You are on page 1of 38

1|ADR CASES SET 1

G.R. No. L-16398 December 14, 1921 In his amended complaint he alleges that after the commencement of the action, the defendant
requested that its liability should be submitted to arbitration, in accord with the provisions of the
A. CHAN LINTE, plaintiff-appellant, policy, and that "plaintiff acceded to the requirement made by said defendant as aforesaid, but not
vs. that the award of arbitration should be conclusive or final, or deprive the courts of jurisdiction, and
LAW UNION AND ROCK INSURANCE CO., LTD., defendant-appellee. by agreement of both plaintiff and defendant Frank B. Ingersoll was named sole arbitrator, and
both parties informally presented evidence before him and he made return of arbitration to the
A. CHAN LINTE, plaintiff-appellant, effect that said plaintiff had only seven bales of hemp destroyed in the fire of April 10, 1918, as
vs. hereinbefore set forth, with which return the said plaintiff is dissatisfied, and comes to this court for
TOKYO MARINE INSURANCE CO., LTD., defendant-appellee. proper action under this amended complaint."1awphil.net

A. CHAN LINTE, plaintiff-appellant, For answer the defendant alleges that, claiming a loss under the policy, the plaintiff made a claim
vs. against the defendant for P5,000, that a difference arose between them as to the amount of the
THE CHINE FIRE INSURANCE CO., LTD., defendant-appellee. alleged loss, and that, under the terms of the policy, an arbitrator was agreed upon and selected
by the mutual consent of both parties, for the purpose of deciding the alleged difference; that on
Crossfield & O'Brien for appellant. December 28, 1918, the arbitrator found that only seven bales of hemp of the grade "ovillo" were
Fisher & DeWitt for appellees. destroyed.

For supplemental answer to the amended complaint, the defendant further alleges that on July 8,
1919, the arbitrator filed a supplemental report and award wherein he finds from the evidence
submitted that the local value of the seven bales of plaintiff's hemp destroyed by fire on April 10,
1918, was P608.34; that in addition to the defendant's policy, the same property was covered by
JOHNS, J.:
two other fire insurance polices, by each of which the property in question was insured to the
value of P5,000 against the loss; that defendant has offered and is now willing to pay plaintiff its
The plaintiff is a resident adult of the Philippine Islands, and the defendants are fire insurance one-third of the loss in full satisfaction of its liability.
companies duly licensed to do business here.
x x x           x x x          x x x
Plaintiff alleges that he was the owner of 30,992.50 kilos of hemp stored in the warehouse in
Calbayog, Province of Samar, Philippine Islands, which on the 25 of March, 1916, he requested
The other insurance companies are Tokyo Marine Insurance Co., Ltd., and the Chine Fire
the defendant Law Union and Rock Insurance Co., Ltd., to insure against loss by fire in the sum of
Insurance Co., Ltd., defendants and appellees.
P5,000, and upon the date it issued its policy No. 1,787,379 in favor of the plaintiff against such
loss until 4 o'clock p.m., of the 22nd of March, 1917, and that the policy was delivered to the
plaintiff in consideration of which he paid the company a premium of P87.50. that in consideration After the filing of the amended complaint, both parties agreed upon Frank B. Ingersoll as
of other previous payments, the policy was renewed from time to time and continued in force and arbitrator, and submitted to him the evidence pro and con. His first finding was made on
effect to and including March 22, 1919; that during the life of the policy the hemp was destroyed December 28, 1918, and on July 8, 1919, he filed a supplemental report in which he found the
by fire in the bodega where it was insured; that its value was P21,296.27; that he at once notified value of the property destroyed to be P608.34.
the defendant of the loss, and in all other respects complied with the terms and conditions of the
policy, and made a demand for the payment of the full amount of the insurance. That defendant It was stipulated "that the arbitration clauses of the policies of insurance issued by the Law Union
refused and still refuses to pay the same or any part thereof, and plaintiff prays for judgment for and Rock Insurance Co., Ltd., and the Chine Fire Insurance Co., Ltd., are in terms as follows, to
P5,000, with interest and costs. wit:
2|ADR CASES SET 1

"If any difference arises as to the amount of any loss or damage, such waived their right to contend that such arbitration is conclusive, and that no evidence of
difference shall independently of all other questions be referred to the decision the amount of the loss alleged to have been suffered by plaintiff should be considered,
of an arbitrator, to be appointed in writing by the parties in difference, or, if they but that his right to recover is limited to the amount of damage found by the arbitrator to
cannot agree upon a single arbitrator, to the decision of two disinterested have been suffered by him.
persons as arbitrators, of whom one shall be appointed in writing by each of the
parties within two calendar months after having been required so to do in writing On November 6, 1919, "it is hereby stipulated and agreed that the above entitled causes be and
by the other party. In case either party shall refuse or fail to appoint an arbitrator they are hereby submitted to the court upon the evidence taken at the trial and the depositions
within two calendar months after receipt of notice in writing requiring taken in Samar before the justice of the peace of the municipality of Calbayog, and by him
appointment, the other party shall be at liberty to appoint a sole arbitrator; and transmitted to the clerk of this court; provided, that nothing herein contained shall be construed as
in case of disagreement between the arbitrators, the difference shall be referred a waiver of the contention of defendants that the award of the arbitrator is conclusive, and that no
to the decision of an umpire who shall have been appointed by them in writing evidence of the amount of the loss other than such award should be considered."
before entering on the reference and who shall sit with the arbitrators and
preside at their meetings. The death of any party shall not revoke or affect the After the testimony was taken, the trial court rendered judgment against each of the defendants
authority or powers of the arbitrator, arbitrators or umpire respectively; and in for P202.78, and that plaintiff should pay the costs of the action, from which he appealed, claiming
the event of the death of an arbitrator or umpire, another shall in each case be that the court erred in holding that the decision of the arbitrator is conclusive or in any way binding
appointed in his stead by the party or arbitrators (as the case may be), by whom on the plaintiff; that the arbitrator's decision is in the main supported by the evidence; and that it
the arbitrator or umpire so dying was appointed. The costs of the reference and erred in not awarding judgment for the plaintiff, is prayed for in his complaint.
of the award shall be in the discretion of the arbitrator, arbitrators or umpire
making the award. And it is hereby expressly stipulated and declared that it It will be noted that the policies of the Law Union and Rock Insurance Co., Ltd., and The Chine
shall be a condition precedent to any right of action or suit upon this policy that Fire Insurance Co., Ltd., provide for arbitration and expressly stipulated "that it shall be a condition
the award by such arbitrator, arbitrators or umpire of the amount of the loss or precedent to any right of action or suit upon this policy that the award by such arbitrator,
damage if disputed shall be first obtained." arbitrators or umpire of the amount of the loss or damage if disputed shall be first obtained," and
that the action was brought without making any effort to adjust the loss by arbitration. The policy
That the arbitration clause in the policy issued by the Tokyo Marine Insurance Company, of Tokyo Marine Insurance Co., Ltd., provides that in the event of a different it "shall be submitted
Limited, is as follows, to wit: to arbitrators, indifferently chosen, whose award, or that of their umpire, shall be
conclusive."1awphil.net
If any difference shall arise with respect to any claim for loss or damage by fire and no
fraud be suspected, and the Company does not elect to rebuild, repair, reinstate or After the action was brought, and upon the request of the defendant, an arbitrator was chosen to
replace same, such difference shall be submitted to arbitrators, indifferently chosen, whom the evidence of the loss was submitted. On December 28, 1918, he found that only seven
whose award, or that of their umpire, shall be conclusive. bales of hemp of the grade "ovillo" were destroyed, but did not then make any finding as to its
value. July 8, 1919, he made and filed a supplemental report in which he found that the value of
Any liability arising out of the fire should be borne by the defendants in equal parts; that each of the hemp destroyed by the fire of April 10, 1918, was P608.34.
them has offered in writing to pay the plaintiff its one-third of the amount of the plaintiff's loss, as
ascertained by the arbitrator. The plaintiff contends; First, that the arbitration clauses are null and void as against public policy;
second, that the award of the arbitrator of December 28, 1918, without finding the value of the
It is understood that in making this stipulation plaintiff shall not be deemed to have property destroyed, was final, and that on July 8, 1919, he had no authority to make a
waived his right to contend, as a matter of law or fact, that the award of the arbitrator is supplemental finding as to the value of the property; and, third, that upon the evidence the court
not conclusive upon him and that the arbitrator was without authority to supplement or should have found for the plaintiff. Upon the first point he cites the case of Wahl and
amend his findings after having once rendered decision; and that defendants have not Wahl vs. Donaldson, Sims and Co. (2 Phil., 301), which apparently sustains his contention. That
3|ADR CASES SET 1

case holds that "a clause in a contract providing that all matters in dispute between the parties action on the award the award itself is conclusive evidence of all matters therein
shall be referred to arbitrators and to them alone is contrary to public policy and cannot oust the contained, provided the arbitrators have not exceeded the powers delegated to them by
courts of jurisdiction." the agreement of submission. The courts regard matters submitted as concluded by the
award, and in an action thereon they will not review the merits of the arbitrators' findings.
In Chang vs. Royal Exchange Assurance Corporation of London (8 Phil., 399), agreement was
very similar to the one here with the two defendants above quoted, and it was there held that such Corpus Juris, vol. 5, p. 16, says:
a condition for arbitration is valid, and that, unless there was an effort to comply, no action could
be maintained. The statement of controversies by arbitration is an ancient practice at common law. In its
broad sense it is a substitution, by consent of parties, of another tribunal for the tribunals
In Allen vs. Province of Tayabas (38 Phil., 356), it is said: provided by the ordinary processes of law; a domestic tribunal, as contradistinguished
from a regularly organized court proceeding according to the course of the common law,
. . . It would be highly improper for courts out of untoward jealousy to annul laws or depending upon the voluntary act of the parties disputant in the selection of judges of
agreements which seek to oust the courts of their jurisdiction. . . . Unless the agreement their own choice. Its object is the final disposition, in a speedy and inexpensive way, of
is such as absolutely to close the doors of the courts against the parties, which the matters involved, so that they may not become the subject of future litigation
agreement would be void. (Wahl and Wahl vs. Donaldson, Sims and Co. [1903], 2 Phil., between the parties.
301), courts will look with favor upon such amicable arrangements and will only with
great reluctance interfere to anticipate or nullify the action of the arbitrator. . . . On page 20, it is said:

In the instant case, it will be noted that sometime after the action was commenced and upon the APPROVED METHOD OF SETTLEMENT; FAVORED BY CONSTRUCTION.
request of the defendants, the plaintiff agreed to arbitrate under the terms and provisions of the
policies; that the parties mutually agreed upon an arbitrator; and that each appeared before him — Although arbitration was recognized at the common law as a mode of adjusting
and offered his or its evidence upon the questions in dispute. There is no claim or pretense that matters in dispute, especially such as concerned personal chattels and personal wrongs,
the proceedings were not honestly and fairly conducted. Having formally agreed and submitted to yet, from efforts perceptible in the earlier cases to construe arbitration proceedings and
an arbitration after the action was commenced, it may well be doubted whether the plaintiff can at awards so as to defeat them, it would seem that they were not originally favored by the
this time question the validity of the proceedings, except upon the ground of fraud or mistake. courts. This hostility, however, has long since disappeared, and, by reason of the fact
that the proceeding represents a method of the parties' own choice and furnishes a more
Ruling Case Law, vol. 2, p. 359, says that when the subject-matter of a pending suit is submitted expeditious and less expensive means of settling controversies than the ordinary course
to arbitration without rule of court "there is a conflict among the authorities as to whether or not the of regular judicial proceedings, it is the policy of the law to favor arbitration. Therefore
mere submission effects a discontinuance of the action. The majority rule is that the parties every reasonable intendment will be indulged to give effect to such proceedings, and in
themselves show an intent to discontinue the pending suit by substituting another tribunal, so that favor of the regularity and integrity of the arbitrators' acts.
a submission furnishes ground for a discontinuance."
On page 43, it is said:
On page 352 of the same volume, it is said:
Where a contract contains a stipulation, not that all questions arising thereunder, whether
Arbitration as a method of settling disputes and controversies is recognized at common as to the validity or effect of such contract, or otherwise, shall be submitted to arbitration,
law. The award of the arbitrators is binding on the parties, but, in the absence of statute, but that the decision of arbitrators on a certain question or questions, such as the
the successful party can only enforce his rights thereunder by a suit at law. Thus the only quantity, quality, or price of materials or workmanship, the value of work, the amount of
gain by a common law arbitration is the substitution of the definite findings of the award loss or damage, or the like, shall be a condition precedent to the right of action on the
as the basis of a suit, in the place of the former unsettled rights of the parties. In an contract itself, no fixed sum being stated in the contract, such stipulation will be enforced,
4|ADR CASES SET 1

because the parties to a contract have a right to adopt whatever method they see fit for
determining such questions, and until the method adopted has been pursued, or some
sufficient reason given for not pursuing it, no action can be brought on the contract.
"Freedom to contract for arbitration to this extent," it has been said, "imports no invasion
of the province of the courts, and there is no ground upon which a right so essential to
the convenient transaction of modern business affairs can be denied," nor is such
agreement objectionable as being against public policy. In order to give effect to such an
agreement it must of course appear that the matter proposed to be referred is a
difference, within the meaning of the agreement.

In the instant case, there was no dispute about the policy of insurance or the fire. The only real
difference was the amount of the loss which plaintiff sustained, and that was the only question
submitted to arbitration. In December, the arbitrator found the amount of plaintiff's hemp which
was destroyed, but did not find its value.

Hence the award on the question submitted was not complete or final. In the finding of the actual
value of the hemp, there was no change or revision of any previous finding. It was simply the
completion by the arbitrator of an unfinished work. No formal notice was served on the arbitrator,
and he was not removed or discharged, and until such time as his duties were fully performed, or
he was discharged, he would have the legal right to complete his award. The plaintiff, having
agreed to arbitration after the action was commenced and submitted his proof to the arbitrator, in
the absence of fraud or mistake, is estopped and bound by the award. Where a plaintiff has
commenced an action to recover upon an insurance policy, and then voluntarily submits the
amount of his loss to arbitration, he cannot ignore or nullify the award and treat it as void upon the
ground that he is dissatisfied with the decision.

Judgment is affirmed, with costs to the appellee. So ordered.


5|ADR CASES SET 1

G.R. No. L-21549             October 22, 1924 The defendant company appealed from this judgment, and alleges that the lower court erred in
having held itself with jurisdiction to take cognizance of and render judgment in the cause; in
TEODORO VEGA, plaintiff-appellee, holding that the defendant was bound to supply cars gratuitously to the plaintiff for the cane; in not
vs. ordering the plaintiff to pay to the defendant the sum of P2,866 for the cars used by him, with
THE SAN CARLOS MILLING CO., LTD., defendant-appellant. illegal interest on said sum from the filing of the counterclaim, and the costs, and that said
judgment is contrary to the weight of the evidence and the law.
Fisher, Dewitt, Perkins, & Brady, John R. McFie, Jr., Jesus Trinidad, and Powell & Hill for
appellant. The first assignment of error is based on clause 23 of the Mill's covenants and clause 14 of the
R. Nolan and Feria & La O for appellee. Planter's Covenant as they appear in Exhibit A, which is the same instrument as Exhibit 1.

Said clauses are as follows:

23. That it (the Mill — Party of the first part) will submit and all differences that may arise
ROMUALDEZ, J.: between the Mill and the Planters to the decision of arbitrators, two of whom shall be
chosen by the Mill and two by the Planters, who in case of inability to agree shall select a
This action is for the recovery of 32,959 kilos of centrifugal sugar, or its value, P6,252, plus the fifth arbitrator, and to respect and abide by the decision of said arbitrators, or any three of
payment of P500 damages and the costs. them, as the case may be.

The defendants filed an answer, and set up two special defenses, the first of which is at the same xxx     xxx     xxx
time a counterclaim.
14. That they (the Planters--Parties of the second part) will submit any and all differences
The Court of First Instance of Occidental Negros that tried the case, rendered judgment, the that may arise between the parties of the first part and the parties of the second part of
dispositive part of which is as follows: the decision of arbitrators, two of whom shall be chosen by the said parties of the first
part and two by the said party of the second part, who in case of inability to agree, shall
By virtue of these considerations, the court is of opinion that with respect to the select a fifth arbitrator, and will respect and abide by the decision of said arbitrators, or
complaint, the plaintiff must be held to have a better right to the possession of the 32,959 any three of them, as the case may be.
kilos of centrifugal sugar manufactured in the defendants' central and the latter is
sentenced to deliver them to the plaintiff, and in default, the selling price thereof, It is an admitted fact that the differences which arose between the parties, and which are the
amounting to P5,981.06 deposited in the office of the clerk of the court. Plaintiff's claim subject of the present litigation have not been submitted to the arbitration provided for in the
for damages is denied, because it has not been shown that the defendant caused the above quoted clauses.
plaintiff any damages. Plaintiff is absolved from defendant's counterclaim and declared
not bound to pay the such claimed therein. Plaintiff is also absolved from the Defendant contends that as such stipulations on arbitration are valid, they constitute a condition
counterclaim of P1,000, for damages, it not having been proved that any damages were precedent, to which the plaintiff should have resorted before applying to the courts, as he
caused and suffered by defendant, since the writ of attachment issued in this case was prematurely did.
legal and proper. Without pronouncement as to costs.
The defendant is right in contending that such covenants on arbitration are valid, but they are not
So ordered. for the reason a bar to judicial action, in view of the way they are expressed:
6|ADR CASES SET 1

An agreement to submit to arbitration, not consummated by an award, is no bar to suit at The second raises the most important question in this controversy, to wit: Whether or not the
law or in equity concerning the subject matter submitted. And the rule applies both in defendant was obliged to supply the plaintiff which cars gratuitously for cane.
respect of agreements to submit existing differences and agreements to submit
differences which may arise in the future. (5 C. J., 42.) The Central, of course, bound itself according to the contract exhibit A in clause 3 of the
"Covenant by Mill," as follows:
And in view of the terms in which the said covenants on arbitration are expressed, it cannot be
held that in agreeing on this point, the parties proposed to establish the arbitration as a condition 3. That it will construct and thereafter maintain and operate during the term of this
precedent to judicial action, because these clauses quoted do not create such a condition either agreement a steam or motor railway, or both, for plantation use in transporting sugar
expressly or by necessary inference. cane, sugar and fertilizer, as near the center of the can ands as to contour of the lands
will permit paying due attention to grades and curves; that it will also construct branch
Submission as Condition Precedent to Suit. — Clauses in insurance and other contracts lines at such points as may be necessary where the present plantations are of such
providing for arbitration in case of disagreement are very similar, and the question shape that the main line cannot run approximately through the center of said plantations,
whether submission to arbitration is a condition precedent to a suit upon the contract free of charge to the Planters, and will properly equip said railway with locomotives or
depends upon the language employed in each particular stipulation. Where by the same motors and cars, and will further construct a branch line from the main railway line, mill
agreement which creates the liability, the ascertainment of certain facts by arbitrators is and warehouses to the before mentioned wharf and will further construct yard
expressly made a condition precedent to a right of action thereon, suit cannot be brought accomodations near the sugar mill. All steam locomotives shall be provided which
until the award is made. But the courts generally will not construe an arbitration clause as effective spark arresters. The railway shall be constructed upon suitable and properly
ousting them of their jurisdiction unless such construction is inevitable, and consequently located right-of-way, through all plantations so as to give, as far as practicable, to each
when the arbitration clause is not made a condition precedent by express words or plantations equal benefit thereof; said right-of-way to b two and one-half meters in width
necessary implication, it will be construed as merely collateral to the liability clause, and on either said from the center of track on both main line and switches and branches.
so no bar to an action in the courts without an award. (2 R. C. L., 362, 363.)
By this covenant, the defendant, the defendant bound itself to construct branch lines of the railway
Neither does not reciprocal covenant No. 7 of said contract Exhibit A expressly or impliedly at such points on the estate as might be necessary, but said clause No. 3 can hardly be construed
establish the arbitration as a condition precedent. Said reciprocal covenant No. 7 reads: to bind the defendant to gratuitously supply the plaintiff with cars to transport cane from his fields
to the branch lines agreed upon on its estate.
7. Subject to the provisions as to arbitration, hereinbefore appearing, it is mutually
agreed that the courts of the City of Iloilo shall have jurisdiction of any and all judicial But on March 18, 1916, the defendant company, through its manager Mr. F. J. Bell, addressed the
proceedings that may arise out of the contractual relations herein between the party of following communication to the plaintiff:
the first and the part is of the second part.
DEAR SIR: In reply to yours of March 15th.
The expression "subject to the provisions as to arbitration, hereinbefore appearing" does not
declare such to be a condition precedent. This phrase does not read "subject to the arbitration," Yesterday I tried to come out to San Antonio to see you but the railway was full
but "subject to the provisions as to arbitration hereinbefore appearing." And, which are these of cars of San Jose and I could not get by with my car. I will try again as soon
"provisions as to arbitration hereinbefore appearing?" Undoubtedly clauses 23 and 14 quoted as I finish shipping sugar. The steamer is expected today.
above, which do not make arbitration a condition precedent.
I had a switch built in the big cut on San Antonio for loading your cane near the
We find no merit in the first assignment of error. boundary of Santa Cruz. will not this sufficient? We have no another switch here
and I hope you can get along with the 3 you now have.
7|ADR CASES SET 1

Some of the planters are now using short switches made of 16-lb. portable We do not find sufficient reason to support the second assignment of error.
track. These can be placed on the main line at any place and cars run off into
the field and loaded. I think one on your hacienda would repay you in one The point raised in the third assignment of error is a consequence of the second. If the plaintiff
season. was entitled, as we have said, to use the cars gratuitously, the defendant has no right to demand
any payment from him for the use of said cars.
The rain record can wait.
The other assignments of error are consequences of the preceding ones.
                              Sincerely yours,
We find nothing in the record to serve as a legal and sufficient bar to plaintiff's action against the
SAN CARLOS MILLING CO., LTD.           (Sgd.) F.J. BELL          defendant for the delivery of the sugar in question, or its value. A discussion as to the retention of
"Manager"           this deposit to apply upon what is due by reason thereof made in the judgment appealed from, is
here necessary. The parties do not raise this question in the present instance. Furthermore, it has
It is suggested to the plaintiff in this letter that he install a 16-lb. rail portable track switch, to be not been proven that the plaintiff owes the defendant anything by reason of such deposit.
used in connection with the main line, so the cars may run on it. It is not suggested that he
purchase cars, and the letter implies that the cars mentioned therein belong to the defendant. The judgment appealed from is hereby affirmed with the costs of this instance against the
appellant. So ordered.
As a result of this suggestion, the plaintiff bought a portable track which cost him about P10,000,
and after the track was laid, the defendant began to use it without comment or objection from the Johnson, Street and Villamor, JJ., concur.
latter, nor payment of any indemnity for over four years.
G.R. No. L-37878             November 25, 1932
With this letter Exhibit D, and its conduct in regard to the same, the defendant deliberately and
intentionally induced the plaintiff to believe that by the latter purchasing the said portable track, MANILA ELECTRIC COMPANY, petitioner,
the defendant would allow the free use of its cars upon said track, thus inducing the plaintiff to act vs.
in reliance on such belief, that is, to purchase such portable track, as in fact he did and laid it and PASAY TRANSPORTATION COMPANY, INC., ET AL., respondents.
used it without payment, the cars belonging to the defendant.
Ross, Lawrence & Selph for petitioner.
This is an estoppel, and defendant cannot be permitted to gainsay its own acts and agreement. Rivera & Francisco for respondent Pasay Transportation Co.
P. A. Remigio for respondent E. B. Gutierrez. A. M. Zarate for respondent Raymundo
The defendant cannot now demand payment of the plaintiff for such use of the cars. And this is Transportation Co.
so, not because the fact of having supplied them was an act of pure liberality, to which having Vicente Ampil for respondent J. Ampil.
once started it, the defendant was forever bound, which would be unreasonable, but because the
act of providing such cars was, under the circumstances of the case, of compliance of an
obligation to which defendant is bound on account of having induced the plaintiff to believe, and to
act and incur expenses on the strenght of this belief.
MALCOLM, J.:
The question of whether or not the plaintiff was under the necessity of first showing a cooperative
spirit and conduct, does not affect the right which he thus acquired of using the cars in question The preliminary and basic question presented by the petition of the Manila Electric Company,
gratuitously. requesting the members of the Supreme Court, sitting as a board of arbitrators, to fix the terms
8|ADR CASES SET 1

upon which certain transportation companies shall be permitted to use the Pasig bridge of the We would not be understood as extending the principles governing arbitration and award too far.
Manila Electric Company and the compensation to be paid to the Manila Electric Company by Unless the arbitration agreement is such as absolutely to close the doors of the courts against the
such transportation companies, relates to the validity of section 11 of Act No. 1446 and to the parties, the courts should look with favor upon such amicable arrangements. We can also
legal right of the members of the Supreme Court, sitting as a board of arbitrators, to act on the perceive a distinction between a private contract for submission to arbitration and agreements to
petition. Act No. 1446 above referred to is entitled. "An Act granting a franchise to Charles M. arbitrate falling within the terms of a statute enacted for such purpose and affecting others than
Swift to construct, maintain, and operate an electric railway, and to construct, maintain, and the parties to a particular franchise. Here, however, whatever else may be said in extenuation, it
operate an electric light, heat, and power system from a point in the City of Manila in an easterly remains true that the decision of the board of arbitrators is made final, which if literally enforced
direction to the town of Pasig, in the Province of Rizal." Section 11 of the Act provides: "Whenever would leave a public utility, not a party to the contract authorized by Act No. 1446, without
any franchise or right of way is granted to any other person or corporation, now or hereafter in recourse to the courts for a judicial determination of the question in dispute.
existence, over portions of the lines and tracks of the grantee herein, the terms on which said
other person or corporation shall use such right of way, and the compensation to be paid to the Counsel for the petitioner rely principally on the case of Tallassee Falls Mfg. Co. vs.
grantee herein by such other person or corporation for said use, shall be fixed by the members of Commissioner's Court [1908], 158 Ala., 263. It was there held that an Act of a state legislature
the Supreme Court, sitting as a board of arbitrators, the decision of a majority of whom shall be authorizing the commissioners' court of a certain county to regulate and fix the rate of toll to be
final." charged by the owners of a bridge is not unconstitutional as delegating legislative power to the
courts. But that is not the question before us. Here the question is not one of whether or not there
When the petition of the Manila Electric Company was filed in this court, it was ordered that the has been a delegation of legislative authority to a court. More precisely, the issue concerns the
petitioner be required to serve copies on the Attorney-General and the transportation companies legal right of the members of the Supreme Court, sitting as a board of arbitrators the decision of a
affected by the petition. Thereafter, the Attorney-General disclaimed any interest in the majority of whom shall be final, to act in that capacity.
proceedings, and opposition was entered to the petition by a number of public utility operators. On
the submission of memoranda after an oral hearing, the petition was made ready for resolution. We run counter to this dilemma. Either the members of the Supreme Court, sitting as a board of
arbitrators, exercise judicial functions, or the members of the Supreme Court, sitting as board of
Examining the statutory provision which is here invoked, it is first noted that power is attempted to arbitrators, exercise administrative or quasi judicial functions. The first case would appear not to
be granted to the members of the Supreme Court sitting as a board of arbitrators and to the fall within the jurisdiction granted the Supreme Court. Even conceding that it does, it would
Supreme Court as an entity. It is next seen that the decision of a majority of the members of the presuppose the right to bring the matter in dispute before the courts, for any other construction
Supreme Court is made final. And it is finally observed that the franchise granted the Manila would tend to oust the courts of jurisdiction and render the award a nullity. But if this be the proper
Electric Company by the Government of the Philippine Islands, although only a contract between construction, we would then have the anomaly of a decision by the members of the Supreme
the parties to it, is now made to effect the rights of persons not signatories to the covenant. Court, sitting as a board of arbitrators, taken therefrom to the courts and eventually coming before
the Supreme Court, where the Supreme Court would review the decision of its members acting as
The law calls for arbitration which represents a method of the parties' own choice. A submission to arbitrators. Or in the second case, if the functions performed by the members of the Supreme
arbitration is a contract. The parties to an arbitration agreement may not oust the courts of Court, sitting as a board of arbitrators, be considered as administrative or quasi judicial in nature,
jurisdiction of the matters submitted to arbitration. These are familiar rules which find support in that would result in the performance of duties which the members of the Supreme Court could not
articles 1820 and 1821 of the Civil Code. Citation of authority is hardly necessary, except that it lawfully take it upon themselves to perform. The present petition also furnishes an apt illustration
should be recalled that in the Philippines, and in the United States for that matter, it has been held of another anomaly, for we find the Supreme Court as a court asked to determine if the members
that a clause in a contract, providing that all matters in dispute between the parties shall be of the court may be constituted a board of arbitrators, which is not a court at all.lawphil.net
referred to arbitrators and to them alone, is contrary to public policy and cannot oust the courts of
jurisdiction (Wahl and Wahl vs. Donaldson, Sims & Co. [1903], 2 Phil., 301; The Supreme Court of the Philippine Islands represents one of the three divisions of power in our
Puentebella vs. Negros Coal Co. [1927], 50 Phil., 69; Vega vs. San Carlos Milling Co. [1924], 51 government. It is judicial power and judicial power only which is exercised by the Supreme Court.
Phil., 908; District of Columbia vs. Bailey [1897], 171 U. S., 161.) Just as the Supreme Court, as the guardian of constitutional rights, should not sanction
usurpations by any other department of the government, so should it as strictly confine its own
9|ADR CASES SET 1

sphere of influence to the powers expressly or by implication conferred on it by the Organic Act. to act on the petition of the Manila Electric Company. As a result, the members of the Supreme
The Supreme Court and its members should not and cannot be required to exercise any power or Court decline to proceed further in the matter.
to perform any trust or to assume any duty not pertaining to or connected with the administering of
judicial functions. Avanceña, C.J., Street, Villamor, Ostrand, Villa-Real, Abad Santos, Hull, Vickers, Imperial and
Butte, JJ., concur
The Organic Act provides that the Supreme Court of the Philippine Islands shall possess and
exercise jurisdiction as heretofore provided and such additional jurisdiction as shall hereafter be EN BANC
prescribed by law (sec. 26). When the Organic Act speaks of the exercise of "jurisdiction" by the
Supreme Court, it could not only mean the exercise of "jurisdiction" by the Supreme Court acting [G.R. No. L-9090. September 10, 1957.]
as a court, and could hardly mean the exercise of "jurisdiction" by the members of the Supreme
Court, sitting as a board of arbitrators. There is an important distinction between the Supreme EASTBOARD NAVIGATION, LTD., Plaintiff-Appellant, v. JUAN YSMAEL and COMPANY,
Court as an entity and the members of the Supreme Court. A board of arbitrators is not a "court" INC., Defendant-Appellant.
in any proper sense of the term, and possesses none of the jurisdiction which the Organic Act
contemplates shall be exercised by the Supreme Court.lawph!l.net Ross, Selph, Carrascoso & Janda and Delfin L. Gonzalez for the plaintiff and Appellant.

In the last judicial paper from the pen of Chief Justice Taney, it was said: Claro M. Recto for the defendant and appellant.

The power conferred on this court is exclusively judicial, and it cannot be required or
authorized to exercise any other. . . . Its jurisdiction and powers and duties being defined SYLLABUS
in the organic law of the government, and being all strictly judicial, Congress cannot
require or authorize the court to exercise any other jurisdiction or power, or perform any
other duty. . . . The award of execution is a part, and an essential part of every judgment 1. CHARTER PARTY; COMPULSORY ARBITRATION, WHEN BIDDING UPON THE PARTIES;
passed by a court exercising judicial power. It is no judgment, in the legal sense of the CASE AT BAR. — The defendant corporation., through its president and general manager,
term, without it. Without such an award the judgment would be inoperative and nugatory, chartered plaintiff’s vessel to load a cargo of scrap iron in the Philippines for Buenos Aires. The
leaving the aggrieved party without a remedy. It would be merely an opinion, which charter party agreement contained, besides the regular charter party printed form, a typewritten
would remain a dead letter, and without any operation upon the rights of the parties, clause providing a foreign compulsory arbitration in case of any dispute that may arise out of said
unless Congress should at some future time sanction it, and pass a law authorizing the agreement. It appears that the defendant corporation, through its said president and general
court to carry its opinion into effect. Such is not the judicial power confided to this court, manager, signed not only the printed portion of the charter party but the typewritten portion as
in the exercise of its appellate jurisdiction; yet it is the whole power that the court is well, which contains the arbitration clause. Moreover, after a dispute as to the liability of the
allowed to exercise under this act of Congress. . . . And while it executes firmly all the defendant corporation arose, said president and general manager appointed lawyers in New York
judicial powers entrusted to it, the court will carefully abstain from exercising any power to represent defendant corporation in the arbitration proceedings to be held in that state. Held: If
that is not strictly judicial in its character, and which is not clearly confided to it by the the defendant corporation did not really intend to submit its dispute with the plaintiff to arbitration,
Constitution. . . . (Gordon vs. United States [1864], 2 Wall., 561; 117 U. S., 697 the logical step it should have taken would be to repudiate the act of its president and general
Appendix.) manager, but far from doing so, it approved and ratified it by subsequent acts which clearly
indicate that it was agreeable to said arbitration. Consequently, said arbitration agreement is
Confirming the decision to the basic question at issue, the Supreme Court holds that section 11 of binding on the defendant corporation, and the arbitration proceedings as well as the arbitration
Act No. 1446 contravenes the maxims which guide the operation of a democratic government decision rendered pursuant thereof, as confirmed by the District Court of New York, are valid;
constitutionally established, and that it would be improper and illegal for the members of the hence enforceable in this jurisdiction.
Supreme Court, sitting as a board of arbitrators, the decision of a majority of whom shall be final,
2. ID.; ARBITRATION AGREEMENT VALID; ARBITRATION LAW IN THIS JURISDICTION
10 | A D R C A S E S S E T 1

STATED. — While there are authorities which hold that "a clause in a contract providing that all
matters in dispute between the parties shall be referred to arbitrators and to them, is contrary to
public and cannot oust the courts of jurisdiction" (Manila Electric Co. v. Pasay Transportation Co., BAUTISTA ANGELO, J.:
57 Phil., 600, 603), however, there are authorities which favor" the more intelligent view that
arbitration, as an inexpensive speedy and amicable method of settling disputes, and as a means
of avoiding litigation, should receive every encouragement from the courts which may be This is an appeal from a decision of the Court of First Instance of Manila ordering defendant to
extended without contravening sound public policy or settled law" (3 Am. Jur., p. 835). congress pay to plaintiff the sum of $53,037.89 as awarded by a board of arbitrators on June 20, 1950 and
has officially adopted this modern view when it reproduced in the new Civil Code the provisions of confirmed by the District Court of New York, U. S. A. on August 15, 1950, with legal interest
the Old Code on arbitration. And only recently it approved Republic Act No. 876 expressly thereon from December 5, 1950 until its payment, and the costs of suit.
authorizing arbitration of future disputes.
The facts involved in this case which are necessary to be considered in this appeal are stated by
3. FOREIGN CORPORATIONS; CAPACITY TO SUE EVEN WITHOUT A LICENSED. — A the trial court in its decision which we find to be substantially correct. They are: "On July 25, 1949,
foreign corporation has capacity to sue even without a license to transact business; if it is not Atkins, Kroll & Co., Inc., Manila, wrote defendant Juan Ysmael & Co., Inc., (letter Exh. 1) advising
engaged in business in the Philippines. Isolated transactions do not constitute engaging in that plaintiff Eastboard Navigation, Ltd., of Toronto, Canada, owners of the S/S Eastwater, ‘have
business within the purview of Sections 68 and 69 of the Corporation Law so as to bar a foreign accepted your terms of payment and are agreed to charter the S/S Eastwater to Juan Ysmael &
corporation from seeking redress in the Philippine courts. Company, Inc., Manila, (to load cargo of scrap iron in the Philippines for Buenos Aires) under the
following terms and conditions: . . . (10) Clause Paramount: Terms and conditions for this Charter
4. Foreign exchange TAX; CIRCUMSTANCES DEFEATING CLAIM FOR PAYMENT; ABOLITION Party not explicitly or otherwise stated in this letter of confirmation are to be as per general
OF TAX. — Considering that the plaintiff failed to present any evidence that the defendant’s conditions of regular Charter Party form. Will you kindly signify confirmation of the above terms by
refusal to pay the award is due to fraud or bad faith; that if there is any agreement to pay the signing the original and four copies of this letter? A formal copy of the Charter Party document will
instant obligation in a currency other than the Philippine currency, the same is null and void as be forwarded to you within a few days. Atkins, Kroll & Co., Inc., Manila, acting solely as agents for
contrary to public policy (Republic Act No. 529), and the most that it could be demanded is to pay and in behalf of the owners of the S/S Eastwater by cable or letter authority, sincerely hope we
said obligation in Philippine currency to be measured in the prevailing rate of exchange at the time may be of service to all parties concerned and that the cargo will go forward as scheduled in a
the obligation was incurred (section 1, Idem.); that inasmuch as the decree of New York District satisfactory manner.’ Defendant signed said letter thus, ‘For Charter Party: Juan Ysmael & Co.,
Court which is now sought to be enforced does not specify the place where the obligation should Inc., K. H. Hemady, President.’ On the same date, July 25, 1949, charter party agreement (Exhibit
be paid, and hence the judgment debtor, herein defendant, may discharge the same here in A) was executed containing, besides the regular charter party printed form, a typewritten clause
Manila which is its domicile; Held: There is no valid reason for upholding the claim that the reading: ‘Clauses Nos. 16 to 31 inclusive and U.S.A. Clause Paramount, War Risks Clauses 1
defendant, should it be ordered to pay the award, the pay the foreign exchange tax required by and 2, Now Jason Clause and Both-to-Blame Collision Clauses, as attached, to be considered as
the law at the time the obligation fell due. fully incorporated herein and to form part of this Charter Party.’ Clause No. 29 reads as
follows:chanrob1es virtual 1aw library
5. ATTORNEY’S FEES; WHEN THE PLAINTIFF MAY BE ENTITLED TO FEES. — In order that
the plaintiff may be entitled to attorney’s fees under Article 2208, sub-paragraph 5, of the new ‘It is mutually agreed that should any dispute arise between Owners and Charterers, the matter in
Civil Code, it is necessary that it be proven that defendant acted "in gross and evident bad faith" in dispute shall be referred to three persons at New York for arbitration, one to be appointed by each
refusing plaintiff’s claim. Since plaintiff did not present any evidence on this point the lower did not of the parties hereto, and the third by the two so chosen; their decision or that of any two of them,
err in denying its claim on this score. shall be final, and for the purpose of enforcing any award, this agreement may be made a rule of
the Court. The arbitrators shall be commercial men. Should the two so chosen not be able to
agree who the third arbitrator should be, then the New York Produce Exchange is to appoint such
third Arbiter. The amount in dispute shall be placed in escrow at New York subject to the decision
DECISION of the arbitrators.’
11 | A D R C A S E S S E T 1

"On September 8, 1949, Atkins, Kroll & Co., Inc., Manila, again wrote defendant company as ‘We expect to be able to report to you on the above-described collection sometime next week.’
follows (letter EXhibit 3):chanrob1es virtual 1aw library
"On December 3, 1949, defendant Company wrote the Bank of America (Manila) (letter Exhibit 3-
‘We are today in receipt of the following cable instructions from our principals the Eastboard B) as follows:chanrob1es virtual 1aw library
Navigation Ltd., regarding the release of your bills of lading covering balance of your scrap iron
loaded at Manila:jgc:chanrobles.com.ph ‘Please transmit by telegraphic transfer to Irving Trust Company, New York, the amount of Ten
Thousand Dollars ($10,000), for the account of Eastboard Navigation Ltd., Toronto, Canada, to be
"Re Yours sixth agree release bladings against full payment of freight and guarantee by Irving held as deposit for demurrage due the SS Eastwater, together with the $15,000 previously
Trust Newyork fifteen thousand dollars covering possible demurrage to be settled in accordance remitted to them. The amount shall be held pending result of the arbitration of the dispute
with ruling of arbitration board Newyork please have Ysmael immediately nominate their between this Company and Eastboard Navigation.’
arbitrator"
"The dispute mentioned in its preceding letter having arisen, under date of April 5, 1950, the
‘In order to facilitate your negotiations of your documents with the Bank of America we shall defendant cabled Attys. Manning, Harnisch and Hollinger of New York City as follows: ‘Through
appreciate very much your putting up a guarantee by Irving Trust New York for the sum of US recommendation of Mr. Morris Lipsett we request you kindly present our case before Arbitration
$15,000.00 and to nominate the name of your arbitrator immediately.’ Board re charter vessel S/S Eastwater Writing" (Exhibit 2). And in its letter Exhibit 2-B of the same
date to said attorneys, defendant confirmed its request as follows:chanrob1es virtual 1aw library
"On October 1, 1949, the Bank of America, Manila Office, wrote defendant company (letter Exhibit
3-A) as follows:chanrob1es virtual 1aw library ‘Our good friend, Mr. Morris E. Lipsett, of the Lipsett Pacific Corporation, 80 Wall Street, New
York, has highly recommended your law firm to us to present our case to the arbitration in a case
‘In accordance with verbal instructions of your President, Mr. K. Hemady, your draft for we have with the Eastboard Navigation Co., Ltd., in connection with our charter of their vessel the
$76,354.55 and attached documents were airmailed this morning to the above bank together with S/S Eastwater. May we, therefore, request you to act as such attorney for us, and you may bill us
the relative bills of lading which were surrendered to us by Atkins Kroll & Co., Inc., for account and accordingly for your services in the matter.
by order of Eastboard Navigation, Ltd. of Toronto.
‘We have already spent a considerable sum on this case, not to mention the inconvenience it has
‘The documents, which were sent for collection, cover the third and last shipment under the caused us, and we are most anxious that the matter be terminated as soon as possible.
assignment made to you by Mr. Hector Corvera under the terms of the subject credit and
cover:chanrob1es virtual 1aw library ‘Pertinent papers and documents regarding the matter have been turned over to Mr. Lipsett, and
we have requested him to turn those over to you for your purposes. Should you, however, need
x       x       x further information regarding the matter, or should you need our assistance at this end, please
feel free to ask us.’

‘Deposit account Demurrage under Arbitration — $15,000. "On May 23, 1959, Messrs, Manning, Harnisch and Hollinger, acting as attorneys for defendant
Juan Ysmael & Co., Inc., executed with the attorney for plaintiff Eastboard Navigation Ltd.,
x       x       x arbitration agreement (Exhibit B) which reads:chanrob1es virtual 1aw library

‘We, the undersigned, hereby mutually covenant and agree to submit, and hereby do submit to
‘We have requested the Irving Trust Company to advise us by cable when the above amounts Charles I. Lambert, Richard Nathan and Donald E. Simmons, as Arbitrators, for their adjudication
have been paid. In the event of non-payment, we have requested that they deliver the bills of and award, a controversy existing between us relating to the liability if any, of the undersigned,
lading to the Eastboard Navigation Ltd., under cable advice. Juan Ysmael & Co., Inc., charterers to the undersigned, Eastboard Navigation, Ltd., owners of the
S/S Eastwater, for demurrage, discharging expenses, wharfage, extra meals agency fees, crew
12 | A D R C A S E S S E T 1

overtime and miscellaneous expenses, under charter party of the S/S Eastwater dated July 25th, shares; Felipe Ysmael, 770 shares; Carlos Kemel Ysmael, 830 shares; Juan Ysmael y Cortes, 1
1949. share; and Gabriel Ysmael, 1 share or a total of 17,000 shares; that plaintiff, during the time
material to this case, was not licensed to transact business in the Philippines; that this is the first
‘And we mutually covenant and promise that the award to be made by said Arbitrators or by a business transaction made locally by plaintiff, although previously plaintiff’s vessel was chartered
majority of them, shall be well and faithfully kept and observed by us, and by each of us. by the National Rice and Corn Corporation to carry rice cargo to the Philippines, the charter party
thereto being dated April 5, 1949; that the charter party Exhibit A is one approved by the
‘And it is hereby further mutually agreed that a judgment of the United States District Court for the Documentary Council of the Baltic and White Sea Conference and that one of its standard
Southern District of New York shall be rendered upon the award made pursuant to this stipulation is a clause regarding arbitration; that K. H. Hemady, now deceased, as president and
submission. general manager of defendant, for 25 years had entered into numerous other contracts with third
parties in representation of defendant all of which were never ratified nor repudiated by its Board
‘WITNESS, our hands this 23rd day of May, 1950.’ of Directors; that one of the arbitrators Richard Nathan was appointed by defendant corporation,
another one Donald E. Simmons was appointed by plaintiff, and these two appointed a third one
"Pursuant to said arbitration agreement, the three arbitrators in New York City passed upon the Charles P. Lambert; and that the defense that K. H. Hemady was not authorized by the Board of
differences between the plaintiff and the defendant ‘after having heard and received evidence Directors of defendant corporation to enter into the arbitration agreement was raised for the first
submitted by both sides’, and rendered their arbitration decision (Exhibit C). This arbitration time in these proceedings, which means that it was not raised in the arbitration proceedings in
decision was presented by plaintiff to the U.S. District Court, Southern District of New York, for New York, nor in the proceedings held to confirm the award in the U. S. District Court of the
confirmation, (Admiralty No. A165-362) and said Court confirmed the said arbitration decision in Southern District of New York. In addition to this stipulation of facts, plaintiff and defendant
its Order and Final Decree of August 15, 1950, (Exhibit D) ordering ‘that the aforesaid award of submitted documentary evidence.
arbitrators be and the same hereby is in all respects confirmed’, and ‘that the said movant,
Eastboard Navigation, Ltd., recover of and from the said respondent, Juan Ysmael & Company, The lower court rendered judgment affirming the decree of the New York District Court and
Inc., the sum of $53,037.89, with interest thereon from the 20th day of June, 1950, amounting to ordering that it be enforced, from which defendant appealed. Plaintiff likewise appealed but only
$488.24, together with the movant’s costs taxed in the sum of $40.00 and amounting in all to the on the score that the court did not declare defendant liable for the amount of the foreign exchange
sum of $53,566.13 with interest thereon until paid.’" tax due on the judgment and for the fees it agreed to pay to its counsel for this litigation. We will
discuss separately the issues involved in this joint appeal.
Plaintiff brought this action to enforce the aforesaid "Order and Final Decree" pursuant to Section
48, Rule 39 of the Rules of Court which, among others, provides "In case of a judgment against a It is plaintiff-appellant’s contention that, if the decision of the lower court is affirmed, it will have to
person, the judgment is presumptive evidence of a right as between the parties and their pay the foreign exchange tax on the amount awarded therein if the same is to be remitted to its
successors in interest by a subsequent title; but the judgment may be repelled by evidence of a home office at Ontario, Canada; that it should have been exempted from said tax had defendant
want of jurisdiction, want of notice to the party, collusion, fraud, or clear mistake of law or paid the award immediately after it had been confirmed by the U. S. New York District Court
fact."cralaw virtua1aw library because at that time Republic Act No. 601 had not yet been enacted; and that because of
defendant’s undue refusal to pay the same which gave rise to said tax liability, plaintiff will have to
Defendant, in its answer, set up the defense that said judgment cannot be enforced in this shoulder the same. This is a loss which defendant shall pay, plaintiff contends, under Article 1107
jurisdiction because (a) when the New York District Court acted on the case it did not have of the old Civil Code.
jurisdiction over the person of defendant; and (b) the proceeding where said judgment was
rendered was summary, there was no trial on the merits and defendant did not give its consent In the first place, there is no clear proof on record that defendant’s refusal to pay the award is due
thereto. Defendant contends that that judgment does not come within the purview of Section 48, to fraud or bad faith. Plaintiff failed to present any evidence in this regard. On the contrary, the
Rule 39, of the Rules of Court. stand of defendant does not seem to be entirely groundless as evidenced by the several defenses
it set up in its answer which give a clear perspective of the reasons why it declined to pay the
During the hearing, the parties agreed as to the following facts. That defendant is a corporation award which plaintiff demands. In the second place, it would appear that, if there is any
the stock of which is held as follows: Magdalena Hemady, 8,459 shares; K. H. Hemady, 6,939 agreement to pay the instant obligation in a currency other than the Philippine currency, the same
13 | A D R C A S E S S E T 1

is null and void as contrary to public policy (Republic Act No. 529), and the most that it could be Hemady. This document is in printed form with the blanks properly filled out, at the bottom of
demanded is to pay said obligation in Philippine currency to be measured in the prevailing rate of which appears a typewritten clause which states, "Clauses Nos. 16 to 31 inclusive and U. S. A.
exchange at the time the obligation was incurred (section 1, Idem.) . Finally, inasmuch as the Clause Paramount, War Risks Clauses 1 and 2, Now Jason Clause and Both-to-Blame Collision
decree of the New York District Court which is now sought to be enforced does not specify the Clauses, as attached, to be considered as fully incorporated herein and to form part of this
place where the obligation should be paid, the judgment debtor, herein defendant, may discharge Charter Party." (Italics supplied) Both the printed form and the typewritten sheet containing
the same here in Manila which is its domicile. We find therefore no valid reason for upholding the Clauses Nos. 16 to 31 inclusive, were signed by the contracting parties. Clause 29 in the
claim that defendant, should it be ordered to pay the award, pay the foreign exchange tax typewritten form refers to the arbitration agreement, and reads as follows:jgc:chanrobles.com.ph
required by law at the time the obligation fell due. At any rate, this question would appear now to
be moot for the reason that said tax has already been abolished (Republic Act No. 1394). "29. It is mutually agreed that should any dispute arise between Owners and the Charterers, the
matter in dispute shall be referred to three persons at New York for arbitration, one to be
The next issue raised by plaintiff-appellant refers to the failure of the lower court to award to it the appointed by each of the parties hereto, and the third by the two so chosen; their decision or that
fees which it agreed to pay to its counsel in connection with the present litigation under Article of any two of them, shall be final, and for the purpose of enforcing any award, this agreement may
2208, sub-paragraph 5, of the new Civil Code. The alleged sub- paragraph allows a winning party be made a rule of the Court. The Arbitrators shall be commercial men. Should the two so chosen
to recover attorneys fees "where the defendant acted in gross and evident bad faith in refusing to not be able to agree who the third Arbitrator should be, then the New York Produce Exchange is
satisfy the plaintiff’s plainly valid, just and demandable claim." From this it would appear that to to appoint such third Arbiter. The amount in dispute shall be placed in escrow at New York,
entitle plaintiff to attorneys’ fees on this ground, it is necessary that it be proven that defendant subject to the decision of the arbitrators."cralaw virtua1aw library
acted "in gross and evident bad faith" in refusing plaintiff’s claim. Since, as we have already
stated, plaintiff did not present any evidence on this point, the lower court did not err in denying It is now contended that while K. H. Hemady had signed Exhibit A which contains a typewritten
plaintiff’s claim on this score. clause at the end of the document, as well as the typewritten sheets attached thereto, wherein is
embodied Clause 29 which refers to the arbitration agreement, the fact however is that Hemady
Coming now to the appeal of defendant, we may restate the main issues raised in its assignment signed said papers without reading the same and solely on the assumption that they merely
of errors as follows: (a) whether or not defendant agreed to submit to compulsory arbitration its formalized the terms and conditions already agreed upon in the letter of confirmation Exhibit 1. It
dispute with plaintiff in the charter party agreement executed between them, and, in the is emphasized that Hemady never intended to submit any dispute that may arise out of its charter
affirmative, whether such agreement is valid in this jurisdiction; (b) whether or not the arbitration party to compulsory arbitration, much less to recognize the findings or award of the arbitrators that
agreement Exhibit B, is binding on defendant and, in the affirmative, whether or not the arbitration may be appointed by the parties as final and not subject to review by our courts. It is further
proceedings as well as the arbitrators’ decision, are valid and binding on defendant; (c) whether or contended that Hemady signed the document Exhibit A with the understanding that the same
not, on the assumption that said proceedings and decisions are valid, the decree of the U. S. would merely supplement with its "general conditions" the terms and conditions not stated in the
District Court, Southern District of New York, sitting as Admiralty Court, is valid and enforceable in letter of confirmation Exhibit 1, and the typewritten clause attached to the document Exhibit A,
this jurisdiction; and (d) whether or not plaintiff, being a foreign corporation without license to specially that which provides for foreign arbitration, refers to special conditions which were not
transact business in the Philippines, has capacity to sue in this jurisdiction. intended by the parties nor included in the preliminary negotiation conducted between them. This
stand of Hemady, it is contended, is further corroborated by the fact that when he received from
(a) It should be recalled that as a confirmation of the correspondence had between plaintiff’s his lawyers the arbitration agreement Exhibit B, he refused to sign it because it was never his
agents in the Philippines and defendant, represented by its President K. H. Hemady, the former intention to submit his dispute with plaintiff to compulsory arbitration.
sent a letter advising the latter that plaintiff had accepted its offer to charter plaintiff’s vessel S/S
Eastwater to load cargo of scrap iron in the Philippines for Buenos Aires under certain terms and There are many circumstances on record which discredit this claim of defendant-appellant. To
conditions therein enumerated (Exhibit 1). In this letter it is stated that the "terms and conditions begin with, it appears that the charter party agreement Exhibit A is one the original of which was
for this charter party not expressly or otherwise stated in this letter of confirmation are to be as per approved by the Documentary Council of the Baltic and White Sea Conference in 1922 and one of
general conditions of regular charter party form", a formal copy of which would be forwarded to its standard clauses is the arbitration clause and as such the latter, though in typewritten form, is
defendant. This was done, and the form above referred to is Exhibit A which was duly signed by considered as integral part of the agreement. This fact was admitted by defendant’s counsel. In
plaintiff, through its president, and by defendant, through its president and general manager, K. H. the second place, Hemady, as it would appear, signed not only the printed portion of the charter
14 | A D R C A S E S S E T 1

party agreement, but the typewritten portion as well, which contains the arbitration clause, and it to submit their dispute to arbitration, the decision of the arbitration board is nevertheless void
cannot be believed that a businessman of long experience as he was, would affix his signature to because it was not in accordance with the condition of said submission — that the arbitrators
a document involving a very important transaction without knowing its contents and would do so consider only claims or awards not in excess of $25,000.
only on the assumption that it contained mere formalized statements of the terms and conditions
of the letter of confirmation Exhibit 1. Moreover, if Hemady did not intend to submit his dispute The claim that none of the three arbitrators who acted on the dispute was appointed by defendant,
with plaintiff to arbitration as defendant now contends, why did he appoint Messrs. Manning, or under its authority, is untenable, for the same is disproved by the evidence. Thus, during the
Harnisch and Hollinger as lawyer to represent defendant corporation in the arbitration trial of this case the parties agreed as to certain facts which appear to be not disputed among
proceedings to be held in New York? (Exhibits 2 and 2-B) Why did he instruct the Bank of them being that one of the arbitrators who acted in New York on the case, Richard Nathan, was
America on two different occasions to transmit to the Irving Trust Company of New York the total appointed by authority of defendant corporation, and this appears to be supported by the decision
sum of $25,000 to be "held pending result of the arbitration of the dispute between this company of the New York District Court. Thus, in said decision it appears that when the case was called for
(Ysmael) and Eastboard Navigation, Ltd.?" (Exhibit 3-B) If defendant corporation did not really hearing both parties were represented by counsel who submitted documentary evidence among
intend to submit its dispute with the plaintiff to arbitration, the logical step it should have taken which (1) copy of the authorization signed by defendant corporation empowering one Morris E.
would be to repudiate the act of its President Hemady, but far from doing so, it approved and Lipsett to appoint a substitute arbitrator in its behalf, (2) copy of a letter of said Morris E. Lipsett
ratified it by subsequent acts which clearly indicate that it was agreeable to said arbitration. designating Richard Nathan as arbitrator, and (3) copy of the letter of Richard Nathan accepting
his appointment as arbitrator (Exhibit D). Note that Mr. Morris E. Lipsett is the same person who,
(b) The claim that the arbitration proceedings conducted in New York as well as the award of the according to K. H. Hemady, recommended Messrs. Manning, Harnisch and Hollinger to be his
arbitrators cannot bind defendant corporation for the reason that the same were conducted lawyers in the arbitration case in New York and that because he was his good friend Hemady
without its authority or contrary to its instructions, is also untenable. It is true that when accepted his recommendation (Exhibit 2-B). On the strength of this evidence, we cannot therefore
defendant’s counsel sent the document Exhibit B to its President K. H. Hemady for his signature, take seriously the contention that the person, Richard Nathan, who acted as arbitrator in behalf of
the latter returned it without his signature but that defendant’s counsel nevertheless signed the respondent, did so without the authority of the latter.
document in behalf of defendant and submitted it to the Board of Arbitrators, and this act is now
alleged as one undertaken without defendant’s authority or one that would indicate that defendant Of course, defendant now contends that the decision of the arbitrators can have no binding effect
did not agree to submit the dispute to arbitration. But there is one circumstance which justifies the on it because it was rendered without first obtaining its written conformity or approval, or without
action taken by defendant’s counsel in New York. Note that said document Exhibit B is mistakenly its lawyer having first submitted the matter to it for consultation, in accordance with the instruction
termed "arbitration agreement", for it is not so. A perusal thereof would show that it is a mere it has given in its letter dated April 20, 1950 (Exhibit 2-C), but certainly, such instruction, if any, is
agreement to submit the dispute to the arbitrators for arbitration and award. Such is necessary for preposterous under the circumstances, for to allow that to prevail would be to defeat the very
there could be no valid arbitration and award if the arbitrators would not know what to arbitrate purpose of the arbitration. The proceeding would be purposeless for no award can be obtained if
and decide. The arbitration agreement is Clause 29 of the charter party Exhibit A. The fact that the same should be made dependent upon the instruction or approval of any of the parties.
Hemady returned said document Exhibit B unsigned is of no significance for such is a mere
implementation of the authority already previously given by defendant to its counsel Messrs. The contention that defendant corporation has limited its agreement to arbitrate to an amount not
Manning, Harnisch and Hollinger "to present our case to the arbitrators in a case we have with the exceeding $25,000 cannot also be sustained. Such claim is not borne out by the evidence for
Eastboard Navigation Co., Ltd., in connection with our charter of their vessel the "S/S Eastwater," neither the cable nor the letter which defendant sent to its lawyers in New York contains any
contained in its letter dated April 5, 1950 (Exhibit 2-B). The signing of said document Exhibit B by statement limiting their authority to represent it to disputes not exceeding $25,000. In other words,
defendant’s counsel is therefore perfectly within the scope of the authority given them by there is no evidence whatsoever in the record showing that Mr. Hemady understood, or was made
defendant corporation. to understand, that the arbitration proceeding "would be conducted solely for the purpose of
friendly adjustment of disputes limited to and not exceeding the amount of $25,000." Moreover,
But defendant insists that the decision of the arbitrators is not binding upon it because (1) none of the aforesaid deposit merely represents an estimate of the amounts that may accrue to plaintiff for
the arbitrators who acted thereon in accordance with the arbitration agreement had been demurrage pursuant to the charter agreement while the vessel was in transit from Manila to
appointed by defendant, and (2) even if the appointment of Attys. Manning, Harnisch and Buenos Aires and does not include any additional demurrage that may be incurred while the
Hollinger to represent defendant before the arbitration board would be considered as an authority vessel is docked in Buenos Aires waiting for the unloading of the cargo. To sustain defendant’s
15 | A D R C A S E S S E T 1

contention would be to defeat the purpose of the arbitration which is to settle all disputes that may predicated on the alleged fact that defendant was never served with notice, summons, or process
arise out of the contract in connection with the voyage. It cannot therefore be pretended that the relative to the submission of the award of the arbitrators to said court, invoking in support of this
arbitrators acted beyond the scope of their authority. contention the U. S. Arbitration Act of February 12, 1925 under which the New York District Court
confirmed the arbitrators’ award. But we find that the law thus invoked does not sustain
As a corollary to the question regarding the existence of an arbitration agreement, defendant defendant’s pretense, for the same, in case of a non-resident, does not necessarily require that
raises the issue that, even if it be granted that it agreed to submit its dispute with plaintiff to service of notice of the application for confirmation be made on the adverse party himself, it being
arbitration, said agreement is void and without effect for it amounts to removing said dispute from sufficient that it be made upon his attorney (July 30, 1947, c. 392, section 1, 61 Stat. 669, p. 4
the jurisdiction of the courts in which the parties are domiciled or where the dispute occurred. It is Exhibit E). This is precisely what was done in this case. Copy of the notice of submission of the
true that there are authorities which hold that "a clause in a contract providing that all matters in award to the District Court of New York was served upon defendant’s counsel who in due time
dispute between the parties shall be referred to arbitrators and to them alone, is contrary to public made of record their appearance and actually appeared when the case was heard. This is clearly
policy and cannot oust the courts of jurisdiction" (Manila Electric Co. v. Pasay Transportation Co., stated in the decision of said court (Exhibit D). It is significant that respondent’s counsel never
57 Phil., 600, 603), however, there are authorities which favor "the more intelligent view that impugned the jurisdiction of the court over defendant nor did they ever plead before it that they
arbitration, as an inexpensive, speedy and amicable method of settling disputes, and as a means were bereft of authority to represent defendant. Defendant cannot therefore in this instance defeat
of avoiding litigation, should receive every encouragement from the courts which may be the effect of this decision by alleging want of jurisdiction, or want of notice, as provided for in
extended without contravening sound public policy or settled law" (3 Am. Jur., p. 835). Congress section 48, Rule 39 of our Rules of Court.
has officially adopted this modern view when it reproduced in the new Civil Code the provisions of
the old Code on Arbitration. And only recently it approved Republic Act No. 876 expressly (d) While plaintiff is a foreign corporation without license to transact business in the Philippines, it
authorizing arbitration of future disputes. Thus section 2 of said Act does not follow that it has no capacity to bring the present action. Such license is not necessary
provides:jgc:chanrobles.com.ph because it is not engaged in business in the Philippines. In fact, the transaction herein involved is
the first business undertaken by plaintiff in the Philippines, although on a previous occasion
"SEC. 2. Persons and matters subject to arbitration. — Two or more persons or parties may plaintiff’s vessel was chartered by the National Rice and Corn Corporation to carry rice cargo from
submit to the arbitration of one or more arbitrators any controversy existing between them at the abroad to the Philippines. These two isolated transactions do not constitute engaging in business
time of the submission and which may be the subject of an action, or the parties to any contract in the Philippines within the purview of Sections 68 and 69 of the Corporation Law so as to bar
may in such contract agree to settle by arbitration a controversy thereafter arising between them. plaintiff from seeking redress in our courts. (Marshall-Wells Co. v. Henry W. Elser & Co. 49 Phil.,
Such submission or contract shall be valid, enforceable and irrevocable, save upon such grounds 70; Pacific Vegetable Oil Corporation v. Angel O. Singson, G. R. No. L- 7917, April 29, 1955.)
as exist at law for the revocation of any contract."cralaw virtua1aw library
Wherefore, the decision appealed from is affirmed, without pronouncement as to costs.
Considering this declared policy of Congress in favor of arbitration of all kinds of disputes, and the
fact that, according to the explanatory note of Republic Act No. 876, "to afford the public a cheap
and expeditious procedure of settling not only commercial but other kinds of controversies most of
the states of the American Union have adopted statutes providing for arbitration, and American
businessmen are reported to have enthusiastically accepted the innovation because of its obvious
advantages over the ordinary court procedure", we find no plausible reason for holding that the
arbitration agreement in question, simply because it refers to a future dispute, is null and void as
being against public policy. (Italics supplied.)

(c) It is contended that the decision rendered by the U. S. District court of New York sitting as an
Admiralty Court, which ratified the award made by the arbitrators, has no binding effect on
defendant corporation, nor can it be enforced in this jurisdiction, for the reason that when said
court acted on the case it did not acquire jurisdiction over said defendant. And this claim is
16 | A D R C A S E S S E T 1

G.R. No. 120105 March 27, 1998 Barely two days later or on July 14, 1993, petitioner filed with the Regional Trial Court of Pasig a
complaint for collection of the balance due under the construction agreement. Named defendants
BF CORPORATION, petitioner, therein were SPI and members of its board of directors namely, Alfredo C. Ramos, Rufo B.
vs. Calayco, Antonio B. Olbes, Gerardo O. Lanuza, Jr., Maximo G. Licauco III and Benjamin C.
COURT OF APPEALS, SHANGRI-LA PROPERTIES, INC., RUFO B. COLAYCO, ALFREDO C. Ramos.
RAMOS, MAXIMO G. LICAUCO III and BENJAMIN C. RAMOS, respondents.
On August 3, 1993, SPI and its co-defendants filed a motion to suspend proceedings instead of
filing an answer. The motion was anchored on defendants' allegation that the formal trade
contract for the construction of the project provided for a clause requiring prior resort to arbitration
ROMERO, J.: before judicial intervention could be invoked in any dispute arising from the contract. The following
day, SPI submitted a copy of the conditions of the contract containing the arbitration clause that it
The basic issue in this petition for review on certiorari is whether or not the contract for the failed to append to its motion to suspend proceedings.
construction of the EDSA Plaza between petitioner BF Corporation and respondent Shangri-la
Properties, Inc. embodies an arbitration clause in case of disagreement between the parties in the Petitioner opposed said motion claiming that there was no formal contract between the parties
implementation of contractual provisions. although they entered into an agreement defining their rights and obligations in undertaking the
project. It emphasized that the agreement did not provide for arbitration and therefore the court
Petitioner and respondent Shangri-la Properties, Inc. (SPI) entered into an agreement whereby could not be deprived of jurisdiction conferred by law by the mere allegation of the existence of an
the latter engaged the former to construct the main structure of the "EDSA Plaza Project," a arbitration clause in the agreement between the parties.
shopping mall complex in the City of Mandaluyong. The construction work was in progress when
SPI decided to expand the project by engaging the services of petitioner again. Thus, the parties In reply to said opposition, SPI insisted that there was such an arbitration clause in the existing
entered into an agreement for the main contract works after which construction work began. contract between petitioner and SPI. It alleged that suspension of proceedings would not
necessarily deprive the court of its jurisdiction over the case and that arbitration would expedite
However, petitioner incurred delay in the construction work that SPI considered as "serious and rather than delay the settlement of the parties' respective claims against each other.
substantial."1 On the other hand, according to petitioner, the construction works "progressed in
faithful compliance with the First Agreement until a fire broke out on November 30, 1990 In a rejoinder to SPI's reply, petitioner reiterated that there was no arbitration clause in the
damaging Phase I" of the Project.2 Hence, SPI proposed the re-negotiation of the agreement contract between the parties. It averred that granting that such a clause indeed formed part of the
between them. contract, suspension of the proceedings was no longer proper. It added that defendants should be
declared in default for failure to file their answer within the reglementary period.
Consequently, on May 30, 1991, petitioner and SPI entered into a written agreement denominated
as "Agreement for the Execution of Builder's Work for the EDSA Plaza Project." Said agreement In its sur-rejoinder, SPI pointed out the significance of petitioner's admission of the due execution
would cover the construction work on said project as of May 1, 1991 until its eventual completion. of the "Articles of Agreement." Thus, on page D/6 thereof, the signatures of Rufo B. Colayco, SPI
president, and Bayani Fernando, president of petitioner appear, while page D/7 shows that the
According to SPI, petitioner "failed to complete the construction works and abandoned the agreement is a public document duly notarized on November 15, 1991 by Notary Public Nilberto
project."3 This resulted in disagreements between the parties as regards their respective liabilities R. Briones as document No. 345, page 70, book No. LXX, Series of 1991 of his notarial register.5
under the contract. On July 12, 1993, upon SPI's initiative, the parties' respective representatives
met in conference but they failed to come to an agreement.4 Thereafter, upon a finding that an arbitration clause indeed exists, the lower court6 denied the
motion to suspend proceedings, thus:
17 | A D R C A S E S S E T 1

It appears from the said document that in the letter-agreement dated May 30, entertains serious doubt whether or not the arbitration clause found in the said
1991 (Annex C, Complaint), plaintiff BF and defendant Shangri-La Properties, Conditions of Contract is binding upon the parties to the Articles of Agreement."
Inc. agreed upon the terms and conditions of the Builders Work for the EDSA (Emphasis supplied.)
Plaza Project (Phases I, II and Carpark), subject to the execution by the parties
of a formal trade contract. Defendants have submitted a copy of the alleged The lower court then ruled that, assuming that the arbitration clause was valid and binding, still, it
trade contract, which is entitled "Contract Documents For Builder's Work Trade was "too late in the day for defendants to invoke arbitration." It quoted the following provision of
Contractor" dated 01 May 1991, page 2 of which is entitled "Contents of the arbitration clause:
Contract Documents" with a list of the documents therein contained, and
Section A thereof consists of the abovementioned Letter-Agreement dated May Notice of the demand for arbitration of a dispute shall be filed in writing with the
30, 1991. Section C of the said Contract Documents is entitled "Articles of other party to the contract and a copy filed with the Project Manager. The
Agreement and Conditions of Contract" which, per its Index, consists of Part A demand for arbitration shall be made within a reasonable time after the dispute
(Articles of Agreement) and B (Conditions of Contract). The said Articles of has arisen and attempts to settle amicably have failed; in no case, however,
Agreement appears to have been duly signed by President Rufo B. Colayco of shall the demand he made be later than the time of final payment except as
Shangri-La Properties, Inc. and President Bayani F. Fernando of BF and their otherwise expressly stipulated in the contract.
witnesses, and was thereafter acknowledged before Notary Public Nilberto R.
Briones of Makati, Metro Manila on November 15, 1991. The said Articles of Against the above backdrop, the lower court found that per the May 30, 1991 agreement, the
Agreement also provides that the "Contract Documents" therein listed "shall be project was to be completed by October 31, 1991. Thereafter, the contractor would pay P80,000
deemed an integral part of this Agreement", and one of the said documents is for each day of delay counted from November 1, 1991 with "liquified (sic) damages up to a
the "Conditions of Contract" which contains the Arbitration Clause relied upon maximum of 5% of the total contract price."
by the defendants in their Motion to Suspend Proceedings.
The lower court also found that after the project was completed in accordance with the agreement
This Court notes, however, that the 'Conditions of Contract' referred to, contains the following that contained a provision on "progress payment billing," SPI "took possession and started
provisions: operations thereof by opening the same to the public in November, 1991." SPI, having failed to
pay for the works, petitioner billed SPI in the total amount of P110,883,101.52, contained in a
3. Contract Document. demand letter sent by it to SPI on February 17, 1993. Instead of paying the amount demanded,
SPI set up its own claim of P220,000,000.00 and scheduled a conference on that claim for July
Three copies of the Contract Documents referred to in the 12, 1993. The conference took place but it proved futile.
Articles of Agreement shall be signed by the parties to the
contract  and distributed to the Owner and the Contractor for Upon the above facts, the lower court concluded:
their safe keeping." (emphasis supplied).
Considering the fact that under the supposed Arbitration Clause invoked by
And it is significant to note further that the said "Conditions of Contract" is not defendants, it is required that "Notice of the demand for arbitration of a dispute
duly signed by the parties on any page thereof — although it bears the initials of shall be filed in writing with the other party . . . . in no case . . . . later than the
BF's representatives (Bayani F. Fernando and Reynaldo M. de la Cruz) without time of final payment . . . "which apparently, had elapsed, not only because
the initials thereon of any representative of Shangri-La Properties, Inc. defendants had taken possession of the finished works and the plaintiff's billings
for the payment thereof had remained pending since November, 1991 up to the
Considering the insistence of the plaintiff that the said Conditions of Contract filing of this case on July 14, 1993, but also for the reason that defendants have
was not duly executed or signed by the parties, and the failure of the failed to file any written notice of any demand for arbitration during the said long
defendants to submit any signed copy of the said document, this Court period of one year and eight months, this Court finds that it cannot stay the
18 | A D R C A S E S S E T 1

proceedings in this case as required by Sec. 7 of Republic Act No. 876, amicably. Failing these efforts then such dispute or difference
because defendants are in default in proceeding with such arbitration. shall be referred to Arbitration in accordance with the rules
and procedures of the Philippine Arbitration Law.
The lower court denied SPI's motion for reconsideration for lack of merit and directed it and the
other defendants to file their responsive pleading or answer within fifteen (15) days from notice. The fact that said conditions of contract containing the arbitration clause bear
only the initials of respondent Corporation's representatives, Bayani Fernando
Instead of filing an answer to the complaint, SPI filed a petition for certiorari under Rule 65 of the and Reynaldo de la Cruz, without that of the representative of petitioner
Rules of Court before the Court of Appeals. Said appellate court granted the petition, annulled Shangri-La Properties, Inc. does not militate against its effectivity. Said
and set aside the orders and stayed the proceedings in the lower court. In so ruling, the Court of petitioner having categorically admitted that the document, Annex A to its reply
Appeals held: dated August 26, 1993 (Annex G, petition), is the agreement between the
parties, the initial or signature of said petitioner's representative to signify
The reasons given by the respondent Court in denying petitioners' motion to conformity to arbitration is no longer necessary. The parties, therefore, should
suspend proceedings are untenable. be allowed to submit their dispute to arbitration in accordance with their
agreement.
1. The notarized copy of the articles of agreement attached as Annex A to
petitioners' reply dated August 26, 1993, has been submitted by them to the 2. The respondent Court held that petitioners "are in default in proceeding with
respondent Court (Annex G, petition). It bears the signature of petitioner Rufo B. such arbitration." It took note of "the fact that under the supposed Arbitration
Colayco, president of petitioner Shangri-La Properties, Inc., and of Bayani Clause invoked by defendants, it is required that "Notice of the demand for
Fernando, president of respondent Corporation (Annex G-1, petition). At page arbitration of a dispute shall be filed in writing with the other party . . . in no case
D/4 of said articles of agreement it is expressly provided that the conditions of . . . later than the time of final payment," which apparently, had elapsed, not
contract are "deemed an integral part" thereof (page 188, rollo). And it is at only because defendants had taken possession of the finished works and the
pages D/42 to D/44 of the conditions of contract that the provisions for plaintiff's billings for the payment thereof had remained pending since
arbitration are found (Annexes G-3 to G-5, petition, pp. 227-229). Clause No. 35 November, 1991 up to the filing of this case on July 14, 1993, but also for the
on arbitration specifically provides: reason that defendants have failed to file any written notice of any demand for
arbitration during the said long period of one year and eight months, . . . ."
Provided always that in case any dispute or difference shall
arise between the Owner or the Project Manager on his Respondent Court has overlooked the fact that under the arbitration
behalf and the Contractor, either during the progress or after clause —
the completion or abandonment of the Works as to the
construction of this Contract or as to any matter or thing of Notice of the demand for arbitration dispute shall be filed in
whatsoever nature arising thereunder or in connection writing with the other party to the contract and a copy filed
therewith (including any matter or being left by this Contract with the Project Manager. The demand for arbitration shall be
to the discretion of the Project Manager or the withholding by made within a reasonable time after the dispute has arisen
the Project Manager of any certificate to which the Contractor and attempts to settle amicably had failed; in no case,
may claim to be entitled or the measurement and valuation however, shall the demand be made later than the time of
mentioned in clause 30 (5) (a) of these Conditions' or the final payment except as otherwise expressly stipulated in the
rights and liabilities of the parties under clauses 25, 26, 32 or contract (emphasis supplied)
33 of these Conditions), the Owner and the Contractor hereby
agree to exert all efforts to settle their differences or dispute
19 | A D R C A S E S S E T 1

quoted in its order (Annex A, petition). As the respondent Court there said, after be obtained. Hence, to petitioner, the Court of Appeals should have dismissed the petition
the final demand to pay the amount of P110,883,101.52, instead of paying, for certiorari because the remedy of appeal would still be available to private respondents at the
petitioners set up its own claim against respondent Corporation in the amount of proper time.7
P220,000,000.00 and set a conference thereon on July 12, 1993. Said
conference proved futile. The next day, July 14, 1993, respondent Corporation The above contention is without merit.
filed its complaint against petitioners. On August 13, 1993, petitioners wrote to
respondent Corporation requesting arbitration. Under the circumstances, it The rule that the special civil action of certiorari may not be invoked as a substitute for the remedy
cannot be said that petitioners' resort to arbitration was made beyond of appeal is succinctly reiterated in Ongsitco v. Court of Appeals8 as follows:
reasonable time. Neither can they be considered in default of their obligation to
respondent Corporation. . . . . Countless times in the past, this Court has held that "where appeal is the
proper remedy, certiorari will not lie." The writs of certiorari and prohibition are
Hence, this petition before this Court. Petitioner assigns the following errors: remedies to correct lack or excess of jurisdiction or grave abuse of discretion
equivalent to lack of jurisdiction committed by a lower court. "Where the proper
A remedy is appeal, the action for certiorari will not be
entertained. . . . Certiorari is not a remedy for errors of judgment. Errors of
THE COURT OF APPEALS ERRED IN ISSUING THE EXTRAORDINARY judgment are correctible by appeal, errors of jurisdiction are reviewable
WRIT OF CERTIORARI ALTHOUGH THE REMEDY OF APPEAL WAS by certiorari."
AVAILABLE TO RESPONDENTS.
Rule 65 is very clear. The extraordinary remedies of certiorari, prohibition
B and mandamus are available only when "there is no appeal or any plain,
speedy and adequate remedy in the ordinary course of law . . . ." That is why
THE COURT OF APPEALS ERRED IN FINDING GRAVE ABUSE OF they are referred to as "extraordinary." . . . .
DISCRETION IN THE FACTUAL FINDINGS OF THE TRIAL COURT THAT:
The Court has likewise ruled that "certiorari will not be issued to cure errors in proceedings or
(i) THE PARTIES DID NOT ENTER INTO correct erroneous conclusions of law or fact. As long as a court acts within its jurisdiction, any
AN AGREEMENT TO ARBITRATE. alleged errors committed in the exercise of its jurisdiction will amount to nothing more than errors
of judgment which are reviewable by timely appeal and not by a special civil action of certiorari."9
(ii) ASSUMING THAT THE PARTIES DID
ENTER INTO THE AGREEMENT TO This is not exactly so in the instant case. While this Court does not deny the eventual jurisdiction
ARBITRATE, RESPONDENTS ARE of the lower court over the controversy, the issue posed basically is whether the lower court
ALREADY IN DEFAULT IN INVOKING prematurely assumed jurisdiction over it. If the lower court indeed prematurely assumed
THE AGREEMENT TO ARBITRATE. jurisdiction over the case, then it becomes an error of jurisdiction which is a proper subject of a
petition for certiorari before the Court of Appeals. And if the lower court does not have jurisdiction
On the first assigned error, petitioner contends that the Order of the lower court denying the over the controversy, then any decision or order it may render may be annulled and set aside by
motion to suspend proceedings "is a resolution of an incident on the merits." As such, upon the the appellate court.
continuation of the proceedings, the lower court would appreciate the evidence adduced in their
totality and thereafter render a decision on the merits that may or may not sustain the existence of However, the question of jurisdiction, which is a question of law depends on the determination of
an arbitration clause. A decision containing a finding that the contract has no arbitration clause the existence of the arbitration clause, which is a question of fact. In the instant case, the lower
can then be elevated to a higher court "in an ordinary appeal" where an adequate remedy could
20 | A D R C A S E S S E T 1

court found that there exists an arbitration clause. However, it ruled that in contemplation of law, Appeals that they produced in the trial court a notarized duplicate original copy of the construction
said arbitration clause does not exist. agreement because what were submitted were mere photocopies thereof. The contract(s)
introduced in court by private respondents were therefore "of dubious authenticity" because: (a)
The issue, therefore, posed before the Court of Appeals in a petition for certiorari is whether the the Agreement for the Execution of Builder's Work for the EDSA Plaza Project does not contain
Arbitration Clause does not in fact exist. On its face, the the question is one of fact which is not an arbitration clause, (b) private respondents "surreptitiously attached as Annexes "G-3" to "G-5"
proper in a petition for certiorari. to their petition before the Court of Appeals but these documents are not parts of the Agreement
of the parties as "there was no formal trade contract executed," (c) if the entire compilation of
The Court of Appeals found that an Arbitration Clause does in fact exist. In resolving said question documents "is indeed a formal trade contract," then it should have been duly notarized, (d) the
of fact, the Court of Appeals interpreted the construction of the subject contract documents certification from the Records Management and Archives Office dated August 26, 1993 merely
containing the Arbitration Clause in accordance with Republic Act No. 876 (Arbitration Law) and states that "the notarial record of Nilberto Briones . . . is available in the files of (said) office
existing jurisprudence which will be extensively discussed hereunder. In effect, the issue posed as Notarial Registry Entry only," (e) the same certification attests that the document entered in the
before the Court of Appeals was likewise a question of law. Being a question of law, the private notarial registry pertains to the Articles of Agreement only without any other accompanying
respondents rightfully invoked the special civil action of certiorari. documents, and therefore, it is not a formal trade contract, and (f) the compilation submitted by
respondents are a "mere hodge-podge of documents and do not constitute a single intelligible
It is that mode of appeal taken by private respondents before the Court of Appeals that is being agreement."
questioned by the petitioners before this Court. But at the heart of said issue is the question of
whether there exists an Arbitration Clause because if an Arbitration Clause does not exist, then In other words, petitioner denies the existence of the arbitration clause primarily on the ground
private respondents took the wrong mode of appeal before the Court of Appeals. that the representatives of the contracting corporations did not sign the "Conditions of Contract"
that contained the said clause. Its other contentions, specifically that insinuating fraud as regards
For this Court to be able to resolve the question of whether private respondents took the proper the alleged insertion of the arbitration clause, are questions of fact that should have been
mode of appeal, which, incidentally, is a question of law, then it has to answer the core issue of threshed out below.
whether there exists an Arbitration Clause which, admittedly, is a question of fact.
This Court may as well proceed to determine whether the arbitration clause does exist in the
Moreover, where a rigid application of the rule that certiorari cannot be a substitute for appeal will parties' contract. Republic Act No. 876 provides for the formal requisites of an arbitration
result in a manifest failure or miscarriage of justice, the provisions of the Rules of Court which are agreement as follows:
technical rules may be relaxed. 10 As we shall show hereunder, had the Court of Appeals
dismissed the petition for certiorari, the issue of whether or not an arbitration clause exists in the Sec. 4. Form of arbitration agreement. — A contract to arbitrate a controversy
contract would not have been resolved in accordance with evidence extant in the record of the thereafter arising between the parties, as well as a submission to arbitrate an
case. Consequently, this would have resulted in a judicial rejection of a contractual provision existing controversy, shall be in writing and subscribed by the party sought to
agreed by the parties to the contract. be charged, or by his lawful agent.

In the same vein, this Court holds that the question of the existence of the arbitration clause in the The making of a contract or submission for arbitration described in section two
contract between petitioner and private respondents is a legal issue that must be determined in hereof, providing for arbitration of any controversy, shall be deemed a consent
this petition for review on certiorari. of the parties of the province or city where any of the parties resides, to enforce
such contract of submission. (Emphasis supplied.).
Petitioner, while not denying that there exists an arbitration clause in the contract in question,
asserts that in contemplation of law there could not have been one considering the following The formal requirements of an agreement to arbitrate are therefore the following: (a) it must be in
points. First, the trial court found that the "conditions of contract" embodying the arbitration clause writing and (b) it must be subscribed by the parties or their representatives. There is no denying
is not duly signed by the parties. Second, private respondents misrepresented before the Court of that the parties entered into a written contract that was submitted in evidence before the lower
21 | A D R C A S E S S E T 1

court. To "subscribe" means to write underneath, as one's name; to sign at the end of a either delay in the completion of the construction work or by force majeure or the fire that partially
document. 11 That word may sometimes be construed to mean to give consent to or to attest.12 gutted the project. The almost two-year delay in paying its liabilities may not therefore be wholly
ascribed to private respondent SPI.
The Court finds that, upon a scrutiny of the records of this case, these requisites were complied
with in the contract in question. The Articles of Agreement, which incorporates all the other Besides, private respondent SPI's initiative in calling for a conference between the parties was a
contracts and agreements between the parties, was signed by representatives of both parties and step towards the agreed resort to arbitration. However, petitioner posthaste filed the complaint
duly notarized. The failure of the private respondent's representative to initial the "Conditions of before the lower court. Thus, while private respondent SPI's request for arbitration on August 13,
Contract" would therefor not affect compliance with the formal requirements for arbitration 1993 might appear an afterthought as it was made after it had filed the motion to suspend
agreements because that particular portion of the covenants between the parties was included by proceedings, it was because petitioner also appeared to act hastily in order to resolve the
reference in the Articles of Agreement. controversy through the courts.

Petitioner's contention that there was no arbitration clause because the contract incorporating said The arbitration clause provides for a "reasonable time" within which the parties may avail of the
provision is part of a "hodge-podge" document, is therefore untenable. A contract need not be relief under that clause. "Reasonableness" is a relative term and the question of whether the time
contained in a single writing. It may be collected from several different writings which do not within which an act has to be done is reasonable depends on attendant circumstances. 15 This
conflict with each other and which, when connected, show the parties, subject matter, terms and Court finds that under the circumstances obtaining in this case, a one-month period from the time
consideration, as in contracts entered into by correspondence. 13 A contract may be encompassed the parties held a conference on July 12, 1993 until private respondent SPI notified petitioner that
in several instruments even though every instrument is not signed by the parties, since it is it was invoking the arbitration clause, is a reasonable time. Indeed, petitioner may not be faulted
sufficient if the unsigned instruments are clearly identified or referred to and made part of the for resorting to the court to claim what was due it under the contract. However, we find its denial
signed instrument or instruments. Similarly, a written agreement of which there are two copies, of the existence of the arbitration clause as an attempt to cover up its misstep in hurriedly filing
one signed by each of the parties, is binding on both to the same extent as though there had been the complaint before the lower court.
only one copy of the agreement and both had signed it. 14
In this connection, it bears stressing that the lower court has not lost its jurisdiction over the case.
The flaw in petitioner's contentions therefore lies in its having segmented the various components Section 7 of Republic Act No. 876 provides that proceedings therein have only been stayed. After
of the whole contract between the parties into several parts. This notwithstanding, petitioner the special proceeding of arbitration 16 has been pursued and completed, then the lower court may
ironically admits the execution of the Articles of Agreement. Notably, too, the lower court found confirm the award 17 made by the arbitrator.
that the said Articles of Agreement "also provides that the 'Contract Documents' therein listed
'shall be deemed an integral part of this Agreement,' and one of the said documents is the It should be noted that in this jurisdiction, arbitration has been held valid and constitutional. Even
'Conditions of Contract' which contains the Arbitration Clause.'" It is this Articles of Agreement that before the approval on June 19, 1953 of Republic Act No. 876, this Court has countenanced the
was duly signed by Rufo B. Colayco, president of private respondent SPI, and Bayani F. settlement of disputes through arbitration. 18 Republic Act No. 876 was adopted to supplement the
Fernando, president of petitioner corporation. The same agreement was duly subscribed before New Civil Code's provisions on arbitration. 19 Its potentials as one of the alternative dispute
notary public Nilberto R. Briones. In other words, the subscription of the principal agreement resolution methods that are now rightfully vaunted as "the wave of the future" in international
effectively covered the other documents incorporated by reference therein. relations, is recognized worldwide. To brush aside a contractual agreement calling for arbitration
in case of disagreement between the parties would therefore be a step backward.
This Court likewise does not find that the Court of Appeals erred in ruling that private respondents
were not in default in invoking the provisions of the arbitration clause which states that "(t)he WHEREFORE, the questioned Decision of the Court of Appeals is hereby AFFIRMED and the
demand for arbitration shall be made within a reasonable time after the dispute has arisen and petition for certiorari DENIED. This Decision is immediately executory. Costs against petitioner.
attempts to settle amicably had failed." Under the factual milieu, private respondent SPI should
have paid its liabilities tinder the contract in accordance with its terms. However, SO ORDERED.
misunderstandings appeared to have cropped up between the parties ostensibly brought about by
22 | A D R C A S E S S E T 1
23 | A D R C A S E S S E T 1

G.R. No. 141833            March 26, 2003 Because of the dispute, petitioner filed with the Regional Trial Court (RTC) of Makati (Branch 141)
a Complaint10 for the collection of the amount representing the alleged balance due it under the
LM POWER ENGINEERING CORPORATION, petitioner, Subcontract. Instead of submitting an Answer, respondent filed a Motion to Dismiss,11 alleging that
vs. the Complaint was premature, because there was no prior recourse to arbitration.
CAPITOL INDUSTRIAL CONSTRUCTION GROUPS, INC., respondent.
In its Order12 dated September 15, 1987, the RTC denied the Motion on the ground that the
PANGANIBAN, J.: dispute did not involve the interpretation or the implementation of the Agreement and was,
therefore, not covered by the arbitral clause.13
Alternative dispute resolution methods or ADRs -- like arbitration, mediation, negotiation and
conciliation -- are encouraged by the Supreme Court. By enabling parties to resolve their disputes After trial on the merits, the RTC14 ruled that the take-over of some work items by respondent was
amicably, they provide solutions that are less time-consuming, less tedious, less confrontational, not equivalent to a termination, but a mere modification, of the Subcontract. The latter was
and more productive of goodwill and lasting relationships.1 ordered to give full payment for the work completed by petitioner.

The Case Ruling of the Court of Appeals

Before us is a Petition for Review on Certiorari2 under Rule 45 of the Rules of Court, seeking to On appeal, the CA reversed the RTC and ordered the referral of the case to arbitration. The
set aside the January 28, 2000 Decision of the Court of Appeals3 (CA) in CA-GR CV No. 54232. appellate court held as arbitrable the issue of whether respondent’s take-over of some work items
The dispositive portion of the Decision reads as follows: had been intended to be a termination of the original contract under Letter "K" of the Subcontract.
It ruled likewise on two other issues: whether petitioner was liable under the warranty clause of
"WHEREFORE, the judgment appealed from is REVERSED and SET ASIDE. The the Agreement, and whether it should reimburse respondent for the work the latter had taken
parties are ORDERED to present their dispute to arbitration in accordance with their over.15
Sub-contract Agreement. The surety bond posted by [respondent] is [d]ischarged."4
Hence, this Petition.16
The Facts
The Issues
On February 22, 1983, Petitioner LM Power Engineering Corporation and Respondent Capitol
Industrial Construction Groups Inc. entered into a "Subcontract Agreement" involving electrical In its Memorandum, petitioner raises the following issues for the Court’s consideration:
work at the Third Port of Zamboanga.5
"A
On April 25, 1985, respondent took over some of the work contracted to petitioner.6 Allegedly, the
latter had failed to finish it because of its inability to procure materials.7 Whether or not there exist[s] a controversy/dispute between petitioner and respondent regarding
the interpretation and implementation of the Sub-Contract Agreement dated February 22, 1983
Upon completing its task under the Contract, petitioner billed respondent in the amount of that requires prior recourse to voluntary arbitration;
P6,711,813.90.8 Contesting the accuracy of the amount of advances and billable
accomplishments listed by the former, the latter refused to pay. Respondent also took refuge in "B
the termination clause of the Agreement.9 That clause allowed it to set off the cost of the work that
petitioner had failed to undertake -- due to termination or take-over -- against the amount it owed
the latter.
24 | A D R C A S E S S E T 1

In the affirmative, whether or not the requirements provided in Article III 1 of CIAC Arbitration over be set off against the amounts it owed petitioner? (3) How much were the advances and
Rules regarding request for arbitration ha[ve] been complied with[.]"17 billable accomplishments?

The Court’s Ruling The resolution of the foregoing issues lies in the interpretation of the provisions of the Agreement.
According to respondent, the take-over was caused by petitioner’s delay in completing the work.
The Petition is unmeritorious. Such delay was in violation of the provision in the Agreement as to time schedule:

First Issue: "G. TIME SCHEDULE


Whether Dispute Is Arbitrable
"[Petitioner] shall adhere strictly to the schedule related to the WORK and complete the
Petitioner claims that there is no conflict regarding the interpretation or the implementation of the WORK within the period set forth in Annex C hereof. NO time extension shall be granted
Agreement. Thus, without having to resort to prior arbitration, it is entitled to collect the value of by [respondent] to [petitioner] unless a corresponding time extension is granted by [the
the services it rendered through an ordinary action for the collection of a sum of money from Ministry of Public Works and Highways] to the CONSORTIUM."20
respondent. On the other hand, the latter contends that there is a need for prior arbitration as
provided in the Agreement. This is because there are some disparities between the parties’ Because of the delay, respondent alleges that it took over some of the work contracted to
positions regarding the extent of the work done, the amount of advances and billable petitioner, pursuant to the following provision in the Agreement:
accomplishments, and the set off of expenses incurred by respondent in its take-over of
petitioner’s work. "K. TERMINATION OF AGREEMENT

We side with respondent. Essentially, the dispute arose from the parties’ ncongruent positions on "[Respondent] has the right to terminate and/or take over this Agreement for any of the
whether certain provisions of their Agreement could be applied to the facts. The instant case following causes:
involves technical discrepancies that are better left to an arbitral body that has expertise in those
areas. In any event, the inclusion of an arbitration clause in a contract does not ipso facto divest x x x           x x x           x x x
the courts of jurisdiction to pass upon the findings of arbitral bodies, because the awards are still
judicially reviewable under certain conditions.18 ‘6. If despite previous warnings by [respondent], [petitioner] does not execute
the WORK in accordance with this Agreement, or persistently or flagrantly
In the case before us, the Subcontract has the following arbitral clause: neglects to carry out [its] obligations under this Agreement."21

"6. The Parties hereto agree that any dispute or conflict as regards to interpretation and Supposedly, as a result of the "take-over," respondent incurred expenses in excess of the
implementation of this Agreement which cannot be settled between [respondent] and contracted price. It sought to set off those expenses against the amount claimed by petitioner for
[petitioner] amicably shall be settled by means of arbitration x x x."19 the work the latter accomplished, pursuant to the following provision:

Clearly, the resolution of the dispute between the parties herein requires a referral to the "If the total direct and indirect cost of completing the remaining part of the WORK exceed
provisions of their Agreement. Within the scope of the arbitration clause are discrepancies as to the sum which would have been payable to [petitioner] had it completed the WORK, the
the amount of advances and billable accomplishments, the application of the provision on amount of such excess [may be] claimed by [respondent] from either of the following:
termination, and the consequent set-off of expenses.
‘1. Any amount due [petitioner] from [respondent] at the time of the termination of this
A review of the factual allegations of the parties reveals that they differ on the following questions: Agreement."22
(1) Did a take-over/termination occur? (2) May the expenses incurred by respondent in the take-
25 | A D R C A S E S S E T 1

The issue as to the correct amount of petitioner’s advances and billable accomplishments "2. All customs duties, import duties, contractor’s taxes, income taxes, and other taxes
involves an evaluation of the manner in which the parties completed the work, the extent to which that may be required by any government agencies in connection with this Agreement
they did it, and the expenses each of them incurred in connection therewith. Arbitrators also need shall be for the sole account of [petitioner]."23
to look into the computation of foreign and local costs of materials, foreign and local advances,
retention fees and letters of credit, and taxes and duties as set forth in the Agreement. These data Being an inexpensive, speedy and amicable method of settling disputes,24 arbitration -- along with
can be gathered from a review of the Agreement, pertinent portions of which are reproduced mediation, conciliation and negotiation -- is encouraged by the Supreme Court. Aside from
hereunder: unclogging judicial dockets, arbitration also hastens the resolution of disputes, especially of the
commercial kind.25 It is thus regarded as the "wave of the future" in international civil and
"C. CONTRACT PRICE AND TERMS OF PAYMENT commercial disputes.26 Brushing aside a contractual agreement calling for arbitration between the
parties would be a step backward.27
x x x           x x x           x x x
Consistent with the above-mentioned policy of encouraging alternative dispute resolution
"All progress payments to be made by [respondent] to [petitioner] shall be subject to a methods, courts should liberally construe arbitration clauses. Provided such clause is susceptible
retention sum of ten percent (10%) of the value of the approved quantities. Any claims by of an interpretation that covers the asserted dispute, an order to arbitrate should be granted.28 Any
[respondent] on [petitioner] may be deducted by [respondent] from the progress doubt should be resolved in favor of arbitration.29
payments and/or retained amount. Any excess from the retained amount after deducting
[respondent’s] claims shall be released by [respondent] to [petitioner] after the issuance Second Issue:
of [the Ministry of Public Works and Highways] of the Certificate of Completion and final Prior Request for Arbitration
acceptance of the WORK by [the Ministry of Public Works and Highways].
According to petitioner, assuming arguendo that the dispute is arbitrable, the failure to file a formal
x x x           x x x           x x x request for arbitration with the Construction Industry Arbitration Commission (CIAC) precluded the
latter from acquiring jurisdiction over the question. To bolster its position, petitioner even cites our
"D. IMPORTED MATERIALS AND EQUIPMENT ruling in Tesco Services Incorporated v. Vera.30 We are not persuaded.

"[Respondent shall open the letters of credit for the importation of equipment and Section 1 of Article II of the old Rules of Procedure Governing Construction Arbitration indeed
materials listed in Annex E hereof after the drawings, brochures, and other technical data required the submission of a request for arbitration, as follows:
of each items in the list have been formally approved by [the Ministry of Public Works
and Highways]. However, petitioner will still be fully responsible for all imported materials "SECTION. 1. Submission to Arbitration -- Any party to a construction contract wishing to
and equipment. have recourse to arbitration by the Construction Industry Arbitration Commission (CIAC)
shall submit its Request for Arbitration in sufficient copies to the Secretariat of the CIAC;
"All expenses incurred by [respondent], both in foreign and local currencies in connection PROVIDED, that in the case of government construction contracts, all administrative
with the opening of the letters of credit shall be deducted from the Contract Prices. remedies available to the parties must have been exhausted within 90 days from the time
the dispute arose."
x x x           x x x           x x x
Tesco was promulgated by this Court, using the foregoing provision as reference.
"N. OTHER CONDITIONS
On the other hand, Section 1 of Article III of the new Rules of Procedure Governing Construction
x x x           x x x           x x x Arbitration has dispensed with this requirement and recourse to the CIAC may now be availed of
26 | A D R C A S E S S E T 1

whenever a contract "contains a clause for the submission of a future controversy to arbitration," Since petitioner has already filed a Complaint with the RTC without prior recourse to arbitration,
in this wise: the proper procedure to enable the CIAC to decide on the dispute is to request the stay or
suspension of such action, as provided under RA 876 [the Arbitration Law].37
"SECTION 1. Submission to CIAC Jurisdiction — An arbitration clause in a construction
contract or a submission to arbitration of a construction dispute shall be deemed an WHEREFORE, the Petition is DENIED and the assailed Decision AFFIRMED. Costs against
agreement to submit an existing or future controversy to CIAC jurisdiction, petitioner.
notwithstanding the reference to a different arbitration institution or arbitral body in such
contract or submission. When a contract contains a clause for the submission of a future SO ORDERED.
controversy to arbitration, it is not necessary for the parties to enter into a submission
agreement before the claimant may invoke the jurisdiction of CIAC."

The foregoing amendments in the Rules were formalized by CIAC Resolution Nos. 2-91 and 3-
93.31

The difference in the two provisions was clearly explained in China Chang Jiang Energy
Corporation (Philippines) v. Rosal Infrastructure Builders et al.32 (an extended unsigned
Resolution) and reiterated in National Irrigation Administration v. Court of Appeals,33 from which
we quote thus:

"Under the present Rules of Procedure, for a particular construction contract to fall within
the jurisdiction of CIAC, it is merely required that the parties agree to submit the same to
voluntary arbitration Unlike in the original version of Section 1, as applied in the Tesco
case, the law as it now stands does not provide that the parties should agree to submit
disputes arising from their agreement specifically to the CIAC for the latter to acquire
jurisdiction over the same. Rather, it is plain and clear that as long as the parties agree to
submit to voluntary arbitration, regardless of what forum they may choose, their
agreement will fall within the jurisdiction of the CIAC, such that, even if they specifically
choose another forum, the parties will not be precluded from electing to submit their
dispute before the CIAC because this right has been vested upon each party by law, i.e.,
E.O. No. 1008."34

Clearly, there is no more need to file a request with the CIAC in order to vest it with jurisdiction to
decide a construction dispute.

The arbitral clause in the Agreement is a commitment on the part of the parties to submit to
arbitration the disputes covered therein. Because that clause is binding, they are expected to
abide by it in good faith.35 And because it covers the dispute between the parties in the present
case, either of them may compel the other to arbitrate.36
27 | A D R C A S E S S E T 1

G.R. No. 174938               October 1, 2014 BF Corporation eventually completed the construction of the buildings.7 Shangri-La allegedly took
possession of the buildings while still owing BF Corporation an outstanding balance.8
GERARDO LANUZA, JR. AND ANTONIO O. OLBES, Petitioners,
vs. BF Corporation alleged that despite repeated demands, Shangri-La refused to pay the balance
BF CORPORATION, SHANGRI-LA PROPERTIES, INC., ALFREDO C. RAMOS, RUFO B. owed to it.9 It also alleged that the Shangri-La’s directors were in bad faith in directing Shangri-
COLAYCO, MAXIMO G. LICAUCO III, AND BENJAMIN C. RAMOS, Respondents. La’s affairs. Therefore, they should be held jointly and severally liable with Shangri-La for its
obligations as well as for the damages that BF Corporation incurred as a result of Shangri-La’s
DECISION default.10

LEONEN, J.: On August 3, 1993, Shangri-La, Alfredo C. Ramos, Rufo B. Colayco, Maximo G. Licauco III, and
Benjamin C. Ramos filed a motion to suspend the proceedings in view of BF Corporation’s failure
Corporate representatives may be compelled to submit to arbitration proceedings pursuant to a to submit its dispute to arbitration, in accordance with the arbitration clauseprovided in its contract,
contract entered into by the corporation they represent if there are allegations of bad faith or quoted in the motion as follows:11
malice in their acts representing the corporation.
35. Arbitration
This is a Rule 45 petition, assailing the Court of Appeals' May 11, 2006 decision and October 5,
2006 resolution. The Court of Appeals affirmed the trial court's decision holding that petitioners, as (1) Provided always that in case any dispute or difference shall arise between the Owner or the
director, should submit themselves as parties tothe arbitration proceedings between BF Project Manager on his behalf and the Contractor, either during the progress or after the
Corporation and Shangri-La Properties, Inc. (Shangri-La). completion or abandonment of the Works as to the construction of this Contract or as to any
matter or thing of whatsoever nature arising there under or inconnection therewith (including any
In 1993, BF Corporation filed a collection complaint with the Regional Trial Court against Shangri- matter or thing left by this Contract to the discretion of the Project Manager or the withholding by
Laand the members of its board of directors: Alfredo C. Ramos, Rufo B.Colayco, Antonio O. the Project Manager of any certificate to which the Contractor may claim to be entitled or the
Olbes, Gerardo Lanuza, Jr., Maximo G. Licauco III, and Benjamin C. Ramos.1 measurement and valuation mentioned in clause 30(5)(a) of these Conditions or the rights and
liabilities of the parties under clauses 25, 26, 32 or 33 of these Conditions), the owner and the
BF Corporation alleged in its complaint that on December 11, 1989 and May 30, 1991, it entered Contractor hereby agree to exert all efforts to settle their differences or dispute amicably. Failing
into agreements with Shangri-La wherein it undertook to construct for Shangri-La a mall and a these efforts then such dispute or difference shall be referred to arbitration in accordance with the
multilevel parking structure along EDSA.2 rules and procedures of the Philippine Arbitration Law.

Shangri-La had been consistent in paying BF Corporation in accordance with its progress billing x x x           x x x          x x x
statements.3 However, by October 1991, Shangri-La started defaulting in payment.4
(6) The award of such Arbitrators shall be final and binding on the parties. The decision of the
BF Corporation alleged that Shangri-La induced BF Corporation to continue with the construction Arbitrators shall be a condition precedent to any right of legal action that either party may have
of the buildings using its own funds and credit despite Shangri-La’s default.5 According to BF against the other. . . .12 (Underscoring in the original)
Corporation, ShangriLa misrepresented that it had funds to pay for its obligations with BF
Corporation, and the delay in payment was simply a matter of delayed processing of BF On August 19, 1993, BF Corporation opposed the motion to suspend proceedings.13
Corporation’s progress billing statements.6
In the November 18, 1993 order, the Regional Trial Court denied the motion to suspend
proceedings.14
28 | A D R C A S E S S E T 1

On December 8, 1993, petitioners filed an answer to BF Corporation’s complaint, with compulsory In its May 11, 2006 decision,29 the Court of Appeals dismissed petitioners’ petition for certiorari.
counter claim against BF Corporation and crossclaim against Shangri-La.15 They alleged that they The Court of Appeals ruled that ShangriLa’s directors were necessary parties in the arbitration
had resigned as members of Shangri-La’s board of directors as of July 15, 1991.16 proceedings.30 According to the Court of Appeals:

After the Regional Trial Court denied on February 11, 1994 the motion for reconsideration of its [They were] deemed not third-parties tothe contract as they [were] sued for their acts in
November 18, 1993 order, Shangri-La, Alfredo C. Ramos, Rufo B. Colayco,Maximo G. Licauco III, representation of the party to the contract pursuant to Art. 31 of the Corporation Code, and that as
and Benjamin Ramos filed a petition for certiorari with the Court of Appeals.17 directors of the defendant corporation, [they], in accordance with Art. 1217 of the Civil Code,
stand to be benefited or injured by the result of the arbitration proceedings, hence, being
On April 28, 1995, the Court of Appeals granted the petition for certiorari and ordered the necessary parties, they must be joined in order to have complete adjudication of the controversy.
submission of the dispute to arbitration.18 Consequently, if [they were] excluded as parties in the arbitration proceedings and an arbitral
award is rendered, holding [Shangri-La] and its board of directors jointly and solidarily liable to
Aggrieved by the Court of Appeals’ decision, BF Corporation filed a petition for review on certiorari private respondent BF Corporation, a problem will arise, i.e., whether petitioners will be bound
with this court.19 On March 27, 1998, this court affirmed the Court of Appeals’ decision, directing bysuch arbitral award, and this will prevent complete determination of the issues and resolution of
that the dispute be submitted for arbitration.20 the controversy.31

Another issue arose after BF Corporation had initiated arbitration proceedings. BF Corporation The Court of Appeals further ruled that "excluding petitioners in the arbitration proceedings . . .
and Shangri-La failed to agree as to the law that should govern the arbitration proceedings.21 On would be contrary to the policy against multiplicity of suits."32
October 27, 1998, the trial court issued the order directing the parties to conduct the proceedings
in accordance with Republic Act No. 876.22 The dispositive portion of the Court of Appeals’ decision reads:

Shangri-La filed an omnibus motion and BF Corporation an urgent motion for clarification, both WHEREFORE, the petition is DISMISSED. The assailed orders dated July 28, 2003 and January
seeking to clarify the term, "parties," and whether Shangri-La’s directors should be included in the 19, 2005 of public respondent RTC, Branch 157, Pasig City, in Civil Case No. 63400, are
arbitration proceedings and served with separate demands for arbitration.23 AFFIRMED.33

Petitioners filed their comment on Shangri-La’s and BF Corporation’s motions, praying that they The Court of Appeals denied petitioners’ motion for reconsideration in the October 5, 2006
be excluded from the arbitration proceedings for being non-parties to Shangri-La’s and BF resolution.34
Corporation’s agreement.24
On November 24, 2006, petitioners filed a petition for review of the May 11, 2006 Court of
On July 28, 2003, the trial court issued the order directing service of demands for arbitration upon Appeals decision and the October 5, 2006 Court of Appeals resolution.35
all defendants in BF Corporation’s complaint.25 According to the trial court, Shangri-La’s directors
were interested parties who "must also be served with a demand for arbitration to give them the The issue in this case is whether petitioners should be made parties to the arbitration
opportunity to ventilate their side of the controversy, safeguard their interest and fend off their proceedings, pursuant to the arbitration clause provided in the contract between BF Corporation
respective positions."26 Petitioners’ motion for reconsideration ofthis order was denied by the trial and Shangri-La.
court on January 19, 2005.27
Petitioners argue that they cannot be held personally liable for corporate acts or obligations.36 The
Petitioners filed a petition for certiorari with the Court of Appeals, alleging grave abuse of corporation is a separate being, and nothing justifies BF Corporation’s allegation that they are
discretion in the issuance of orders compelling them to submit to arbitration proceedings despite solidarily liable with Shangri-La.37 Neither did they bind themselves personally nor did they
being third parties to the contract between Shangri-La and BF Corporation.28 undertake to shoulder Shangri-La’s obligations should it fail in its obligations.38 BF Corporation
also failed to establish fraud or bad faith on their part.39
29 | A D R C A S E S S E T 1

Petitioners also argue that they are third parties to the contract between BF Corporation and Upon the court’s order, petitioners and Shangri-La filed their respective memoranda. Petitioners
Shangri-La.40 Provisions including arbitration stipulations should bind only the parties.41 Based on and Maximo G. Licauco III, Alfredo C. Ramos, and Benjamin C. Ramos reiterated their arguments
our arbitration laws, parties who are strangers to an agreement cannot be compelled to arbitrate.42 that they should not be held liable for Shangri-La’s default and made parties to the arbitration
proceedings because only BF Corporation and Shangri-La were parties to the contract.
Petitioners point out thatour arbitration laws were enacted to promote the autonomy of parties in
resolving their disputes.43 Compelling them to submit to arbitration is against this purpose and In its memorandum, Shangri-La argued that petitioners were impleaded for their solidary liability
may be tantamount to stipulating for the parties.44 under Section 31 of the Corporation Code. Shangri-La added that their exclusion from the
arbitration proceedings will result in multiplicity of suits, which "is not favored in this
Separate comments on the petition werefiled by BF Corporation, and Maximo G. Licauco III, jurisdiction."60 It pointed out that the case had already been mooted by the termination of the
Alfredo C.Ramos and Benjamin C. Ramos.45 arbitration proceedings, which petitioners actively participated in.61 Moreover, BF Corporation
assailed only the correctness of the Arbitral Tribunal’s award and not the part absolving Shangri-
Maximo G. Licauco III Alfredo C. Ramos, and Benjamin C. Ramos agreed with petitioners that La’s directors from liability.62
Shangri-La’sdirectors, being non-parties to the contract, should not be made personally liable for
Shangri-La’s acts.46 Since the contract was executed only by BF Corporation and Shangri-La, only BF Corporation filed a counter-manifestation with motion to dismiss63 in lieu of the required
they should be affected by the contract’s stipulation.47 BF Corporation also failed to specifically memorandum.
allege the unlawful acts of the directors that should make them solidarily liable with Shangri-La for
its obligations.48 In its counter-manifestation, BF Corporation pointed out that since "petitioners’ counterclaims
were already dismissed with finality, and the claims against them were likewise dismissed with
Meanwhile, in its comment, BF Corporation argued that the courts’ ruling that the parties should finality, they no longer have any interest orpersonality in the arbitration case. Thus, there is no
undergo arbitration "clearly contemplated the inclusion of the directors of the corporation[.]"49 BF longer any need to resolve the present Petition, which mainly questions the inclusion of petitioners
Corporation also argued that while petitioners were not parties to the agreement, they were still in the arbitration proceedings."64 The court’s decision in this case will no longer have any effect on
impleaded under Section 31 of the Corporation Code.50 Section 31 makes directors solidarily the issue of petitioners’ inclusion in the arbitration proceedings.65
liable for fraud, gross negligence, and bad faith.51 Petitioners are not really third parties to the
agreement because they are being sued as Shangri-La’s representatives, under Section 31 of the The petition must fail.
Corporation Code.52
The Arbitral Tribunal’s decision, absolving petitioners from liability, and its binding effect on BF
BF Corporation further argued that because petitioners were impleaded for their solidary liability, Corporation, have rendered this case moot and academic.
they are necessary parties to the arbitration proceedings.53 The full resolution of all disputes in the
arbitration proceedings should also be done in the interest of justice.54 The mootness of the case, however, had not precluded us from resolving issues so that principles
may be established for the guidance of the bench, bar, and the public. In De la Camara v. Hon.
In the manifestation dated September 6, 2007, petitioners informed the court that the Arbitral Enage,66 this court disregarded the fact that petitioner in that case already escaped from prison
Tribunal had already promulgated its decision on July 31, 2007.55 The Arbitral Tribunal denied BF and ruled on the issue of excessive bails:
Corporation’s claims against them.56 Petitioners stated that "[they] were included by the Arbitral
Tribunal in the proceedings conducted . . . notwithstanding [their] continuing objection While under the circumstances a ruling on the merits of the petition for certiorari is notwarranted,
thereto. . . ."57 They also stated that "[their] unwilling participation in the arbitration case was done still, as set forth at the opening of this opinion, the fact that this case is moot and academic should
ex abundante ad cautela, as manifested therein on several occasions."58 Petitioners informed the not preclude this Tribunal from setting forth in language clear and unmistakable, the obligation of
court that they already manifested with the trial court that "any action taken on [the Arbitral fidelity on the part of lower court judges to the unequivocal command of the Constitution that
Tribunal’s decision] should be without prejudice to the resolution of [this] case."59 excessive bail shall not be required.67
30 | A D R C A S E S S E T 1

This principle was repeated in subsequent cases when this court deemed it proper to clarify commercial kind. It is thus regarded as the "wave of the future" in international civil and
important matters for guidance.68 commercial disputes. Brushing aside a contractual agreement calling for arbitration between the
parties would be a step backward.
Thus, we rule that petitioners may be compelled to submit to the arbitration proceedings in
accordance with Shangri-Laand BF Corporation’s agreement, in order to determine if the Consistent with the above-mentioned policy of encouraging alternative dispute resolution
distinction between Shangri-La’s personality and their personalities should be disregarded. methods, courts should liberally construe arbitration clauses. Provided such clause is susceptible
of an interpretation that covers the asserted dispute, an order to arbitrate should be granted. Any
This jurisdiction adopts a policy in favor of arbitration. Arbitration allows the parties to avoid doubt should be resolved in favor of arbitration.74 (Emphasis supplied)
litigation and settle disputes amicably and more expeditiously by themselves and through their
choice of arbitrators. A more clear-cut statement of the state policy to encourage arbitration and to favor interpretations
that would render effective an arbitration clause was later expressed in Republic Act No. 9285:75
The policy in favor of arbitration has been affirmed in our Civil Code,69 which was approved as
early as 1949. It was later institutionalized by the approval of Republic Act No. 876,70 which SEC. 2. Declaration of Policy.- It is hereby declared the policy of the State to actively promote
expressly authorized, made valid, enforceable, and irrevocable parties’ decision to submit their party autonomy in the resolution of disputes or the freedom of the party to make their own
controversies, including incidental issues, to arbitration. This court recognized this policy in arrangements to resolve their disputes. Towards this end, the State shall encourage and actively
Eastboard Navigation, Ltd. v. Ysmael and Company, Inc.:71 promote the use of Alternative Dispute Resolution (ADR) as an important means to achieve
speedy and impartial justice and declog court dockets. As such, the State shall provide means for
As a corollary to the question regarding the existence of an arbitration agreement, defendant the use of ADR as an efficient tool and an alternative procedure for the resolution of appropriate
raises the issue that, even if it be granted that it agreed to submit its dispute with plaintiff to cases. Likewise, the State shall enlist active private sector participation in the settlement of
arbitration, said agreement is void and without effect for it amounts to removing said dispute from disputes through ADR. This Act shall be without prejudice to the adoption by the Supreme Court
the jurisdiction of the courts in which the parties are domiciled or where the dispute occurred. It is of any ADR system, such as mediation, conciliation, arbitration, or any combination thereof as a
true that there are authorities which hold that "a clause in a contract providing that all matters in means of achieving speedy and efficient means of resolving cases pending before all courts in the
dispute between the parties shall be referred to arbitrators and to them alone, is contrary to public Philippines which shall be governed by such rules as the Supreme Court may approve from time
policy and cannot oust the courts of jurisdiction" (Manila Electric Co. vs. Pasay Transportation to time.
Co., 57 Phil., 600, 603), however, there are authorities which favor "the more intelligent view that
arbitration, as an inexpensive, speedy and amicable method of settling disputes, and as a means ....
of avoiding litigation, should receive every encouragement from the courts which may be
extended without contravening sound public policy or settled law" (3 Am. Jur., p. 835). Congress SEC. 25. Interpretation of the Act.- In interpreting the Act, the court shall have due regard to the
has officially adopted the modern view when it reproduced in the new Civil Code the provisions of policy of the law in favor of arbitration.Where action is commenced by or against multiple parties,
the old Code on Arbitration. And only recently it approved Republic Act No. 876 expressly one or more of whomare parties who are bound by the arbitration agreement although the civil
authorizing arbitration of future disputes.72 (Emphasis supplied) action may continue as to those who are not bound by such arbitration agreement. (Emphasis
supplied)
In view of our policy to adopt arbitration as a manner of settling disputes, arbitration clauses are
liberally construed to favor arbitration. Thus, in LM Power Engineering Corporation v. Capitol Thus, if there is an interpretation that would render effective an arbitration clause for purposes
Industrial Construction Groups, Inc.,73 this court said: ofavoiding litigation and expediting resolution of the dispute, that interpretation shall be adopted.
Petitioners’ main argument arises from the separate personality given to juridical persons vis-à-vis
Being an inexpensive, speedy and amicable method of settling disputes, arbitration — along with their directors, officers, stockholders, and agents. Since they did not sign the arbitration
mediation, conciliation and negotiation — is encouraged by the Supreme Court. Aside from agreement in any capacity, they cannot be forced to submit to the jurisdiction of the Arbitration
unclogging judicial dockets, arbitration also hastens the resolution of disputes, especially of the
31 | A D R C A S E S S E T 1

Tribunal in accordance with the arbitration agreement. Moreover, they had already resigned as 8. To enter into merger or consolidation with other corporations as provided in this Code;
directors of Shangri-Laat the time of the alleged default.
9. To make reasonable donations, including those for the public welfare or for hospital,
Indeed, as petitioners point out, their personalities as directors of Shangri-La are separate and charitable, cultural, scientific, civic, or similar purposes: Provided, That no corporation,
distinct from Shangri-La. domestic or foreign, shall give donations in aid of any political party or candidate or for
purposes of partisan political activity;
A corporation is an artificial entity created by fiction of law.76 This means that while it is not a
person, naturally, the law gives it a distinct personality and treats it as such. A corporation, in the 10. To establish pension, retirement, and other plans for the benefit of its directors,
legal sense, is an individual with a personality that is distinct and separate from other persons trustees, officers and employees; and
including its stockholders, officers, directors, representatives,77 and other juridical entities. The law
vests in corporations rights,powers, and attributes as if they were natural persons with physical 11. To exercise such other powers asmay be essential or necessary to carry out its
existence and capabilities to act on their own.78 For instance, they have the power to sue and purpose or purposes as stated in its articles of incorporation. (13a)
enter into transactions or contracts. Section 36 of the Corporation Code enumerates some of a
corporation’s powers, thus: Because a corporation’s existence is only by fiction of law, it can only exercise its rights and
powers through itsdirectors, officers, or agents, who are all natural persons. A corporation cannot
Section 36. Corporate powers and capacity.– Every corporation incorporated under this Code has sue or enter into contracts without them.
the power and capacity:
A consequence of a corporation’s separate personality is that consent by a corporation through its
1. To sue and be sued in its corporate name; representatives is not consent of the representative, personally. Its obligations, incurred through
official acts of its representatives, are its own. A stockholder, director, or representative does not
2. Of succession by its corporate name for the period of time stated in the articles of become a party to a contract just because a corporation executed a contract through that
incorporation and the certificate ofincorporation; stockholder, director or representative.

3. To adopt and use a corporate seal; Hence, a corporation’s representatives are generally not bound by the terms of the contract
executed by the corporation. They are not personally liable for obligations and liabilities incurred
4. To amend its articles of incorporation in accordance with the provisions of this Code; on or in behalf of the corporation.

5. To adopt by-laws, not contrary to law, morals, or public policy, and to amend or repeal Petitioners are also correct that arbitration promotes the parties’ autonomy in resolving their
the same in accordance with this Code; disputes. This court recognized in Heirs of Augusto Salas, Jr. v. Laperal Realty Corporation79 that
an arbitration clause shall not apply to persons who were neither parties to the contract nor
6. In case of stock corporations, to issue or sell stocks to subscribers and to sell treasury assignees of previous parties, thus:
stocks in accordance with the provisions of this Code; and to admit members to the
corporation if it be a non-stock corporation; A submission to arbitration is a contract. As such, the Agreement, containing the stipulation on
arbitration, binds the parties thereto, as well as their assigns and heirs. But only they.80 (Citations
7. To purchase, receive, take or grant, hold, convey, sell, lease, pledge, mortgage and omitted)
otherwise deal with such real and personal property, including securities and bonds of
other corporations, as the transaction of the lawful business of the corporation may Similarly, in Del Monte Corporation-USA v. Court of Appeals,81 this court ruled:
reasonably and necessarily require, subject to the limitations prescribed by law and the
Constitution;
32 | A D R C A S E S S E T 1

The provision to submit to arbitration any dispute arising therefrom and the relationship of the severally for all damages resulting therefrom suffered by the corporation, its stockholders or
parties is part of that contract and is itself a contract. As a rule, contracts are respected as the law members and other persons.
between the contracting parties and produce effect as between them, their assigns and heirs.
Clearly, only parties to the Agreement . . . are bound by the Agreement and its arbitration clause When a director, trustee or officer attempts to acquire or acquires, in violation of his duty, any
as they are the only signatories thereto.82 (Citation omitted) interest adverse to the corporation in respect of any matter which has been reposed inhim in
confidence, as to which equity imposes a disability upon him to deal in his own behalf, he shall be
This court incorporated these rulings in Agan, Jr. v. Philippine International Air Terminals Co., liable as a trustee for the corporation and must account for the profits which otherwise would have
Inc.83 and Stanfilco Employees v. DOLE Philippines, Inc., et al.84 accrued to the corporation. (n)

As a general rule, therefore, a corporation’s representative who did not personally bind himself or Based on the above provision, a director, trustee, or officer of a corporation may be made
herself to an arbitration agreement cannot be forced to participate in arbitration proceedings made solidarily liable with it for all damages suffered by the corporation, its stockholders or members,
pursuant to an agreement entered into by the corporation. He or she is generally not considered a and other persons in any of the following cases:
party to that agreement.
a) The director or trustee willfully and knowingly voted for or assented to a patently
However, there are instances when the distinction between personalities of directors, officers,and unlawful corporate act;
representatives, and of the corporation, are disregarded. We call this piercing the veil of corporate
fiction. b) The director or trustee was guilty of gross negligence or bad faith in directing
corporate affairs; and
Piercing the corporate veil is warranted when "[the separate personality of a corporation] is used
as a means to perpetrate fraud or an illegal act, or as a vehicle for the evasion of an existing c) The director or trustee acquired personal or pecuniary interest in conflict with his or
obligation, the circumvention of statutes, or to confuse legitimate issues."85 It is also warranted in her duties as director or trustee.
alter ego cases "where a corporation is merely a farce since it is a mere alter ego or business
conduit of a person, or where the corporation is so organized and controlled and its affairs are so Solidary liability with the corporation will also attach in the following instances:
conducted as to make it merely an instrumentality, agency, conduit or adjunct of another
corporation."86 a) "When a director or officer has consented to the issuance of watered stocks or who,
having knowledge thereof, did not forthwith file with the corporate secretary his written
When corporate veil is pierced, the corporation and persons who are normally treated as distinct objection thereto";87
from the corporation are treated as one person, such that when the corporation is adjudged liable,
these persons, too, become liable as if they were the corporation. b) "When a director, trustee or officer has contractually agreed or stipulated to hold
himself personally and solidarily liable with the corporation";88 and
Among the persons who may be treatedas the corporation itself under certain circumstances are
its directors and officers. Section 31 of the Corporation Code provides the instances when c) "When a director, trustee or officer is made, by specific provision of law, personally
directors, trustees, or officers may become liable for corporate acts: liable for his corporate action."89

Sec. 31. Liability of directors, trustees or officers. - Directors or trustees who willfully and When there are allegations of bad faith or malice against corporate directors or representatives, it
knowingly vote for or assent to patently unlawful acts of the corporation or who are guilty of gross becomes the duty of courts or tribunals to determine if these persons and the corporation should
negligence or bad faith in directing the affairs of the corporation or acquire any personal or be treated as one. Without a trial, courts and tribunals have no basis for determining whether the
pecuniary interest in conflict with their duty as such directors or trustees shall be liable jointly and veil of corporate fiction should be pierced. Courts or tribunals do not have such prior knowledge.
Thus, the courts or tribunals must first determine whether circumstances exist towarrant the courts
33 | A D R C A S E S S E T 1

or tribunals to disregard the distinction between the corporation and the persons representing it. obligations are transferred to them upon assignment. In other words, the assignor’s rights and
The determination of these circumstances must be made by one tribunal or court in a proceeding obligations become their own rights and obligations. In the same way, the corporation’s
participated in by all parties involved, including current representatives of the corporation, and obligations are treated as the representative’s obligations when the corporate veil is pierced.
those persons whose personalities are impliedly the sameas the corporation. This is because Moreover, in Heirs of Augusto Salas, this court affirmed its policy against multiplicity of suits and
when the court or tribunal finds that circumstances exist warranting the piercing of the corporate unnecessary delay. This court said that "to split the proceeding into arbitration for some parties
veil, the corporate representatives are treated as the corporation itself and should be held liable and trial for other parties would "result in multiplicity of suits, duplicitous procedure and
for corporate acts. The corporation’s distinct personality is disregarded, and the corporation is unnecessary delay."91 This court also intimated that the interest of justice would be best observed
seen as a mere aggregation of persons undertaking a business under the collective name of the if it adjudicated rights in a single proceeding.92 While the facts of that case prompted this court to
corporation. direct the trial court to proceed to determine the issues of thatcase, it did not prohibit courts from
allowing the case to proceed to arbitration, when circumstances warrant.
Hence, when the directors, as in this case, are impleaded in a case against a corporation, alleging
malice orbad faith on their part in directing the affairs of the corporation, complainants are Hence, the issue of whether the corporation’s acts in violation of complainant’s rights, and the
effectively alleging that the directors and the corporation are not acting as separate entities. They incidental issue of whether piercing of the corporate veil is warranted, should be determined in a
are alleging that the acts or omissions by the corporation that violated their rights are also the single proceeding. Such finding would determine if the corporation is merely an aggregation of
directors’ acts or omissions.90 They are alleging that contracts executed by the corporation are persons whose liabilities must be treated as one with the corporation.
contracts executed by the directors. Complainants effectively pray that the corporate veilbe
pierced because the cause of action between the corporation and the directors is the same. However, when the courts disregard the corporation’s distinct and separate personality from its
directors or officers, the courts do not say that the corporation, in all instances and for all
In that case, complainants have no choice but to institute only one proceeding against the purposes, is the same as its directors, stockholders, officers, and agents. It does not result in an
parties.1âwphi1 Under the Rules of Court, filing of multiple suits for a single cause of action is absolute confusion of personalities of the corporation and the persons composing or representing
prohibited. Institution of more than one suit for the same cause of action constitutes splitting the it. Courts merely discount the distinction and treat them as one, in relation to a specific act, in
cause of action, which is a ground for the dismissal ofthe others. Thus, in Rule 2: order to extend the terms of the contract and the liabilities for all damages to erring corporate
officials who participated in the corporation’s illegal acts. This is done so that the legal fiction
Section 3. One suit for a single cause of action. — A party may not institute more than one suit for cannot be used to perpetrate illegalities and injustices.
a single cause of action. (3a)
Thus, in cases alleging solidary liability with the corporation or praying for the piercing of the
Section 4. Splitting a single cause of action;effect of. — If two or more suits are instituted on the corporate veil, parties who are normally treated as distinct individuals should be made to
basis of the same cause of action, the filing of one or a judgment upon the merits in any one is participate in the arbitration proceedings in order to determine ifsuch distinction should indeed be
available as a ground for the dismissal of the others. (4a) disregarded and, if so, to determine the extent of their liabilities.

It is because the personalities of petitioners and the corporation may later be found to be indistinct In this case, the Arbitral Tribunal rendered a decision, finding that BF Corporation failed to prove
that we rule that petitioners may be compelled to submit to arbitration. the existence of circumstances that render petitioners and the other directors solidarily liable. It
ruled that petitioners and Shangri-La’s other directors were not liable for the contractual
However, in ruling that petitioners may be compelled to submit to the arbitration proceedings, we obligations of Shangri-La to BF Corporation. The Arbitral Tribunal’s decision was made with the
are not overturning Heirs of Augusto Salas wherein this court affirmed the basic arbitration participation of petitioners, albeit with their continuing objection. In view of our discussion above,
principle that only parties to an arbitration agreement may be compelled to submit to arbitration. In we rule that petitioners are bound by such decision.
that case, this court recognizedthat persons other than the main party may be compelled to
submit to arbitration, e.g., assignees and heirs. Assignees and heirs may be considered parties to WHEREFORE, the petition is DENIED. The Court of Appeals' decision of May 11, 2006 and
an arbitration agreement entered into by their assignor because the assignor’s rights and resolution of October 5, 2006 are AFFIRMED.
34 | A D R C A S E S S E T 1

SO ORDERED.
35 | A D R C A S E S S E T 1

G.R. No. L-12283            July 25, 1918 14, 1914, and costs. Defendant moved for a new trial, which was denied, duly excepted and
perfected a bill of exceptions to this court.
ARTHUR F. ALLEN, plaintiff-appellee,
vs. Appellant's assignments of error relate to the findings of fact and two main issues of law. We pass
THE PROVINCE OF TAYABAS, defendant-appellant. the facts for the moment, and two main issues of law. We pass the facts for the moment, to
discuss the legal questions.
Provincial Fiscal of Tayabas Crispin Oben for appellant.
Lawrence & Ross for appellee. The first contention of appellant is that the Province of Tayabas is not obligated to pay the
contractor anything because the contract was not approved by the Governor-General. This
MALCOLM, J.: position is absolutely untenable. The law in force when the contract entered into and when the
action was tried, section 2, Act No. 83, as amended by Act No. 1600, made the approval of the
On April 18, 1914, the Province of Tayabas, represented by the Director of Public Works, and Governor-General a prerequisite only to the purchase and conveyance of real estate by a
Arthur F, Allen, contractor, entered into a contract whereby the contractor agreed to construct five province. The grammatical construction of the English text, which is controlling, makes this
reenforced concrete bridges for P39,200. This contract was in the usual form. One provision was perfectly clear. Moreover, the law now in force (Administrative Code of 1917, section 2068) has
that the bridges were to be constructed "in accordance with the said advertisements, instructions removed any possibility of doubt and has at the same time revealed legislative intention, by
to bidders, general conditions, plans, specifications, proposal, and this agreement." Other placing the requirement for the Governor-General's approval of transfers of real estate by
paragraphs of the contract concerned the method and rate of payment for extras. provinces in a section separate and distinct from the section of the Code giving the corporate
powers of provinces.
Four of the bridges were accepted by the Government and paid for. The dispute between the
parties arose as to the fifth bridge, No. 53.3 and as to certain extras. As to this bridge, the The remaining legal issue merits more extended consideration. Appellant's contention is that the
Province of Tayabas paid to the contractor P4,360 on account of the contract price thereof, but certificate by the district engineer and the Director of Public Works must be obtained before suit
refused to pay the balance of P2,840 because plaintiff had deviated from the specifications and can be brought on a contract; that the findings of these officials are conclusive; and that the
because the work was defective. The province further refused to pay for certain extras. To recover complaint must contain an averment to this effect. Appellee's reply must contain an averment to
the balance upon the contract was the purpose of the contractor in bringing action for P9,685 this effect. Appellee's reply is that neither the law nor the contract requires the submission to
(amended complaint), alleged to be due him by the Province of Tayabas. The common averments arbitration of disputes between the Government and the contractor, and that a mere
of the six causes of action were: (1) Residence; (2) the contract; (3) the faithful compliance "with administrative procedure incident to payment has been established.
all the terms and conditions of the said contract" on the part of the contractor, and completion and
delivery of the bridges in question; (4) refusal of defendant to pay plaintiff the balance due for Act No. 1401, as amended by Act No. 1752, was in force when this action was instituted. The
bridge No. 53.3 for certain extras, and as damages, although frequently requested to do so. same provisions are now found in slightly altered phraseology in section 1917-1923 of the
Defendant demurred to the complaint on the ground that it did not state facts sufficient to Administrative Code of 1917. The law gives a district engineer supervision over all contacts
constitute a cause of action, because: (a) The approval of the Governor-General to the contract connected with public works, which exceed the estimated cost of P500. Section 6 of Act No. 1401,
had not been given as contemplated by section 2 of the Provincial Government Act (No. 83) and as amended by section 3 of Act No. 1752, reads:
(b) the certificate for payment had not been accomplished by the Director of Public Works or the
district engineer as provided by section 6, of Act No. 1401, as amended. The demurrer was No payments, partial or final, shall be made on any public works without a certificate on
overruled. Thereupon defendant answered, renewing as a special defense the grounds of the the vouchers therefor to the effect that the work for which payment is contemplated has
demurrer, alleging defective work on the part of the plaintiff, and admitting a total of P2,454.78, been accomplished, inspected, and accepted. Such certificate for work under the
the amount certified by the Director of Public Works and the district engineer, as due the plaintiff. supervision of the district engineer shall be signed by him or his duly authorized
The trial court gave judgment for the plaintiff-contractor for P4,905, with legal interest from July
36 | A D R C A S E S S E T 1

representative. For work not under his supervision such certificate shall be signed by the right of the Director, hereby reserved, to reject the whole or any portion of the aforesaid
provincial treasurer. work should the same be found to have been constructed in violation of any of the
conditions or covenant of this contract.
Section 1922 of the Administrative Code of 1917, reads:
Both the law and the contract provide in mandatory language for a certificate of acceptance by the
No payment, partial or final, shall be made on any public work of construction or repair Director of Public Works or his representative before any payment shall be made on any public
without a certificate on the voucher therefor to the effect that the work for which payment work for the Government.
is contemplated has been accomplished in accordance with the terms of the contract and
has been duly inspected and accepted. Such certificate shall be signed by a duly Contracts of this character, giving into the hands of a third person or of the purchaser the power of
authorized representative of the Director of Public Works having full knowledge of the acceptance or non-acceptance, are not unusual. Courts have frequently upheld them. The law
facts in the case. regards the parties as competent to contract in this manner. Municipal and provincial contracts,
being on the same footing as those of natural persons, may not be breached with impunity. That
Contractors are of course bound to take notice of the provisions of the law relating to contracts. mutuality exists in undoubted. The party who deliberately enters into such an agreement, whether
Statutory requirements cannot be departed from for the accommodation of either party to a wisely or unwisely, must abide by it. The public corporation, in the absence of a showing of fraud
contract. As a matter of acts, in the present instance, this obligation is intensified in so far as the or concealment, is estopped by the approval of its officer who is authorized to accept the work,
contractor is concerned for the instructions to bidders contains this clause: "The contractor shall from contesting the contractor's right to the contract price. (City of Omaha vs. Hammond [1876],
comply with all existing or future laws, the municipal or provincial building ordinances and 94 U.S., 98; City Street Improvement Co. vs. City of Marysville, [1909], 155 cal., 419.) Likewise,
regulations in so far as the same are binding upon or affect the parties hereto, the work, or those the contractor must not only deliver a product with which the party of the second party ought to be
engaged thereon." (No. 23). satisfied, but with which he must be satisfied, or he is not bound to accept it. The rule is well-
settled that in the absence of fraud or of such gross mistake as would necessarily imply bad faith,
The instructions to bidders, a part of the contract, under the heading of "Payments," also contains contractors with public corporations are concluded by the decisions of engineers or like officers
the following: where the contract contains such a stipulation. The public corporation can rely on the provision in
a contract that performance by the other party shall be approved by or satisfactory to it, or a
51. Payments will be made monthly, based upon the estimates of work satisfactorily particular officer, board or committee. (Second Nat. Bank vs. Pan-American Bridge Co. [1910],
completed and accepted by the Director during the preceding month. Upon such 183 Fed., 391, reviewing Federal decisions; Silsby Manuf'g Co. vs. Town of Chico [1885], 24
estimates the Province of Tayabas, P.I. shall pay to the contractor a sum equal to ninety Fed., 893; 23 L.R.A. [1910], 322, Notes.)
(90) per cent thereof up to and until such time as the total work shall have been
completed or the contract canceled, as herein provided. A leading example is the case of Sweeney vs. United States ([1883], 109 U.S., 618), in which a
contractor sought to recover from the United States the price of wall built by him around the
52. The acceptance of the work from time to time for the purpose of making partial National Cemetery. The contract provided that the wall shall be received and become the property
payments, shall not be considered as a final acceptance of the work in question. of the United States after the officer or civil engineer, to be designated by the Government to
inspect the work, should certify that it was in all respects such as the contractor agreed to
53. Whenever the contract, in the opinion of the Director, shall be completely performed construct. The officer designated for that purpose refused to so certify on the ground that neither
on the part of the contractor, the Director shall proceed promptly to measure the work the material nor the workmanship was such as the contract required. As the officer exercised an
and shall make out and certify the final estimates and acceptance for the same. The honest judgment in making his inspection and as there was on his part neither fraud nor such
province shall then, excepting for cause herein specified, pay to the contractor promptly grave mistake as implied bad faith, it was adjudged that the contractor had no cause of action on
after the execution of said certificate the remainder which shall be found due, excepting the contract against the United States.
therefrom such sum or sums as may be lawfully retained under any of the provisions of
this contract; Provided, That nothing herein contained shall be construed to waive the
37 | A D R C A S E S S E T 1

The old common law rule required a strict or literal performance of contracts. The modern rule a clause providing that in the event of a loss under the policy, unless the company shall deny all
sanctions a substantial performance of contractual relations. The law now looks to the spirit of the liability, as a condition precedent to the bringing of any suit by the insured upon the policy, the
contract and not to its letter. Even though a plaintiff is not entirely free from fault or omission, the latter should first submit the question of liability and indemnity to arbitration. Such a condition, the
courts will not turn him away if he has in good faith mad substantial performance. Of course the Supreme Court of the Philippines held in Chang vs. Royal Exchange Assurance Corporation of
terms of the contract may be such that the contract has agreed that the another shall have the London ([1907], 8 Phil., 399), is a valid one in law, and unless it be first complied with, no action
absolute and unreviewable right to reject the article or work if not satisfied with it; in such case the can be brought.
contractor shall abide by his word. But when the terms, or the nature of the contract, or the
circumstances are such as to make it doubtful, whether the contractor has made any such unwise What then are the remedies of the contractor? In the first place he has his administrative remedy,
agreement, the courts will ordinarily construe the contract as an "agreement to do the thing in which is to complete the work substantially according to the contract and ask for the approval of
such way as reasonably ought to satisfy the defendant." (Parlin & Orendorff Co. vs. City of the proper official. If such officer refuse or culpably neglect to perform a ministerial duty, such as
Greenville [1904], 127 Fed., 55; Swain vs. Seamens [1870], 9 Wall., 254.) Thus, it has been held making out the warrant, it is possible that mandamus will lie to coerce the officer. A stipulation
that the provision of a contract to perform work for the city requiring the contractor to obtain the requiring the approval of some one as a condition to a recovery by the contractor would not bar
certificate of the city engineer that the work has been done in accordance with the contract and the party of his remedies by action at law. The right to redress in the courts where substantial
the approval of such work by certain boards or committees, before he is entitled to payment compliance with the terms of a contract are set forth, and where the proof discloses the
therefor, does not deprive him of the right to recover for the work, if it has been done in substantial withholding of the certificate by an officer for insufficient reasons, should not be taken away by
conformity to the contract, because the city's officers arbitrarily or unreasonably refuse the inference or anything short of a district agreement to waive it. (Aetna Indemnity Co. vs. Waters
certificate and approval called for. (City of Elizabeth vs. Fitzgerald [1902], 200 U.S., 611.) [1909], 110 Md., 673.) As a condition precedent to action by the courts, fraud or bad faith on the
part of the responsible Government official, or arbitrary or unreasonable refusal of the certificate
Substantial performance and the unfounded refusal of the certificate of approval can be proved in or approval must be alleged and proved.
various ways. Thus, acceptance and occupancy of the building by the owner amounts to an
acknowledgment that the work has been performed substantially as required by the contract. To concentrate our facts and legal principles — we find the contractor supported by one expert
(Campbell and Go-Tauco vs. Behn, Meyer & co. [1904], 3 Phil., 590 affirmed on appeal to the insisting that the work and the materials actually conform to the specifications; and we have this
United States Supreme Court [1905], 200 U.S., 611.) Other circumstances, as partial payment, as resolutely denied by competent Government engineers. We find substantial performance of the
also show acquiescence on the part of purchaser. contract not proved to the satisfaction of the Government's technical adviser, but proved to the
satisfaction of the trial court. Ordinarily, we would not review the facts unless the findings of the
Appellee speaks of the provisions of the law and the portions of the contract in questions as trial court are plainly and manifestly contrary to the proof. But here it was incumbent on the trial
possibly constituting an arbitration agreement. We deem these provisions to be more correctly court to take about the same view of the findings of the Government's engineers as the appellate
labeled a condition precedent to the contractor's right to obtain payment; the condition is for the court would take of the findings of the trial court, or that any court would take of the findings of
satisfaction of the Government. Nevertheless, considered as species of abitration, it was a customs boards, assessors, and the like. In order to set aside the action of the Director of Public
convenient and proper method, duly agreed upon between the parties, to determine questions Works or his authorized representative, fraud or bad faith on the part of these engineers must be
that would necessarily arise in the performance of the contract, about which men might honestly established. Has this been proved? The judge in the course of his decision incidentally remarked:
differ. It would be highly improper, for courts out of untoward jealousy of their jurisdiction. The "It may as well be said here that there appears to have been a great deal of ill-feeling between
New York theory of refusal to uphold such agreements, because of the opinion that they violate plaintiff and the engineer in charge of this construction." Is this observation in connection with the
the spirit of the laws creating the courts, is hardly agreed to by more progressive jurisdictions. testimony of the plaintiff and of one engineer sufficient to demonstrate fraud or bad faith? We
(See U.S. Asphalt Refining Co. vs. Trinidad Lake Petroleum Co. [1915], 222 Fed., 1006.) Unless think not. In other words we believe that the contractor cannot maintain an action for the stipulated
the agreement is such as absolutely to close the doors of the courts against the parties, which price when the engineer has in good faith, in pursuance of the contract, withheld his certificate.
agreement would be void (Wahl and Wahl vs. Donaldson, Sims & Co. [1903], 2 Phil., 301), courts The decision of the responsible engineer cannot be subjected to the revisory power of the courts
will look with favor upon such amicable arrrangements and will only with great reluctance interfere without doing violence to the terms of the contract and the law.
to anticipate or nullify the action of the arbitrator. For instance, a policy of fire insurance, contained
38 | A D R C A S E S S E T 1

The Province of Tayabas, having accepted bridge No. 53.2, should of course pay the balance
due, or P2,840. It should not be permitted to deduct the cost of the test of the bridge, P900.12, for
this is a legal question for resolution by the courts, and the contract contains no such stipulation.
(See Ripley vs. U.S. [1912], 223 U.S., 695.) But the findings of the Government engineers on all
the other points covered by causes of action 2, 3, 4, 5 and 6 are deemed to be conclusive, fraud
or bad faith not having been proved. Thus, we have P2,840, plus P269.10, plus P214.80, plus P6,
plus P25, or P3,354.90 due plaintiff.

One point made by appellant is that the demurrer to the complaint was improperly overruled. An
elementary principle of pleading heretofore approved by this court in Government of Philippine
Islands vs. Inchausti & Co. ([1913], 24 Phil., 315) is brought to our notice, namely: "If the plaintiff's
right of action depends upon a condition precedent he must allege and prove the fulfillment of the
condition or a legal excuse for its non-fulfillment. And if he omits such allegation, his declaration,
complaint, or petition, will be bad on demurrer." Undoubtedly, the complaint should have alleged
either the performance of the condition precedent, approval by the Director of Public Works or the
District Engineer, or a good and sufficient excuse for not obtaining it. It is possible that if sitting in
first instance, we would so hold with defendant, but on appeal such a backward sweep would
avail nothing but delay. Moreover, the complaint contains the general averment that the plaintiff
fully and faithfully complied with all the terms and conditions of the said contract, while some
months subsequent to the filing of the complaint but previous to the trial, the defendant accepted
the bridge. A failure to allege a condition precedent or a legal reason for dispensing with it may be
cured by the issues tendered by the answer and the proof. (Donegan vs. Houston [1907], 5 Cal.
App., 626.)

To summarize, we are of opinion and so hold that the law makes the approval of the Governor-
General a prerequisite only to the purchase or conveyance of real property by a province; that the
provisions of the law and the form of the contract, usually followed in this jurisdiction, providing for
the certificate of approval by the Director of Public Works or his representative, are in the nature
of a condition precedent, which must be alleged and proved, and that this certificate is conclusive
in the absence of a showing of fraud or bad faith.

Judgment shall be modified so that the plaintiff shall recover from the defendant P3,354.90 with
legal interest thereon from July 14, 1914, until paid, without special finding as to costs in either
instance. So ordered.

You might also like