site Works

Division 3 Concrete

Division 4 Masonry

Division 5 Metals

Division 6 Wood and Plastic

Division 7 Thermal and Moisture Protection

Division 8 Doors and Windows

Division 9 Finishes

Division 10 Specialties

Division 14 Conveying System

Division 15 Mechanical Works

Division 16 Electrical Works

Queen Rania Foundation- EDRAAK Contents


DIVISION 1 - General Requirements
1. Principles of Measurement

1.1 This method of measurement provides a uniform basis for measuring bills of quantities
for works of construction. More detailed information than is required by this document
may be given to define the precise nature of works or the circumstances under which it
is to be carried out.

1.2 Amendments to this method of measurement for use in a particular locality or adopted
for work not envisaged by this document shall be stated; an appendix is to be provided
for such amendments.

1.3 This method of measurement may be applied equally to the measurement of proposed
works and of complete works.

2. Bills of Quantities

2.1 the objects of bills of quantities are

a. to assist in the accurate preparation of tenders, by providing for measurement of


quantities on a uniform basis.

b. to provide a basis for the financial control of a project, in accordance with the
conditions of contract.

c. All quantities shown in the bill of quantities are approximate and the purpose of
such quantities is to obtain a close estimate of the value of the tender contract.
However, the contractor shall be paid for the actual amount of work carried out in
accordance with the contract as determined by direct measurement during the
progress of the works whether the actual quantities are more or less than those
shown on the bills of quantities. Those quantities are not intended to be used by
the contractor for the materials take-off and ordering.

2.2 Bills of quantities shall describe and represent the works to be carried out; work which
cannot be measured accurately shall be described as approximate or given in bills of
approximate quantities.

2.3 Conditions of contract, drawings and specifications shall be provided with the bills of
quantities.

2.4 The section headings and classifications do not impose restrictions upon the format
and presentation of bills of quantities.

3. Measurement
3.1 Works shall be measured net as fixed in position and each measurement shall be
taken to nearest 10 millimeters; this principle shall not apply to dimension stated in
descriptions.

3.2 Unless otherwise stated, no deduction shall be made from items required to be
measured by area voids of less than 0.36 m2.

3.3 Minimum deductions of void shall refer only to voids within the edges of measured
areas; voids which are at the edges of measured area shall always be deducted,
irrespective of size.

Queen Rania Foundation- EDRAAK 1/1 General Requirements


DIVISION 1 - General Requirements (Cont’d)

3. Measurement (cont’d)

3.4 These principles of measurement may be used with other units of measurement but the
particular amendments shall be stated.

3.5 Notwithstanding these principles of measurement, a separate minor building or


structure may be enumerated.

4. Items to be Fully Inclusive

4.1 Unless otherwise stated, all items shall be fully inclusive of all that is necessary to fulfil
the liabilities and obligations arising out of contract and shall include:

a) Labor and all associated costs.


b) Materials, goods and all associated costs
c) Provision of plant
d) Temporary works
e) Establishment charges, overheads and profit

5. Description of Items

5.1 items which are required to be enumerated, or for which an item is required, shall be
fully described.

5.2 Items which are to be measured by length or depth shall state the cross-sectional size
and shape, girth or ranges of girths or such other information as may be appropriate.

5.3 Items which are to be measured by weight shall state the thickness or such other
information as may be appropriate.

5.4 Items which are to be measured by weight shall state the materials thickness or such
other information as may be appropriate

5.5 Notwithstanding this method of measurement, proprietary items may be measured in a


manner appropriate to the manufacturer's tariff or customary practice.

5.6 The description of items in bills of quantities may refer to other documents or drawings
and any reference to such information shall be understood to fulfil any requirement of
this method of measurement, alternatively, reference may be made to published
information.

Queen Rania Foundation- EDRAAK 1/2 General Requirements


DIVISION 1 - General Requirements (Cont’d)

6. Dayworks.

6.1 The cost of labor in dayworks shall be given as a sum; alternatively, a schedule of the
different categories of labor may be given containing a provision for hourly rates.

6.2 The cost of labor included in a sum or schedule shall include wages, bonuses and all
allowances paid to operative directly engaged on dayworks (including those operating
mechanical plant and transport) in accordance with the appropriate employment
agreement or, where no such agreement exists, the actual payments made to the work
people concerned.

6.3 The cost of materials in dayworks shall be given as a sum; alternatively, a schedule
may be given containing a provision for pricing different materials.

6.4 The cost of materials included in a sum or schedule shall be the net invoiced price,
including delivery to site.

6.5 The cost of constructional plant employed exclusively in dayworks shall be given
containing a provision for hourly rates for each category.

6.6 The cost of constructional plant included in a sum or schedule shall include fuel,
drivers, consumable stores, repairs, maintenance and insurance of plant.

6.7 An item shall be given for the addition of establishment charges, overheads and profit
to each of the sums or schedules of labor, materials,, or plant.

6.8 Establishment charges, overhead's and profit shall include:

a) Costs related to the employment of labor.


b) Costs related to the storage of materials, including handling and waste in storage.
c) Contractor's administrative arrangements.
d) Constructional plant, except plant employed exclusively on dayworks.
e) Contractor’s facilities.
f) Temporary works.
g) Sundry items.

7. Conditions of Contract

7.1 The Tenderer is deemed to have covered in his unit rates all the requirements of the
Conditions of Contract.

8. Specification

8.1 The Tenderer is deemed to have covered in his unit rates all the requirements of the
technical specifications.

Queen Rania Foundation- EDRAAK 1/3 General Requirements


DIVISION 1 - General Requirements (Cont’d)

9. Restrictions

9.1 The tenderer is deemed to have covered in his unit rates for Restrictions, which shall
include

a) Access to an possession or use of the site.


b) Limitations of working space.
c) Limitations of working hours.
d) The maintenance of existing services on, under or over the site.
e) The execution of completion of the working in any specific order, sections or
phases,
f) Items of a like nature.

10. Contractor's Administrative Arrangements

10.1 The tenderer is deemed to have covered in his unit rates for contractor's administrative
arrangements, which shall include:

a. Site administration
b. Supervision.
c. Security.
d. Safety, health and welfare of work-people
e. Transport of work-people

11 Constructional Plant

11.1 The tenderer is deemed to have covered in his unit rates for constructional plant, which
shall include:

a) Small plant and tools.


b) Scaffolding.
c) Cranes and lifting plant.
d) Site transport.
e) Plant required for specific Trades.

12. Contractor's Facilities

12.1 The tenderer is deemed to have covered in his unit rates for facilities required by the
contractor, which shall include:

a) Accommodation and buildings, including offices laboratories, compounds , stores,


Messrooms and living accommodation.
b) Temporary guard rails.
c) Temporary roads, including hard standings and crossings.
d) Water for the works; particulars shall be given if water will be supplied to the
contractor.
e) Lighting and power for the works, particulars shall be given if current will be
applied to the contractor.
f) Temporary telephones.
g) Any other facilities (e.g. signboards, progress, photographs …etc.).

Queen Rania Foundation- EDRAAK 1/4 General Requirements


DIVISION 1 - General Requirements (Cont’d)

13. Temporary Works

13.1 The tenderer is deemed to have covered in his unit rates for temporary works which
shall include:

a) Traffic diversion
b) Access roads
c) Bridges
d) Cofferdams
e) Pumping.
f) Compressed air for tunneling

14 Sundry Items

14.1 The tenderer is deemed to have covered in his unit rates for sundry items, which shall
include:

a) Testing of materials
b) Testing of the works.
c) Protecting the works from inclement weather.
d) Removing rubbish, protective casings and coverings and cleaning the works at
completion.
e) Traffic regulations.
f) Maintenance of public and private roads.
g) Drying out the works.
h) Control of noise and pollution.
i) All statutory obligations.

Queen Rania Foundation- EDRAAK 1/5 General Requirements


DIVISION 2 - Sitework

02050 - Demolition and Alteration Works

Demolition and alteration items and the like shall be measured as indicated in the bills of
quantities.

All salvage items arising from dismantling items should be stored properly and handed over
to the owner all as per the Engineer's Instructions.

The unit rate is deemed to include:

- Cutting concrete or other materials using approved methods.

- Clearing away from site as the work proceeds materials arising from the demolition
and alteration work.

- All temporary supports and shoring deemed necessary incidental to demolition and
alteration works.

- Making good to the existing structure, finishing and services as required.

- Removal of finishing to walls, slabs, floors that are to be demolished.

- Re-use all materials are in good conditions

Queen Rania Foundation- EDRAAK 2/ 1 Methods of Measurement


DIVISION 2 – Sitework (Cont’d)

02100 - Excavation and Earthworks


02110 – Clearing
02211 – Rock Removal
02219 - Structural Excavation and Backfill
02223 - Backfilling

1. Excavation

Each kind of excavation is given separately

Excavation is given in cubic meters. The quantities given are the bulk before
excavating.

The unit rate is deemed to include:

- Any method of excavating and working.


- Excavating in any material whatsoever encountered including rock.
- Variations to bulk.
- Commencing excavating at any level, and excavating to any depth.
- Any width of trench and any number of pits.
- Curved excavation.
- Excavating below ground water level (irrespective of any difference between the
post-contract and pre-contract level).

- Excavating next to existing services and around existing services crossing excavations
including temporary support, temporarily re-routing, sealing and removing services as
required.

- Breaking out existing materials and hard paving including concrete, reinforced
concrete, brick-work, blockwork, stone work, drains, and coated macadam or asphalt
and the like.

- Extra excavation for working space and to accommodate earthwork support including
additional disposal, backfilling, work below ground water level, breaking out and
earthwork support.

- Disposal of excavated material, on site or off site, including spreading and leveling or
depositing in spoil heaps, providing tip and paying fees and multiple handling.

- Backfilling to excavations around foundations, walls and columns with material arising
from excavations or imported materials including depositing and compacting in layers
and multiple handling.

- Surface treatments including compacting surface of ground and bottoms of


excavations, leveling and grading to falls, trimming slopping surfaces and trimming
vertical surfaces to sides of cuttings (including trimming in rock) and applying
herbicides and pesticides.

- All necessary compaction for existing soil.

Queen Rania Foundation- EDRAAK 2/ 2 Methods of Measurement


DIVISION 2 – Sitework (Cont’d)

2. Filling

Filling materials is given in cubic meters.

The unit rate is deemed to include:

- Preparing surfaces to receive filling.


- Filling of any thickness
- Multiple handling
- Filling and compacting in layers including leveling and grading to falls and slopes.

02517- Interlocking Concrete Pavers

- Interlocking concrete tiles are given in square meters, the unit rate is deemed to include
sand bed materials and all necessary related works and materials

02521 – Precast Concrete Units

1. Precast concrete curbstone is given in linear meter

The unit rate is deemed to include:

a- Excavation works, concrete works, formwork, pointing and all necessary related
materials and works.
b- Bedding mortars and other fixings materials.
c- Jointing, grouting and cleaning.

02950 – Trees, Plants and Ground Cover

1. Trees, plants and ground covers as indicated in BOQ.

2. The unit rate is deemed to include all necessary preparation works and all related
works and materials.

Queen Rania Foundation- EDRAAK 2/ 3 Methods of Measurement


DIVISION 3 - Concrete

03200 - Concrete Reinforcement

1. Bar reinforcement

Bar reinforcement is given in Kilograms.

The unit rate is deemed to include:


- Preparing schedules for bar bending.
- Fixing bars in any position and in any member.
- Fixing bars horizontally, vertically and sloping.
- Any diameter, section and length of bars.
- Forming straight, bent and curved bars and links.
- Cutting, lapping and jointing (including special joints)
- Hooks, tying wire, spacers, chairs and the like.
- The weight of surface treatments and rolling margin.

Queen Rania Foundation- EDRAAK 3/ 1 Methods of Measurement


DIVISION 3 - Concrete (Cont'd)

03100 - Concrete Formwork


03300 - Cast-in-place Concrete
03370 - Concrete Curing

1.0 In Situ Concrete

Each class of concrete is given separately, stating the kind of cement and whether
plain or reinforced.

Wall and column kickers are included with the measurement of walls and columns
respectively.

Columns are measured from top of slab to underside of beams or slab above.

Projections, nibs, attached columns and the like are included with the measurement of the
adjacent member .

Columns are only measured as such when their length on plan is not exceeding four times
their thickness.

Details of each type of composite or complex unit and feature are stated in descriptions.

Unless other wise stated in B.O.Q. in situ concrete is given in cubic meters measured net
except that deductions are not made for the following:

- Reinforcement.
- Steel sections of area not exceeding 0.50m2
- Cast in accessories.
- Voids not exceeding 0.05 m3 volume.

The unit rate is deemed to include:

- Formwork to all surfaces, edges, sloping, tops, grooves, chamfers, niches, end of
walls, sides of voids, opening and the like.
- Designing mixes.
- Any method of pouring, placing, compacting and curing.
- Pouring on or against earth or unblended hard-core.
- Any thickness, cross-sectional area or number of members.
- Horizontal, sloping and vertical.

Queen Rania Foundation- EDRAAK 3/ 2 Methods of Measurement


DIVISION 3 - Concrete (Cont'd)

03100 - Concrete Formwork


03300- Cast-in-place concrete (cont'd)
03370 - Concrete Curing (cont'd)

1.0 In Situ Concrete (Cont'd)

The unit rate is deemed to include:

- Placing or finishing to falls and cross falls.


- Basic finish as struck from formwork (including curved or troughed formwork) and
tamped worked finish.
- Extra width of concrete or formwork to edges of blinding beds.
- Formwork, left in Formwork or other form of temporary support to top of sloping upper
surfaces of blinding beds.
- Day joints (construction joints) and joints required in the forming of bays including
Formwork and treatment of reinforcement crossing the joint.
- All labours on concrete including working around pipes or cables, cutting channels,
chases, mortices, pockets and holes and including subsequent grouting or filling and
making good

03346 - Concrete Floor Finishing

Stamped concrete floors are given in square meters, the unit rate is deemed to include
preparation works and all necessary related works and materials

03450 – Architectural Precast Concrete

Precast concrete office desk are enumerated, the unit rate is deemed to include
reinforcement steel bars, fixings, wooden works, decoration and all necessary related works
and materials.

Queen Rania Foundation- EDRAAK 3/ 3 Methods of Measurement


Division 4 - Masonry

04100 - Mortar
04220 - Concrete Masonry Unit

1.0 Generally

1.1 Each kind of hollow and solid block and brick is given separately. Those used in
work constructed as Formwork and with joint reinforcement are each so
described.

1.2 Work of each of the following types is given separately and measured in square
meters:

i) 100 mm thick walls.


ii) Cavity walls.

1.3 Work is deemed to be vertical unless otherwise described.

1.4 Thickness of wall is stated in descriptions. Thickness stated is the nominal


thickness unless otherwise described.

1.5 Curved work is to be measured separately.

1.6 Walls, are given in square meters measured on the center line of the material.
No deduction is made for voids not exceeding 0.36m2

1.7 The unit rate is deemed to include:

Mortar for bedding and jointing

Type of bond and method of pointing.

Raking out joints or leaving rough joints to form key.

Battering work (i.e. sloping with parallel sides),

Extra materials for curved work, tapering work and for work bonded at back to
other work.

Building against or tying to other work (i.e. not bonded) , including extra material.

Temporary strutting to work used as Formwork.

Joint reinforcement in reinforced work.

Overhand building.

Queen Rania Foundation- EDRAAK 4/1 Methods Of Measurement


Division 4 – Masonry (Cont’d)

04100 - Mortar (cont'd)


04220 - Concrete Masonry Unit (cont'd)

1.7 The unit rate is deemed to include (cont’d);

Forming cavities in hollow walls and between wall and other work, including
providing wall ties, and closing cavities at ends, tops and around openings
including extra materials.

Bonding ends of walls to other work including providing ties reinforcement and
anchorage or other fixings and extra material in bonding.

Pinning up load bearing walls to structural soffits and filling voids with mortar.

Reveals, angles and intersections.

Rough and fair cutting.

Grooves, throats, mortices, chases, rebates, holes, stops, mitres and the like.

Weather fillets and like and pointing in flashing including cutting grooves or
chases.

Labours in returns, ends and angles.

Building in or cutting and pinning ends of lintels, sills, bearing bars, steps,
timbers, steel sections and the like.

Templates for forming openings and lift shafts, centering, and temporary
supported protection to built-in frames.

Fixings in position.

Lintels, bond beams and stiffener columns.

Formwork and steel bars reinforcement for lintels, bond beams and stiffener
column.

Queen Rania Foundation- EDRAAK 4/2 Methods Of Measurement


Division 4 – Masonry (Cont’d)

04450 - Natural Stone Works

1.0 Generally

1.1 Stone walls are given in square meters.


1.2 Vanity units are enumerated.
1.3 Stone coping and sills are given in linear meters.

1.2 The unit rate is deemed to include:

Cement and sand mortar bed and backing

Pointing and jointing

Sealant – Expansion joint filler, if required

Metal anchors, related accessories and steel mesh

Special stones, such as external, internal and triangular angles, heads, jambs,
sills…etc.

Movement joints, cleaning, sealing and pointing

Mechanical fixation system (where required)

All necessary related works and materials

Queen Rania Foundation- EDRAAK 4/3 Methods Of Measurement


DIVISION 5 - Metals

05120 – Structural Steel

1.0 Steel Structure

Unless otherwise stated structural steel shall be measured as indicated in


BOQ.

The unit rate is deemed to include:

- Fittings, caps, brackets, fixings, bolts, distance pieces.


- Welding and grouting bases.
- Holding down bolts, protective treatment, surface treatments.
- Fabrication and erection.
- Rivets, nuts, washers and welding materials.
- Trial erection, rolling margin.
- Holes for other trades.
- Fire rated Painting and decoration and all necessary related works and
materials.

2.0 Corrugated steel sheet are given in square meters, the unit rate is deemed to include
all necessary bolts, sheets, welding, fixings, fittings, accessories and fire protection
paint.

05500 - Miscellaneous Metal Fabrications

Steel plates
steel plates are given in linear meters, the unit rate is deemed to include fixings,
fittings, accessories, welding, angles, painting and all necessary related works and
materials.

Steel tubes
steel tubes are given in linear meters, the unit rate is deemed to include fixings,
fittings, accessories, welding, angles, painting and all necessary related works and
materials

Aluminum Canopy
Aluminum canopy are enumerated, the unit rate is deemed to include fixings, fittings,
accessories, welding, angles, painting and all necessary related works and materials.

Steel Stairs
Steel stairs are enumerated, the unit rate is deemed to include fixings, fittings,
accessories, welding, angles, painting and all necessary related works and materials.

Painted Steel Fence


Painted steel fence are given in linear meters, the unit rate is deemed to include
fixings, fittings, accessories, welding, angles, painting and all necessary related
works and materials.

Galvanized steel edge


Galvanized steel edge are given in linear meters, the unit rate is deemed to include
fixings, fittings, accessories, welding, angles and all necessary related works and
materials.

Queen Rania Foundation- EDRAAK 5/1 Methods of Measurement


DIVISION 5 – Metals (Cont’d)

05520 - Handrails and Railings

Balustrade is given in linear meters

The unit rate is deemed to include:

- Handrail

- All necessary posts, railing, fixings, fittings, accessories, welding, painting,


decoration and all related works and materials.

Queen Rania Foundation- EDRAAK 5/2 Methods of Measurement


Division 6 – Wood and Plastic

06200 Finish Carpentry

1.0 Wooden Desk

Wooden desk are enumerated, the unit rate is deemed to include all necessary,
fixings, fittings, accessories, painting and all necessary related works and
materials.

2.0 Kitchen Cabinets

Kitchen cabinets floors or walls are given in linear meter, the unit rate is deemed
to include drawers, doors, shelves, fixings, accessories, hardware, painting and
decoration and all necessary related works and materials

06243 - Wood Veneer Faced paneling

1.0 Wooden Cladding

Wood cladding are given in linear meters, the unit rate is deemed to include
Wooden backing supports, skirting, grooves, fixings, accessories, painting works
“as specified” and decoration and all related works and materials.

06400 – Architectural Wood Works

1.0 Wooden Benches

Wooden benches are enumerated, the unit rate is deemed to include Wooden
backing supports, grooves, fixings, accessories, painting works “as specified” and
decoration and all related works and materials.

Queen Rania Foundation- EDRAAK 6/1 Method of Measurement


DIVISION 7 - Thermal and Moisture Protection

Thermal and moisture protection

Each kind of thermal and moisture protection items are given separately stating the type of
material.

The thermal and moisture protection items are given in square meters unless otherwise
indicated measured the area in contact with the base. No deduction is made for voids not
exceeding 0.36m2.

03300 - Cast-In-Place Concrete

1. Concrete screed to roof and protection topping are given in square meters.

2. The unit rate is deemed to include:


a. Forming shallow channels within the thickness of concrete screed to roofs and
protection topping.
b. Temporary support work to face of risers and the like
c. Angle fillet around the parameters shall be measured in linear meters

07111 - Bituminous Membrane Waterproofing For under ground Works


07535 – Modified Bitumen Roofing Membrane

- Bituminous membrane waterproofing is measured in square meters.


- Modified bitmen roofing membrance are given in square meters.

The unit rate is deemed to include:

- Primers, bonding compounds, adhesives and keying mixes.


- Applying coatings by brush or spray
- Sloping and curved work to coatings.
- Work of any width, height or girth.
- Work laid to falls and crossfalls, and intersections on sloping work.
- Extra material for lapping membranes including adhesive tape.
- Internal and external angles, fillets and the like.
- Edges, arises and turning into grooves or channels and sealing.
- Cutting, notching and bending membranes.
- Holes for pipes and the like, forming collars and sealing.
- Membrane waterproofing or under ground works.
- Joint works at L sections
- Corners
- Strips
- Preparation works
- Special items used in conjunction with the membrane
- All necessary related works and materials.

07191 – Vapour Barrier

Vapour barrier is given in square meters, the unit rate is deemed to include fixings and all
necessary related works and materials

Queen Rania Foundation- EDRAAK 7/ 1 Methods of Measurement


DIVISION 7 - Thermal and Moisture Protection

07212 - Rigid Insulation

Extruded polystyrene thermal insulation are given in square meter, the unit rate is deemed to
include fixings and all related works and materials.

07320 – Roofing tiles

Ceramic roof tiles are given in square meters, the unit rate is deemed to include cement and
sand mortar bed, sandfill materials, grouting, jointing and all necessary related works and
materials.

07600 – Flashing and Sheet Metal

Metal flashing is given in linear meters, the unit rate is deemed to include fixings and all
necessary related works.

Sundries

- Natural gravel bed is given in square meters, the unit rate is deemed to include all
necessary preparation works.

- Cartonal protection board is given in square meters, the unit rate is deemed to include
all necessary fixings.

- Geo-textile separating layer is given in square meters, the unit rate is deemed to
include all necessary fixings.

Queen Rania Foundation- EDRAAK 7/ 2 Methods of Measurement


Division 8 - Doors and Windows
08110 - Steel Doors
08111 - Standard Steel Frames

1. Doors are enumerated.

2. The unit rate is deemed to include:

a- Frames and fixing accessories


b- Glazing (where required)
c- Sealing and mastic
d- Make openings for louvers
e- Decoration and painting
f- Hardware sets.
g- Fire insulation for fire doors
h- All necessary related works and materials as mentioned in BOQ and
as per specifications

08210 - Wood Doors & Frames

1. Doors are enumerated.

2. The unit rate is deemed to include:

a- Frames, Subframes, architrave and fixing materials.


b- Glass and Glazing (where required)
c- Decoration and painting.
d- Hardware sets.
e- Fire insulation for fire doors.
f- All necessary related works and materials.

08520 - Aluminum Windows and Doors

1. Aluminum windows are enumerated

2. The unit rate is deemed to include: -


a. Frames and sub frames
b. Powder coating / Anodization
c. Aluminum angles, profiles and frames
d. Fixing to surrounds, bedding pointing, sealants and blocking
e. Hardware sets
f. Aluminum flashing
g. Weather stripping, mastic sealants at trims
h. Glass and glazing as specified
i. Fly screens
j. Scaffolding, carnage & hoisting
k. All necessary fixings, fittings, accessories and related works and
materials as shown on drawing and as mentioned in BOQ and as per
specifications.
l. Protection of the works until handing over

Queen Rania Foundation- EDRAAK 8/1 Method of Measurement


Division 8 - Doors and Windows (Cont’d)

08700- Hardware

1. Hardware sets shall not be measured separately but shall be deemed


included with the related measured work .

2. The unit rate is deemed to include fixing with screws to match and fixing to
metal and wood doors.

08800 - Glazing

1. Doors are enumerated.

2. Glass partitions are enumerated.

3. The unit rate is deemed to include: -

a- Glass and glazing.

b- Frames, aluminum bases, mastic sealants, handles, hardware, plywood


backing and accessories.

c- Fixings, supports, studs and channels

d- All necessary related works and materials

Queen Rania Foundation- EDRAAK 8/2 Method of Measurement


Division 9 – Finishes

09220 - Portland Cement Plaster

1. Work items in this section shall be measured as the net area covered. Work to
reveals of openings and all other narrow widths shall be included in the
measurement.

2. The unit rate is deemed to include:

a- Cement sand plaster materials as specifications section (plaster guides


should be for walls and ceilings).

b- All mixes mentioned in specification section.

c- Metal accessories, expansion joints and anchorages as specified in the


specifications.

d- Completion of the work as specified.

e- Angles beads, casing stops and wire mesh

f- Watertight additive materials for special plaster

g- All necessary related works and materials.

h- Grooves if any.

09250 Gypsum Board Partitions

Gypsum board walls are given in square meter.

The unit rate is deemed to include gypsum layers, studs, fixings, fittings,
accessories, skimcoats and all necessary related works and materials as
mentioned in BOQ.

Queen Rania Foundation - EDRAAK 9/1 Method of Measurement


Division 9 – Finishes (cont’d)

09260 Gypsum Board False Ceiling Systems

1- False ceilings as shown on relevant details in this section shall be


measured in square meters for the net area covered as measured on plan
including suspension system.

2- The unit rate is deemed to include:-

a- Supply and fix Gypsum board false ceilings horizontally or vertically


as specified.

b- Hanging System as specified, and as shown on detail Drawings.

c- Cut to size where required.

d- All necessary Works for the completion of this item.

e- Forming of electromechanical openings.

f- Skim Coats

09410 – Portland Cement Terrazzo

1- Work items in this section are measured in square meters.

2- The unit rate is deemed to include:

a- Preparing subsurface as specifications.


b- Mortar bed and grouting.
c- Expansion and contraction joints.
e- Appropriate sand bed underlay.
f- Handling and storing
g- Grinding with carborandum machine and polishing.
h- Pointing, grouting and cleaning

09544 – Stretched Fabric Ceiling System

1- Stretched fabric ceiling system are given in square meters.

2- The unit rate is deemed to include fixings, suspension system and all
necessary related works and materials

Queen Rania Foundation - EDRAAK 9/2 Method of Measurement


Division 9 – Finishes (cont’d)

09570 - Wood Flooring

1- Work items in this section are measured in square meters as the net
surface area of finish.

2- Wood skirting is measured in linear meter

3- The unit rate is deemed to include:

a- Preparing subsurface as specifications.


b- All necessary underlay layers as required
c- All necessary special painting and protecting coating

09570a Wood Ceilings

1- Suspended ceilings are given in square meters

2- The unit rate is deemed to include:

a- All fixings for support any system.


b- Edge trims and angles including necessary timber grounds.
c- Corner angles to upstands
d- Cutting and fitting around openings including grills, registers and light
fittings.
e- Providing access points to space above.
f- Supplementary framing around fixtures.
g- All related works and materials as mentioned in Bills of Quantities.

09610 - Stone Flooring

1- Flooring are given in square meters


2- Steps are given in linear meters

2- The unit rate is deemed to include:

a- Cement and sand mortar bed.


b- Sand fill materials.
c- Cutting, pointing and cleaning
d- All necessary related works

09650 - Resilient Flooring

Vinyl sheets flooring is given in square meter, the unit rate is deemed to include
preparation works, special adhesive materials, cutting and fixings and all
necessary related works and materials.

Queen Rania Foundation - EDRAAK 9/3 Method of Measurement


Division 9 – Finishes (cont’d)

09691 - Natural Marble

Generally

- Marble floors are given in square meters.

The unit rate is deemed to include:

a- Setting beds, mixtures, sealants ... etc. as specified.


b- White and/or colored cement for jointing and grouting as specified.
c- Polishing including powder and/or paste materials.
d- Forming expansion and contraction joints.
e- Straight and curved cutting.
f- Handling and Storing
g- All necessary related materials and works as indicated on the drawings
and as called for in the specifications

09695 Carpeting with Underlay

1- Carpet flooring are given in square meters

2- The unit rate is deemed to include:

- Cutting, adhesive and underlay.


- All necessary related works and materials

09900 Painting

1- Painting is given in square meters for the net area covered. Work to narrow
widths will be incorporated in the measurement.

2- Painting for all metal and wooden works shall not be measured separately,
but shall be deemed included with the related measured works.

3- The unit rate is deemed to include:

a- Preparation works.
b- Under coats as per specifications.
c- All necessary related materials and works.

Queen Rania Foundation - EDRAAK 9/4 Method of Measurement


DIVISION 10 - Specialties

10110 – Visual Display Units

- Boards are given in square meters, the unit rate is deemed to include fixings, fittings,
accessories and all necessary related works and materials

10162 - Toilet Compartment

- Toilet compartments are enumerated, the unit rate is deemed to include doors, fixings,
fittings, accessories, handless, hardware and all necessary related works and
materials

10440 – Signs

- Alucobond Signs are enumerated, the unit rate is deemed to include preparation works
and all necessary related works and materials as mentioned in BOQ and as per
specifications

Queen Rania Foundations - EDRAAK 10/1 Method of Measurement


DIVISION 14 – CONVEYING SYSTEM

1. CENERAL RULES FOR CONVEYING SYSTEM

1.01 Conveying system generally is deemed to include:

Supply, installation, testing, commissioning, putting into satisfactory


operation and handing over complete systems.

Provision of maintenance and operation manuals, shop drawings, as built


drawings and spare parts and submitting required number of copies,

Co- ordination with other trades including minor approved modifications


and additions to ensure compatibility.

Minor items and accessories required for normal operation and


maintenance.

Marking the positions of and cutting or forming holes, mortises, chases


and the like in any surface and making good all work disturbed.

Assembling and jointing together component parts of composite units and


providing any necessary jointing materials.

Patterns, moulds, templates and the like,

Priming or painting off site and proprietary finishes or surface treatments


applied as part of the manufacturing process.

Corrosion protective treatments and coatings to fixings, hangers and


supporting materials,

Sleeves through walls, ceiling and floors including cover plates.

Fire sealants,

Brackets and supports, separation beams

Temporary works and removing and making good after,

Loose keys, tools and spares and the like, except where required to be
given separately,

Plates, labels and tags for the identification of plant, equipment, cables,
switches and the like.

Queen Rania Foundation - EDRAAK 14/1 Method of Measurement


DIVISION 14 – CONVEYING SYSTEM (CONT'D)

1. GENERAL RULS FOR CONVEYING SYSTEM (CONT’D)

1.02 Conveying system generally is deemed to include (cont'd):

Temporarily operating each installation, including attendants, special


insurance and providing power supply.

Cutting and pinning ends of supports or equipment, ancillaries, fittings,


trucking, trays and the like.

Painting on site including colour coding,

Builder’s work in connection, except where required to be measured


separately,

Training Employer’s personnel in operation and maintenance of systems.

2. ELEVATORS

1. Generally

1.1 Each kind of elevators are given separately, type, size, pattern,
capacity, loading, length, floor served … etc. are stated, where
appropriate.

1.2 Elevator is enumerated.

1.3 The unit rate is deemed to include:

All works listed in the general rules.

Auxiliaries, controls, indicators and accessories.

Wires, cables, conduits, wireways and earthing.

Finishing and architectural works for elevator rooms, doors, panels


and elevations as shown on drawings mentioned in BOQ and as
per specifications.

All necessary scaffolding, supporting and all related builders works


and materials.

Queen Rania Foundation - EDRAAK 14/2 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS


A. PREAMBLES (FOR ELECTROMECHANICAL WORKS)

1. The Bills of Quantities shall be read in conjunction with the Instructions to


Tenderer's, General and Special Conditions of Contract, Technical
Specifications, Appendices and Drawings. The documents are to be taken as
mutually explanatory and inter-related to one another.

2. Unless otherwise mentioned, all quantities of works shall be measured “Net” in


accordance to the drawings or/as ordered by the engineer, and generally,
according to method of measurement, attached herewith.

3. In the case of discrepancy in quantities of works performed by the contractor and


those shown on the drawings, and should such discrepancy by acceptable to the
employer, then the quantities agreed by the Engineer shall be taken into account
in the measurement of quantities.

4. All quantities shown in the Bill of Quantities are approximate, and the purpose of
such quantities is to obtain a close estimate of the value of the works. However,
the contractor shall be paid for the actual amount of work the contractor carries
out in accordance with the contract, as determined by direct measurement during
the progress of the works whether the actual quantities are more or less than
those shown in the Bills of Quantities. Those quantities are not intended to be
used by the contractor for the ordering of materials.

5. The Unit Price and the rates inserted in the Bills of Quantities respectively shall be
comprehensive and shall include for complying in all respects with the
requirements of the Technical Specifications, drawings and all other related tender
documents. This shall cover all the obligations under the contract and all matters
deemed necessary for the proper construction, completion of and remedy of
defects in the works. No claims for additional payment will be allowed for any
error, or misunderstanding of the work involved by the contractor.

6. In the Bills of Quantities, a unit price or rate shall be inserted against its respective
item with quantities only. The value of any item left unpriced shall be deemed to
be covered by other rates and prices entered in the Bills of Quantities.

7. All measurements of the executed works called for in the Contract shall be based
on the unit price stated in the Bills of Quantities and made according to the
specifications. Any work done by the Contractor, but not called for in the Contract
or not requested in writing by the Engineer, shall not be included in the
measurement.

8. The unit rate of the materials and equipment shall be based on the Specification, all
components as required and specified under each item concerned in the
Specifications, Technical Data and Notes on Contract Drawings, and all other
Contract documents.

Queen Rania Foundation - EDRAAK 15/1 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)

A. PREAMBLES (FOR ELECTROMECHANICAL WORKS) (CONT'D)

9. The Bills of quantities are classified under headings and sections with the same
reference numbers and titles as the specifications.

10. Each section referred to in the Bills of quantities shall be read in conjunction with
the respective section and with all other related sections of specifications.

11. The Bills of Quantities, Specifications, Schedule of Equipment and Drawings and
all other Contract documents are complementary to each other.

12. It is the responsibility of Contractor to check the locations and quantities of the
materials and equipment to be executed in accordance with the contract
drawings.

13. The Unit Rate is deemed include the following:

General

1. Supply of materials and equipment.

2. Off loading and handling from trucks on site to place of installation.

3. Installation of materials and equipment.

4. All civil work required and connected with the electromechanical installations,
such as: equipment concrete bases and supports, cutting through walls and
slabs for passage of pipes and conduits and ducts, pipe sleeves, repatching,
fixing of pipe and duct hangers and supports to structure, wooden frames for air
outlets and louvers and wall mounted fans, excavation and backfilling, riggings,
hosting, water proofing, cleaning, protection and painting..

5. All testing, balancing, adjusting, commissioning and handling to the Owner


complete operational systems and equipment.

6. Allowance for cleaning and for proper protection of all equipment plants,
electrical installations and structures during insulation and paintings.

7. Disinfection, flushing and water treatment.

Queen Rania Foundation - EDRAAK 15/2 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)

A. PREAMBLES (FOR ELECTROMECHANICAL WORKS) (CONT'D)

General (Cont’d)

8. All labour, materials, tools, instruments, electric power supply, fuel and water
required for installation, testing, balancing, adjusting, disinfection, flushing,
operation and commissioning.

9. Thermal insulation for all equipment, valves, trimming and accessories.

10. System identifications, tags, labels, nameplates and charts.

11. Shop-drawings and as-built drawings.

12. Spare parts and components for ideal running of all services and equipment.

13. Spare parts information and tools.

14. Operation and maintenance manuals.

15. Training.

16. Samples as required by the Engineer.

17. Inspection, testing and rejection of all materials and workmanship.

18. Maintenance of all items supplied by contractor as per Contract Conditions.

19. The price of all electrical driven equipment is deemed to include coordination for
all electrical wiring, conduits, earthing, cables, cable trays, cable ladders,
fixations with all accessories.

20. All electrical wiring, steel conduits, earthing, cables, cables trays, cables ladder,
fixation, complete with all accessories for the connections from the nearest
isolation switch to the equipment with connection of mechanical equipment

21. Surface treatment, priming, under coating, barrier coating, finish painting and
protective paintings and labeling as described in the specifications.

22. Silencer splitters, buffles, profile steel frames, angle frames, boltings to the
served equipment and ducting protection against corrosion and erosion as per
specialized recommended manufacturer.

Queen Rania Foundation - EDRAAK 15/3 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)

B. MECHANICAL MATERIALS AND EQUIPMENT

1. Pipe work: "galvanized steel, iron, Black steel, XLPE, CPVC pipes, PVC pipes,
copper, UPVC for all services".

1.0 Pipework are measured in linear meters.

1.2 Unless otherwise indicated in B.O.Q., the unit rate is deemed to include all
pipe fittings and joints such as elbows, bends, tees, reducers, unions,
expansion joints, flanges, anchoring, sleeves, floor plates, puddle flanges,
safety valves, pressure and temperature gauges, balancing and measuring
taps, test plugs and test points, sockets and all joining materials, and pipe
hangers and supports, and expansion bellows loops and joints,
thermometers, flexible connection and joints, fire retardant and protection
sealants for all pipes crossing fire rated structures, automatic air vents with
isolating valves expect otherwise mentioned, vent caps, zone isolation
valves, all p-traps, s-traps, pipe cleanouts, drain cocks at bottom of risers
and main pipes for drainage system, adapters and dielectric unions for
connecting dissimilar materials, excavation and back-filling, chasing in
walls, painting, pipe protection against corrosion, pipe coating, all kind of
valves, fixed orifice double regulating valves, measuring tabs and orfices
and all accessories as required per specifications and drawings.

2. Drainage Points and Fittings

2.1 Drainage points are enumerated.

2.2 The unit rate is deemed to include all necessary steel cover grating
frames, gaskets, chasing, cutting, excavation, backfilling, builders works,
accessories and fittings.

Queen Rania Foundation - EDRAAK 15/4 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS

B. MECHANICAL MATERIALS AND EQUIPMENT (CONT'D)

3. Sanitary Fixtures

3.1 Sanitary Fixtures are enumerated.

3.2 The unit rate shall include all mixers, flush valves, flush cistern, angle
valves, flexible hoses, flow restrictors, aerators, escutcheons plates, pop-
up drains, p-traps, brackets, adapters, flexible connection, cutting, chasing,
builders works, wall flanges, wall brackets, WC connectors, fixing kits and
all other accessories as called for in specifications.

4. Water Cabinets

4.1 Water cabinets are enumerated.

4.2 The unit rate is deemed to include plastic or steel water cabinet boxes,
brass cold and hot water collectors, ball valves, automatic air vents,
brackets, nipples, union, cover, all other accessories as shown on
drawings and as called for in specifications.

5. Electrical Water Heater (EWH)

5.1 Electrical water heater is enumerated.

5.2 The unit rate is deemed to include fixings, fittings, accessories, electrical
and mechanical connections, pressure relief valve, isolating valves and all
necessary to complete the works.

Queen Rania Foundation - EDRAAK 15/5 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)

B. MECHANICAL MATERIALS AND EQUIPMENT (CONT'D)

6. VRF Outdoor Unit

6.1 VRF outdoor units are enumerated

6.2 The unit rate is deemed to include all necessary fixings, fittings,
accessories, valves, mechanical and electrical connections and as called
for in the drawings and specifications

7. VRF A/C Concealed Type Indoor Units

7.1 VRF A/C indoor units are enumerated.

7.2 The unit rate is deemed to include all necessary fixings, fittings,
accessories, valves, liquid and gas pipes, mechanical and electrical
connections and as called for in the specifications and drawings

Queen Rania Foundation - EDRAAK 15/6 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)


B. MECHANICAL MATERIALS AND EQUIPMENT (CONT'D)

8. Dx Split Units

8.1 DX split units are enumerated.

8.2 The unit rate is deemed to include all necessary fixings, fittings,
accessories, mechanical and electrical connections and as called for in the
specifications and drawings.

9. Fans:

9.1 Fans are enumerated and as indicated in BOQ.

9.2 The unit rate is deemed to include, gravity shutters, vibration isolators
resilient mountings, skids and hangers, flexible connections on fan inlet
and outlet, filters where required, insect screen, back draft dampers or
automatic shutter, non-overloading backward aluminum inclined fan wheel,
aluminum roof curbs, pulleys with taper locks, inlet guards, belt guards,
lubrication points, sound attenuators to achieve the NC for the served
space and the outdoor, one set of spare belt drives per each fan, electrical
connections and all other accessories as shown on drawing and as called
in specifications.

10. Ductwork: For Ventilation and Air Conditioning.

10.1 Ductwork weight shall be calculated net in kg unless otherwise indicated in


B.O.Q (the calculation taken from the approved shop drawings based on
the dimensions and length of actual installed ducting only without
calculating the weight of joints, hangers, supports, seames, lapping,
stiffener, dampers, vanes, angles etc. which shall be included in the unit
rate).

10.2 Unless otherwise indicated in B.O.Q., the unit rate is deemed to include
metal sheets ducting with all joints, sealant compound, fire retardant
sealants for all ductwork passing through fire rated structures, hangers and
supports and brackets, reinforcing angles, bird screens, volume access
doors and panels, all vanes, volume splitter damper (VSD), regulating
damper, smoke dampers, expansion with rod and lock screws, coating,
painting all joints, adapter and coupling and all accessories as specified
and as shown on drawings and as called for in the specifications.

Queen Rania Foundation - EDRAAK 15/7 Method of Measurement


MECHANICAL WORKS

DIVISION 15 - MECHANICAL WORKS (CONT'D)

B. MECHANICAL MATERIALS AND EQUIPMENT (CONT'D)

11. Insulation :

11.1 Duct insulation are given in square meter for the installed ducting.

11.2 The unit rate is deemed to include all joints, sealant compounds, bands,
vapour barrier, and all finishing, coating protection and cladding with all
accessories as called for in the specifications.

12. Air Terminal, Diffusers, Air Grills, Registers and Door Grills, Volume and Fire
Dampers, Flexible Connection

12.1 Air terminal, diffusers, ….. etc. are enumerated.

12.2 The unit rate is deemed to include all materials associated and
components, flashing, clips, shims, fastening devices, separating panels,
anchors, painting, frames, flashing, neoprene gaskets, all accessories and
associated works shown on drawings and indicated as per specifications.

13. Pumps: All kinds of pumps for all services

13.1 Pumps are enumerated / sets

13.2 The unit rate is deemed to include:

13.3 Isolating valves, globe valves, check valves, strainers, pressure gauges,
pressure relief vent, air release valves, flexible connections, vibration
isolators, control panels, concrete base with elastic interlayer for remove
vibrations electrical connections, concrete base and antivibration pad as
shown on the drawings and as called for in the specifications.

13.4 Pump control panel, adjustable frequency driver, sensor transmitters,


differential pressure sensor, and all related power control accessories as
shown on the drawings and as called for in the specifications, coordination
with the control equipment specialist for the recommended locations and
sizes of all sensor transmitters and differential pressure sensors.

- Isolating valves, check valves, strainers, pressure gauges, differential


pressure switch, 20mm pressure relief vent air release valves, flexible
connections, vibration isolators, concrete base and anti vibration pad.

Queen Rania Foundation - EDRAAK 15/8 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK

1. STATIC UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM

Generally

1.01 Each kind of static UPS system is given separately, stating the
capacity and reference where appropriate.

1.02 Reference, net output rating in kVA and kW, input and output
voltages, phases and frequency are stated in descriptions

1.03 Static UPS system is enumerated.

1.04 Reference of UPS served, and rating in kVA, where appropriate,


are stated in description.

The unit rate is deemed to include:

- Batteries and battery racks and interconnecting cables and


accessories.
- Termination of incoming and outgoing cables including cable
terminal boxes and accessories.
- Remote control and indicating panels and interconnects.
- Concrete base or any kind of steel support.

Queen Rania Foundation - EDRAAK 16/1 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

2. MAIN, SUBMAIN AND SECONDARY DISTRIBUTION


PANELBOARDS

1. Generally

1.01 Each kind of distribution boards are given separately, stating


the reference

1.02 Distribution boards are enumerated.

1.03 The unit rate is deemed to include:

Termination of incoming and outgoing cables to panel boards


including cable glands, terminations and accessories.

Fixing and support structures and materials required for installation


such as trenches, drain chequered plates, heavy duty covers,
support, concrete base … etc. of wall or floor mounted equipment
as indicated.

Termination of the earthing system.

Termination of neutral cables

MCCB's, MCB’s contractors, time switches, busbars, circuit


breakers, couplings, meters, clamps and microprocessor metering
devices, selector switch indication lamsp bush buttons, relays, and
current transformers.

All necessary fittings, accessories and related works and materials.

Queen Rania Foundation - EDRAAK 16/2 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

3. MAIN CIRCUITS FEEDERS, CONDUCTORS, CABLES AND


RELATED ACCESSORIES

1. Generally

1.01 Each kind of feeders, busbar trunking and cables are given
separately (except where required to be included with other
items), stating the type, size and method of installation.

1.02 Feeders, busbar trunking and cables are given in meters,


measured the net length.

1.03 The unit rate is deemed to include:

Conduits and fittings, draw wires and the like.

Cable connectors and cable joints (where permitted) including joint


boxes, sealing boxes, shrouds and the like and materials and heat
for making the joints,

Allowance in cable length for cables entering fittings and


accessories, equipment or the like.

All necessary components and accessories for fixing cables on


walls, ceilings and on cable trays, ladders, and trunking.

In buildings underground trenches, ducts, and sleeves.

All necessary fittings, lugs, glands, brackets and all related works
and materials.

All necessary connection.

All necessary excavation and backfilling

Queen Rania Foundation - EDRAAK 16/3 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

4. CABLE TRAYS, LADDERS, TRUNKING AND THE LIKE

1. Generally

1.01 Each kind of cable trays and the like as shown on drawings
are included with other items.

1.02 The unit rate is deemed to include:

Mounting fittings, including cutting and jointing

Jointing between sections, bends, tees, etc.,

Components for earth continuity and bonding to earthing main bar,

Adaptors and connections between trunking and items of


equipment or the like requiring the use of flanges and/or the forming
of apertures.

Supports including fixing

Mounting fittings, jointing between sections, rising elbows, bends,


tees, intersections (with integral fixings for adaptor plates and cross
over bridges).

Terminator and cover plates.

Adaptors and connections between trunking and items of


equipment of or the like requiring the use of flanges and/or the
forming of apertures.

Holding down devices, gasket, fasteners, etc.

Outlet box and cover,

Queen Rania Foundation - EDRAAK 16/4 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

5. EQUIPMENT AND POWER POINTS AND ACCESSORIES

1. Generally

1.01 Each kind of equipment and power points and accessories


are given separately stating rating and type.

1.02 Equipment, power points, isolating switches and


accessories are enumerated.

1.03 The unit rate is deemed to include:

- Wiring, conduits, cables, junction boxes and


connections.
- Protective earthing conductors, fixings, supports and
accessories.
- All necessary related works and materials.

6. POWER SOCKET OUTLETS POINTS AND ACCESSORIES

1. Generally

1.01 Each kind of wiring devices including socket outlets,


electrical outlets the like are given separately, stating the
type and / or rating.

1.02 Wiring devices, power points and the like are enumerated.

1.03 The unit rate of points and socket outlets are deemed to
include:

Wires including protective earthing conductors, conduits, junction


box, trunking and other raceways and fittings from outlet back to
upstream outlet or controlled circuit or to final branch circuit
panelboard,

Fixing and supporting material.

All necessary fittings, accessories and all related works and


materials.

1.04 The unit rate of floor box include all necessary bends, tees,
elbows, boxes, supports, pull cords, chasing in floors,
painting and protection against corrosion

Queen Rania Foundation - EDRAAK 16/5 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

7. LIGHTING SYSTEM

1. Lighting and Switches points and accessories

1.01 Lighting and switches points are each given separately.

1.02 Each kind of lighting fixture and switches is given


separately, stating the type.

1.03 Lighting points and lighting fixtures are enumerated.

1.04 Switches points and switches are enumerated.

1.05 The unit rate of lighting and switches points is deemed to


include.

Wires, conduits, boxes and cables.

Wires including protective earthing conductors, conduits, junction


box, trunking and other raceways and fittings from outlet back to
upstream outlet or to final branch circuit panel board.

1.06 The unit rate of switches are deemed to include:

Covers, boxes and ancillaries.

Fixing and supporting material.

All necessary fixings, fittings and accessories.

1.07 The unit rate of lighting fixtures is deemed to include:

Internal wires, starters, transformer, ballast control gear, diffusers,


controllers and switches

Fixing and supporting material.

Queen Rania Foundation - EDRAAK 16/6 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

8. TV SYSTEM

1. TV System

1.01 Each of the following items are each given separately:

TV outlet points
TV socket outlets

1.02 TV outlet points and socket outlets are enumerated.

1.03 The unit rate is deemed to include:

- Cables and wires with all necessary cable terminations and


accessories.

- Termination of conduits with all necessary conduit fittings,


boxes, …. etc.

- Conduits, boxes, covers, fixings, fittings, accessories, ancillaries


and all necessary related works and materials as indicated in
BOQ and as shown on drawings and as per specifications.

Queen Rania Foundation - EDRAAK 16/7 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

9. TELEPHONE AND DATA SYSTEM

1. Telephone and Data System

1.01 Each of the following items are each given separately:

Telephone and data points


Telephone and data socket outlets
Intermediate distribution frames
Telephone and data cables
PABX
Switch panels
Server
Main distribution frame

1.02 Equipment, points, outlets, distribution frames, cables,…etc


are measured as BOQ.

1.03 The unit rate is deemed to include:

- Mounting with necessary fixing materials and supports,

- Cables and wires with all necessary cable terminations


accessories.

- Termination of conduits with all necessary conduit fittings,


boxes, …. etc.

- Conduits, covers, fixings, fittings, accessories, ancillaries and all


necessary related works and materials as indicated in BOQ, as
shown on drawings and as per specifications.

10. CCTV SYSTEM

1. Each of the following items are given separately:

- CCTV Cameras
- CCTV Rack

2. Each of the above items are measured as indicated in the BOQ

2.1 The unit rate is deemed to include for cameras conduits, boxes,
cables, wires, racks, connections, terminations and all
necessary related works and materials.

2.2 The unit rate is deemed to include for CCTV – Rack switch
board, channel networks DVR for main building, staff building
and hangers, monitor screen and all cables, wires, conduits and
connections.

Queen Rania Foundation - EDRAAK 16/8 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

11. FIRE ALARM SYSTEM

1. Each of the following items are given separately

- Fire alarm control panel


- Fire alarm devices points
- Fire alarm devices

The unit rate is deemed to include for the following:

A. Fire alarm devices points

- Conduits, wires, cables, pull and junction boxes, terminations and


connections.

B. Fire alarm devices

- Cover, fixings, fittings and all necessary connections.

C. Fire alarm control panel

- Internal wires, conduits, cables, indication lamps, rest button,


switches, battery charger, back up batteries, amplifiers, emergency
power supply, fixings, fittings, accessories, terminations and
connections.

12. EARTHING SYSTEM

1. Generally

1.01 Earthing system is given as an item

1.02 The unit rate is deemed to include a complete system including


earthing pits, protective earthing conductors run with branch circuit
wiring and connection of the cables armouring with suitable cable
glands to the earth bar at both ends, cooper busbars, earthing
roads, clamps, earthing manholes, bounding of mechanical
equipment.

Queen Rania Foundation - EDRAAK 16/9 Method of Measurement


ELECTRICAL WORK

DIVISION 16 - ELECTRICAL WORK (CONT'D)

13. BUILDER’S WORK

1. Generally

1.01 Builder’s work in connection with electrical installations is not given


separately (except where specifically required) and is deemed to
be included in the unit rates of electrical installations.

1.02 Bases/foundations and supports (where not forming an integral


part of the building structure) are deemed to be included with the
equipment unit rates for lighting columns and masts.

1.03 Trenches for main cables is not given separately and is deemed to
be included in the unit rates of cables.

2. Manholes, Handholes and other Underground Structures

2.1 Manholes, handholes and other underground structures (where not


forming an integral part of the building structure or included
specifically where appropriate) are each given separately, stating
the type and/or size.

2.2 Manholes, handholes and other underground structures are


enumerated.

2.3 The unit rate is deemed to include:

Excavation including backfilling, disposal of surplus excavated


material and earthworks support.

Concrete, reinforcement, formwork and water-proofing.

Blockwork, brickwork and rendering.

Building in ends of pipes including cutting pipes.

Step irons, covers and frames.

Queen Rania Foundation - EDRAAK 16/10 Method of Measurement


BILLS OF QUANTITIES
BILLS OF QUANTITIES

TABLE OF CONTENTS

BILL NO. I Preliminaries

BILL NO. 1 Main Building

BILL NO. 2 External Works

Queen Rania Foundation- EDRAAK Contents


BILL NO. I

PRELIMINARIES
BILL NO. I
PRELIMINARIES

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES

A The Contractor is deemed to investigate the


site to ascertain the exact nature of the project
and allow in his prices for completion of all the
works whether or not shown specifically in the
tender / contract documents. 1 Item INCLUDED

B The Contractor is deemed to include in his


prices, all costs to comply with the instructions,
rules and specifications stipulated or observed
by the Local Government Authorities, such as
Town Planning, Municipality, Drainage, Water
and Electricity Departments, Civil Defence
Department, etc. at the time of tender even if
these stipulations are not shown in Drawings
and Specifications. 1 Item INCLUDED

C The Contractor is deemed to include in his


prices, for the provision of : 1 Item INCLUDED

1) 3 sets of Workshop Drawings for the Engineer


approval prior to fabrication . Access should be
allowed to the Engineer for any necessary
Workshop inspection.

2) One set of construction records which includes


check lists (e.g. soil, concrete, paint, etc.,) and
list of approved materials used for construction
with suppliers contact numbers.

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/1 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

A The Contractor is deemed to include in his


prices for sufficient power and water, including
connections for construction purposes and
testing of electrical and mechanical equipment
in the building at the time of handing over the
project. 1 Item INCLUDED

B The Contractor shall propose all sub-


Contractors to Engineer approval and
wherever applicable, these sub-Trade
Contractors shall be from the first class in a
local department classification 1 Item INCLUDED

C The Contractor is to ensure that he is holding


a valid Municipality Contracting License in the
area of the works since Building Permit will be
issued only to those registered with the local
Municipality controlling the project area. 1 Item N/A N/A

D The Contractor shall be responsible to file for


all formalities for and collecting the Building
Permit from the appropriate Municipality and
payment of all charges incurred herewith. 1 Item N/A N/A

E On completion of the whole of the works , the


Contractor shall conduct test of water proofing
by flooding the roof with water for 24 hours in
the presence of the Engineer . The
waterproofing for the roof shall be carried out
by a specialized waterproofing sub Contractor
and to be guaranteed by the Contractor and
SubContractor for the perfect performance for
10 years from the date of issuance of the
completion certificate
1 Item INCLUDED

F The Contractor shall submit 10 years


guarantee for all external painting , starting
from the date of issuance of the completion
certificate. 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/2 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

A Before commencing with the works, the


Contractor should obtain clearance from all
concerned departments and shall allow in his
prices for doing so. 1 Item INCLUDED

Form of Agreement
B The Contractor shall describe and list below
and price herein any obligations contained in
form of agreement for which he has not
allowed elsewhere and wishes to price
separately. 1 Item INCLUDED

Conditions of Contract

C The Contractor shall describe and list below


and price herein any obligations contained in
Condition of Contract for which he has not
allowed elsewhere and wishes to price
separately. 1 Item INCLUDED

Drawings
D The Contractor shall describe and list below
and price herein any obligations contained in
Drawings for which he has not allowed
elsewhere and wishes to price separately 1 Item INCLUDED

Specifications
E The Contractor shall describe and list below
and price herein any obligations contained in
Specifications for which he has not allowed
elsewhere and wishes to price separately 1 Item INCLUDED

Bills of Quantities
F The Contractor shall describe and list below
and price herein any obligations contained in
methods of measurement and Bill of
Quantities for which he has not allowed
elsewhere and wishes to price separately 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/3 - Main Building
Queen Rania Foundation - EDRAAK - I/4 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Form of Tender

A The Contractor shall describe and list below


and price herein any obligations contained in
Form of Tender and Appendix for which he
has not allowed elsewhere and wishes to price
separately 1 Item INCLUDED

Plant and Tools

B The Contractor is to include for all mechanical


and non-mechanical plant, tools and vehicles
required for the expeditious carrying out of the
works in accordance with the contract
documents and list below and price any
mechanical and non-mechanical plant, tools
and vehicles for which he has not allowed
elsewhere and wishes to price separately 1 Item INCLUDED
C Carnage and Material Handling 1 Item INCLUDED
D Personnel Transport 1 Item INCLUDED

Site Boundary Demarcation Certificate


E The Contractor shall be responsible for
obtaining the site Boundary Demarcation
Certificate from the survey section of Amman
Municipality and to agree the location of the
site Boundary Markers with the survey section.
The Contractor shall provide a copy of the
Demarcation certificate to the Engineer's
approval 1 Item N/A N/A

Temporary Roads

F The Contractor shall prepare and maintain


such temporary roads as may be necessary
from the site to the nearest Municipality road
and also within the site. The roads shall be
positioned in accordance with the Engineer's
Instructions and shall be kept free from access
at all times
1 Item INCLUDED

To Collection JD INCLUDED

Queen Rania Foundation - EDRAAK - I/5 - Main Building


BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Site Survey and Setting Out


A As soon as the Contract has been signed, the
Contractor shall make an accurate survey of
the Site showing the existing ground levels
and shall furnish the Engineer with two copies
of the survey drawings 1 Item INCLUDED
B A permanent datum point must be established
during this operation to the approval of the
Engineer 1 Item INCLUDED
C The Contractor shall be held responsible for
the correctness of the Site Survey 1 Item INCLUDED

Existing Services
D The Contractor shall be responsible for the
protection of all existing services within the
Site and shall make good any damage to
existing services resulting from his carrying
out of the Works to the satisfaction of the
Engineer and relevant authority. The
Contractor shall be responsible for giving
notice to the relevant authority where
temporary or permanent re-routing of existing
services is found to be necessary and shall
provide attendance upon any Contractor
employed to carry out such re-routing 1 Item INCLUDED
Contractor's Working Area
E The Contractor is responsible for his working
area 1 Item INCLUDED

Electrical Power and Lighting


F The Contractor shall arrange and provide for
an adequate temporary supply of all necessary
electrical power and lighting of the works
including electrical power for the consumption
of electricity or supporting, operating and
maintaining generators at his own expense
until handing over the works 1 Item INCLUDED

To Collection JD INCLUDED

Queen Rania Foundation - EDRAAK - I/6 - Main Building


BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils
PRELIMINARIES (CONT'D)
Water
A The Contractor shall arrange for an adequate
temporary supply of water for the works,
suitable for all purposes, until handing over
and shall pay all charges for the consumption
of water used. The Contractor will be
responsible for supplying & maintaining
equipment including any necessary pumps,
storage tanks, distribution pipework, ... etc.,
required for the execution of the works 1 Item INCLUDED
Telephone
B The Contractor shall arrange for a telephone
to be installed on the site for the duration of
the contract and shall pay all charges in
connection with permits installations, rental,
calls and removal on completion 1 Item INCLUDED
Labour Camp
A labour camp is not permitted on site
watchmen and security staff only may be
accommodated 1 Item INCLUDED
Storage
C The Contractor shall provide and maintain
adequate weatherproof sheds for storage of
materials, furniture and equipment and
remove same on completion of the works 1 Item INCLUDED
Site Facilities for Contractor's Staff
D The Contractor shall provide temporary sheds,
offices, messrooms, sanitary accommodation
and the like for the use of his Agent and Site
Staff such offices shall be complete with
lighting, furniture, equipment and attendance,
and shall be open at all reasonable hours to
receive instructions, notices and other
communication for the duration of the
Contract. Such temporary buildings shall be
cleared away on completion 1 Item INCLUDED
Assistance & Instruments for Engineer's
E The Contractor shall provide at all times for
the duration of the Contract all such chainmen,
staff men, workmen and survey instruments as
may be required for the proper construction
and completion of the Works. 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/7 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Office Facilities for the Owner/


Engineer Representative.
A The Contractor shall furnish a temporary office
facility not less than 2 private offices , room
approximate floor area = 40 square meters , it
shall be located where directed and shall be
reserved for the Engineer 's representative
use only . Adequate lighting , power, heating
and stationary shall be furnished and
maintained by the Contractor . Entrance door
shall be equipped with substantial lock . The
entire facility , including furniture , will remain
the property of the Contractor and shall be
removed from the site after completion of the
whole project construction works
1 Item INCLUDED

The Contractor shall furnish new office


furniture and equipment as follows:-
B Office desks 2 No. INCLUDED

C Swivel chairs 2 No. INCLUDED

D Straight chairs 4 No. INCLUDED

E PC computer, Pentium 4 2 No. INCLUDED

F Calculators 2 No. INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/8 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Office Facilities for the Owner/


Construction Manager's (Cont'd)
A External telephone lines with (6) extensions 0 No. N/A N/A

B Fax machine with line. 0 No. N/A N/A

C Telephone mobile with monthly charges 1 No. INCLUDED

D Also provide the appropriate manuals,


handbooks, application pacs, supplies and
consumables to operate the system for the
duration of the Project. All equipment for the
computing system shall remain the property of
the Engineer upon completion of the Project. 1 No. INCLUDED

E Heavy duty copy machine with automatic


feeder and sorter 0 No. N/A N/A

F Full size plan racks complete with slats and


hardware for mounting drawings 0 No. N/A N/A

G Half size plan racks complete with slats and


hardware for mounting drawings 0 No. N/A N/A

H Cooker 1 No. INCLUDED

J Refrigerator 1 No. INCLUDED

K Drinking water cooler 1 No. INCLUDED

L First aid cabinet complete with supplies 1 No. INCLUDED

M Electrical soft drink dispenser and cooler 0 No. N/A N/A

N Air conditioning for the whole offices 1 No. INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/9 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Labour and Materials

A The Contractor shall provide such labour,


materials and transportation as the Engineer's
Representative may require to assist him in
carrying out tests and checks on materials and
workmanship and setting out, and
measurement of the Works 1 Item INCLUDED

Tests

B The Contractor shall allow for all tests required


by the Specifications to be carried out
including providing all necessary materials and
samples 1 Item INCLUDED

Samples

C The Contractor shall allow for providing and


submitting to the Engineer as he may require,
samples of all materials and goods which the
Contractor proposes to incorporate into the
works 1 Item INCLUDED

Record Drawings

D The Contractor shall prepare and submit to the


Engineer record drawings as required by the
specification 1 Item INCLUDED

Shop Drawings

E The Contractor shall provide at any time


before commencement or during the progress
of the work shop drawings as directed by the
Engineer 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/10 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

As-Built Drawings

A The Contractor shall carry out the correction of


all prints of Drawings including the preparation
on completion of the Works one transparency
and six prints of As-Built Drawings 1 Item INCLUDED

Progress Photographs
B The Contractor shall provide to the Engineer
each month 2 set of twelve photographs
showing work in progress from viewpoints
selected by the Engineer. 1 Item INCLUDED

C Four copies of each photograph (180 x 130


mm in colour ) together with the negative shall
be provided with a description and the date of
the taking incorporated on the front of each
print 1 Item INCLUDED

Scaffolding

D The Contractor shall provide, erect, maintain,


dismantle and clear away at completion proper
and adequate internal and external scaffolding
including that required for all Sub-Contractors
and nominated Specialists. Any holes shall be
made good to match the adjacent surfaces as
the scaffolding is dismantled. The Contractor
shall be entirely responsible for all safety
precautions in connection with scaffolding and
for its entire sufficiency for the work 1 Item INCLUDED

Temporary Hoarding

E The Contractor shall provide temporary, gates,


fencing, hoarding, planked footways, guard
rails, gantries and the like, and the hoarding
remains as property of the Employer after
completion of the works. 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/11 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils
PRELIMINARIES (CONT'D)
Reports
A The Contractor shall submit a weekly report in
writing to the Engineer, in an agreed form,
giving weekly records of the following items:- 1 Item INCLUDED

Number of men employed on the Site divided


into staff, tradesmen and others
Accidents to employees reportable by statute

Weather conditions on each day and night


Progress of the Works in general terms.
Plant on Site
Materials on Site
Materials orders schedule showing date order
was
placed, expected delivery date and present
status
for all the materials required for the project.

This report is to be submitted before the third


day of the following week

The Contractor shall submit to the Engineer


each month a report comprising the following:-

Progress chart
Progress photographs (as described above)
Statement regarding the progress of the Works
Extent and nature of the Work completed
Any problems relating to the Works (with
adequate documentation if applicable).
Financial statement
Records of materials, equipment and plant
tested with copies of the test results
Detailed schedule of work to be performed
during the coming month and a general listing
of work to be performed during the coming
three months
The Contractor shall submit to the Engineer, in
addition to the monthly report a report at
quarterly intervals which will provide more
general information about the Works
The content and format of all Reports shall be
subject to the approval of the Engineer
To Collection JD INCLUDED

Queen Rania Foundation - EDRAAK - I/12 - Main Building


BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Copies of Orders

A Provide the Engineer's with a copy of all


orders for the supply of materials or goods
required in connections with the Works as the
Engineer may specify 1 Item INCLUDED

Traffic Regulations

B The Contractor shall comply in all respect with


the Employer's regulations and directions
concerning the movement of the Contractor's
vehicles 1 Item INCLUDED

Records

C In addition to those records which are


specifically required by the specifications to be
kept (e.g. test cubes of concrete, air
temperatures, etc.,) a site record shall be kept
of the completion dates of the various works in
each trade, with particular reference to work
which requires time for drying out, such as
solid backgrounds which receive in situ screed
and finishing including the completion times of
the individual layers of such application 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/13 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Protection

A Adequate protection against any form of


damage or deterioration shall be provided for
all sections of the Works. This shall include
protective tapes, casings, guard rails and the
like, which shall be provided if necessary.
Particular care shall be taken to mask self
finished surfaces during the application of
adjacent in situ work, and windows and doors
during the application of sprayed finishes 1 Item INCLUDED

B In pursuance of his obligations under the


Conditions of Contract, the Contractor shall
wherever required or directed by the Engineer
cover up and protect the Works from the
weather and from damage by his own or other
workmen performing subsequent operations.
He shall provide all necessary dust sheets,
barriers and guard rails and clear away same
at completion 1 Item INCLUDED

C The Contractor shall take all reasonable and


proper steps for the protection of all places on
or about the Works which may be dangerous
to his workmen or any other persons or to
traffic. The Contractor shall provide and
maintain signs, red warning lamps and
barricades as necessary in such places 1 Item INCLUDED

Cleaning the Works

D Immediately prior to handing over the Works


the Contractor shall thoroughly clean all
buildings and landscaped areas and generally
clean the Works ready for occupation all to the
approval of the Engineer 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/14 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

Sign Boards

A The Contractor shall provide and maintain one


sign board for the Site , consisting of painted
galvanized steel board plate , steel tubular
section, steel angles, size about 4.00 x 6.45 m
high all painted with two coats white oil paint
back and front and supported above the
ground with steel framing and struts painted
matt black and set into the ground and fixed in
concrete foundations with all necessary flood
lights 1 Item N/A N/A

The boards shall be lettered by a skilled


signwriter in Arabic and English to the
Engineer approval and shall include:

(a) The Project's Name


(b) The Employer's Name
(c) The Engineer Name.
(d) The Contractor's Name
(e) Sub contractor's Name
(f) The Consultant's Name
(g) The Project details
(h) The Quantity Surveyor Name
Large scale layouts are to be submitted to the
Engineer for approval before manufacture. No
advertising material other than the above will
be permitted
No other sign boards or advertisements on or
around the site will be permitted unless
approved by the Engineer

Insurances
B The Contractor shall provide and maintain with
an approved Insurance Company All Risks
Insurance, Third Party Insurance, and
Workmen's Compensation Insurance as
required in the Conditions of Contract 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/15 - Main Building
Queen Rania Foundation - EDRAAK - I/16 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

PRELIMINARIES (CONT'D)

De-Watering System

A Allow for all necessary de-watering


requirements in compliance with the sequence
of operation and as per the Engineer
requirements 1 Item INCLUDED

Shoring System

B Allow for all necessary protection and shoring


system for the existing building in compliance
with the sequence of operation and as per the
Engineer requirements 1 Item INCLUDED

To Collection JD INCLUDED
Queen Rania Foundation - EDRAAK - I/17 - Main Building
BILL I
PRELIMINARIES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

I/1 INCLUDED
I/2 INCLUDED
I/3 INCLUDED
I/4 INCLUDED
I/5 INCLUDED
I/6 INCLUDED
I/7 INCLUDED
I/8 INCLUDED
I/9 INCLUDED
I/10 INCLUDED
I/11 INCLUDED
I/12 INCLUDED
I/13 INCLUDED
I/14 INCLUDED
I/15 INCLUDED

Total Bill I - Preliminaries To General Summary JD INCLUDED

Queen Rania Foundation - EDRAAK - I/18 - Main Building


BILL NO. 1

MAIN BUILDING
DIVISION 2

SITEWORKS
BILL NO. 1
DIVISION 2 - SITEWORKS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SITEWORKS

02050 - Demolish and Alteration works

Carefully demolish, dismantle and remove the


following existing items, including all
necessary cutting, protection, cutting of
reinforcement steel bars, removing, loading
and cart away debris materials from site to an
approved dumping area, complete

A Demolish and cartaway existing basement


foundation and ground beams 1 Item

B Demolish and cartaway existing slab on grade,


150mm thick 93 m2

C Demolish existing cavity walls, various thicknesses


163 m2

D Demolish existing concrete block walls, various


thicknesses 231 m2

E Remove existing metal canopy for back entrance 98 m2

F Remove and cartaway existing metal sheet roof


canopy 19 m2

G Remove and cartaway existing metal roofing for


staircase with steel structural works 28 m2

H Remove and cartaway existing toilet


compartment, comprising of 4 No. units, 3 Nos
dividers and 1 No. front panel 2 No.

J Remove existing vanity units, size 3600mm long 1 No.

K Ditto, size 3700mm long 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/2/1 - Main Building


BILL NO. 1
DIVISION 2
SITEWORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SITEWORKS (CONT'D)

02050 - Demolish and Alteration works (cont'd)

Carefully demolish, dismantle and remove the


following existing items, including all
necessary cutting, protection, cutting of
reinforcement steel bars, removing, loading
and cart away debris materials from site to an
approved dumping area, complete (cont'd)

A Remove existing sanitary fixtures, pipeworks, fire


fighting system, …etc 1 Item

B Remove and cart away existing lighting fixtures,


electrical instalation 1 Item

C Demolish and cartaway existing roof covering


system, including membrane sheets, foam
concrete, cement and sand screed and protection
layer 417 m2

To Collection JD

Queen Rania Foundation - EDRAAK - 1/2/2 - Main Building


BILL NO. 1
DIVISION 2
SITEWORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SITEWORKS (CONT'D)

02100 - Excavation and Earthworks


02110 - Clearing
02211 - Rock Removal
02219- Structure Excavation and Backfill
02223 - Backfilling

Excavation

Excavation in any kind of soil, rock … etc.,


starting at natural ground levels down to
bottom of basecourse levels, including
compacted backfill materials around
foundations and removal of surplus
materials from site to an approved
dumping area, complete

A Basement excavation and the like 211 m3

Excavation in any kind of soil, rock …etc,


starting at existing reduced levels down to
bottom of blinding under foundation
levels, including compacted backfill
materials around foundations and removal
of surplus materials from site to an
approved dumping area, complete

B Structural excavation and the like 26 m3

Filling

Imported basecourse fill materials


including all necessary compaction,
complete

C Beds, 150mm thick 11 m3

To Collection JD

Queen Rania Foundation - EDRAAK - 1/2/3 - Main Building


BILL NO. 1
DIVISION 2
SITEWORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SITEWORKS (CONT'D)

02950-Trees, plants and ground cover

Interior landscape green wall including


pump and electrical connections,
complete as shown on drawing A22 detail
No. W1/F4

A Green wall including planter and soil material 11 m2

To Collection JD

Queen Rania Foundation - EDRAAK - 1/2/4 - Main Building


BILL NO. 1
DIVISION 2
SITEWORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/2/1

Page No. 1/2/2

Page No. 1/2/3

Page No. 1/2/4

Total Bill No. 1 / Division 2 - Siteworks To Summary JD

Queen Rania Foundation - EDRAAK - 1/2/5 - Main Building


DIVISION 3

CONCRETE
BILL NO. 1
DIVISION 3 - CONCRETE

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

CONCRETE

03200- Concrete Reinforcement

Deformed high yield steel bar reinforcement


of characteristic strength (420) Mpa, grade
(60), including all necessary bending, hooks,
tying wires, distance blocks and spacers,
complete
A Various Diameters 3706 kg

03100 - Concrete Formwork


03300- Cast-In Place Concrete
03370 - Concrete Curing

Plain concrete, grade (15), 15Mpa at 28 days


cube compressive strength with Ordinary
Portland cement, including formwork,
complete

B Blinding, 50mm thick, trowelled smooth 4 m3

Reinforced cast-in-place concrete grade (35),


35Mpa at 28 days cube compressive strength
with Ordinary Portland cement, including all
necessary formwork, complete

C Slab on grade, 150mm thick 11 m3

D Raft foundation 4 m3

E Neck of walls and attached columns 4 m3

F Suspended solid slabs, 150mm thick 2 m3

G Ditto, 250mm thick 2 m3

H Walls and attached columns, various thicknesses 54 m3

J Stiffening walls 12 m3

K Steps, staircases and landings 1 m3

To Collection JD

Queen Rania Foundation - EDRAAK - 1/3/1 - Main Building


BILL NO. 1
DIVISION 3
CONCRETE
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

CONCRETE (CONT'D)

03100 - Concrete Formwork (Cont'd)


03300- Cast-In Place Concrete (Cont'd)
03370 - Concrete Curing (Cont'd)

Cast in Place Concrete coping including


fixings, fittings, water drip, steel anchors and
form works, complete

A Coping, 270mm wide x 100mm thick 202 m

03450 - Architectural Precast Concrete

Pre-cast concrete office desk, comprising


175mm thick reinforced concrete ring,
reinforcement steel bars, 12mm thick
tempered glass partitions and doors,
laminated wooden frame, wood blocking, led
light strips, wooden desk, seat, all necessary
fixings, fittings, accessories, hardware,
painting and decoration works, complete as
shown on drawing A34 and as specified

B Pre-cast concrete office desk, ring shape, overall


diameter 2100mm x 1000mm wide 3 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/3/2 - Main Building


BILL NO. 1
DIVISION 3
CONCRETE
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/3/1

Page No. 1/3/2

Total Bill No. 1 / Division 3 - Concrete To Summary JD

Queen Rania Foundation - EDRAAK - 1/3/3 - Main Building


DIVISION 4

MASONRY
BILL NO. 1
DIVISION 4 - MASONRY

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MASONRY

04100 - Mortar
04220 - Concrete Masonry Unit

Hollow concrete blockwork including mortar bed,


joints, concrete lintels, jambs, heads, sills,
cutting, jointing, metal angles, bonding beams
and stiffiner columns, complete

A Walls, 100mm thick 238 m2

B Cavity walls, 530mm "overall" thick, comprising


200mm thick hollow concrete block walls for outer
skin, 150mm thick hollow concrete block walls for
inner skin and 180mm thick cavity 6 m2

Solid concrete blockworks including mortar bed,


joints, concrete lintels, jambs, heads, sills,
cutting, jointing, metal angles, bonding beams
and stiffiner columns, complete

C Walls, 100mm thick, against basement walls 47 m2

04450 - Natural Stone works

Vanity units comprising 30mm thick polished


Karaki stone tops, fascia, backsplash, including
all necessary supporting system, wood framing,
fixings, fittings, painting and accessories,
complete

D Vanity unit, 1970mm long x 500mm wide, with


cutouts for two No. basins 1 No.

E Ditto, 2170mm long x 500mm wide, with cutouts for


three No. basins 1 No.

To Collection JD

Queen Rania Foundation- EDRAAK - 1/4/1 - Main Building


BILL NO. 1
DIVISION 4
MASONRY
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MASONRY (CONT'D)

04450 - Natural Stone works (cont'd)

Stone coping "Local type", white color, including


cement and sand mortar bed, all necessary
fixings, pointing and fixings, complete

A Coping, 260mm wide x 30mm thick 27 m

Stone sills "Local type", white color, including


cement and sand mortar bed, cutting, jointing,
polishing and grouting, complete

B Sills, 410mm wide x 30mm thick 23 m

To Collection JD

Queen Rania Foundation- EDRAAK - 1/4/2 - Main Building


BILL NO. 1
DIVISION 4
MASONRY
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/4/1

Page No. 1/4/2

Total Bill No. 1 / Division 4 - Masonry To Summary JD

Queen Rania Foundation- EDRAAK - 1/4/3 - Main Building


DIVISION 5

METALS
BILL NO. 1
DIVISION 5 - METALS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

METALS

05120 - Structural Steel

Steel structure works including all necessary


bolts, anchors, sealants, painting, angles,
plates, drilling, grouting, welding, screws,
connections, fixings, fittings and accessories,
complete

A Beams HEA100 27 m

Corrugated steel sheets including all


necessary fixings, fittings and accessories,
complete

B To staircases 33 m2

05500 - Miscellaneous Metal Fabrications

Steel plates, including all necessary fixings,


welding, fittings, accessories, bolts, screws
and special painting, complete

C Steel plates, size 200x5mm, to elevations 876 m

Steel tubes, including all necessary fixings,


fittings, welding, accessories, bolts, screws
and "wooden look" finish with white upper
face, complete

D Steel tubes, size 200x30mm, to elevations 270 m

Aluminum canopy, including steel structural


works, fixings, aluminum cladding, fittings, all
necessary welding and decoration works,
complete

E Aluminum canopy, 2380mm long x 870mm wide x


200mm thick 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/5/1 - Main Building


BILL NO. 1
DIVISION 5
METALS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

METALS (CONT'D)

05500 - Miscellaneous Metal Fabrications


(cont'd)

40mm diameter steel tubes, including 3mm


thick steel trunks U-shaped: 50x250mm, 10mm
rod roll black, all necessary fixings, fittings,
accessories and painting, complete

A Steel tubes, for basement ceiling 37 m2

Steel stairs, comprising checked plate, stone


steps, bolts, steel balustrade, painting and
accessories, complete

B Steel stairs, 33 No. steps, size 300mm wide x


169.2mm high, 2No. Flights and 1 No. landing size
1200mm x 1200mm, "overall" height 2200mm 1 No.

05520- Handrails and Railings

Painted steel design balustrade "approval by


the architectural engineer", including all
necessary handrail, fixings, fittings,
accessories and painting, complete as shown
on drawing A07 detail No. 1 and as specified

C Balustrade, 900mm high 21 m

To Collection JD

Queen Rania Foundation - EDRAAK - 1/5/2 - Main Building


BILL NO. 1
DIVISION 5
METALS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/5/1

Page No. 1/5/2

Total Bill No. 1 / Division 5 - Metals To Summary JD

Queen Rania Foundation - EDRAAK - 1/5/3 - Main Building


DIVISION 6

WOOD AND PLASTIC


BILL NO. 1
DIVISION 6 - WOOD AND PLASTIC

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

WOOD AND PLASTIC

06200-Finish Carpentry

Kitchen cabinet, comprising HDF wooden


cabinets, kitchen sink, drawers, doors,
shelves, all necessary fixings, fittings,
accessories, hanging system, handles,
hardware and painting, complete

A Kitchen cabinet, floor mounted 6 m

B Ditto, wall mounted 6 m

06243 - Wood faced paneling

Wooden cladding, comprising 18mm thick HDF


wooden panels, 25mm thick sound insulation
foam, 25mm thick fiber glass, 18mm thick HDF
wooden perforated panels, 20mm thick
sponge, 10mm thick felt fabric, 50x50mm
wooden studs, all necessary fixings, fittings,
accessories and decoration works, complete
as shown on drawing A15

C Wooden cladding, for voice room 21 m2

Wooden cladding, comprising 18mm thick HDF


wooden panels, 50mm thick sound insulation
foam, 50mm thick fiber glass, 18mm thick HDF
wooden perforated panels, 50x100mm wooden
studs, all necessary fixings, fittings,
accessories and decoration works, complete
as shown on drawing A15

D Wooden cladding, for studio 100 m2

Total Bill No. 1 / Division 6 - Wood and Plastic


To Summary JD

Queen Rania Foundation - EDRAAK - 1/6/1 - Main Building


DIVISION 7

THERMAL AND MOISTURE PROTECTION


BILL NO. 1
DIVISION 7 - THERMAL & MOISTURE PROTECTION

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

THERMAL & MOISTURE PROTECTION

03300 - Cast in Place Concrete

Concrete screed including all necessary


preparation works, complete

A To elevator roofs, 50mm thick 6 m2

B To staircase roofs, 100mm thick, above


corrugated sheets 33 m2

Cement and sand (1:4) protection screed,


complete

C To roofs, 50mm thick 417 m2

D To staircase roofs 25 m2

E Angil fillet, 50mm x 50mm, to elevator roof 9 m

F Ditto, 100mm x 100mm 202 m

G Ditto, size 100mm x 100mm, to staircase roofs 21 m

Cement and sand concrete screed with


cementiuos topping, including all necessary
preparation works, complete

H To roofs, 50mm thick 417 m2

07111 - Waterproofing Membrane for Under


Ground Works

Approved 4mm thick torch applied


waterproofing membrane sheets, with non-
woven polyster minimum weight (200) gr/m2,
complete

J Horizontally 85 m2

K Vertically 47 m2

To collection JD

Queen Rania Foundation - EDRAAK - 1/7/1 - Main Building


BILL NO.1
DIVISION 7
THERMAL & MOISTURE PROTECTION
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

THERMAL & MOISTURE PROTECTION


(CONT'D)

07191- Vapour Barrier

Vapour barrier sheets, including all


necessary fixings and overlaping, complete

A To elevator roof, horizontally 6 m2

1000 gage polyethelene sheets, including all


necessary fixings, complete as shown on
demolition plan footings drawing section A-A

B Laid horizontally 35 m2

C Laid vertically 102 m2

07212 - Rigid Insulation

Extruded polystyrene thermal rigid


insulation, density (32-35) kg/m3, complete

D 30mm thick, to cavity walls 6 m2

Thermal insulation, including expanded


cork, all necessary fixings, complete

E To elevator roof, horizontally 6 m2

07320 - Roofing Tiles

Ceramic roof tiles on and including cement


and sand mortar bed, sandfill materials,
grouting, jointing and cleaning, complete

F To staircase roof, 10mm thick 25 m2

To collection JD

Queen Rania Foundation - EDRAAK - 1/7/2 - Main Building


BILL NO.1
DIVISION 7
THERMAL & MOISTURE PROTECTION
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

THERMAL & MOISTURE PROTECTION


(CONT'D)

07535 - Modified Bitumen Roofing Membrane

4mm thick torch applied bitumenenous


waterproofing membrance sheets, including
bitumen primer coating, mastic sealant in
grooves, fixings and overlaps, complete

A To elevator roofs, horizontally 6 m2

B Ditto, vertically 1 m2

C To staircase roof, horizontally 25 m2

D Ditto, vertically 2 m2

4mm thick torch applied bitumenous


waterproofing membrance sheets
(elastomeric bitumen), including bitumen
primer coating, mastic sealant in grooves,
fixings and overlaps, complete

E To roofs, horizontally 417 m2

F Ditto, vertically 81 m2

07600 - Flashing and Sheet Metal

Metal flashing including mastic fill in groove


all necessary fixings and accessories,
complete

G To parapet walls, size 150mm wide x 1mm thick 202 m

To collection JD

Queen Rania Foundation - EDRAAK - 1/7/3 - Main Building


BILL NO.1
DIVISION 7
THERMAL & MOISTURE PROTECTION
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

THERMAL & MOISTURE PROTECTION


(CONT'D)

Sundries

Natural gravel bed, including all necessary


preparation works, complete

A To elevator roof, 50mm thick, horizontally 6 m2

Geo-Textile separating layer, non- woven


semi permeable membrance minimum
weight 140gr/m2, including all necessary
fixings, complete

B To roofs, 200mm thick 417 m2

4mm thick cartonal protection boards


including all necessary fixings, complete

C Horizontally 85 m2

To collection JD

Queen Rania Foundation - EDRAAK - 1/7/4 - Main Building


BILL NO.1
DIVISION 7
THERMAL & MOISTURE PROTECTION
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

COLLECTION

Page No. 1/7/1

Page No. 1/7/2

Page No. 1/7/3

Page No. 1/7/4

Total Bill No. 1 / Division 7 - Thermal &


To Summary JD
Moisture Protection

Queen Rania Foundation - EDRAAK - 1/7/5 - Main Building


DIVISION 8

DOORS AND WINDOWS


BILL NO. 1
DIVISION 8 - DOORS AND WINDOWS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS & WINDOWS

08110-Steel Doors
08111-Standard Steel Frames

Steel door, including all necessary frames, steel


grill door, stainless steel hinges, flush bolt, single
panic bolt, cylinder panic lock, panic bar
concealed vertical rod, door closer, lever handle,
all necessary fixings, fittings, accessories,
hardware and painting, complete

A Type D1, size 900mm wide x 2200mm high 1 No.

08210 - Wood Doors and Frames

Flush wooden doors including frames, subframes,


architraves, stainless steel hinges, mortise
cylinder and latch (SASH LOCK), lever handle,
back plate, push plate, protection plate, kick plate,
door closer, all necessary fixings, fittings,
accessories, handles, hardware, painting and
decoration, complete

B Type D2, size 900mm wide x 2200mm high, swing door


1 No.

C Type D5, size 1000mm wide x 2200mm high, swing

door with vision panel, size 500mm wide x 600mm high 1 No.

D Type D6, size 1000mm wide x 2200mm high, swing


door 1 No.

E Type D7, size 1000mm wide x 2200mm high, with


removable fixed panel opens outward 1 No.

F Type D8, size 900mm wide x 2200mm high, swing door


2 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/8/1 - Main Building


BILL NO. 1
DIVISION 8
DOORS & WINDOWS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS & WINDOWS (CONT'D)

08210 - Wood Doors and Frames (cont'd)

Fire rated, flush wooden doors, including frames,


subframes, architraves, stainless steel hinges,
cylinder and lath (SASH lock), lever handle, back
plate, kick plate, door closer, escutcheons, all
necessary fixings, fittings, accessories, handles,
hardware, painting and decoration works, complete

A Type D3, size 900mm wide x 2200mm high 1 No.

Wooden doors, comprising double layer of 18mm


thick HDF wooden panels, 25mm thick sound
insulation foam, double layer of 10mm thick
sponge, double layer of 10mm thick felt fabric,
wooden frame and architrave, all necessary
fixings, fittings, accessories, handles, hardware,
painting and decoration works, complete

B Wooden doors, size 1100mm wide x 2200mm high, for


studio room 1 No.

C Ditto, size 1200mm wide x 2200mm high, for studio


room 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/8/2 - Main Building


BILL NO. 1
DIVISION 8
DOORS & WINDOWS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS & WINDOWS (CONT'D)

08520 - Aluminum Windows and Doors

Double glazed, aluminum windows comprising


6mm thick clear glass for each skins and 12mm
thick airgap, all necessary 50x 50mm aluminum
frames, architraves, fixings, accessories,
hardware, silicon, mastic sealants, rubber pad,
rubber seal, rod foam, hardwood blocking,
adjustable frame and fittings, complete

A Type NW1, size 2800mm wide x 2240mm high 1 No.

B Type NW2, size 1050mm wide x 2240mm high, swing


type 1 No.

C Type NW3, size 1040mm wide x 2240mm high, swing


type 1 No.

D Type NW4, size 2800mm wide x 2240mm high 1 No.

E Type NW5, size 3740mm wide x 1000mm high, with


metal screen 1 No.

F Type NW6, size 2900mm wide x 2790mm high 1 No.

G Type NW7, size 1630mm wide x 600mm high 1 No.

H Type NW8, size 2600mm wide x 600mm high 1 No.

J Type NW9, size 700mm wide x 2260mm high 1 No.

K Windows, size 3000mm wide x 1790mm high, as


shown on drawing AD1, detail No. W4,F1 2 No.

L Ditto, size 5300mm wide x 1790mm high, as shown on


drawing AD1, detail No. W4/F1 2 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/8/3 - Main Building


BILL NO. 1
DIVISION 8
DOORS & WINDOWS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS & WINDOWS (CONT'D)

08520 - Aluminum Windows and Doors (cont'd)

Double glazed, aluminum curtain walls, including


spandrel insert panel, AVU-resistant sealing
compouned, glazing, inner transom edge,
aluminum frames, architraves, fixings,
accessories, hardware, mastic sealants and
fittings, complete

A Type NCW1, size 2380mm wide x 5250mm high 1 No.

08800 - Glazing

Double glazed, tempered glass partitions,


comprising 6mm thick tempered glass for each
skins and 12mm thick airgap, all necessary
aluminum frames, fixings, fittings, accessories,
handles and hardware, complete (doors measured
elsewhere)

B Aluminum glass partitions, size 3480mm long x


2850mm high, (1 No. door, ref. D10) 1 No.

C Ditto, size 3640mm long x 2850mm high, (1 No. door,


ref. D10) 1 No.

D Ditto, size 3650mm long x 2850mm high, (1 No. door,


ref. D4) 1 No.

E Ditto, size 8910mm long x 2850mm high, (1 No. door,


ref. D4) 1 No.

F Ditto, size 10330mm long x 2850mm high, (1 No. door,


ref. D11) 1 No.

G Ditto, size 18496mm long x 2850mm high, (1 No. door,


ref. D4 and 3 No. doors, ref. D10) 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/8/4 - Main Building


BILL NO. 1
DIVISION 8
DOORS & WINDOWS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS & WINDOWS (CONT'D)

08800 - Glazing (CONT'D)

10mm thick tempered clear glass doors, fully-


glazed, including all necessary glazed, frames,
pull handle, upper hanging rail, hardware, fixings,
fittings and accessories, complete

A Type D10, single leaf, size 1000mm wide x 2200mm


high, sliding doors 6 No.

B Type D11, double leaves, size 2000mm wide x


2200mm high, sliding doors 1 No.

10mm thick fully-glazed doors, including all


necessary glazed, aluminum frames, floor spring -
double acion, mortise cylinder and latch (SASH
lock), lever handles, fixings, fittings and
accessories, complete

C Type D4, single leaf, size 1000mm wide x 2200mm


high, swing doors 6 No.

Double glazed doors, "pivoted" type including


aluminum frames, tempered clear glass, top and
bottom pivot sets, mortise cylinder and latch
(SASH lock), protection plate, clear glass, lever
handle, hardware, fixings, fittings and accessories,
complete

D Type D12, size 2380mm wide x 2800mm high 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/8/5 - Main Building


BILL NO. 1
DIVISION 8
DOORS & WINDOWS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/8/1

Page No. 1/8/2

Page No. 1/8/3

Page No. 1/8/4

Page No. 1/8/5

Total Bill No. 1 / Division 8 - Doors & Windows To Summary JD

Queen Rania Foundation - EDRAAK - 1/8/6 - Main Building


DIVISION 9

FINISHES
BILL NO. 1
DIVISION 9 - FINISHES

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES

09220 - Portland Cement Plaster

20mm thick cement and sand plastering


including all necessary casing stops, angle
beads and wire mesh, complete

A To concrete or blockwalls, internally 959 m2

B Ditto, externally, to elevations 1027 m2

09250 - Gypsum Board Partitions

Gypsum board partitions, including 75mm thick


sound insulation, all necessary fixings, fittings,
aluminum U-profile bottom size 75x75x0.2mm,
aluminum U-profile top size 128 x 30 x 2mm ,
skim coat and accessories, complete

C Gypsum board partitions 32 m2

09260 - Gypsum Board False Ceiling Systems

12.5mm thick gypsum board false ceiling


systems including all necessary angles, fixings,
fittings, accessories, suspension system,
grooves, corner taps and skim coats, complete

D Gypsum board false ceilings 16 m2

E Ditto, to wet area, water repellent 27 m2

F Bulkheads, 200mm high, to wet area 14 m

Perforated gypsum board false ceiling systems


including all necessary fixings, fittings,
accessories, suspension system, grooves,
corner taps and skim coats, complete

G Perforated gypsum board false ceiling 395 m2

H Bulkhead, 200mm high 179 m

To Collection JD

Queen Rania Foundation - EDRAAK - 1/9/1 - Main Building


BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES (CONT'D)

09410- Portland Cement Terrazo

Terrazo floor tiles on and including cement and

sand mortar bed and backing, sandfill materials,

grouting, jointing and cleaning, complete

A To floors, size 300 x 300 x 30mm thick, under vinyl


floors 45 m2

B To landing 2 m2

C Treads, size 300mm wide 4 m

D Risers, size 170mm high 4 m

09544 - Stretched Fabric Ceiling Systems

Stretch fabric including all necessary gypsum


board box 200mm high, metal framing system,
metal angles, fixings and suspension system,
complete

E Stretch fabric, to gypsum board suspended ceilings 73 m2

Felt fabric wrapping panels consisting of


double layers of 3mm thick felt fabric wrapping,
50mm thick sound insulation foam, 50x50mm
wooden studs, all necessary fixings, fittings,
accessories and painting, complete as shown
on drawing A15

F Felt fabric wrapping panels, for ceiling at studio


room 56 m2

To Collection JD
Queen Rania Foundation - EDRAAK - 1/9/2 - Main Building
BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES (CONT'D)

09570- Wood Flooring

Wood flooring comprising 18mm thick HDF


wooden panels, 26mm thick fiber glass, 10mm
thick rubber sheets, 30 x 100mm wooden
beams at 600x600mm grid, all necessary
fixings, fittings, accessories and decoration
works, complete as shown on drawing A15

A Wood flooring, to voice room 3 m2

Wooden flooring, comprising 18mm thick HDF


wooden panels, 50mm thick sound instulation
foam, 50mm thick fiber glass, 18mm thick HDF
wooden perforated panels, 50 x 100mm wood
studs, all necessary fixings, fittings,
accessories and decoration works, complete as
shown on drawing A15

B Wood flooring, to studio 26 m2

10mm thick HDF wooden skirting, including all


necessary fixings, fittings, wooden spacers,
accessories and painting, complete

C Skirting, ref.SF1 223 m

D Ditto, to gypsum board partitions, ref.SF1 35 m

To Collection JD

Queen Rania Foundation - EDRAAK - 1/9/3 - Main Building


BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES (CONT'D)

09570a- Wood Ceilings

Wooden suspended ceiling, comprising 18mm


thick HDF wooden panels, 25mm thick sound-
insulation foams, 25mm thick fiber glass, 18mm
thick sponge, 10mm thick felt fabric, 50 x 50mm
wood studs, suspension system, all necessary
fixings, fittings, accessories and decoration
works, complete as shown on drawing A15

A Wooden suspended ceiling, for voice room 3 m2

09610-Stone Flooring

First quality, "Local type" stone flooring tiles on


and including cement and sand mortar bed,
sandfill materials, pointing and cleaning,
complete

B To landings 7 m2

C To ramps 2 m2

D Treads, 300mm wide x 30mm thick 1 m

E Risers, 170mm high x 20mm thick 1 m

To Collection JD
Queen Rania Foundation - EDRAAK - 1/9/4 - Main Building
BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES (CONT'D)

09650- Resilient Flooring

Vinyl sheets flooring, including all necessary


adhesive materials, fixings, cutting and
accessories, complete

A To floors 45 m2

B To landings 2 m2

C Treads, size 300mm wide 4 m

D Risers, size 170mm high 4 m

09691 - Natural Marble

First quality, "Karaki" Marble floor tiles, honed


finish, on and including cement and sand
mortar bed, sandfill materials, cutting, jointing,
polishing and grouting, complete

E To floors, size 300x300x30mm thick, ref. FF2 5 m2

09695- Carpeting With Underlay

Carpet flooring, including all necessary


adhesive materials, underlay and fixings,
complete

F Carpet flooring, 10mm thick, for voice room 3 m2

09900 - Painting

Emulsion paint including all necessary under


coats and preparation works, complete

G To plastered walls, internally 959 m2

H To gypsum board suspended ceilings 429 m2

J To bulkheads 39 m2

K To gypsum board partitions 32 m2


To Collection JD

Queen Rania Foundation - EDRAAK - 1/9/5 - Main Building


BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES (CONT'D)

09900 - Painting (cont'd)

Weather sheild paint including all necessary


preparation works, complete

A To plastered walls, externally, to elevations 1027 m2

B To parapet walls 263 m2

Epoxy coating, 2mm thick self levelling,


transparent including all necessary under coats
and preparation works, complete

C To floors, ref. FF1 406 m2

Green paint coated with transparent matt


acrylic paint, including all necessary
preparation works, complete

D To wood floors, for studio 56 m2

E To wood cladding, for studio 100 m2

To Collection JD
Queen Rania Foundation - EDRAAK - 1/9/6 - Main Building
BILL NO. 1
DIVISION 9
FINISHES
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

Collection

Page No. 1/9/1

Page No. 1/9/2

Page No. 1/9/3

Page No. 1/9/4

Page No. 1/9/5

Page No. 1/9/6

Total Bill No. 1 - Division 9 - Finishes To Summary JD

Queen Rania Foundation - EDRAAK - 1/9/7 - Main Building


DIVISION 10

SPECIALTIES
BILL NO. 1
DIVISION 10 - SPECIALTIES

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SPECIALTIES

10110 - Visual Display Units

Tackboard "cork", including all necessary


fixings, fittings, accessories and decoration
works, complete

A To plastered walls 52 m2

B To gypsum board partitions 13 m2

Markerboard "white color" including all


necessary fixings, fittings, accessories and
decoration works, complete

C To plastered walls 55 m2

Chalkboard "Black color", including all


necessary fixings, fittings, accessories and
decoration works, complete

D To plastered walls 23 m2

10162 - Toilet Compartments

Hard laminated toilet compartments,


including all necessary doors, handles,
hardware, accessories, fixings and fittings,
complete

E Toilet compartment, comprising 3No. Units,


2No. divider panels, size 1500mm long x
2200mm high, 1No. front panel, size 3000mm
long x 2200mm high including 3 No. doors, type
D9 1 No.

F Ditto, comprising 2No. Units, 1No. divider panel,


size 1500mm long x 2200mm high, 1No. front
panel, size 2030mm long x 2200mm high
including 2 No. doors, type D9 1 No.

Total Bill No. 1 / Division 10 - Specialties To Summary JD

Queen Rania Foundation - EDRAAK - 1/10/1 - Main Building


DIVISION 14

CONVEYING SYSTEM
BILL NO. 1
DIVISION 14 - CONVEYING SYSTEM

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

CONVEYING SYSTEM

14200 - Elevators

Passenger elevator including all necessary


controllers, car and landing doors, internal
car finish, mirror, handrail, assemblies,
automatic push button control
system,landing controls alarms, interior
design works, control panels, suspension
system, complete as shown in drawings and
technical specifications

A Passenger elevator, shaft size 3200x 2300mm,


3 stops, 3 floors, travel distance approximate
13660mm 1 No.

Total Bill No. 1 / Division 14 - Conveying


System To Summary JD

Queen Rania Foundation - EDRAAK - 1/14/1 - Main Building


DIVISION 15

MECHANICAL WORKS
BILL NO. 1
DIVISION 15 - MECHANICAL WORKS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS

DRAINAGE, VENT AND RAIN WATER SYSTEM

UPVC pipes, 10 bar, including all necessary civil


works, fixings, fittings and connections,
complete

A 50mm diameter 15 m

B 80mm diameter 27 m

C 110mm diameter 48 m

UPVC pipes, 16 bar, including all necessary civil


works, fixings, fittings and connections,
complete

D 80mm diameter 5 m

UPVC perforated pipes, including all necessary


civil works, fixings, fittings, accessories and
connections, complete

E 80mm diameter 7 m

UPVC Drainage Fittings and Outlets, complete

Floor Drain

F Floor drain, 80mm diameter 6 No.

Floor clean out

G 110mm diameter 3 No.

Clean Out

H 110mm diameter 1 No.

Rain water outlets

J 110mm diameter, roof drain 4 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/1 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

UPVC Drainage Fittings and Outlets, complete


(CONT'D)

Vent Cowl, complete

A 110mm diameter 2 No.

Sanitary Fixtures

Sanitary fixtures including mixers, complete

B Water closet 5 No.

C V.I.P water closet 1 No.

D Urinal 1 No.

E Wash basin 5 No.

F V.I.P. wash basin 1 No.

G Sink (single bowl) 1 No.

Pumps set, including all necessary fixings,


fittings, accessories, valves, flexible hose,
strainers, control panel, electrical and
mechanical connections, complete

H Submersible pumps set, ref. SP-01, 0.1 L/S at 10m


head, one No. duty and 1 No. standby 1 Set

To Collection JD
Queen Rania Foundation - EDRAAK - 1/15/2 - Main Building
BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

Cold and Hot Water Installation

PPR cold and hot water pipes including all


necessary fittings, valves and connections,
complete

A Cold water pipes, 25mm diameter 87 m

B Ditto, 32mm diameter 57 m

C Ditto, 40mm diameter 7 m

D Ditto, 50mm diameter 16 m

E Ditto, 63mm diameter 21 m

PEX pipes, including sleeves, fittings,


accessories, complete as shown on drawings

F 16mm diameter 115 m

G 20mm diameter 20 m

Nozzels and irregation system for green wall


planter, including valves, fixings and
accessories, complete

H Green wall nozzels 1 Item

Hose Bib

J Hose bib, 20m diameter 4 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/3 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

Cold and Hot Water Installation (cont'd)

Water cabinets including all necessary


collectors, fixings, fittings, valves, civil works,
accessories and connections, complete

A Ref. WC-C1, 7 No. cold water outlet and 3 No. hot


water outlet 1 No.

B Ditto, ref. WC-02, 7 No. cold water outlet and 4 No.


hot water outlet 1 No.

Electrical water heater including all necessary


fixing, accessories, valves, thermostats, flexible
hose, suspension system, fittings, mechanical
and electrical connections, complete

C Ref. EWH1, 50 litre capacity 2 No.

Domestic cold water pumps including all


necessary fixings, fittings, strainer, pressure
switch, dry run protection, accessories, control
panels, electrical and mechanical connections,
complete

D Ref. CWP-01, 100 litre capacity, 1 No. duty and 1


No. standby 1 Set

Plastic water tank including all necessary steel


base, fixings, fittings and connections, complete

E Plastic water tank, 2m3 capacity 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/4 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

Fire Fighting System

Fire extinguisher, complete

A Fire extinguisher, 6kg capacity 1 No.

FM200 System

FM-200 fire extinuishing system comprising


FM200 cylinder 15kg capacity, control panel,
valves, FM200 nozzels and pipeworks, smoke
detectors, warning plate with alarm horn, visual
indicator flashing red light discharge lamp,
manual abort station, multi-tone horn with
strobe, emergency release unit, complete

B For server room 9m2 "approximate area" 1 Item

HVAC Control Installation

VRF outdoor units, cooling and heating including

all necessary fixings, fittings, accessories,

mechanical and electrical connections, complete

C Ref. VRF-OU-01 3 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/5 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

HVAC Control Installation (cont'd)

Concealed type ducted indoor units, cooling and


heating, including all necessary fixings, fitttings,
accessories, liquid and gas pipes, insualtion
materials, mechanical and electrical
connections, complete

A Ref. IU-01, 450 L/S 1 No.

B Ref. IU-02, 300 L/S 1 No.

C Ref. IU-03, 300 L/S 1 No.

D Ref. IU-04, 300 L/S 1 No.

E Ref. IU-05, 210 L/S 1 No.

F Ref. IU-06, 450 L/S 1 No.

G Ref. IU-07, 300 L/S 1 No.

H Ref. IU-08, 450 L/S 1 No.

J Ref. IU-09, 450 L/S 1 No.

K Ref. IU-10, 525 L/S 1 No.

L Ref. IU-11, 570 L/S 1 No.

M Ref. IU-12, 130 L/S 1 No.

N Ref. IU-13, 450 L/S 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/6 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

HVAC Control Installation (cont'd)

Split unit, including all necessary fixings,


fittings, accessories, mechanical and electrical
connections, complete

A Ref. SU-1 and OU-01 1 No.

Condensate drain (CPVC) pipes including all


necessary fittings, connections and valves,
complete

B 50mm diameter 102 m

Exhaust and dirty extract fans, complete

C Ref. EXF-01, 205 L/S in line type 1 No.

D Ref. EXF-02, 250 L/S 1 No.

E Ref. EXF-03, 85 L/S 1 No.

F Ref. EXF-04, 50 L/S 1 No.

Fresh Air fans including floating base, complete

G Ref. FAF-01, 225 L/S 1 No.

H Ref. FAF-02, 155 L/S 1 No.

J Ref. FAF-03, 160 L/S 1 No.

K Ref. FAF-04, 60 L/S 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/7 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

HVAC Control Installation (cont'd)

Gravity shutters, including all necessary fixings,


complete

A Gravity shutter, ref. GS.1, 205 L/S 1 No.

B Ditto, ref. GS-2, 250 L/S 1 No.

C Ditto, ref. GS-3, 185 L/S 1 No.

Duct Works

Galvanized steel sheet ducts, complete

D Supply air ducts 535 kg

E Fresh air ducts 252 kg

F Exhaust air ducts 93 kg

Flexible ducts including connections and fixings,


complete

G To suit duct, size 250x150mm 6 m

H Ditto, size 200x200mm 5 m

J Ditto, size 250x200mm 10 m

K Ditto, size 250x250mm 5 m

L Ditto, size 300x150mm 1 m

M Ditto, size 350x250mm 11 m

N Ditto, size 300x200mm 3 m

P Ditto, size 400x200mm 4 m

Q Ditto, size 450x250mm 7 m

R Ditto, size 500x250mm 2 m

S Ditto, size 600x260mm 1 m

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/8 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

Duct Insulation

Fiber glass thermal insulation, complete

A To square or rectangular supply air ducts 105 m2

Air Terminals

Exhaust (return grilles) including all necessary


fixings, fittings, accessories and frames,
complete

B To suit duct, size 150x150mm 9 m

C Ditto, to suit duct, size 200x150mm 10 m

Exhaust grilles including all necessary fixings,

fittings, accessories and frames, complete

D Type EG-1, 35 L/S, size 150x150mm 7 No.

E Ditto, type EG-2, 205 L/S, size 300x300mm 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/9 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

HVAC Control Installation (Cont'd)

Air Terminals (cont'd)

Supply linear ceiling diffusers, including all


necessary fixings, fittings, accessories and
frame, complete

A SLD, 1500mm length, 125 L/S, 3 slot 1 No.

B Ditto, 1600mm length, 160 L/S, 3 slot 1 No.

C Ditto, 2200mm length, 200 L/S, 3 slot 1 No.

D Ditto, 2400mm length, 210 L/S, 3 slot 2 No.

E Ditto, 2400mm length, 200 L/S, 3 slot 1 No.

F Ditto, 2400mm length, 215 L/S, 3 slot 3 No.

G Ditto, 3200mm length, 300 L/S, 3 slot 3 No.

H Ditto, 3800mm length, 450 L/S, 3 slot 2 No.

J Ditto, 4500mm length, 420 L/S, 3 slot 2 No.

K Ditto, 4500mm length, 450 L/S, 3 slot 2 No.

L Ditto, 7000mm length, 650 L/S, 3 slot 1 No.

Fresh air sand louver including all necessary


fixings, fittings, accessories and frames,
complete

M Ref. FAL-01, size 600x400mm, 225 L/S 1 No.

N Ref. FAL-02, size 500x350mm, 160 L/S 1 No.

P Ref. FAL-03, size 410x350mm, 85 L/S 1 No.

Q Ref. FAL-04, size 410x300mm 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/10 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MECHANICAL WORKS (CONT'D)

HVAC Control Installation (Cont'd)

Air Terminals (cont'd)

Return linear ceiling diffusers, including all


necessary fixings, fittings, accessories and
frame, complete

Return linear diffuser, 1500mm length, 125 L/S, 3


A
slot 1 No.

B Ditto, 1600mm length, 160 L/S, 3 slot 1 No.

C Ditto, 2400mm length, 200 L/S, 3 slot 1 No.

D Ditto, 2400mm length, 215 L/S, 3 slot 3 No.

E Ditto, 2200mm length, 200 L/S, 3 slot 1 No.

F Ditto, 3200mm length, 300 L/S, 3 slot 3 No.

G Ditto, 3400mm length, 425 L/S, 4 slot 2 No.

H Ditto, 4500mm length, 420 L/S, 3 slot 2 No.

J Ditto, 7000mm length, 650 L/S, 3 slot 1 No.

Volume dampers to fit the following duct sizes

including all necessary fixings, complete

K Size 150x100mm 2 No.

L Size 150x150mm 2 No.

M Size 200x100mm 3 No.

N Size 200x150mm 3 No.

P Size 250x100mm 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/15/11 - Main Building


BILL NO. 1
DIVISION 15
MECHANICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/15/1

Page No. 1/15/2

Page No. 1/15/3

Page No. 1/15/4

Page No. 1/15/5

Page No. 1/15/6

Page No. 1/15/7

Page No. 1/15/8

Page No. 1/15/9

Page No. 1/15/10

Page No. 1/15/11

Total Bill No. 1 - Division 15 - Mechanical Works


To Summary JD

Queen Rania Foundation - EDRAAK - 1/15/12 - Main Building


DIVISION 16

ELECTRICAL WORKS
BILL NO. 1
DIVISION 16 - ELECTRICAL WORKS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS

Uninterruptable power supply unit, (UPS)


including all necessary sealed lead acid
battery, battery charger, inverter, wiring,
cables, transfer switch and manual, by-bass
switch, complete

A Ref. UPS, 30 KVA 1 No.

Main, Sub main and secondary Distribution


Boards

Main, sub main and secondary distribution


boards including all necessary ACB, MCCB's,
KWH meters, MCBS isolating switch,
busbars, circuit breakers, current
transformer "where shown", coupling units,
casing, cable clamps, meters,
microprocessor board metering, earthing and
protection equipment, complete

Sub-Main Distribution Boards

B Ref. SMDB 1 No.

Secondary distribution boards including all


necessary MCCB'S, MCB's, bus bars,
coupling units, casing, cable clamps,
earthing and protection equipment, separate
enclosure, complete

C Ref. DB 1 No.

D Ref. DB-G1 1 No.

E Ref. DB-DG2 1 No.

F Ref. DB-DG-U 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/1 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Main Circuits

Feeders, conductors and cables including all


necessary under ground trenches, PVC
ducts, supports, brackets, conduits, sleeves,
cable trays, cable trunks, warning tape,
luges, glands, cable terminals, terminations
and connections, complete

Cable, 600/1000 volt multi core copper cables


/PVC conductor

A Cable, size 4x25mm2 + 1x16mm2 XLPE/PVC


from SMDB to VRV isolating switch 13 m

B Ditto, size 4x16mm2 + 1x16mm2 XLPE/PVC


from SMDB to DG1 15 m

C Ditto, size 4x10mm2 + 1x10mm2 XLPE/PVC


from SMDB to DG2 15 m

D Ditto, size 4x16mm2 + 1x16mm2 XLPE/PVC


from SMDB to DG-U 29 m

E Ditto, size 4x6mm2 + 1x6mm2 XLPE/PVC from


SMDB to lift isolating switch 35 m

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/2 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Equipment Points Installation

Isolating switch points including all


necessary conduits, cables, wires, junction
boxes, connections, terminations to
equipment and accessories, complete

A Points for isolating switches, single phase, SPN,


20A IP-54 2 No.

B Ditto, single phase, SPN, 20A, in weather proof


enclosure 5 No.

C Ditto, single phase, SPN, 13A, in weather proof


enclosure, with indication lamp for VRF, indoor
unit 13 No.

D Ditto, single phase, SPN, 20A, in weather proof


enclosure, for cold water pump 1 No.

E Ditto, single phase, SPN, 20A, in weather proof


enclosure, for outdoor split unit 1 No.

F Ditto, three phase, TPN, 60A, for UPS 1 No.

G Ditto, three phase, TPN, 30A, in weather proof


enclosure, for lift isolating switch 1 No.

H Ditto, three phase, TPN, 80A, in weather proof


enclosure, for VRV-OU-1 1 No.

J Ditto, single phase, SPN, 20A, in weather proof


enclosure, for SP-01 1 No.

K Ditto, single phase SPN, 20A, IP-54 in


weatherproof enclosure for indoor split unit 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/3 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Equipment Points Installation (cont'd)

Isolating switches including all necessary


covers, fixings, fittings and ancillaries,
complete

A Isolating switch, single phase, SPN, 20A, IP-54 2 No.

B Ditto, single phase, SPN, 20A, in weather proof


enclosure, IP-54 5 No.

C Ditto, single phase, SPN, 13A, in weather proof


enclosure, with indication lamp 13 No.

D Ditto, single phase, SPN, 20A, IP-54, in weather


proof enclosure, for indoor split unit 1 No.

E Ditto, three phase, TPN, 60A, for UPS 1 No.

F Ditto, three phase, TPN, 30A, in weatherproof


enclosure, for lift isolating switch 1 No.

G Ditto, three phase, TPN, 80A, in weatherproof


enclosure, for VRV-OU-1 1 No.

H Ditto, single phase, SPN, 20A, in weather proof


enclosure, for SP-01 1 No.

J Ditto, single phase, SPN, 20A, in weatherproof


enclosure for cold water pump 1 No.

K Ditto, single phase SPN, 20A, in weatherproof


enclosure for outdoor split unit 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/4 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Power Installation

Socket outlet points including all necessary

conduits, trunks, wires, cables, pull and

junction boxes and connections, complete

A Points, for 13A, single socket outlet wall


mounted duplex receptacle switched type 83 No.

B
Ditto, for 13A, single socket outlet connected to
UPS, switched type with indication lamp
50 No.

C Ditto, for wall mounted single phase, single


receptacle, 13A, switched type 22 No.

D Ditto, for single phase, single receptacle, 13A,


connected to UPS, switch type, with indication
lamp 3 No.

E Ditto, for single phase, single receptacle, 13A,


connected to UPS, switch type, with indication
lamp, weatherproof type 1 No.

F Ditto, for single phase, duplex receptacle


connected to UPS, switch type, with indication
lamp 8 No.

G Ditto, for single phase, single receptacle floor


mounted 13A, switched type connecting to
dimming system 5 No.

H Ditto, for 13A, single phase, duplex receptacle


connected to UPS, switch type, with indication
lamp 2 No.

J Ditto, for single phase, socket outlet industrial


type, 16A, with earthing pole 1 No.

K Ditto, for single phase, single receptacle 13A,


switch type weather proof with indication lamp
for VRF indoor unit 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/5 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Power Installation (Cont'd)

Socket outlet points including all necessary


conduits, trunks, wires, cables, pull and
junction boxes and connections, complete
(Cont'd):-

A Points, for single phase, duplex receptacle 13A,


switched waterproof type 1 No.

B Ditto, for single phase wall mounted, single


receptacle 13A, switched type, waterproof 1 No.

C Ditto, for single phase floor mounted, single


receptacle 13A, switched for floor lamp
connected to dimming system 2 No.

D
Ditto, for suspended ceiling single phase, single
receptacle on ceiling trunk for studio equipment
24 No.

E Ditto, for switched spur outlet, flush mounted in


wall 4 No.

F Ceiling mounted outlets for projector lift 2 No.

G Electrical connection for motorized curtains 3 No.

H Ditto, for motorized screen 2 No.

J Ditto, for camera 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/6 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Power Installation (Cont'd)

Sundries

A Three compartments floor box 1 No.

B Four compartments floor box 3 No.

Socket outlets including all necessary


covers, boxes and ancillaries, complete

C 13A, single socket outlet wall mounted duplex


receptacle, switched type 83 No.

D Single socket outlet wall type duplex receptacle


switched type, connected to UPS with indication
lamp 50 No.

E Ditto, wall mounted single phase, single


receptacle 13A, switched type 22 No.

F Ditto, single phase, single receptacle, 13A,


connected to UPS, switched type, with indication
lamp 3 No.

G Ditto, weather proof 1 No.

H Single phase, duplex receptacle connected to


UPS, switch type, with indication lamp 8 No.

J Single phase, single receptacle floor mounted


13A, switched type connecting to dimming
system 5 No.

K
13A, single phase, duplex receptacle connected
to UPS, switch type, with indication lamp
2 No.

L Single phase, socket outlet industrial type, 16A,


with earthing pole 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/7 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Power Installation (Cont'd)

Sundries (Cont'd)

Socket outlets including all necessary


covers, boxes and ancillaries, complete
(C t'd)
A Single phase, single receptacle 13A, switch type
weather proof with indication lamp for VRF
indoor unit 1 No.

B Single phase, duplex receptacle 13A, switched


waterproof type 1 No.

C Single phase wall mounted, single receptacle


13A, switched type, waterproof 1 No.

D Single phase floor mounted, single receptacle


13A, switched for floor lamp connected to
dimming system 2 No.

E
Suspended ceiling single phase, single
receptacle on ceiling trunk for studio equipment
24 No.

F Switched spur outlet, flush mounted in wall 4 No.

G Ceiling mounted outlet for projector lift 2 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/8 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Power Installation (Cont'd)

Power points including all necessary


conduits, boxes, cables, wires, covers,
ancillaries, connections and terminations,
complete

A Points for exhaust air fan 4 No.

B Ditto, fresh air fan 4 No.

C Ditto, electrical water heater 2 No.

Power switches including all necessary


covers, boxes, switches and ancillaries,
complete

D 10A, wall / ceiling mounted double pole switch


with fan symbol 8 No.

E 16A, double pole switch with pilot lamp for E-


water heater 2 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/9 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils
ELECTRICAL WORKS (CONT'D)
Lighting Installation

Lighting points including all necessary


conduits, conductors, cables, wires, junction
and pull boxes, connections, accessories and
fittings, complete

A Lighting points, generally 129 No.

B Ditto, for indirect light 16 No.

Lighting switch points including all


necessary conduits, cables, wires, junction
and pull boxes, connections, fittings and
accessories, complete

C 10A, one gang, one way switch points 11 No.

D 10A, two gang, two way switch points 2 No.

E 10A, two gang, one way switch points 6 No.

F Dimmer switch points 2 No.

G 10A, one gang, two way switch points 4 No.

H Grid switch point, ref. GS-A 2 No.

J Grid switch point, ref. GS-B 1 No.

Lighting switches including all necessary


covers, boxes and ancillaries, complete

K 10A, one gang, one way switch 11 No.

L 10A, two gang, two way switch 2 No.

M 10A, two gang, one way switch 6 No.

N Dimmer switch 2 No.

P 10A, one gang, two way switches 4 No.

Q Grid switch, ref. GS-A 2 No.

R Grid switch, ref. GS-B 1 No.


To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/10 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Lighting Installation (cont'd)

Lighting Fixtures

Lighting fixtures including all necessary


starters, transformer, ballast, control gear,
lamps, lamp holders, diffusers, internal wires,
suspension system, supports, clamps,
conduits, connections, terminations, fixings,
fittings and accessories, complete

A Type L1, 13W, recessed led neutral white


lighting fixture with power supply, IP-43, as
IGUZZINI code M260 3 No.

B Type L1, with emergency kit 3 No.

C Type L2, 13W, recessed led neutral white


lighting fixture with power supply, IP-20, as
IGUZZINI code M260 13 No.

D Ditto, type EL2, with emergency kit 2 No.

E Lighting fixtures type L3, 21W, ceiling mounted


led neutral white lighting fixture with electronic
control gear, IP20, as IGUZZINI code M010 13 No.

F Ditto, with emergency kit 3 No.

G Type L4, 38W, recessed led warm white lighting


fixture with electronic control gear, IP-20, as
IGUZZINI code MT19 45 No.

H Ditto, with emergency kit 10 No.

J Type L5, 38W, recessed led warm white lighting


fixture with electronic control gear, IP-20, as
IGUZZINI code MT11 9 No.

K Ditto, with emergency kit, type EL5 5 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/11 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Lighting Installation (cont'd)

Lighting Fixtures (cont'd)

Lighting fixtures including all necessary


starters, transformer, ballast, control gear,
lamps, lamp holders, diffusers, internal wires,
suspension system, supports, clamps,
conduits, connections, terminations, fixings,
fittings and accessories, complete (cont'd)

A Type L6, led strip light 4000K, 10W/M, IP20 60 m

B Type L7, led strip light 6000K, 10W/M, IP20, as


IGUZZINI code MT97 135 m

C Type L8, 20W, recessed led neutral white


lighting fixture with power supply, IP-20, as
IGUZZINI code M262 2 No.

D Ditto, with emergency kit 4 No.

E Type G1, 1W, wall mounted led emergency


lighting fixture, 3 hours, duration led lamp, IP-42 3 No.

F Type G2, 1W, ceiling mounted led emergency


lighting fixture, 3 hours, duration led lamp, with
double sided exit sign, IP-42 4 No.

G Type D, 18W, wall mounted compact flourescent


lighting fixture with electronic control gear, IP-66,
as IGUZZINI code 8699 3 No.

H Ditto, type B5 2 No.

J Type X5, small projector flood light 2 No.

K Type X6, wall mounted light (general) 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/12 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Lighting Installation (cont'd)

Lighting Fixtures (cont'd)

Lighting switch panels (LSP) including all


necessary contactor, relays, push battons,
selector switches, indication lamps,
conduits, cables, wires, connections,
terminations, fixings, fittings and
accessories, complete

A Ref. LSP 1 No.

SMATV System

Television outlet points including all


necessary wires, conduits, boxes, cables,
junction boxes and connection to relevant
boxes / TV outlet, complete for:

B TV outlet points 5 No.

TV socket outlets including all necessary


covers, connections, terminations and
fixings, complete

C Wall mounted TV socket outlets 5 No.

TV Satellite including all necessary cables,

conduits, boxes and fixings, complete

D (Nile sat satellite) 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/13 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Telephone & Data System

Telephone and data outlet points including all


necessary conduits, trunks, wires, cables,
pull and junction boxes and connections,
complete

A Points for telephone outlets, (RJ11) 56 No.

B Ditto, inside floor box 4 No.

C Ditto, data outlets, (RJ45) 66 No.

D Ditto, inside (floor box) 4 No.

E Ditto, wall mounted dual type data outlet 8 No.

F Ditto, ceiling mounted data outlet for projector 4 No.

G Wireless access point 4 No.

Telephone and data socket outlets including


all necessary covers, connections,
terminations and accessories, complete

H Telephone outlets, (RJ11) 56 No.

J Ditto, inside floor box 4 No.

K Data outlets, (RJ45) 66 No.

L Ditto, inside (floor box) 4 No.

M Wall mounted dual type data socket outlets 8 No.

N Ceiling mounted data outlet for projector 4 No.

Data cabinet including all necessary fixings,

fittings, accessories, conduits, cables, wires,

connections and terminations, complete

P Data cabinet 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/14 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

CCTV System

CCTV devices including all necessary


conduits, wires, cables, boxes, connections,
terminations, fixings, covers, fittings and
suspension system, complete

A Fixed camera, indoor type 1 No.

B Ditto, outdoor type, weather proof 1 No.

CCTV-Rack comprising switch board, 1x16


channel network DVR for the building 14"
monitor screen computer including all
necessary fixings, fittings, accessories,
conduits, wires, cables, connections and
terminations, complete

C CCTV-Rack 1 No.

Access Door Control System

Access door control equipment and devices


including all necessary conduits, boxes,
wires, cables, outlets, connections, junction
box, covers, accessories, fixings and fitting,
complete

D Card reader (CR) 5 No.

E Time attendance panel (card/finger print reader) 1 No.

F Request to exit (REX) 4 No.

G Magnetic contact 5 No.

H Electric lock 5 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/15 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Fire Alarm System

Fire alarm control panel with voice


evacuation and two way fire main telephone
system, including indication lamps, rest
button, switches, battery charger, back-up
batteries, 50 watt amplifiers, accessories,
connections, cables, wires, interface,
emergency power supply (230V, 50HZ), VAC,
conduits and terminations, complete

A Fire alarm control panel, ref. FACP1, 4 zone 1 No.

Fire alarm points including all necessary


conduits, pull and junction boxes, cables,
wires, connections and terminations,
complete

B Smoke detectors points 31 No.

C Fire alarm manual pull station with sounder


stopper cover points 3 No.

D Fire alarm audio / visual points 3 No.

E Monitor module points 1 No.

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/16 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Item Description Quantity Unit Rate Amount
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Fire Alarm System (Cont'd)

Fire alarm devices including all necessary


accessories, covers, fixings and fittings,
complete

A Smoke detectors 31 No.

B Fire alarm manual pull station with sounder


stopper cover 3 No.

C Fire alarm audio / visual 3 No.

D Monitor module 1 No.

E End of line resistance point 3 No.

Earthing System

Earthing system for electrical systems


including all conductors, copper bars/tape,
tap-clamps, main copper bus bar inside
enclosure panel, inspection manhole and all
other accessories necessary needed to get
less than (2) ohm, including main conductor
connected between earthing network to main
earth bus bar and from main bus bar to all
electrical systems, including all civil works,
end bonding of all exposed conductive parts
and extreneous conductive parts, complete

F Earthing for electrical installations 1 Item

G Earthing for low current installations 1 Item

H Earthing for mechanical equipment 1 Item

To Collection JD

Queen Rania Foundation - EDRAAK - 1/16/17 - Main Building


BILL NO. 1
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page No. 1/16/1

Page No. 1/16/2

Page No. 1/16/3

Page No. 1/16/4

Page No. 1/16/5

Page No. 1/16/6

Page No. 1/16/7

Page No. 1/16/8

Page No. 1/16/9

Page No. 1/16/10

Page No. 1/16/11

Page No. 1/16/12

Page No. 1/16/13

Page No. 1/16/14

Page No. 1/16/15

Page No. 1/16/16

Page No. 1/16/17

Total Bill No. 1 - Division 16 - Electrical Works


To Summary JD

Queen Rania Foundation - EDRAAK - 1/16/18 - Main Building


SUMMARY 1
Queen Rania Foundation-EDRAAK
BILL NO. 1 - MAIN BUILDING
SUMMARY 1

Div. Description Quantity Unit Rate Amount


No. JD/Fils JD/Fils

SUMMARY 1

2 Siteworks

3 Concrete

4 Masonry

5 Metals

6 Wood And Plastic

7 Thermal and Moisture Protection

8 Doors and Windows

9 Finishes

10 Specialties

14 Conveying System

15 Mechanical Works

16 Electrical Works

Total Carried to General Summary JD

- S1 -
BILL NO. 2

EXTERNAL WORKS
DIVISION 2

SITEWORKS
BILL NO. 2
DIVISION 2 - SITEWORKS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SITEWORKS

02223-Backfilling

Filling

Compacted subbase course "Gravelly Soil" fill


materials, CBR > 80, including all necessary
compaction, complete

A Subbase, 150mm thick 69 m3

Compacted basecourse "crushed stone" fill


materials, CBR > 80, including all necessary
cpmpaction, complete

B Basecourse, 150mm thick 69 m3

Marle basecourse fill materials, including all


necessary compaction, complete

C Basecourse, 100mm thick 1 m3

02517-Interlocking Concrete Pavers

Interlocking floor tiles on and including


sandfill materials, cement and sand mortar
bed, cutting, jointing and cleaning, complete

D Interlocking tiles, size 100 x 100mm, gray color 458 m2

02521-Precast Concrete Units

Curbstone including excavation works,


backfilling, blinding base, cement and sand
mortar bed and backing, cutting, jointing,
pointing, painting and cleaning, complete

E Curbstone, with chamfered edges, 150mm wide x


250mm high, curved on plan, dark color 167 m

Total Bill No. 2 / Division 2 - Siteworks To Summary JD

Queen Rania Foundation -EDRAAK - 2/2/1 - External Works


DIVISION 3

CONCRETE
BILL NO. 2
DIVISION 3 - CONCRETE

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

CONCRETE

03346-Concrete Floor Finishing

Cast-in-place stamped concrete floors, white


finish, including all necessary preparation
works, complete

A Stamped concrete floor, 50mm thick 107 m2

Total Bill No. 2 / Division 3 - Concrete To Summary JD

Queen Rania Foundation-EDRAAK

-2/3/1 - - Extrnal Works


DIVISION 4

MASONRY
BILL NO. 2
DIVISION 4 - MASONRY

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

MASONRY

04100-Mortar
04220-Concrete Masonry Units

Hollow concrete blockworks (1:4) including


concrete lintels, jambs, heads, sills, stiffener
columns, bond beams, mortar bed, jointing
and all necessary accessories and cutting,
complete

A Walls, 200mm thick, ( projecting screen wall) 15 m2

04450-Natural Stone Works

First quality, Karaki stone walls, including


cement and sand mortar bed and backing,
plain concrete backing, special stones such as
heads, jambs, sills, external and internal
angels, grooves, weather shield sealant,
jointing and pointing, complete

B To boundary walls, 500mm course height 38 m2

First quality, stone walls "to match existing",


including cement and sand mortar bed and
backing, plain concrete backing, special
stones such as heads, jambs, sills, external
and internal angels, grooves, weather shield
sealant, jointing and pointing, complete

C To existing main boundary walls 4 m2

Total Bill No. 2 / Division 4 - Masonry To Summary JD

Queen Rania Foundation-EDRAAK - 2/4/1 - External Works


DIVISION 5

METALS
BILL NO. 2
DIVISION 5 - METALS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

METALS

05500-Miscellenous Metal Fabrication

5mm thick galvanized steel edge, including all


necessary fixings, fittings and accessories,
complete

A Galvanized steel edge, 210mm wide 9 m

Painted steel metal fence, gray color, including


all necessary fixings, fittings, accessories and
painting, complete

B Painted steel metal fence, size 1640mm long x


2090mm high, to boundary walls 1 No.

C Ditto, size 3080mm long x 1790mm high, to


boundary walls 1 No.

Total Bill No. 2 / Division 5 - Metals To Summary JD

Queen Rania Foundation-EDRAAK - 2/5/1 - External Works


DIVISION 6

WOOD AND PLASTIC


BILL NO. 2
DIVISION 6 - WOOD AND PLASTIC

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

WOOD AND PLASTIC

06400-Architectural Wood Work

Composite wooden bench, including all


necessary fixings, fittings, accessories,
painting and decoration works, complete

A Wooden bench, size 9930mm long x 410mm wide


x 480mm high 1 No.

B Ditto, size 10200mm long x 600mm wide x


480mm high 1 No.

Total Bill No. 2 / Division 6 - Wood And plastic


To Summary JD

Queen Rania Foundation-EDRAAK - 2/6/1 - External Works


DIVISION 8

DOORS AND WINDOWS


BILL NO. 2
DIVISION 8 - DOORS AND WINDOWS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

DOORS AND WINDOWS

08110-Steel doors
08111-Standard steel doors

Painted steel gates, gray color, including all


necessay fixings, fittings, accessories and
hardware, complete

A Painted steel gate, size 2230mm long x 2370mm


high 1 No.

B Ditto, size 4390mm long x 1770mm high 1 No.

Total Bill No. 2 / Division 8 - Doors and


Windows To Summary JD

Queen Rania Foundation-EDRAAK - 2/8/1 - External Works


DIVISION 9

FINISHES
BILL NO. 2
DIVISION 9 - FINISHES

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

FINISHES

09220-Portland Cement Plaster

20mm thick, cement and sand plastering


including all necessary plaster stops,
grooving, angle beads and wire mesh,
complete

A To block and concrete walls, externally, to


projecting screen wall 30 m2

09570- Wood Flooring

Hard wood weather treated flooring,


including all necessary fixings, fittings, 120 x
100 x 50mm IRON U-profile fixation,
accessories and decoration works, complete

B To floors, size 100 x 30mm 137 m2

09610-Stone Flooring

First quality, Karaki stone flooring tiles on


and including cement and sand mortar bed,
sand fill materials, pointing and cleaning,
complete

C To floors, 100mm thick 5 m2

D Strip, 100mm wide x 100mm thick 101 m

09900-Painting

Weather sheild paint, "white color" including


all necessary preparation works and under
coats, complete

E To projecting screen block walls 30 m2

Two coats, epoxy paint, including all


necessary preparation works and under
coats, complete

F To original fence, 1700mm high 8 m

Total Bill No. 2 / Division 9 - Finishes To Summary JD

Queen Rania Foundation-EDRAAK - 2/9/1 - External Works


DIVISION 10

SPECIALTIES
BILL NO. 2
DIVISION 10 - SPECIALTIES

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

SPECIALTIES

10440-Signs

Alucobond signs, extruded, including all


necessary fixings, fittings and accessories,
complete

A Project sign, "overall" size 3400mm long x


1400mm high x 50mm thick 1 No.

Total Bill No. 2 / Division 10 - Specialties To Summary JD

Queen Rania Foundation-EDRAAK - 2/10/1 - External Works


DIVISION 16

ELECTRICAL WORKS
BILL NO. 2
DIVISION 16 - ELECTRICAL WORKS

Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS

KWHM

Kilo watt hour meter including all necessary


connections, complete

A KWHM 1 No.

Main Circuits

Feeders, conductors and cables including all


necessary excavation, back filling, warning
tape, protection block, ….. etc. underground
trenches, ducts, supports, brackets,
conduits, sleeves, luges, glands, cable
terminals, termination and connections,
complete

Cable, 600/1000 volt multi core copper cables


/PVC conductor

B Cable, size 4x95mm2 + 1x50mm2,


XLPE/SWA/PVC from existing MDB to SMDB 90 m

Equipment Points Installation

Isolating switch point including all necessary


conduits, cables, wires, junction boxes,
connections, terminations to equipment and
accessories, complete

C Point for isolating switch, single phase (SPN) for


main gate 2 No.

Isolating switches including all necessary


covers, junction boxes, fixing, fittings and
ancillaries, complete

D Isolating switch, single phase, weatherproof for


main gate 2 No.

To Collection JD

Queen Rania Foundation-EDRAAK -2/16/1 - External Works


BILL NO. 4
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Lighting Installation

Lighting points including all necessary


conduits, conductors, cables, wires, junction
and pull boxes, connections, accessories and
fittings, complete

A Lighting points 43 No.

Grid switch panel including all necessary


conduits, cables, wires, junction and pull
boxes, connections, fittings and accessories,
complete

B Ref. G.S-C 1 No.

Lighting Fixtures

Lighting fixtures including all necessary


starters, transformer, ballast, control gear,
lamps, lamp holders, diffusers, internal wires,
suspension system, supports, clamps,
conduits, connections, terminations, fixings,
fittings and accessories, complete

C Type X1, hanging light fixture (on tree) 6 No.

D Type X2, floor embedded up-light spot light 11 No.

E Type X3, one meter tall bollard light 8 No.

F Type X4, large projector flood light 9 No.

G Type X5, small projector (flood light) 3 No.

H Type X6, wall mounted light (general) 1 No.

J Type X7, 5 meter tall reflected lighting column 4 No.

K Type X8, hidden linear uplight 1 No.

To Collection JD

Queen Rania Foundation-EDRAAK -2/16/2 - External Works


BILL NO. 4
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

ELECTRICAL WORKS (CONT'D)

Lighting Installation (cont'd)

CCTV System

CCTV devices including all necessary


conduits, wires, cables, boxes, connections,
terminations, fixings, covers, fittings and
suspension system, complete

A Fixed zoom camera, outdoor, weatherproof 3 No.

Sundries

Power manholes, including all necessary


earthworks, reinforced concrete floors, walls
and slabs, finishings, waterproofing, steel
ladder, heavy duty steel cover, complete as
shwon on drawings and per specifications

B Power manhole, size 600x600x600mm deep 4 No.

To Collection JD

Queen Rania Foundation-EDRAAK -2/16/3 - External Works


BILL NO. 4
DIVISION 16
ELECTRICAL
WORKS
Rate Amount
Item Description Quantity Unit
JD/Fils JD/Fils

COLLECTION

Page 2/16/1

Page 2/16/2

Page 2/16/3

Total Bill No. 2 - Division 16 - Electrical Works


To Summary 2 JD

Queen Rania Foundation-EDRAAK -2/16/4 - External Works


SUMMARY 2
Queen Rania Foundation-EDRAAK
BILL NO. 2 - EXTERNAL WORKS
SUMMARY 2

Div. Description Quantity Unit Rate Amount


No. JD/Fils JD/Fils

SUMMARY 2

2 Siteworks

3 Concrete

4 Masonry

5 Metals

6 Wood And Plastic

8 Doors and Windows

9 Finishes

10 Specialties

16 Electrical Works

Total Carried to General Summary JD

- S2 -
GENERAL SUMMARY
Queen Rania Foundation-EDRAAK
GENERAL SUMMARY

BILL Description Quantity Unit Rate Amount


No. JD/Fils JD/Fils

GENERAL SUMMARY

* Preliminaries

1 Main Building

2 External Works

Total Carried to Form of Tender JD

- GS -

You might also like