Start Target

Project Item
date date
No. Validate & Correct label information Application 29-Mar-19 23-Aug-19
1 - Discuss detail about requirement. 1-Apr-19 5-Apr-19
(Wk14)
2 - Study print label room work flow. 8-Apr-19 12-Apr-19
(Wk15)

3 - Design program work flow. 18-Apr-19 3-May-19


(Wk16-18)
4 - Design and create database. 6-May-19 24-May-19
(Wk19-20)

5 - Design and create user interface for each module. 27-May-19 14-Jun-19
(Wk33)

6 - Coding program. 24-Jun-19 26-Jul-19


(Wk34)
7 - Verify label data is correct with requester. 30-Jul-19 9-Aug-19
(Wk34)
8 - Debug program and trial run in production line. 13-Aug-19 23-Aug-19
(Wk35)

Total :=
Times % Target % Actual
Status
Develop by item by item

5 days 5% 5% Done

5 days 5% 5% Done

10 days 10% 10% Done

15 days 15% 15% Done

15 days 20% 20% Done

15 days 20% 15% ongoing

9 days 10% 0% ongoing

12 days 15% 0% ongoing

86 days 100% 70%