Professional Documents
Culture Documents
Authors:
Capstone Mining Corp.
Prepared by:
Gregg Bush, P.Eng.
Amec Foster Wheeler Environment &
Infrastructure Inc.
Tony J. Freiman, PE
Kirkham Geosystems Ltd
Capstone Mining Corp. Garth Kirkham, PGeo., FGC
Suite 2100 – 510 W Georgia Street KWM Consulting Inc
Vancouver, British Columbia, V6B 0M3 Ken Major, P.Eng.
Canada Independent Mining Consultants, Inc.
John Marek, PE, SME-RM
SRK Consulting (U.S.), Inc.
Corolla Hoag, CPG, SME-RM
Date and Signature Page
The effective date of the Pinto Valley Mine PV3 Prefeasibility Study for Pinto Valley Mine in Miami,
Arizona, is 1 January 2016.
Prepared by:
Tony J. Freiman, PE
The qualified person for the mineral reserve is John Marek of IMC. John Marek did not audit or verify the
block model or the statement of mineral resources. Scientific and technical information about the
mineral reserves is based on forward-looking information. Metal price assumptions, resource modelling
assumptions, factors applied and risks are explained in the relevant sections of this report. Changes in
these could impact the mineral reserve in a positive or negative way.
1.11 Environment
PVM has well-established environmental, health/industrial hygiene, and safety procedures and
protocols. These procedures adhere to federal and state requirements and to internal Capstone
guidance to reduce impacts to the environment and to provide a safe work environment for employees
and contractors. Numerous site characterization studies have been completed at PVM to support
operations, environmental permitting efforts, closure planning, and other investigations. PVM is subject
to health and safety regulations under the supervision of the Mine Safety and Health Administration
(MSHA), Arizona State Mine Inspector’s Office (ASMIO), Arizona Department of Transportation, and
other federal and state agencies. Capstone is committed to its employees and to the communities in
which it works to operate under high standards of corporate safety, environmental and social
responsibility. PVM has established relationships with the local communities and stakeholders;
communication channels are in place for direct interaction with stakeholders as required.
1.13 Permitting
The major authorizations permitting and governing operations for PVM include an APP, Air Quality
Permit, Arizona Pollutant Discharge Elimination System (AZPDES) Individual permit, and Multi-Sector
General Permit (MSGP) for storm water discharge all issued by ADEQ, a MLRP approved by ASMIO, and a
Plan of Operations (POO) approved by the USFS.
1.17 Recommendations
Key recommendations have been noted below:
Actual vs predicted ore reconciliations should be carefully evaluated in the short and medium
term to determine if additional drilling is required.
Ensuring the recommended pit slope angles are achieved is one of the primary keys to success
of this plan. This is to be accomplished through ongoing geotechnical mapping and monitoring
the effectiveness of slope depressurization. Drilling programs may be required to increase
confidence levels of predictions.
Continue efforts to improve operating efficiency of all equipment.
An evaluation of bottlenecks limiting production above 56,000 tonnes per day.
Monitor phreatic levels in the tailings storage facilities to ensure they are within design
standards.
Initiate environmental analyses and the permitting process in 2016.
4.1 Location
This property is located at the west end of the Globe-Miami mining district, approximately 11 miles west
of Globe and 80 miles east of Phoenix, Arizona, at 33°23′32″ N and 110°58′15″ W (Figure 4-1).
Figure 4-1: Pinto Valley Mine Location Map (Google Maps, 2015)
4.4 Permitting
All required permits for current operation to 2026 have been obtained and are current except for the
USFS consolidated Plan of Operations, which is in the process of being amended. New permits are
required to extend the operation to 2039. Refer to Section 20 – Environmental Studies, Permitting, and
Social or Community Impact for detailed permit information, including a list of required permits. The
current key environmental items required to extend operations to 2039 are a modified:
Expansion Plan of Operations, and
Aquifer Protection Permit (APP) to permit the increased waste rock storage, a new waste rock
storage and expanded tailings facilities.
4.5 Royalties
There are 30 unpatented lode claims located outside of the PVM property boundary that have a 2% net
smelter return (NSR) royalty. The proposed mine plan does not impact those claims, and as such, no
royalty payments are expected.
geology.com 2014
Figure 5-1: Pinto Valley Mine Location
5.4 Physiography
PVM is located in east-central Arizona, in the structural transition zone between the Sonoran section of
the Basin and Range physiographic province to the south-southwest and the Colorado Plateau to the
north. The terrain surrounding the mine property is generally mountainous, dominated by sharp
landforms and prolific exposures of a variety of bedrock formations present in the region.
PVM lies entirely along the eastern flank of Pinto Creek, with numerous southwest-trending to
northwest-trending ephemeral Pinto Creek tributaries crossing the property. Most of the headwaters of
these tributaries originate along a regional surface water divide that runs north to south near the
eastern PVM property line. All surface water runoff from the site ultimately flows into Pinto Creek, just
west of the boundary of the property. Pinto Creek flows from the south to the north into Roosevelt
Lake, an artificial impoundment constructed along the Salt River.
PVM is near the boundary of areas mapped as the Interior Chaparral biotic community and the Arizona
Upland subdivision of Sonoran desert scrub biotic community.
BHP 2012
Figure 7-1: Pinto Valley Mine Geology Plan
7.1.11 Alluvium
Tertiary and Quaternary alluvium is a poly-lithologic detritus of some boulder-sized, but mostly cobble-
and more finely sized, poorly sorted and poorly cemented sediments. Detritus lines the low-lying areas,
commonly occurring at the base of steep slopes undergoing active erosion. Components often show
evidence of reworking, resedimentation, and welding by modern calcrete and silcrete cements.
Based on the E- and AD-Series results, the total relative sampling standard deviation for the split core
samples above 0.1% TCu is estimated to be approximately 8%; 86% of the sampling variance is due to
core splitting and sample preparation errors, and 14% is due to analytical variance within the PVM lab.
Instrumentation errors associated with the QA/QC analytical process are responsible for approximately
0.5% of the total variance. The relative bias of approximately 2.5% between PVM and Skyline is the
result of an absolute bias of −2.7% between Skyline and the international standard; these results are
summarized in Table 11-2.
The sampling and preparation errors of the RC samples could not be fully determined due to a lack of
field duplicates. Field sampling of RC cuttings are generally associated with lower variances than
sampling of drill core, which can offset the higher laboratory variances measured for the 1996 and 1997
programs. The analytical bias seen in these samples, corrected for the Skyline bias, is estimated to be
4% lower than the international standards.
The PVM QA/QC procedures have been based on leading practices as defined by BHP and used
throughout BHP's group of assets. These have been developed in conjunction with other BHP base
metal mines. These processes continue to be utilized on-site, to the best of the authors’ knowledge.
Prior to the 2010 through 2013 drilling campaigns, there is limited information with respect to the
molybdenum analyses and QA/QC. Charts shows the respective laboratory; Skyline and ALS Global,
results of the analyses for the field (Figure 11-4 and Figure 11-5), coarse (Figure 11-6 and Figure 11-7)
and pulp (Figure 11-8) duplicates. The molybdenum QA/QC illustrate that quality control measures used
at both laboratories are variable and that there is a relatively high failure rate for all analyses methods.
As there are no reference sample analyses (ie. Standards), it is difficult to ascertain whether the cause of
the issues and lack of analytical precision originate at PVM or at Skyline and ALS Global however with
both laboratories experiencing similar failure rates.
A total of 183 field duplicates were submitted for analysis with a scatterplot of the results shown in
Figure 11-9 and Figure 11-10. Warning and error lines are set at respective 15% and 20% limits with
regard to the relative difference between duplicate pair assays. Returned TCu analyses show that 23
1.0
0.9
0.8
0.7
Check
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-9: Scatterplots showing Field Duplicates for %TCu for 2015 Drilling
0.022
0.020
0.018
0.016
0.014
Check
0.012
0.010
0.008
0.006
0.004
0.002
0.000
0.000 0.001 0.002 0.003 0.004 0.005 0.006 0.007 0.008 0.009 0.010 0.011 0.012 0.013 0.014 0.015 0.016 0.017 0.018 0.019 0.020 0.021 0.022 0.023 0.024
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-10: Scatterplots showing Field Duplicates for %Mo for 2015 Drilling
SKYLINE
CuT_MEA_pct : Check Stage C
0.6
0.4
Check
0.2
0.0
0.0 0.2 0.4 0.6
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-11: Scatterplots Coarse Duplicates for %TCu for 2015 Drilling
0.013
0.012
0.011
0.010
0.009
0.008
Check
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0.000
0.000 0.001 0.002 0.003 0.004 0.005 0.006 0.007 0.008 0.009 0.010 0.011 0.012 0.013
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-12: Scatterplots Coarse Duplicates for %Mo for 2015 Drilling
SKYLINE
CuT_MEA_pct : Check Stage P
0.6
0.4
Check
0.2
0.0
0.0 0.2 0.4 0.6
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-13: Scatterplots Pulp Duplicates for %TCu for 2015 Drilling
0.011
0.010
0.009
0.008
0.007
Check
0.006
0.005
0.004
0.003
0.002
0.001
0.000
0.000 0.001 0.002 0.003 0.004 0.005 0.006 0.007 0.008 0.009 0.010 0.011
Original
X=Y Warning Error RMA Regression Threshold Normal Warning Error
Figure 11-14: Scatterplots Coarse Duplicates for %Mo for 2015 Drilling
In the QP’s opinion, the sample preparation, analysis QA/QC and security protocols follow accepted
industry standards. Based on the data and results, it is the authors opinion that the complied database
is valid and of sufficient quality to be used for this mineral resource estimate.
13.1.1 Grinding
Bond ball work index tests and/or modified Bond work index tests were competed on drill core samples
for the PV2 Project. Figure 13-1 provides an analysis of the Bond ball mill work index data. Table 13-1 is
an indication of the lithological ore distributions expected in the mine plan included in this report.
The predominant ore type has been identified as Ruin Granite and the data indicates that the work
index is distributed over a narrow range from 13.5 kWh/t to 15.5 kWh/t. Further analysis completed by
BHP indicated based on the location within the pit that there may be an opportunity to split the Ruin
Granite into “soft” and “hard” classifications.
13.1.2 Flotation
In October 2006 BHP completed a review of past metallurgical testwork. The compilation was made of
all test work that was conducted in the plant lab between 1992 and 1995, and of which the reports were
located in the PVM library. Figure 13-3 summarizes the grade-recovery relationship for rougher
flotation.
The model that was developed predicted a copper cleaner recovery of 93.34% which reduced the overall
copper recovery to 85%. The historical cleaner recovery at Pinto Valley was indicated in one of the
reviewed reports to be about 97.3%. Typical porphyry copper cleaners operate above the 97.3% level
and the model provided in Table 13-3 could be predicting lower recoveries than are achieved in the
plant.
The analysis of the FLEET cleaner flotation model indicates that the copper recovery peaks at a mill feed
grade of about 0.50% Cu. Based on this inversion and declining cleaner flotation recovery with
increasing grade the application of the fixed cleaner recovery to the model appears to provide a more
realistic expectation for the cleaner flotation circuit.
The sample, collected from the ball mill feed in January 2014 and forwarded to ALS in Kamloops, British
Columbia, was prepared for use in a preliminary metallurgical test program. The focus of the program
was to evaluate the rougher flotation recovery based on flotation feed size and flotation time. Figure
13-8 presents the results from the testwork for the copper and the moly recovery to the rougher
flotation concentrate.
The testwork was completed at different grinds. The initial tests were based on 8 minutes rougher
flotation time. The results of the initial tests indicated that the copper and moly recoveries and the
mass pull to the rougher concentrate decreased as the flotation feed became coarser. The decrease
appeared to become more significant as the flotation feed K80 approached 300 microns. Based on the
results of the preliminary tests the K80 300µ and K80 364µ flotation tests were repeated with the lab
flotation times extended to 20 minutes. The extended flotation times showed improved recoveries but
time did not achieve the same recoveries.
The grind / flotation time / recovery relationship has an impact on the throughput optimization of the
Pinto Valley process facilities.
Flotation testwork consisted of open circuit rougher flotation tests. The rougher testwork program was
followed by regrind and open circuit cleaner flotation testwork. The rougher flotation testwork was
consistent for most of the samples tested, Table 13-6. The rougher recovery for the Eastern Pushback
Upper Level sample was the lowest and was 6% lower than the ROM sample.
Table 13-6: Rougher Flotation Recovery
Feed Recovery Lab
Ore Description
Grade 250u 300u
ROM 0.38 92.40 91.30
E.PB.LL. 0.29 87.20
E.PB.ML 0.30 89.20
E.PB.UL 0.32 85.00 84.00
N.PB.LL 0.29 90.10
N.PB.ML 0.26 87.60
Aplite 0.22 90.90
As a result of the rougher and open circuit cleaner flotation testwork 2 locked cycle flotation tests were
completed. One test was completed on a 50:50 composite of Eastern Pushback Lower and Mid Level
zones. The other test was completed on a 50:50 composite of the Northern Pushback Lower and Mid
Level zones. The locked cycle tests concluded with lower than expected concentrate grades (23%) and
overall copper recoveries of about 85% Cu. Visual observation indicated that there was a high load of
pyrite recovered to the copper concentrate. A brief microscopic examination of these concentrates
indicated that the pyrite and chalcopyrite minerals were liberated with the conclusion that higher grade
concentrates could be expected by modifying the reagent addition rates in the testwork.
The scope of this testwork program did not include reagent or testwork optimizations.
The results of the grinding testwork indicated that the ore types that will be expected in the pushbacks
will behave similarly to the range of ores currently being processed. In the 2014 43-101 Technical
Report the majority of the ore zones (Ruin Granite) tested in the Bond ball mill work index range of 13.5
to 15.5. A Diabase ore zone was identified that had higher work indexes ranging from 17.0 to 17.5. The
Eastern Pushback Upper Level ore tested in the recent program exhibited similar work index properties
Pinto Valley Mine Life Extension Study, February 2016 Page | 84
to diabase ore. When the drill core sample for the Eastern Push Back Upper Level was examined in
detail it was determined that diabase was included in the sample composite. Review of the mine plan
indicates that diabase makes up less than 1% of the ore body so processing will have to be managed to
ensure minimal impact on overall throughput and recovery.
The throughput model based on target grind size for the single stage ball mill circuit defined in the
Technical Report should be applicable for PV3 ore.
For PV2 the projected copper flotation recovery based on mill feed grade for the Pinto Valley ore was
represented by:
RCu = ((9.8864) x (%Cu) + 87.041) x 0.973))
In Table 13-7 the copper flotation recovery has been projected for each of the composites and
compared to the lab flotation results. Fitting the current testwork to this model indicated that the
testwork results were consistent with previous work and that the same recovery model can be applied
for most of the Pushback ore zones.
Table 13-7: Comparing Flotation Test Recovery to Projected Recovery
Recovery
Feed
Ore Description Lab Calculated
Grade
250u 300u Rougher Combined
ROM 0.38 92.40 91.30 90.80 88.35
E.PB.LL. 0.29 87.20 89.91 87.48
E.PB.ML 0.30 89.20 90.01 87.58
E.PB.UL 0.32 85.00 84.00 90.20 87.77
N.PB.LL 0.29 90.10 89.91 87.48
N.PB.ML 0.26 87.60 89.61 87.19
Aplite 0.22 90.90 89.22 86.81
As in the grinding testwork the Eastern Pushback Upper Zone ore is the anomaly with a significantly
lower recovery (-6.0%) than the ROM. The lower recovery is also consistent with previous observations
for Diabase ores.
13.3.1 Summary
The Pinto Valley operation has been making changes to the operating and maintenance procedures and
practices in the crushing and grinding circuits in order to identify opportunities to increase the plant
throughput. Operating data from the August 2015 through October 2015 operating period was
analyzed. This analysis of the key operating parameters indicated that:
Primary Crushing
o Coarser Product (measured by on-line digital camera)
o 34.9% -1” (vs 45.5%)
13.4.1 Crushing
Based on the various availabilities at the 0.47inch (12mm) product size the Bruno model indicates that
existing crusher facility is limited to:
68% availability = 48470 stpd
71% availability = 50610 stpd
75% availability = 53460 stpd
85% availability = 60282 stpd (54800 mtpd)
It should be noted that the Bruno model has used screens with different profiles than the screens
installed in order to attain throughputs similar to plant levels. The screens are a primary bottle neck in
increasing plant throughput.
The July 1, 2013 to January 7, 2014 crusher operating data collected by the mine was evaluated to
determine site measurement of the crusher plant capacity. Nominal throughput for each secondary
crusher circuit was estimated at about 1000 short tons per operating hour (2930tph combined).
13.4.2 Grinding
The Pinto Valley grinding circuit utilizes single stage ball mill grinding to prepare the product from the
fine crushing facility for flotation. To model the grinding circuit the focus has been to develop the model
using the Bond ball mill work index calculations and incorporating the correction factors. The variables
inputted to the Bond equation include: the Bond ball mill work index (metric); fine crushing plant
product size, F80; the grinding circuit product size, P80. When compared to the plant data for an ore
work index of 14.6 there was an indication that the grinding circuit throughput was about 10% higher
than projected by the work index model. The plant data was analyzed from 3 months of 2014
continuous operating activity. Table 13-8 projects the plant throughput, in short tons per hour, for a
range of work indexes from 13.5 to 16.5. The 10% model adjustment has been included.
Table 13-8: Production Model (2014)
Plant Adjustment (stpd) 62981 59445 56161 53107 50262 47610 45134
Plant Adjustment (mt/d) 57255 54041 51056 48279 45693 43282 41031
Pinto Valley Mine Life Extension Study, February 2016 Page | 86
Model Throughput (mt/d) 52050 49128 46414 43890 41539 39347 37301
Grinding Availability 95.0% 95.0% 95.0% 95.0% 95.0% 95.0% 95.0%
Plant Feed Rate (t/h) 2282.9 2154.8 2035.7 1925.0 1821.9 1725.7 1636.0
Feed Size, F80 (μm) 11000 11000 11000 11000 11000 11000 11000
Product Size, F80 (μm) 280 280 280 280 280 280 280
Ball Mill Work Index, Wi 13.5 14.0 14.5 15.0 15.5 16.0 16.5
Drive Losses 3% 3% 3% 3% 3% 3% 3%
Unit Power, kWh/t 7.84 8.31 8.79 9.30 9.83 10.37 10.94
Motor, kw available 17904 17904 17904 17904 17904 17904 17904
Motor, hp available 24000 24000 24000 24000 24000 24000 24000
Motor, hp installed 24000 24000 24000 24000 24000 24000 24000
Figure 13-10 provides a graph and linear equation for the interpretation of the model results for the
specific conditions of F80 = 11000µ and P80 =280µ. The model and representative equation will change
for varying feed and product conditions.
Table 13-9 is a projection of the grinding circuit throughput applying the 2015 measurements of circuit
operating parameters.
Table 13-9: Production Model (2015)
Plant Adjustment (stpd) 64836 61169 57766 54602 51658 48915 46357
Plant Adjustment (mt/d) 58942 55608 52514 49638 46962 44468 42142
Model Throughput (mt/d) 53583 50553 47740 45126 42693 40426 38311
Grinding Availability 95.6% 95.6% 95.6% 95.6% 95.6% 95.6% 95.6%
Plant Feed Rate (t/h) 2334.4 2204.4 2079.9 1966.0 1860.0 1761.2 1669.1
Feed Size, F80 (μm) 11760 11760 11760 11760 11760 11760 11760
Product Size, F80 (μm) 280 280 280 280 280 280 280
Ball Mill Work Index, Wi 13.5 14.0 14.5 15.0 15.5 16.0 16.5
13.4.3 Flotation
The metallurgical review indicated that modelling of the flotation recovery has not produced consistent
models. The PV2 project requires the push back of the open pit in multiple directions and the
expectations should be that the mill performance will be very similar to the existing mill. Figure 13-11 is
a representation of the FLEET simulated rougher flotation recovery for copper.
Pinto Valley Mine Life Extension Study, February 2016 Page | 100
Figure 14-11: Plan View of Mine and Gold Gulch Fault Block Grade Shell Models: ≥0.3%TCu (ore) in red;
<0.3%TCu and ≥0.1%TCu (low grade mineralization) in green; and <0.1%TCu (waste) in blue.
Pinto Valley Mine Life Extension Study, February 2016 Page | 101
Figure 14-12: Plan View of Mine and Gold Gulch Fault Block Grade Shell Model; ≥0.3%TCu (ore) in red;
<0.3%TCu and ≥0.1%TCu (low grade mineralization), Faults in grey.
Pinto Valley Mine Life Extension Study, February 2016 Page | 102
Figure 14-13: Plan View of Mine and Gold Gulch Fault Block Grade Shell Model showing ≥0.3%TCu (ore)
in red.
Pinto Valley Mine Life Extension Study, February 2016 Page | 103
Figure 14-14: Northwest-Southeast Cross-Section (A-A’) ≥0.3%TCu in red, <0.3%TCu and ≥0.1%TCu
Grade Shells in green.
Figure 14-15: Southwest-Northeast Cross-Section (B-B’) ≥0.3%TCu in red, <0.3%TCu and ≥0.1%TCu in
green.
Due to the issues encountered in and around the granodiorite unit, box plots were useful in analyzing
whether this unit could be treated independently of the other lithological units in the estimation
process. In addition, of potential concern was whether the diabase and aplite dikes would require
segregation as a separate set of domain classes during the estimation process. Box plots were run for
the various lithology units, as shown in Figure 14-15, which illustrates that the aplite dikes are very
similar in nature to the Ruin Granite, which are interpreted to crosscut horizontally. Therefore, the Ruin
Granite and the aplite dikes were grouped as a common domain for the estimation. Furthermore, the
diabase dikes are also very similar, as is the granite porphyry, so it was decided that creating subsets of
the lithologic units within the mineralized envelopes was not necessary. However, it is clear that the
granodiorite exhibits lower grade than the other units and should be treated separately particularly
Pinto Valley Mine Life Extension Study, February 2016 Page | 104
when considering that there have been issues during mining in and around the granodiorite. Table 14-3
lists the assay statistics which show each element within the mineralized solids.
14.3 Topography
The topography used is the current topographic surface as at December 31, 2015. Figure 14-17: Plan
View of Topographic Solid shows the topographic solid with the ‘reasonable prospects’ pit overlain in
plan view.
Pinto Valley Mine Life Extension Study, February 2016 Page | 105
Figure 14-17: Plan View of Topographic Solid
14.4 Composites
It was determined that a 45 ft composite length minimizes the smoothing of the grades, and also
reduces the influence of typically narrow, higher-grade samples. This falls into alignment with the 45 ft
bench height used for mine planning.
Figure 14-18 and Figure 14-19 show the box plots for copper and molybdenum within the mineralized
envelopes. The basic statistics shown in the figures indicate that the copper and molybdenum data are
reasonably distributed. Copper composites have a relatively low coefficient of variation while the CV for
the molybdenum composites is relatively high particularly within the >0.3% grade shell.
Pinto Valley Mine Life Extension Study, February 2016 Page | 106
Figure 14-18: Box Plot for Copper Composites by Zone
Pinto Valley Mine Life Extension Study, February 2016 Page | 107
Figure 14-19: Box Plot for Molybdenum Composites by Zone
Figure 14-20 through Figure 14-23 show contact plots copper and molybdenum within the 0.1% and
0.3% grade envelopes for copper. As expected, the copper values show a clear, abrupt transition at the
contact between the 0.1%–0.3% and the 0.3% TCu grade envelopes justifying a hard boundary. In
addition, the contact plots at the 0.1% boundary, also shows an abrupt transition and therefore also
justifies a hard boundary. However, the contact plot for molybdenum shows little, if any, transition
between the two grade envelopes. This shows that the molybdenum may be evaluated and
interpolated as one continuous mineralized domain.
Pinto Valley Mine Life Extension Study, February 2016 Page | 108
Figure 14-20: Contact Plots for Copper
Pinto Valley Mine Life Extension Study, February 2016 Page | 109
Figure 14-21: Contact Plots for Copper
Pinto Valley Mine Life Extension Study, February 2016 Page | 110
Figure 14-22: Contact Plots for Molybdenum
Pinto Valley Mine Life Extension Study, February 2016 Page | 111
Figure 14-23: Contact Plots for Molybdenum
14.5 Outliers
Cumulative frequency plots shown in Figure 14-24 and Figure 14-25 for %TCu and %Mo illustrate that at
1.6% TCu and 0.05% Mo, there is a break in the log normal plot. This represents 0.1% of the copper
composites and 0.4% of the molybdenum composites, which require implementation of a grade-limiting
strategy.
One is by physically cutting the grades of the assays or composites, and the other is by limiting the
influence that a high-grade sample has by limiting the distance to which it contributes to the grade of a
block estimate. In the case of the PVM deposit, the distance (radius) threshold chosen was 150 ft, which
equates to the adjacent, adjoining blocks and no farther.
Pinto Valley Mine Life Extension Study, February 2016 Page | 112
Figure 14-24: Cumulative Frequency Plot for %TCu
Pinto Valley Mine Life Extension Study, February 2016 Page | 113
14.7 Block Model Definition
The block model used is the same as that for the March 2014 mineral resources defined according to the
limits shown in Figure 14-26.
The block model is orthogonal and non-rotated, reflecting the orientation of the deposit. The chosen
block size was 100 ft × 100 ft × 45 ft to roughly reflect the available drillhole spacing and bench height
and to adequately represent the deposit with a representative amount of discrete points in three
dimensions. In addition, this was the selected SMU for past operations and for going forward.
Pinto Valley Mine Life Extension Study, February 2016 Page | 114
Range Y Range X Range Z Rotation Z Rotation X Rotation Y
Zone Metal C0 C1 C2
(ft) (ft) (ft) (deg) (deg) (deg)
0.1 –
668.4 2,240.6 1,108.1 -8 51 -20
0.3%
0.134 0.663 0.204 153.9 204.6 540.6 5 12 11
<0.1% %TCu
1,108.2 18,672.4 1,767.6 41 87 51
The estimation strategy for %TCU and %ASCu employed a four stage process. The grades for %TCU and
%ASCu are estimated using ordinary kriging within each of the respective grade shells separately and
stored. In addition, the grades are estimated within the granodiorite unit only using inverse distance to
the second power as there is insufficient data to derive meaningful variograms. The final %TCU and
%ASCu grades are then combined on a relative weighted basis using the partial as a percentage to do
the weighting.
The estimation plan includes the following:
• Store the mineralized zone code and percentage of mineralization.
• Estimate the grades for each of the metals within each of the mineralized grade shells using
ordinary kriging in a single pass.
• Estimate the grades for each of the metals within granodiorite unit using ID2 in a single pass.
• Include a minimum of 2 composites and a maximum of 16, with a maximum of 4 from any 1
drillhole.
• Combine the individual grades into a whole block diluted grade by weighting by the partials
stored as a percentage.
Pinto Valley Mine Life Extension Study, February 2016 Page | 115
The estimation of %Mo was performed using a single pass ordinary kriging run irrespective of grade shell
domain or lithology domain.
The amount of data available for estimating Ag, Au and Fe is limited and therefore estimating these
elements in the same manner would not result in any meaningful results.
Pinto Valley Mine Life Extension Study, February 2016 Page | 117
$3.30/lb Cu, $10.00/lb Mo, 88% Cu recovery, 50% Mo recovery, $1.50/ton mining costs, $1.50/ton G&A
costs, $5.00/ton milling costs, and a pit slope of 45°. The pit optimization results are used solely for the
purpose of testing the “reasonable prospects for eventual economic extraction” and do not represent an
attempt to estimate mineral reserves. The optimization results are used to assist with the preparation
of a mineral resource statement and to select and appropriate reporting assumptions.
It is important to note that the resources are reported below the most current topography at the
effective date which is the January 1, 2016 topographic surface as shown in Figure 1-17. In addition, the
method used for reporting the resources is by creating a solid between the 2016 topography and the
“reasonable prospects” pit and then reporting the volumes as a percentage of the partial blocks as
opposed to less accurate method of whole block reporting. Figure 14-27 shows a plan view of the %TCu
grades for blocks falling within the reasonable prospects pit.
Figure 14-27: Plan View of Block Model at Elevation 3050’ with TCu Grades
The mineral resources are listed in Table 14-8 for %TCu and %Mo.
The mineral resources were estimated by Kirkham Geosystems Ltd and are effective January 1, 2016.
The estimate includes results from drill programs conducted in 2015 and a revised geological model,
revised grade shell models and adjustments to the estimation strategy based on a better, current
understanding of the character of the deposit particularly at the boundaries.
Pinto Valley Mine Life Extension Study, February 2016 Page | 118
Table 14-8: Mineral Resources at 0.17% TCu Cutoff Grade1, 2 - Imperial
Contained
Imperial Copper Molybdenum Contained
Molybdenum
(MTons) (%) (%) Copper (M Lbs)
(M Lbs)
Measured (M) 714.2 0.34 0.008 4,843.4 118.6
Indicated (I) 851.3 0.26 0.006 4,387.8 105.6
Total M&I 1,565.5 0.30 0.007 9,231.5 224.1
Inferred 138.9 0.25 0.005 686.7 13.9
1. Mineral Resources are reported inclusive of Mineral Reserves.
2. Totals may not be exactly due to rounding.
3. The economic assumptions include the following: $3.30/lb Cu, $10.00/lb Mo, 88% Cu recovery, 50% Mo recovery,
$1.50/ton mining costs, $1.50/ton G&A costs, $5.00/ton milling costs, and a pit slope of 45°
Table 14-9: Mineral Resources at 0.17% TCu Cutoff Grade1, 2 (Metric Units)
Contained
Metric Copper Molybdenum Contained
Molybdenum
(M Tonnes) (%) (%) Copper (M Lbs)
(M Lbs)
Measured (M) 647.9 0.34 0.008 4,843.4 118.6
Indicated (I) 772.3 0.26 0.006 4,387.8 105.6
Total M&I 1,420.2 0.30 0.007 9,231.5 224.1
Inferred 126.0 0.25 0.005 686.7 13.9
1. Mineral Resources are reported inclusive of Mineral Reserves.
2. Totals may not be exactly due to rounding.
3. The economic assumptions include the following: $3.30/lb Cu, $10.00/lb Mo, 88% Cu recovery, 50% Mo recovery,
$1.50/ton mining costs, $1.50/ton G&A costs, $5.00/ton milling costs, and a pit slope of 45°
Mineral resources are not mineral reserves until they have demonstrated economic viability. Mineral
resource estimates do not account for a resource’s mineability, selectivity, mining loss, or dilution.
These estimates include Inferred mineral resources that are normally considered too geologically
speculative for the application of economic considerations; therefore, they are unable to be classified as
mineral reserves. Also, there is no certainty that these Inferred mineral resources may be converted
into Measured or Indicated resources as a result of future drilling or after applying economic
considerations.
Pinto Valley Mine Life Extension Study, February 2016 Page | 119
A full set of cross sections, long sections, and plans were used to check the block model visually,
showing the block grades and the composite. There was no evidence that any blocks were wrongly
estimated. It appears that every block grade can be explained as a function of the following:
• Surrounding Composites
• Correlogram Models Used
• Estimation Plan Applied
Pinto Valley Mine Life Extension Study, February 2016 Page | 120
15 Mineral Reserve Estimates
The mineral reserve was developed by IMC and is the total of all proven and probable category material
planned for processing from the mine plan. Development of the final open pit design and mineral
reserve was based on the best economic limit. There were no limits or constraints incorporated from
the current operating permit at Pinto Valley. The qualified person for the mineral reserves is John
Marek, President of IMC.
The mineral reserve at PVM is based on industry standard mine planning practices than are applied at
similar open pit mines. The floating cone algorithm combined with practical phase designs and trials of
alternative mine production schedules were used to set the mine plan and production schedule. The
mineral reserve is the total of all material planned for processing within the mine production schedule.
Early in the development of this mine plan, IMC designed a series of preliminary phases or push backs
that initially targeted a floating cone that was based on a copper price of $2.75/lb. Additional
expansions beyond that price were also developed using metal prices as high as $3.50/lb copper.
Mine schedules were developed that progressively added pushbacks to the mine life. The impact of
each additional pushback on the mine plan was evaluated economically.
When complete, the schedule analysis did not support the production of all material that was within the
$2.75/lb floating cone. Two pushbacks (east and north walls) were proven to be economic. The west
and southwest pushbacks did not contribute to the overall project economics on a time value of money
basis because of their high strip ratios and the time required to release the ore at depth. The east and
north walls of the floating $2.75 cone were used as the guide to develop the final PV3 pushback
sequence for this study.
Table 15-1: Base Case Floating Cone Input – Pinto Valley Project
Cone Input Item Cost or Recovery
Mining Cost Inputs to Cones
Direct Mine Operating Cost $1.60/tonne
Haulage Cost Increment per Bench $0.041/tonne /bench depth above/below 4040 bench
Average Total Mining Cost With Haul Increment $2.05/tonne
Bench Discounting 1%/bench of depth below the 4895 bench
Process Costs for Mill Operation
General and Administrative Cost $1.52/tonne
Milling Cost $5.14/tonne
Flotation Process Recovery - Copper
All Except Diabase Recovery (%) = ((Cu Grade × 9.8864) + 87.041) × 0.973
Diabase Recovery (%) = ((Cu Grade × 9.8864) + 82.041) × 0.973
Molybdenum Recovery 45%
Concentrate Transport Costs
International Transport $ 116.04/dry tonne
Domestic Transport $ 14.95/dry tonne
Total Transport $ 130.99/dry tonne
Treatment and Refining Costs for Copper
Moisture Content of Copper Concentrate 9%
Copper Concentrate Grade 27.50%
Copper Smelting Recovery 96%
Copper Smelting Cost $90/dry tonne
Pinto Valley Mine Life Extension Study, February 2016 Page | 122
Copper Refining Cost $0.090 (refining cost/lb recovered Cu)
Total Cost /lb recovered Cu $0.4326 (SMRF cost/lb recovered Cu – net credits)
Treatment and Refining Costs for Molybdenum
Molybdenum Payable from Roaster 97%
Molybdenum Roasting Costs $1.50/lb recovered Mo
Molybdenum Concentrate Moisture Content 4.50%
Molybdenum Concentrate Grade 48.00%
Net Transport and Roasting Cost for Molybdenum $1.50 (cost/lb recovered Mo)
Metal Prices for Base Case
Copper Price $2.75/lb Cu
Molybdenum Price $12.50/lb Mo
Slope Angles, SRK Recommendations Floating Cone Slope (IRA Angles/OSA Angles)
Pinal Schist in Gold Gulch/West End Fault Zone 27°/27° OSA Used for Floating Cone
Pinal Schist Shear 27°/24°
South wall Unit Pinal Schist 27°
West wall Post Mineral Group, West Wall Shear 32°/30°
East wall Post Mineral Group 48°/42°
West wall Diabase / Limestone 42°
East wall Diabase/Limestone 48°/42°
Northwest Pit Bottom Corner [1] 45°
Ruin Granite, All walls 48°/42°
Bummer Fault Zone (0-120, 160-360) 42°
Bummer Fault Zone (120-160) 36°
Granodiorite in Gold Gulch/West End Shear Zone 28°
East wall Granodiorite 46°/40°
Granite Porphyry, All [1] 34°
Diabase in Gold Gulch/West End Shear Zone 32°/30°
Waste Rock, All 32°/27°
[1] Slope Angle Modifications during Late 2015 based on operational experience and guidance by CNI.
Pinto Valley Mine Life Extension Study, February 2016 Page | 123
Figure 15-1: Floating Cone at $2.75/lb Copper, Used as Guidance for Phase Design Blue Line is the Patented Claim Boundary
Pinto Valley Mine Life Extension Study, February 2016 Page | 124
Figure 15-2: Final Pit Design for Mineral Reserve
Pinto Valley Mine Life Extension Study, February 2016 Page | 125
15.2 Statement of Mineral Reserve
The mineral reserve was developed by tabulating the contained measured and indicated (proven and
probable) material inside of the designed pit at the mill cutoff grades. The mineral reserve is based on
the PV mine schedule in Table 16-3. The schedule utilizes a declining cutoff grade to improve the
project return on investment. The initial cutoff grades are 0.18/0.19% TCu in 2016/2017 which reduce
to internal cutoff grade (0.17% TCu) in 2023. During 2029 to 2032, the cutoff is again elevated to
maintain a consistent head grade.
PVM has operated a run-of-mine (ROM) dump leach on low-grade sulfide ores for many years. This
study assumes that leaching will cease after 2018 due to waste rock storage requirements. The final pit
design and the mineral reserve have not included the ROM dump leach in the floating cone analysis or in
the mineral reserve. Material that is incurred at ROM leach grade is treated as waste. It is not
incorporated into the statement of mineral reserves on Table 15-2. Table 15-2 summarizes the mineral
reserves at PVM remaining after 1 January 2016.
The mineral reserves and the mining plan are based on an in-place tonnage factor of 2.513 tonnes/m3
(12.75 ft3/short ton).
The qualified person for the estimation of the mineral reserve is John Marek of Independent Mining
Consultants, Inc. John Marek did not audit or verify the block model or the statement of mineral
resources. The Pinto Valley block model was transferred to IMC during December 2015. The installation
and tabulation of the model was confirmed in conjunction with Mr. Kirkham and the Pinto Valley mine
planning department.
Changes to the resource model could impact the mineral reserve in a positive or negative way. Changes
could occur due to improved interpretation and/or additional drilling and sampling in the Pinto Valley
district.
Metal price changes could materially change the estimated mineral reserves in either a positive or
negative way. Pit wall instability could impact the remaining reserves in a negative way depending on
the time and area of occurrence. Capstone and their geotechnical contractors have addressed pit wall
stability.
Table 15-2: Mineral Reserves, Remaining After 1 January 2016 (metric)
Cutoff Mineral Reserve Contained Metal
Class
%TCu M tonnes %Tcu %Mo Cu M Lbs Mo M Lbs
Proven 0.18-0.17 350.1 0.33 0.009 2,550.3 71.8
Probable 0.18-0.17 123.7 0.25 0.007 691.2 20.1
Proven and Probable 0.18-0.17 473.8 0.31 0.009 3,241.5 91.9
Tonnes are in metric tonnes of 1000 kg
Moly is molybdenum metal
Base metal prices USD$2.75/lb and USD$12.50/lb Moly
Pinto Valley Mine Life Extension Study, February 2016 Page | 126
16 Mining Methods
PVM is an open-pit hard-rock mine, producing copper bearing sulfide ore to a conventional milling and
flotation concentrator. Conventional open-pit mining utilizes the cycle of drilling, blasting, loading, and
hauling of material to the respective destinations. Ore is hauled to the primary crusher for processing,
low-grade material is hauled to low-grade stockpiles and stored for later processing, and waste rock
material is hauled to waste storage facilities. Mining is accomplished on 45 ft benches. The qualified
person for this section is John Marek of IMC.
This prefeasibility study incorporates a moderate mill throughput increase in addition to extending the
mine life beyond 2026 to 2038. The current mill capacity of 54,000 tonnes per day (19,760 ktonnes/yr)
will be expanded to 56,000 tonnes per day (20,440 ktonnes/yr) beginning in 2017. The mine production
schedule was developed with the goal of maintaining mill feed and maximizing the project return on
investment.
The mine plan is scheduled to move 116,400 tpd (42,480 ktonnes/yr) of total material during 2016 and
123,100 tpd (44,900 ktonnes/yr) in 2017. Beginning in 2018, the mine will ramp-up to the total tonnage
movement of 132,900 tpd (48,500 ktonnes/yr) until ore is exposed in the final mine phase in 2031.
From then on, the total material movement reduces to slightly more than the ore rate.
The mine plans presented in this section were developed by Independent Mining Consultants, Inc.,
(IMC), based upon the block model of the deposit that was developed and provided by G. Kirkham. The
model blocks are 100 by 100 ft on plan with 45 ft bench heights.
The mining plan is reported in Metric units. One tonne is a metric tonne of 1,000 kilograms, equivalent
to 2204.62 lbs. Ktonnes means 1,000 tonnes. Metal grades are in percent by weight.
Pinto Valley Mine Life Extension Study, February 2016 Page | 127
IMC has designed three pushbacks that expand the pit beyond 2026 that further develop the pit to the
east and north.
In total, there are seven phase designs that were used as input to the development of the PVM
schedule. The mining phases are a combination of work completed by Pinto Valley engineering staff and
IMC. The phase designs in order of extraction are:
PV1_v2c Designed by PV Engineering Staff, PV1 (current pit bottom)
PV2 _v2c_ECD Designed by PV Engineering Staff, East Castle Dome
PV2_v2c_JH Designed by PV Engineering Staff, Jewel Hill
PV2_v2c_WCD Designed by PV Engineering Staff, West Castle Dome
East Phase Designed by IMC for PV3
North Phase No. 1 Designed by IMC for PV3
North Phase No. 2 Designed by IMC for PV3
Phase PV1_v2c reflects the current operation in the bottom of the Pinto Valley mine to be completed in
year 2018. Jewel Hill is an eastern pushback that was designed to continue the operation through year
2022. The Jewel Hill phase has been sub-phased by PVM Engineering to enable development in the
Castle Dome area to the south to proceed ahead of the Jewel Hill eastern portion.
The location of the phase designs, particularly Jewel Hill, East, and North are illustrated on Figure 16-1.
Inter-ramp slope angles for the phase design are summarized in the next subsection. The overall and
inter-ramp slopes were reviewed and recommended by geotechnical contractor SRK Consulting (SRK).
In addition to slope angles, the following road and pushback geometries complete the mine design
parameters:
Haul Road Width: 115-ft
Haul Road Grade: 10% Maximum
Minimum Width Between Pushbacks: 300-ft Nominal
The tonnage and grade at multiple cutoff grades were tabulated from the designed phases on a bench-
by-bench basis. Those tabulations were used as input to the development of the mine production
schedule.
Pinto Valley Mine Life Extension Study, February 2016 Page | 128
Figure 16-1: Location of Phase Designs on the 3860 Bench
Pinto Valley Mine Life Extension Study, February 2016 Page | 129
Mining of slopes in the Pinal schist is not planned in the design. For reference, slopes in the Pinal Schist
have a history of displacement and are at limit equilibrium Factor-of-Safety = 1.0. PVM has safely
maintained operational activities with displacing slopes using a range of mitigating controls based on
observation and a slope monitoring program.
Slope depressurization is recommended for operational considerations and is required
for stability of the Whitetail conglomerate and the granodiorite in the west wall.
The recommended slope angle in each domain of the pit is the flattest angle produced
by the catch bench, inter-ramp, or overall slope analyses.
The recommended inter-ramp slope angles for design of the phases is summarized on Table 16-1.
Table 16-1: Inter-ramp Slope Angles, from SRK Consulting
Single Bench Double Bench
Sector
45 ft Height 90 ft Height
Ruin Granite - 48
Whitetail Southwest 35 -
Whitetail Northeast 48
West Wall Shear Zone 28-32 -
Diabase 42 48 East Wall
Pinal Schist 27 -
Pinal Schist Shear Zone 24 -
Granodiorite 40 48 Lt 200 ft high
Limestone West 40 West Wall 48 East Wall-
Historic Waste Dumps 32 -
In addition, a Granite Porphyry unit was intersected in the southeast section of the pit that was
originally interpreted as part of the Granodiorite. The Granite Porphyry has recently been interpreted
separately with an inter-ramp slope angle of 34 degrees. In addition to the southeast corner of the pit,
The Granite Porphyry also impacts a portion of the northeast wall in the PV3 East pushback.
Pinto Valley Mine Life Extension Study, February 2016 Page | 130
Figure 16-2: Pit Slope Design Sectors Map
Pinto Valley Mine Life Extension Study, February 2016 Page | 131
16.3 Mine Production Schedule
Pinto Valley mill production is currently planned at 54,000 tpd for 2016. The mill production rate is
planned to increase to 56,000 tpd for 2017 and all future years. The mine production schedule was
developed to release and deliver the required ore to the mill and maximize the project return on
investment.
The total material production rates in the mine were selected after the development of several
alternative schedules which compared alternatives of mining equipment loading capacity. For example,
if an additional shovel was purchased, the mine could move more waste. A higher waste rate would
allow for a higher cutoff grade and a corresponding higher head grade to the mill. The capital cost of
that shovel and the operating cost of moving more material were compared to the benefit of producing
higher grade ore on a time value of money basis.
The alternative schedules and equipment tradeoff evaluations were completed with input from the PVM
engineering and operations department to confirm the production capacity of the equipment being
considered. The best economic schedule resulted using the current equipment fleet without adding any
new or larger units.
At this time, PVM operates the following loading equipment:
2, Hitachi EX5600 hydraulic front shovels with 29.1 cubic meters (38 cubic yard) buckets
2, Cat 994 front end loader equipped with 17.2 cubic meter (22.5 cubic yard) buckets.
Productivity of the two shovels will be somewhat limited during 2016 due to some narrow geometries in
the bottom of the current pit. Those conditions will be improved during 2016 and 2017 so that the
shovels will achieve more efficient productivity by 2018. IMC and PVM established the following total
material movement schedule based on the production capacities of the two shovels assisted by a 994
Front Loader.
2016: 42,480 k tonnes/year = 116,384 tonnes/day
2017: 44,900 k tonnes/year = 123,014 tonnes/day
2018: 48,500 k tonnes/year = 132,877 tonnes/day
48,500 k tonnes/year is maintained until release of ore from the final pushback in year 2032
On average, one operating 994 will contribute about 13% of the loading capacity from 2018 onward.
Prior to that time, the two 994s will contribute up to 25% of the required loading capacity.
PVM is currently operating, the PV3 mine plan and schedule is a continuation and extension of the
current operation. Some road pioneering will be required to begin the development of the Jewel Hill
and East Phase of the pit.
Cutoff grades were established to maximize the project NPV for the selected equipment capacity and
total material rate. The cutoff grade for the mine schedules are based on total copper cutoff grades.
The mill feed cutoff grade changes over time, from 0.19%-0.18% TCu during 2016 through 2022 reducing
to 0.17% TCu in 2023. During 2029 through 2032, the cutoff is increased to values between 0.18% and
0.22% TCu to improve head grade and the project time value economics.
Pinto Valley Mine Life Extension Study, February 2016 Page | 132
During periods when the mill cutoff is above 0.18%, material with grade between the mill cutoff and
0.18% is stockpiled for later processing. The stockpile cutoff is set at a value slightly higher than internal
or marginal cutoff to incorporate the re-mining costs from the stockpile to the crusher.
The mine extraction schedule is illustrated on Table 16-2. Mining from the pit ends mid way through
2038 and stockpile material rehandling commences through till Q1 2039. The mill feed schedule is
shown in Table 16-3. These tables are based on Proven and Probable Mineral Reserves only.
Figure 16-3 illustrates the mine schedule in graphic form.
Table 16-2: Mine Extraction Plan – Mill Rate of 54,000 TPD (2016), 56,000 TPD (2017 and beyond)
Year Cut Off Ore Mined to Mill Ore Mined to Low Grade Stockpile Waste Total Mined
% Tcu M tonnes Tcu % Mo% M tonnes Tcu% Mo% M Tonnes M tonnes
2016 0.18 19.8 0.36% 0.008% 0.0 0.00% 0.000% 22.7 42.5
2017 0.19 20.4 0.34% 0.008% 1.0 0.18% 0.007% 23.5 44.9
2018 0.19 20.4 0.32% 0.011% 1.8 0.19% 0.007% 26.2 48.5
2019 0.17 20.4 0.32% 0.011% 0.0 0.00% 0.000% 28.2 48.6
2020 0.18 20.4 0.35% 0.013% 0.0 0.00% 0.000% 28.1 48.5
2021 0.19 20.4 0.35% 0.008% 0.8 0.19% 0.005% 27.3 48.5
2022 0.18 20.4 0.32% 0.007% 0.0 0.00% 0.000% 28.1 48.5
2023 0.17 20.4 0.29% 0.007% 0.0 0.00% 0.000% 28.1 48.5
2024 0.17 20.4 0.29% 0.008% 0.0 0.00% 0.000% 28.1 48.5
2025 0.17 20.4 0.36% 0.010% 0.0 0.00% 0.000% 28.1 48.5
2026 0.17 20.4 0.40% 0.014% 0.0 0.00% 0.000% 28.1 48.5
2027 0.17 20.4 0.33% 0.014% 0.0 0.00% 0.000% 28.1 48.5
2028 0.17 20.4 0.30% 0.010% 0.0 0.00% 0.000% 28.1 48.5
2029 0.22 20.4 0.28% 0.009% 9.6 0.20% 0.007% 18.5 48.5
2030 0.22 20.4 0.31% 0.009% 1.6 0.20% 0.007% 26.5 48.5
2031 0.18 20.4 0.32% 0.010% 0.0 0.00% 0.000% 28.1 48.5
2032 0.19 20.4 0.31% 0.009% 0.2 0.19% 0.006% 4.1 24.7
2033 0.17 20.4 0.28% 0.008% 0.0 0.00% 0.000% 3.0 23.4
2034 0.17 20.4 0.29% 0.007% 0.0 0.00% 0.000% 3.0 23.4
2035 0.17 20.4 0.27% 0.008% 0.0 0.00% 0.000% 1.4 21.8
2036 0.17 20.4 0.25% 0.008% 0.0 0.00% 0.000% 0.3 20.7
2037 0.17 20.4 0.29% 0.006% 0.0 0.00% 0.000% 0.0 20.4
2038 0.17 9.9 0.28% 0.004% 0.0 0.00% 0.000% 0.0 9.9
2039 0.00 0.0 0.00% 0.000% 0.0 0.00% 0.000% 0.0 0.0
Total 458.9 0.31% 0.009% 15.0 0.20% 0.007% 437.1 910.9
Pinto Valley Mine Life Extension Study, February 2016 Page | 133
Table 16-3: Mill Feed Schedule – Includes low grade stockpile 2038 and 2039
Payable Copper in
Year Mill Feed Mill Head Grade Payable Moly
Concentrate
M tonnes % Cu % Mo M lbs M lbs
2016 19.76 0.36% 0.008% 133.3 1.0
2017 20.44 0.34% 0.008% 130.9 1.4
2018 20.44 0.32% 0.011% 120.0 2.2
2019 20.44 0.32% 0.011% 124.4 2.2
2020 20.44 0.35% 0.013% 134.8 2.6
2021 20.44 0.35% 0.008% 132.2 1.6
2022 20.44 0.32% 0.007% 122.2 1.3
2023 20.44 0.29% 0.007% 110.5 1.3
2024 20.44 0.29% 0.008% 110.5 1.6
2025 20.44 0.36% 0.010% 138.3 2.0
2026 20.44 0.40% 0.014% 153.9 2.9
2027 20.44 0.33% 0.014% 127.4 2.8
2028 20.44 0.30% 0.010% 115.7 2.0
2029 20.44 0.28% 0.009% 106.5 1.7
2030 20.44 0.31% 0.009% 119.1 1.9
2031 20.44 0.32% 0.010% 122.2 2.1
2032 20.44 0.31% 0.009% 118.3 1.8
2033 20.44 0.28% 0.008% 106.1 1.6
2034 20.44 0.29% 0.007% 110.0 1.4
2035 20.44 0.27% 0.008% 102.6 1.6
2036 20.44 0.25% 0.008% 95.2 1.7
2037 20.44 0.29% 0.006% 109.1 1.2
2038 20.44 0.24% 0.006% 90.2 1.2
2039 4.402 0.20% 0.007% 16.0 0.3
Total 473.8 0.31% 0.009% 2,749.4 41.4
Assumptions used: Recovery as per the formulas provided by K. Major, P.Eng and reported in each block
along with 96.5% payable copper. Moly recoveries assume a ramp up from 30% in 2016 to 47% by 2019
and 97% payable.
Pinto Valley Mine Life Extension Study, February 2016 Page | 134
Figure 16-3: Mine Plan – Mill Rate of 54,000 TPD (2016) Increased to 56,000 TPD (2017+)
Pinto Valley Mine Life Extension Study, February 2016 Page | 135
The Main Dump is built in 45 ft vertical lifts. Dumps that were originally designed by Pinto Valley
engineering (Leach, Gold Gulch East, and Gold Gulch West) utilized dump angles of 31.05 degrees with
15 ft setbacks between lifts for an overall average of 28.7 degrees. The IMC design of the Main Dump
utilizes a 37 degree dump face with a 23 ft set back resulting in an overall angle of 28.6 degrees.
A consistent tonnage factor of 1.93 kg/tonne (swell factor of 1.3) has been used to calculate all storage
capacities. Figure 16-13 is an illustration of the end result of all waste storage facilities at the end of the
PV3 mine plan.
Pinto Valley Mine Life Extension Study, February 2016 Page | 136
Figure 16-4: End of 2016
Pinto Valley Mine Life Extension Study, February 2016 Page | 137
Figure 16-5: End of 2017
Pinto Valley Mine Life Extension Study, February 2016 Page | 138
Figure 16-6: End of 2018
Pinto Valley Mine Life Extension Study, February 2016 Page | 139
Figure 16-7: End of 2019
Pinto Valley Mine Life Extension Study, February 2016 Page | 140
Figure 16-8: End of 2020
Pinto Valley Mine Life Extension Study, February 2016 Page | 141
Figure 16-9: End of 2022
Pinto Valley Mine Life Extension Study, February 2016 Page | 142
Figure 16-10: End of 2025
Pinto Valley Mine Life Extension Study, February 2016 Page | 143
Figure 16-11: End of 2030
Pinto Valley Mine Life Extension Study, February 2016 Page | 144
Figure 16-12: End of 2038
Pinto Valley Mine Life Extension Study, February 2016 Page | 145
Figure 16-13: End of 2039 (After West Dump Reclamation)
Pinto Valley Mine Life Extension Study, February 2016 Page | 146
16.6 Mine Operations and Equipment
Mine equipment requirements for the mine plan were calculated based on the annual mine production
schedule, the mine work shift schedule, and equipment productivity estimates. Total material handled
by the mining equipment peaks at 48.5 million tonnes per year during 2018 through 2031.
The decision to continue with the current loading equipment fleet without additional units was
described earlier in this section in the tradeoff between capital investment and mine head grade
benefits. The major addition to mining equipment will be the addition of two haul trucks in 2020 due to
the increased haul distance that will occur as the mine gets deeper and the dumps get higher.
Table 16-4 presents a summary of the total mine fleet that is required for the life of mine. This table
takes the fleet replacements and rebuilds into account to show available units on site.
Mine equipment requirements were not estimated for the following activities:
1. Construction of any major surface water diversion channels and settlement ponds and
dams, other than the ditching and sedimentation ponds for the waste storage areas.
2. Road construction outside of the immediate mine area.
3. Clearing brush and stripping topsoil-growth media in advance of mining or dumping.
4. Contouring or reclamation of dumps at the end of the project.
Table 16-4: Mine Major Equipment Fleet Requirement
Pinto Valley Mine Life Extension Study, February 2016 Page | 147
Major Auxiliary Equipment
For years 2016 and 2017, IMC has coordinated equipment use schedules with PVM operations. From
2018 onward, IMC has applied standard IMC equipment calculations for the remainder of the mine life.
During a shift, IMC calculates efficient hours by accounting for mine site delays and operation
inefficiency. In this, IMC assumes that the mine site will have 1 hour of scheduled delays relating to shift
change and lunches/breaks. An operation efficiency of 50 minutes of every hour is then applied for
unforeseen delays (shovel backups, operator inefficiency).
Efficient Hours / Shift = (12 hour shift – 1 Hour Delay) * (50/60 Operation Efficiency) = 9.17 Hours
IMC calculates availability and use of availability as follows.
Table 16-5 is a summary of the maximum availabilities and use of availabilities that have been applied
for each equipment type. IMC has assumed the equipment accumulates 11.0 metered hours per shift.
Table 16-5: Maximum Equipment Availabilities and Use of Availabilities
Use of
Equipment Type Availability
Availability
Cat MD6420 Blast Hole Drill 80.0% 95.0%
Hitachi EX5600 Shovel 85.0% 95.0%
Cat 994F Loader 85.0% 95.0%
Cat 789 Haul Truck 85.0% 95.0%
Cat D10T Track Dozer 85.0% 88.0%
Cat 834H Wheel Dozer 85.0% 85.0%
Cat 16M Motor Grader 85.0% 88.0%
Cat 777F Water Truck 85.0% 78.0%
Cat 336EL Aux Excavator 85.0% 75.0%
Cat 980H Aux Loader 85.0% 85.0%
16.7.1 Drilling
PVM provided an estimate of drill productivity from their budget forecast for the next 4 years. That
information was provided in terms of feet of hole drilled per year. IMC converted that information to
tonnage drilled per shift for ore and waste. Current practice utilizes different drill patterns for ore and
waste with a higher powder factor in ore to induce more breakage and improve crushing throughput.
All mined material requires drilling and blasting; with the exception of the old waste and leach dumps
and the low grade stockpiles
Pinto Valley Mine Life Extension Study, February 2016 Page | 148
Table 16-6 summarizes the required operating shifts, the fractional drill fleet, the rounded drill fleet, the
fleet utilization, and the number of operators required per year. The table reflects the required number
of drills per year. Table 16-6 indicates more drills on site in the later years than Table 16-5, The three
drills that are on site are underutilized in the later years of the mine when only two drills are required.
Table 16-6: Drill Requirements – Blast Hole Drill
Pinto Valley Mine Life Extension Study, February 2016 Page | 149
16.7.2 Loading
The loading fleet consists of two Hitachi EX5600 hydraulic front shovels equipped with 29.1 cubic
meters (38 cubic yard) buckets and two Cat 994 front end loader equipped with 17.2 cubic meter
(22.5 cubic yard) buckets. These units are matched with Cat 789 haul trucks.
Table 16-7 illustrates the loading unit distribution between shovels and loaders throughout the mine
life. Mine production between the loaders and shovels are rebalanced yearly from 2016-2017. This
is due to the less than optimal operating conditions encountered in the planned pit bottom. By
2018, IMC has assumed that PVM will have improved conditions to slightly raise loading production
for the shovels reducing loader requirements for a mine increased total production rate of 48.5 Mt.
From 2018 on, the shovels will handle the bulk of the mine tonnage (42.4 M tonnes) with a lesser
reliance on the loader fleet for production (6.1 M tonnes). The loaders will also support the shovels
during shovel moves and with material blending.
The hydraulic shovels are the primary loading units at the mine. Table 16-8 summarizes the
hydraulic shovel loading requirements by year, including the required shifts, the fractional and
rounded fleet, the fleet utilization, and the number of operators.
The productivity calculation assumes that the trucks are always loaded to their body limit. The 789
truck load is 174.4 dry tonnes (179.6 wet) for ore and waste. Loader material movements depend
on the required mine utilization as shown in Table 16-9.
The Cat 994 wheel loader will also assist as auxiliary and backup service in addition to assisting
primary production. Beginning 2032, the loaders are scheduled as auxiliary equipment only as the
shovels will handle the remaining production. Table 16-9 summarizes the wheel loader loading
requirements by year, including the required shifts, the fractional and rounded fleet, the fleet
utilization, and the number of operators.
Table 16-7: Mined Tonnage Movement by Shovel and Loader Fleets (re-handle is not included)
By Total
By Shovels Shovel % Loader %
Year Loaders Moved
K tonnes of Total of Total
K tonnes K tonnes
2016 31,860 10,620 42,480 75.0% 25.0%
2017 33,675 11,225 44,900 75.0% 25.0%
2018 42,438 6,063 48,500 87.5% 12.5%
2019 42,525 6,075 48,600 87.5% 12.5%
2020 42,438 6,063 48,500 87.5% 12.5%
2021 42,438 6,063 48,500 87.5% 12.5%
2022 42,438 6,063 48,500 87.5% 12.5%
2023 42,438 6,063 48,500 87.5% 12.5%
2024 42,438 6,063 48,500 87.5% 12.5%
2025 42,438 6,063 48,500 87.5% 12.5%
2026 42,438 6,063 48,500 87.5% 12.5%
2027 42,438 6,063 48,500 87.5% 12.5%
2028 42,438 6,063 48,500 87.5% 12.5%
2029 42,438 6,063 48,500 87.5% 12.5%
Pinto Valley Mine Life Extension Study, February 2016 Page | 150
2030 42,438 6,063 48,500 87.5% 12.5%
2031 42,438 6,063 48,500 87.5% 12.5%
2032 24,693 0 24,693 100.0% 0.0%
2033 23,443 0 23,443 100.0% 0.0%
2034 23,445 0 23,445 100.0% 0.0%
2035 21,820 0 21,820 100.0% 0.0%
2036 20,725 0 20,725 100.0% 0.0%
2037 20,440 0 20,440 100.0% 0.0%
2038 20,440 0 20,440 100.0% 0.0%
2039 4,402 0 4,402 100.0% 0.0%
Total 819,156 106,733 925,888
Pinto Valley Mine Life Extension Study, February 2016 Page | 151
Table 16-9: Wheel Loader Requirements - Cat 994 Loading Cat789D Trucks
Total Loading Shifts/ Fract. Actual Fleet # of # of
Year
K tonnes Shifts Year Fleet Fleet Util. Crews Oper.
2016 10,620 565 730 0.96 1 0.77 4 4
2017 11,225 597 730 1.01 1 0.82 4 4
2017 6,063 522 730 0.89 1 0.72 4 4
2019 6,075 523 730 0.89 1 0.72 4 4
2020 6,063 522 730 0.89 1 0.72 4 4
2021 6,063 522 730 0.89 1 0.72 4 4
2022 6,063 522 730 0.89 1 0.72 4 4
2023 6,063 522 730 0.89 1 0.72 4 4
2024 6,063 522 730 0.89 1 0.72 4 4
2025 6,063 522 730 0.89 1 0.72 4 4
2026 6,063 522 730 0.89 1 0.72 4 4
2027 6,063 522 730 0.89 1 0.72 4 4
2028 6,063 522 730 0.89 1 0.72 4 4
2029 6,063 522 730 0.89 1 0.72 4 4
2030 6,063 522 730 0.89 1 0.72 4 4
2031 6,063 522 730 0.89 1 0.72 4 4
2032 0 200 730 0.34 1 0.27 4 4
2033 0 200 730 0.34 1 0.27 4 4
2034 0 200 730 0.34 1 0.27 4 4
2035 0 200 730 0.34 1 0.27 4 4
2036 0 200 730 0.34 1 0.27 4 4
2037 0 200 730 0.34 1 0.27 4 4
2038 0 200 730 0.34 1 0.27 4 4
2039 0 50 182 0.34 1 0.27 4 4
Total 106,733 9,925 16,972 0.73
16.7.3 Hauling
The current truck fleet at PVM consists of 18 Cat 789 haul trucks. Truck productivity was estimated
using haul time simulation. IMC measured haul profiles for each time period, material type,
pushback and destination for input to simulation. In total 124 profiles were measured.
Truck haulage times of each profile were calculated and the resulting tonnage per truck shift was
used to calculate the required truck operating shifts for each year.
Each of the trucks will be rebuilt once at about 60,000 hours and replaced at about 120,000 hours.
Trucks will be loaded to their body limit of 174.4 dry tonnes (179.6 wet). Shovel and loader loading
unit distribution for truck load times calculated from Table 16-7.
Table 16-10 summarizes the total truck shifts, fractional and actual fleet size, fleet utilization, and
number of operators for each year for the hauling fleet. The EX5600 is the primary loading unit for
Pinto Valley Mine Life Extension Study, February 2016 Page | 152
the fleet. The Cat 994 wheel loader serves as a backup loading unit typically accounting for 12.5% of
total material.
From year 2016 to 2019, an average of 18 trucks are required which increases to a maximum of 20
trucks for years 2020 to 2029. The rebuild and replacement schedule maintains 20 trucks in the
fleet through 2033. They are underutilized to some degree when the requirement is less than 20
trucks.
Pinto Valley Mine Life Extension Study, February 2016 Page | 153
The primary function of the auxiliary equipment is to support the major production units, and
provide safe and clean working areas. Equipment types included in the auxiliary mine fleet are:
4, Caterpillar D10T Track Dozers
3, Caterpillar 834H Wheel Dozers
2, Caterpillar 16M Graders
3, Caterpillar 777F Water Truck
1, Caterpillar 980H Auxiliary Loader
1, Caterpillar 336EL Auxiliary Excavator
2, Caterpillar 777F Fuel and Lube Trucks
The operating hours and shift requirements for the auxiliary equipment are based on current and
planned scheduling practice at PVM.
Pinto Valley Mine Life Extension Study, February 2016 Page | 154
17 Recovery Methods
17.1 Mill Process Design Criteria (2014) and Current Flow Sheet
The various unit operations of PVM have been evaluated to develop the basic process design criteria for
the mill. Where possible, the operating data has been compared to testwork and/or simulation models
to determine suitability for the design criteria. The key elements of the process design criteria include
the following.
Primary Crusher
o Product Size Distribution (operating data)
▪ 80%: 3.5 inches
▪ 45%: 1 inch
▪ 30%: 0.5 inch
Secondary/Tertiary Crushers
o Crushing circuit availability: 75% (projected/historical)
o Crushing circuit P80: 11 mm (operating data)
o Standard Cone Crusher Feed Rate: 3000 tpoh (operating data)
Grinding Circuit
o BMWi: 14.7 (metric) (testwork)
o Grinding circuit availability: 95% (projection)
o Daily Throughput, Nominal: 53,800 stpd (48900mt/d) (model/operating data)
o Cyclone overflow P80: 280 μm (operator input)
Copper Flotation
o Rougher feed density: 37% solids
o Rougher flotation lab residence time: 8 minutes (ALS kinetic tests)
o Plant residence time: 24.8 minutes
o Scale up factor: 3.1 (target > 2.0)
Figure 17-1 is a simplified process flow sheet representing the main unit operations applied in the Pinto
Valley mill.
Pinto Valley Mine Life Extension Study, February 2016 Page | 155
Figure 17-1: Simplified Pinto Valley Process Flowsheet
17.4.4 Flotation
The flotation circuit operates as a staged process designed for the recovery of copper and molybdenum
to individual concentrates. The primary focus of the rougher flotation circuit is to optimize recovery of
the primary sulfide minerals from the gangue into a reduced mass for economic downstream
processing. Cleaner flotation delivers economic concentrate grades for marketing while maintaining
high recoveries.
The flotation reagents used include Flomin™ C-3430 (Xanthate), C-2420 (dithiophosphate), and F-171
(frother). Some of the flotation reagents have been added to the grinding circuit for slurry conditioning,
with addition rates augmented in the flotation circuit where required.
Regrinding of the rougher concentrate is required to provide the further mineral liberation to allow high
concentrate grades and recoveries from the cleaners. The molybdenum in the PVM ore is recovered to
the bulk cleaner concentrate with the copper. The molybdenum flotation circuit provides the
separation of the copper and molybdenum into respective concentrates for marketing.
17.4.4.1 Rougher Flotation
The rougher flotation circuit consists of sixty-five 1,000 ft3 Wemco™ cells configured in three trains, with
cyclone overflow from two ball mills feeding each train. Frother is added to the head of the rougher
flotation cells, with other reagents (that were added at grinding) added as required. The rougher
section is operated in open circuit, with the rougher tailings going directly to the final tailings.
17.4.4.2 Regrind
The rougher concentrate is delivered to the regrind ball mill circuit. Rougher concentrate is combined
with the regrind ball mill discharge and pumped to the closed-circuit cyclones. The target product for
regrind cyclone overflow is P80 of 50 μm. The cyclone overflow is fed to the cleaner flotation circuit,
while the underflow is sent to two regrind mills. The regrind mills operate in closed circuit with the
cyclones.
17.4.4.3 Cleaner Flotation
The cleaner circuit consists of four 8 ft diameter × 40 ft tall column flotation cells operated in parallel.
The column cell concentrate, the final copper-molybdenum bulk concentrate, contains 27%–29% Cu and
0.35%–0.7% Mo. The column cell tails are sent to the cleaner scavenger flotation bank. The cleaner
Pinto Valley Mine Life Extension Study, February 2016 Page | 158
scavenger bank comprises fifteen 300 ft3 Wemco™ flotation cells. The concentrate from the first five
cells is recirculated to the column cells. The concentrate from cells 6 to 15 is recirculated to the head of
the cleaner scavenger bank. The tails of the cleaner scavenger bank are sent to final tailings.
17.4.4.4 Molybdenum Plant
The copper-molybdenum concentrate from the cleaner columns is thickened before being sent to the
molybdenum plant. The plant comprises four banks of Agitair™ rougher cells of six 50 ft3 cells each and
three stages of cleaning using column cells. Sodium hydrosulfide is added to the slurry to provide
depression of copper and iron sulfides. Fuel oil is added as a molybdenum promoter.
17.5 SX-EW
The PVM SX-EW plant was built and commissioned in 1981 to process solutions from the leach grade
material placed on the leach dumps north of the pit. Through 1998, approximately 450 M tonnes of
0.13% TCu material had been placed on the leach, resulting in production of 10 to 15 M lbs of cathode
copper per year in the early 2000s. Over the last few years, the SX-EW has produced in the range of 5 to
8 M lbs of cathode per year due to the declining residual copper inventory in the leach piles. The PV3
plan utilizes the leach area and pregnant solution pond as waste rock storage, resulting in leaching
operations being discontinued at the end of 2018.
Pinto Valley Mine Life Extension Study, February 2016 Page | 159
18 Project Infrastructure
18.1 Site Infrastructure
Existing project infrastructure includes:
Mine Equipment Maintenance Facilities (North Barn, Main Shop, wash bays, tire change area)
Offices complexes (admin, mine, mill)
Heavy and light vehicle fuel storage and distribution
Explosives Plant
Pit dewatering pumps and pipelines
Concentrate dewatering, storage and loadout
Warehousing and Change Rooms
Stormwater ponds and pumping systems
Internal roads and access road FSR 287
Water wells and water pumping systems
First aid facility
Assay lab
Power lines and transformers
Tailings storage and distribution facilities
The increase in mineral reserves will only impact the tailings storage and distribution facilities. All other
infrastructure is adequate to support the mine life increase to 2039.
Pinto Valley Mine Life Extension Study, February 2016 Page | 160
production rate of 64,950 tpd. The design tailings pipeline flow rate is calculated to be 12,930 gpm with
55% solids.
The tailings gradation test results, performed by AMEC, indicate that approximately 10% of the particles
are finer than 4.8 µm, approximately 50% of the particles are finer than 112 µm, and approximately 80%
of the particles are finer than 360 µm.
Pinto Valley Mine Life Extension Study, February 2016 Page | 161
Figure 18-1: TSF4 Layout up to 4180 ft elevation (2039)
Pinto Valley Mine Life Extension Study, February 2016 Page | 162
The mine plan includes raising of the boundary dam by an additional 12 ft. The TSF3 main embankment
will be raised in a sequence of centerline and upstream lifts. These raises will provide 5 million tons of
storage capacity to an elevation of 3,780 ft.
Modifications to the current USFS POO are ongoing. Once the agreement is in place, the plan is for TSF3
to be raised to elevation 3,857 ft, which will provide about 21 million tons of tailings storage.
Pinto Valley Mine Life Extension Study, February 2016 Page | 163
each train are controlled by variable frequency drives (VFDs). Normal operation consists of running two
trains with the third train on standby.
The existing TSF4 Tailings Booster Pump Station will be removed from service in April 2016 and replaced
with the Combined Tailings Booster Pump Station. Delivery of tailings to TSF4 will be through 3 stages of
pumping. The third stage pumps are equipped with VFDs for flow control.
The discharge from the TSF4 Tailings Booster Pump Station consists of a 24-inch polyurethane-lined
steel pipeline up the south side of the TSF4 embankment to the dam crest. The pipeline continues
across the dam crest to the far abutment. Taps for cyclones are spaced approximately 50 ft apart. Up to
16 cyclones may be in operation at any one time. The fine-grained fraction from the cyclone overflow is
piped to the TSF beach. The coarse cyclone underflow material is used to construct the dam
embankment.
The existing reclaim water system consists of barge-mounted pumps and two booster pump stations
conveying water from the southern end of the TSF4 decant pool to the Mill Water Supply Tank. The
nominal design flow rate is 6,500 gpm.
The existing dual barge pumps are Hazleton Model 12DA Type VNCC with 21.5-inch impellers. The
drivers are Westinghouse 186 kW, 3-phase, 4,160 V, 1,174 rpm motors. Both booster pump stations
have two parallel Allis-Chalmers Model 3415 12 × 14 horizontal split case pumps with full-size 45.72 mm
impellers rated for 1,780 rpm. The drivers are GE 450 kW, 3-phase, 4,160 V, 1,800 rpm motors. All of
the reclaim pumps are controlled (kept within their rated pump curve) by back pressure valves that are
partially closed (increasing the back pressure) as the pond level rises.
As the TSF4 decant pool rises, the first booster pump station will no longer be needed and will be
abandoned. At that time, the second booster pump station will be relocated.
18.7 Monitoring
A series of piezometers has been installed to monitor groundwater fluctuations at the current and
previously operated TSFs. The piezometers consist of open standpipes, pneumatic, and vibrating wire
piezometers. The piezometers are measured monthly. Fifty new piezometers were installed in 2015, all
of these piezometers are connected to automated data recorders.
Quarterly monitoring reports of the piezometer readings are prepared and reviewed by the designated
PVM engineer to verify that the TSFs are operated, and are performing, as designed. An annual
Pinto Valley Mine Life Extension Study, February 2016 Page | 164
monitoring report, which includes a summary and graphs of the piezometer measurements, is
submitted to ADEQ.
The active and former TSFs are inspected annually by PVM’s consulting geotechnical engineer.
Feedback is provided on the operation of the TSFs and recommendations, if necessary, are provided to
the PVM management and engineering groups.
Pinto Valley Mine Life Extension Study, February 2016 Page | 165
19 Market Studies and Contracts
19.1 Copper
Copper and copper-based alloys are used in a variety of applications that are used to increase standards
of living. Its continued production and use is essential for society's economic development.
Copper is an important contributor to the national economies of mature, newly developed, and
developing countries. Mining, processing, recycling, and the transformation of metal into a multitude of
products creates jobs and generates wealth. These activities contribute to building and maintaining a
country's infrastructure and create trade and investment opportunities. Copper will continue to
contribute to society’s development well into the future.
Copper and copper-based alloys are used in a variety of applications that are used to increase standards
of living. Its continued production and use is essential for society's economic development. The
consumption of refined copper in its variety of applications is expected to increase at a compound
average growth rate (CAGR) of 2% between now and 2035, requiring significant primary mine
development over the period.
Figure 19-1: Major Uses of Copper: Usage by Region and End-Use Sector - 2013
Pinto Valley Mine Life Extension Study, February 2016 Page | 166
19.3 Copper Concentrate Market
Smelter production capability (concentrate demand) forecast for 2015 is 19.0Mt (Cu contained),
representing a potential 10.1% increase from 2014. Smelter output capability growth is expected to
continue at an overall CAGR of 5.3% p.a. over the period 2014 to 2018. However, with the timing of
some projects remaining uncertain and mines subject to disruptions, a lack of concentrates and
secondary feed material may moderate this increase to around 3.8% p.a. in terms of actual production.
Global smelter production capability is forecast to grow by an average of 1.2% p.a. through to 2035.
19.4 Supply
Global mine production continued to grow during 2014 reaching 18.6Mt, 2.5% higher than the total
achieved during 2013. This increase compares with an 8.2% increase seen in 2013 and a compound
annual average growth rate (CAGR) of just 1.8% over the period 2002 to 2012. Additions to mine
capacity during the period 2014 through to 2018 represent a CAGR of 3.1%. Beyond 2018, mine
production is expected to decline due to reserve depletion to reach 16.3Mt by 2025 and 11.4Mt by
2035. This means that over the forecast period, existing mine production is expected to decline by an
average rate of 2.1% annually. As a result, beyond 2018, increased demand and attrition at existing
mines will mean that the primary market will return to a deficit unless mine projects are developed.
Pinto Valley Mine Life Extension Study, February 2016 Page | 167
19.7 Pinto Valley Mining Corporation
PVM’s current and long term copper concentrate production forecasts are between 190-220 ktonnes
per year. The copper concentrate has two potential destinations; smelters in Arizona (domestic) and
smelters in Asia (international). The domestic bound concentrate is trucked directly to the smelters
from PVM. The international bound concentrate has historically been trucked to the San Manuel
Arizona Railroad (SMARRCO) facility in San Manuel, Arizona, where it was loaded onto trains, shipped to
the Port of Guaymas in western Mexico, and then loaded onto ships destined for Asia. The usage of the
SMAARCO facility has been discontinued at the end of 2015 and the concentrate will be placed in
containers that will be trucked directly to the Port of Guaymas for international shipping.
Pinto Valley Mine Life Extension Study, February 2016 Page | 168
20 Environmental Studies, Permitting and Social or Community
Impact
This section summarizes the environmental issues identified on site, existing permit status,
environmental monitoring, and permitting efforts that may be required throughout the mine life
identified in this study. PVM’s health and safety, and social and community programs are also
discussed.
Pinto Valley Mine Life Extension Study, February 2016 Page | 169
(EHSS) Policy overseen by an EHSS Committee. Each new employee is required to make a commitment
to safety acknowledged by signing the Code of Conduct.
PVM is subject to health and safety regulations under the supervision of the Mine Safety and Health
Administration (MSHA), ASMIO, Arizona Department of Transportation (ADOT), and other federal and
state agencies. New miner training, annual refresher training and training certification to operate
specialized equipment is handled internally at site. Specific health and safety plans and traffic
management plans will be developed for projects that are outside of routine operations throughout the
mine life.
Safety incidents and accidents are reported via an integrated internal notification system. Incidents,
property damage, and injuries are investigated by the area supervisors, assisted by PVM’s Health,
Safety, Environment & Community (HSEC) department and other relevant internal personnel, to review
the causes, and develop preventative and remedial plans.
The safety procedures and personal protective equipment requirements for routine work, emergency
reporting and response protocols, and training such as risk review procedures and environmental
training are well documented and reinforced by the HSEC department as part of employee training. The
HSEC department also oversees industrial hygiene-related programs such as hearing conservation
programs that test employee hearing, monitor noise levels, and work with operations, as required, to
mitigate excessive noise. The department activities include a respiratory protection program, fatigue
management, annual medical examinations, the “back-to-work” assessment following a workplace
illness or injury, the drug and alcohol program and fitness for duty program. Health-related programs
managed primarily by the Human Resources Department include new employee medical screenings.
20.2.1 Groundwater
Water quality analyses of various constituents are required on a quarterly, annual, and biennial basis
from designated seeps/springs, and Point-of-Compliance (POC) wells. Routine self-monitoring report
forms are submitted to ADEQ with the results of water quality monitoring and site inspections.
Pinto Valley Mine Life Extension Study, February 2016 Page | 170
APP compliance reporting requires an annual demonstration of the adequacy of pit containment (i.e. the
Open Pit is a sink with evaporation exceeding the groundwater flowing inwards from surrounding areas
into the Open Pit). A comprehensive groundwater report is required by ADEQ every 5 years to assess
adequacy of POC wells and the passive hydraulic containment in the Open Pit.
Pinto Valley Mine Life Extension Study, February 2016 Page | 171
has been reclaimed and is inspected for seepage and erosion features. AMEC performs an annual
inspection of the two active impoundments (TSF3 & TSF4) and prepares a report that is written and
stamped by an Arizona-registered engineer and submitted to ADEQ. Associated seepage toe drains and
caissons are to be kept free of debris, sediments, vegetation, and other obstructions.
Environmental monitoring for the expanded TSF4 is not expected to require additional downgradient
POC wells or surface water discharge point monitoring from the seepage and stormwater collection
ponds. Any new monitoring related to the expanded facilities, including compliance with tailings
disposal and design height limits, will be conducted as required by the relevant governmental agencies.
Pinto Valley Mine Life Extension Study, February 2016 Page | 172
20.3 Environmental Permit Review Related to PV3
The following analysis is a brief review of current federal and state permits and requirements with
respect to new, expanding and ongoing operations and closure planning at PVM. Any potential actions
or permit amendments that will be required by the PVM LOM expansion are noted.
Pinto Valley Mine Life Extension Study, February 2016 Page | 173
draft EA documents in the recent past, similar to the EIS process. The EIS results in a Record
of Decision (ROD) outlining the evaluated impacts of the project, along with the mitigation
responsibilities of the project proponent.
Approval of the POO will also include consultations with the relevant agencies under the Endangered
Species Act and the National Historic Preservation Act (discussed in Sections 20.3.1.4 and 20.3.1.5,
respectively). The final POO approval process (including NEPA review and consultations) is anticipated
to take approximately 2-3 years from the initiation of scoping. Changes to plan designs prior to scoping
can be incorporated into the process. Design changes after scoping may be incorporated into project
alternatives required to be evaluated in the NEPA document, or may require re-initiation of scoping,
resetting the final POO approval clock.
20.3.1.2 Forest Road Relocation
Currently, Forest Road (FR) 287, also commonly referred to as the Pinto Valley Road provides access to
the mine site and administrative facilities from US Highway 60. FR 287 is a public road that passes through
the Pinto Valley Mine to provide public access to ranches and for recreation on the Tonto National Forest
(TNF). The segment through the Mine on private lands is authorized by an easement and is maintained by
PVM. FR 287 is contemplated to be relocated from its current alignment for construction of the West
Dump
It is anticipated that some level of coordination with TNF will be required for relocation of FR 287. If
necessary, NEPA review for the road relocation may be completed as part of that done for the Plan of
Operations, described in Section 20.3.1.1.
20.3.1.3 CWA Section 404 Permit
Surface water features within the likely footprint of waste rock dumps, TSF3 or TSF4 expansion may be
subject to jurisdiction under the CWA. A request for an Approved Jurisdictional Delineation (AJD) was
submitted to the USACE in February 2015 and supplemented in June 2015. The outcome of the AJD will
determine the nature of the Section 404 permitting process that may be required for placement of fill in
drainages deemed jurisdictional by the USACE. If it is determined that the operation will impact waters
of the U.S. (WOTUS), a Section 404 permit application will be submitted.
The USACE process and procedures for initiation of NEPA are different from the Forest Service. Notably,
the USACE requires an alternatives analysis in accordance with CWA Section 404b1 criteria. Differing
from alternatives identification in NEPA, this evaluation requires that the USACE identify the least
environmentally damaging practicable alternative (LEDPA), which is typically that alternative that results
in the fewest impacts to WOTUS. These alternatives can inform the range of alternatives considered
during NEPA review though in practice only the single project identified as the LEDPA is considered. The
NEPA review for the Section 404 permit is anticipated to be different than that for the USFS POO, as the
federal actions for each are different. Given the currently anticipated level of impacts for the Section
404 permit, the NEPA analysis is likely to be satisfied by the Corps' completion of an EA.
The Section 404 permit process is anticipated to take 1.5 to 2 years from the submittal of the permit
application. One of the primary challenges associated with this permitting effort is to demonstrate that
the proposed action is the LEDPA, despite the fact that it involves the loss of wetland area.
Pinto Valley Mine Life Extension Study, February 2016 Page | 174
20.3.1.4 Endangered Species Act Compliance
Based on a biological screening analysis there are currently two ESA-listed species were identified to
have reasonable potential to occur within the project footprint, the Arizona hedgehog cactus (AHC) and
yellow-billed cuckoo (YBC). In addition, proposed critical habitat for YBC occurs along Pinto Creek within
a mile of the proposed tailings expansion TSF3 onto Forest Service land.
Protocol level survey of AHC was completed for potentially suitable AHC habitat within the operation
expansion areas in June 2015. These surveys were completed on private PVM land in the vicinity of
proposed waste rock dump and TSF3 expansion and no AHC individuals were identified. A survey for the
presence of YBC along Gold Gulch, East Water Canyon and Pinto Creek was completed in August 2015.
No AHC or YBCU were detected during the surveys and accordingly, these species are considered
unlikely to be present or be impacted by the proposed activities.
Ultimately, the federal agencies will be responsible to determine whether or not there is likely to be an
affect to a listed species. Consultation with the U.S. Fish and Wildlife Service (FWS) under ESA Section 7
may be required for both the POO and the Section 404 permit (should a Section 404 permit be
required). The presence of proposed critical habitat immediately down steam of the project elevates
the probability that consultation will be required even though no YBC were detected during surveys in
2015. Although biological screening analysis and species-specific surveys indicate there is limited
potential for ESA-listed species to be present within the project area, there is still potential that the
federal agencies will require further review involving the FWS. As with the NEPA evaluation, the USFS
and USACE will likely conduct separate consultations as the federal actions and decision spaces will
differ. By regulation, Section 7 consultation is to take 135 calendar days, though extensions are
common depending on the extent of impacts to listed species or complexity of the analysis.
20.3.1.5 National Historic Preservation Act Section 106 Compliance
Previous cultural resource surveys have been completed to support ongoing planning on both private
and public lands at Pinto Valley Mine and in the near vicinity. There are numerous cultural resources
that are likely to be considered eligible for the National Register of Historic Places.
Consultation with the State Historic Preservation Officer (SHPO) under NHPA Section 106 is anticipated
to be required for both the POO and the Section 404 permit (should a Section 404 permit be required).
As with the NEPA evaluation, the USFS and USACE will likely conduct separate consultations as the
federal actions and decision spaces will differ. Consultation will include a review of the cultural
resources surveys and recommendations for register eligibility, as well as development, review, and
implementation of an historic properties treatment and data recovery plan. The time and cost to
complete data recovery can be substantial though the actual data recovery effort typically is not
completed until the federal permitting process is complete.
Pinto Valley Mine Life Extension Study, February 2016 Page | 176
until the remains can be properly recovered and repatriated. Any such discoveries must be treated in
accordance with Arizona Revised Statues.
Pinto Valley Mine Life Extension Study, February 2016 Page | 177
Figure 20-1: Perspective view looking north, -30 degrees at planned LOM waste rock, leaching, and
tailings facilities. Future decommissioned LP (gold), existing and expanded tailings (gray), marginal
grade dumps (blue) and planned LOM waste rock (red)
Pinto Valley Mine Life Extension Study, February 2016 Page | 178
Table 20-1: Summary of Key Permitting Considerations.
Assumptions/ Estimated Schedule Start
Permit Effort Agency
Key Considerations Timeframe Point
Federal
Plan of USFS-TNF Given level of impacts, the level 2 to 3+ years Acceptance of
Operations of NEPA analysis and schedule Plan of
(Including NEPA will not differ substantially Operations as
review) whether an EA or EIS is utilized. suitable to initiate
NEPA.
Forest Road USFS-TNF Relocation of FR 287 will be 6 months to 2 Availability of
Relocation required for construction of the years depending road designs
West Dump and is consistent on TNF approach
with easement, but may require
an update to TNF Travel Plan.
CWA Section USACE Assumes an individual permit 2 to 3+ years Submittal of
404 Permit will be required for tailings permit
(Including NEPA facilities. Will need to application.
review) demonstrate LEDPA and secure
viable mitigation option.
Endangered Lead federal Assumes formal consultation for 1 to 1.5 years Submittal of
Species Act agency and potential impacts to ESA listed Biological
Compliance USFWS species as part of Section 404 Assessment to
permit and/or POO approval. federal agency at
draft NEPA
document stage.
National Historic Lead federal Cultural resource sites known to 1-2 years. Completion of
Preservation Act agency and occur within footprint of Estimated survey and
Compliance SHPO expansion areas. If federal timeframe does Acceptance of
permitting is required, a not include final Plan of
treatment plan and consultation data recovery Operations
with SHPO and local tribes will report; however, sufficient to
be required. construction evaluate impacts.
would be Federal agency
Data recovery will need to be permitted can initiate
completed before sites are following data consultation with
disturbed. recovery and an SHPO with final
out of field survey report.
report.
Pinto Valley Mine Life Extension Study, February 2016 Page | 179
Assumptions/ Estimated Schedule Start
Permit Effort Agency
Key Considerations Timeframe Point
State
Aquifer ADEQ APP needed for waste rock and 18 to 30 months Submittal of
Protection tailings facilities; monitoring application with
Permit well installation required. baseline data and
basic engineering.
Individual ADEQ Existing permits are in place. 2 months - 2 Submittal of
AZPDES Permit PV3 facilities may affect existing years application with
outfalls and could require baseline data and
modification of the existing basic engineering.
permit to accommodate new
and modified
stormwater/seepage collection
ponds for expansion areas.
Arizona Multi- ADEQ The current AZMSG-2010 12 months Submittal of
Sector General expires on January 31, 2016. application with
Stormwater The SWPPP will have to be baseline data and
Permit modified to include PV3 basic engineering.
(AZMSGP) facilities and BMPs prior to
initiation of construction or
upon permit expiration.
Air Quality ADEQ Updates to current permit. 6 – 18 months Availability of
Control Permit detailed
emissions and
ambient air
information,
submittal of
application
Dam Safety ADWR PV3 will not utilize jurisdictional NA NA
Permit impoundments (greater than 25
ft embankment height or
greater than 50 ac-ft storage
capacity). However, withdraw
permits of existing dams in Gold
Gulch will be required.
Pinto Valley Mine Life Extension Study, February 2016 Page | 180
Assumptions/ Estimated Schedule Start
Permit Effort Agency
Key Considerations Timeframe Point
Mined Land ASMIO Update existing MLRP. Expect 2 1 year Availability of
Reclamation rounds of comments and general
Plan responses with ASMI. arrangement, and
geotechnical and
geochemical
information
Certificate of Arizona If needed, this would be 2 to 3 years Define power
Environmental Corporation obtained by the power utility needs.
Compatibility Commission (SRP) though PVMC can affect
the process and schedule. New
or refurbished power line across
Forest Service lands will require
NEPA review.
Total 3 to 4 years
Pinto Valley Mine Life Extension Study, February 2016 Page | 181
needed for post-closure monitoring would be abandoned. The MLRP-related closure costs address
closure activities related to ensuring public safety, facility regrading, and revegetation.
APP-related closure costs were updated and approved by ADEQ in 2015 to reflect mine expansion plans
and disturbance through 2026 including a design change in the waste rock disposal facilities. An
application recently submitted to ADEQ in November 2015 to consolidate waste rock disposal facilities
will modify the site-wide closure and post-closure costs again when the application is approved in 2016.
Site-wide closure and post-closure costs have been estimated based on the updated LOM plan to 2039
discussed in this technical report. The costs were calculated based on assumptions documented in the
Closure and Post-Closure Strategy, regrade designs and quantities prepared by AFW and SRK, and
road/utility alignments and disturbance acreages on USFS-lands as compiled by WestLand and SRK.
The total cost for PVM closure and reclamation is estimated to be $143.5 M including $102.0 M in
closure costs and $1.8 M in post-closure costs, and $39.8M in Owner’s Costs. Closure costs include
direct capital costs of $80.9M and indirect costs of $21.1M. Post-closure costs include site inspections,
maintenance, monitoring. Owner’s costs include internal G&A and labor to support the 30-year post-
closure period as well as closure designs, environmental studies and permit amendments and routine
environmental reporting, as needed.
The closure costs by regulatory permit program will be finalized when permit applications have been
submitted, reviewed, and approved by the relevant agency. Based on the LOM configuration discussed
in this technical report, however, the total closure and post-closure costs are estimated to be:
$85.3 M – ADEQ APP program,
$15.4 M – ASMI MLRP program, and
$3.1 M – TNF forest service authorizations and permits.
Capstone and SRK have reviewed the estimated closure and post-closure costs of $143.5 M and believe
the cost estimates are reasonable.
Pinto Valley Mine Life Extension Study, February 2016 Page | 182
distributing information, donations, sponsorships and employee support, employee involvement,
memberships, documentation policies for grievances/complaints, and key roles within the organization
with respect to community engagement. Additional to the procedure are a stakeholder register and a
stakeholder analysis log containing a record of communications with stakeholders. In 2015 PVMC’s
Community Engagement Procedure was bolstered to match organization-wide Capstone standards.
PVM has policies and procedures in place to address security and emergency management. PVMC
follows the Capstone Code of Conduct for compliance with local regulations and to ensure business
ethics in its relationships with its employees, suppliers, vendors, contractor firms, regulators, and local
communities. Specific policies include:
A Whistleblower Policy (Fraud reporting and Investigation);
A Code of conduct that outlines the official complaint procedure; and
An Anti-bribery Policy complements the Code of Conduct with additional guidance on
compliance with applicable anti-bribery and corruption laws and regulations.
Pinto Valley Mine Life Extension Study, February 2016 Page | 183
21 Capital and Operating Costs
21.1 Operating Costs
The LOM operating cost for PVM is projected to be $9.83/tonne milled. These costs do not include
TC/RC and concentrate transportation costs. The operating costs are detailed in Table 21-1.
Table 21-1: Unit Cost Summary
Item Units Life of Mine Average Cost
Mining Cost $/t moved 1.67
Mining Cost $/t milled 3.25
Milling Cost $/t milled 5.10
G&A Cost $/t milled 1.48
Total $/t milled 9.83
The C1 cost is a measure used to calculate the operating cost of producing copper, net of byproduct
credits. The life of mine C1 cost, including mine waste stripping as an operating expense has been
estimated at $2.05/lb copper payable.
Pinto Valley Mine Life Extension Study, February 2016 Page | 184
The mine costs average to $1.67/metric tonne moved. The breakdown by category is shown in Table
21-2. Haulage and auxiliary equipment make up nearly half of the cost. Life of mine average cost per
tonne milled is $3.25.
Table 21-2: Mine Unit Cost Summary
Life of Mine Average Cost
Cost Type
US$/tonne mined
Drilling 0.11
Blasting 0.27
Loading 0.20
Hauling 0.62
Auxiliary 0.22
Mine General 0.05
Maintenance General 0.06
G&A 0.14
Total 1.67
Pinto Valley Mine Life Extension Study, February 2016 Page | 185
Other 0.11
Total 5.10
Pinto Valley Mine Life Extension Study, February 2016 Page | 186
22 Economic Analysis
Under Canadian National Instrument 43-101 regulations, producing issuers may exclude the information
required for ‘Section 22 – Economic Analysis’ on properties currently in production unless the Technical
Report includes a material expansion of current production. Capstone Mining Corp. is a producing issuer
per the definition in the NI-43-101 and a material expansion is not considered in this Technical Report.
Pinto Valley Mine Life Extension Study, February 2016 Page | 187
23 Adjacent Properties
The PVM site is in proximity to the following mining and exploration properties: KGHM’s Carlota Mine
adjacent to PVM, BHP Billiton closed operations in the Globe-Miami area, and Freeport-McMoRan’s
Miami operation. The sources of the information included in this section are historic records, published
reports, and public websites as well as publically disclosed information by KGHM International Ltd. and
Freeport-McMoRan Inc. (FMI). The QP has been unable to verify the information and that the
information herein is not necessarily indicative of the mineralization on the property that is the subject
of the technical report.
Pinto Valley Mine Life Extension Study, February 2016 Page | 188
24 Other Relevant Data and Information
There are no additional data that are relevant to this report.
Pinto Valley Mine Life Extension Study, February 2016 Page | 189
25 Interpretation and Conclusions
25.1 Geology and Mineral Resources
The sampling, sample preparation, analyses and sample security are appropriate for the style of
mineralization and Mineral Resource estimation.
The Mineral Resource estimates are completed to industry standards using reasonable and appropriate
parameters and are acceptable for use in Mineral Reserve estimation. The resource estimates conform
to NI 43-101.
The mineral resources, effective 1 January 2016 and using a 0.17% Cu cut-off grade are:
Measured – 647.9 M tonnes at 0.34% total copper and 0.008% molybdenum1
Indicated – 772.3 M tonnes at 0.26% total copper and 0.006% molybdenum1
Inferred – 126.0 M tonnes at 0.25% total copper and 0.005% molybdenum1
1
The economic assumptions for the reasonable prospects pit include: $3.30/lb Cu, $10.00/lb Mo, 88% Cu recovery, 50% Mo recovery,
$1.50/ton mining costs, $1.50/ton G&A costs, $5.00/ton milling costs, and a pit slope of 45°.
25.5 Permitting
Expanding the mine life to 2039 from 2026 will require revisions of two major items:
Pinto Valley Mine Life Extension Study, February 2016 Page | 190
Aquifer Protection Permit (APP) issued by the Arizona Department of Environmental Quality to
expand an existing tailings facility, waste rock storage facility and permit a new waste rock
storage facility.
An amendment to the Plan of Operations (POO), issued by the US Forest Service, related to:
o Tailings storage expansion
o Mine expansion
o Outstanding permit renewals.
25.6 Risks
While there are significant risks with mining projects, many of those risks are mitigated by being in full
production and the required infrastructure already in place. The major risks remaining that could
materially impact the mine life are:
Financial market conditions, including supply, demand and prices of base metals, goods and
services.
Regulatory and permitting environment complexities, changes and delays
Droughts and/or regulatory changes impacting water supply
Design pit slope angles and unforeseen geotechnical conditions.
Pinto Valley Mine Life Extension Study, February 2016 Page | 191
26 Recommendations
1. Actual vs predicted ore reconciliations should be carefully evaluated in the short and medium
term to determine if additional drilling is required.
2. Ensuring the recommended pit slope angles are achieved is one of the primary keys to success
of this plan. This will be accomplished through ongoing geotechnical mapping and monitoring
the effectiveness of slope depressurization. Drilling programs may be required to increase
confidence levels of predictions.
3. Additional geotechnical and metallurgical testwork prior to commencing the first PV3 pushback
in 2020.
4. Initiate major environmental analyses and permitting processes to ensure adequate time for
regulatory agency reviews.
5. Monitoring and control of the phreatic levels in the TSF embankments is critical to the
performance of the facilities. Additional geotechnical field investigations, including cone
penetration testing, exploratory drilling, laboratory testing and engineering analyses will be
required if phreatic levels in the TSF embankments rise above predicted levels. Methods to
control or mitigate the phreatic rise would be developed. A contingency of $5M has been
included in the PV3 tailings storage capital cost estimate for these efforts, expended in 2021
through 2034.
6. If the USFS POO is not obtained by 2025 additional studies need to be undertaken to raise the
TSF4 boundary dam crest elevations.
Pinto Valley Mine Life Extension Study, February 2016 Page | 192
27 References
Arancibia, O. N and A. H. Clark. 1996 “Early Magnetite Amphibolite Plagioclase Alteration Mineralization
in the Island Copper Porphyry Copper Gold Molybdenum Deposit, British Columbia.” Economic
Geology 91: 402-38
Breitrick, R.A. and Lenzi, G.W., 1987, Pinto Valley Copper Deposit: Arizona Geological Survey Special
Paper 5, p. 260-265,
Capstone Mining Corp., Pinto Valley Mine, 2014 Pre-feasibility Study NI43-101 Technical Report:
published technical report prepared for Capstone Mining Corp., April 28, 2014, 256 p.
Capstone Mining Corp., Integrated Environmental, Health, Safety and Sustainability Policy, Revised
November 7, 2014: corporate policy statement available at
http://capstonemining.com/responsibility/environment/default.aspx.
Capstone Mining Corp., 2015, Sustainability Report: internal company report, 56 p., available at
http://capstonemining.com/responsibility/Sustainability-Report/default.aspx.
Creasey, S.C., 1980, Chronology of intrusion and deposition of porphyry copper ores, Globe-Miami
District, Arizona: Economic Geology, v. 75, p. 830-844.
Davis, B. M. 1997. Some Methods of Producing Interval Estimates for Global and Local Resources. SME
Preprint 97-5.
Gustafson, L. B. and J. P. Hunt. 1975. “The Porphyry Copper Deposit at El Salvador, Chile.” Economic
Geology 70: 857-912.
Meinert, L. D. 2000 “Gold in Skarns Related to Epizonal Intrusions: Reviews.” Economic Geology 13: 347-
75.
Peterson, N.P., Gilbert, C.M and Quick, G.L, 1951, Geology and Ore deposits of the Castle Dome Area,
Gila County, Arizona: U.S. Geological Survey Bulletin 971, 134 p.
Peterson, Nels Paul, 1962, Geology and Ore Deposits of the Globe-Miami District, Arizona: U.S.
Geological Survey Professional Paper 342, 151 p.
Sillitoe, R.H., 2010, Porphyry Copper System: Economic Geology, v. 105, 3-11.
Pinto Valley Mine Life Extension Study, February 2016 Page | 193