TARGET SCHEDULE FOR CONCRETING

IN-SITU for TRESTLE --> Completion target 29 November 2019

2019
GROUP SCOPE SEPTEMBER OKTOBER NOVEMBER
22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WAHYUTO in-situ trestle


line 33-32 line 32-31 line 31-30 line 30-29 line 29-28 line 28-27 line 27-26 line 26-25

GM in-situ trestle
line 2-3 line 1-2 line 13-14 line 14-15 line 15-16 line 16-17 line 24-25 line 25-26

Tatang MM in-situ trestle


line 10-11 line 11-12 line 12-13 line 17-18 line 18-19 line 19-20 line 20-21 line 21-22

Rasmin in-situ trestle


line 3-4 line 5-6 line 6-7 line 7-8 line 8-9 line 9-10 line 22-23 line 23-24

33 29 26 24 22 17 13 10 3 1
WM WM GM RM MM GM MM RM GM

LAYDOWN AREA
(CONSTRUCTION JETTY)
PC SLAB --> none

PC SLAB --> full target finish 4 Okt 2019 PC SLAB --> full

DIAPHRAGM --> none


33 30 23 1
target finish 28 Sep 2019

28 26

MAN POWER
TAHAP I TAHAP II
MAN POWER
MANDOR SCOPE
ACTIVE INACTIVE TOTAL NEW ADD

GM IN-SITU TRESTLE
21 29 50 20
DIPHRAGMA
OFFSHORE TRESTLE 2nd Stage OFFSHORE TRESTLE 1st Stage ONSHORE TRESTLE CAUSEWAY
(LINE 76 - 128) (LINE 34 - 75) (LINE 1 - 33)
RASMIN IN-SITU TRESTLE
60 25 85 15
RM PRECAST SLAB JETTY
WHARF (JETTY)

TATANG IN-SITU TRESTLE


48 17 65 15
MM PRECAST SLAB TRESTLE

WAHYUTO IN-SITU TRESTLE


55 15 70 30
WM PRECAST BEAM JETTY

TOTAL MAN SEA WATER INTAKE


184 86 270 80