Professional Documents
Culture Documents
CIS210
Phase 1: Scheduling
1. Using the Work Breakdown Structure included here, address the major tasks in this
The major tasks are design, development, and testing. The design starts from the
specification of the system, produces design documents, and provides a detailed description of
how the system is built. Implementing a computer program based on a given design document
and taking into account the environment in which the system operates (for example, specific
hardware or software that can be used for development) (Jovanovic & Beric, 2018).The
implementation can be completed in phases, usually using the first system that can be verified
and tested before the final program is released for use. Testing compares the system used with
the construction document with the definitions of requirements, and presents a report of
acceptance, or generally, a list of errors and errors that need to be reviewed in the analysis,
construction, and implementation process for correction (testing often results in waterfall
2. Using the Work Breakdown Structure included here, identify all tasks that have
predecessor tasks.
tasks to be completed (in whole or in part). This is also called meaningful relationships. A logical
relationship can be a dependent relationship between project activities or between tasks and
major steps. Tasks can be linked or dependent on each other. The activities involved in this
dependence are preliminary activities or follow-up activities. The previous task comes first, then
the next task follows later. Previous tasks are tasks that must be completed or at least started
before another project can be started. Follow-up activities to follow the activities of the
predecessor. A precursor to a function that precedes another function, not in chronological order,
A pre-event can have many direct tracking functions. To determine the pre-employment,
you must specify which tasks should be completed before starting the activity you are currently
looking at (the reason could be technology, organization, or approach) (Jovanovic & Beric,
2018).. To determine who will replace you immediately, you need to specify which jobs can start
methodological). There are four possible types of meaningful relationships: end-to-end (task
must be completed before work begins "for him"), end-to-end (task must finish before end of
task "to him"), and then begin to finish (task must be completed before task "a" completed) and
from start to finish (task must begin before task "a" is completed) (Jovanovic & Beric, 2018).
3. Using the table at the end of this document, complete a projected schedule for your part
of the project.
The project manager has entered the estimated hours for each subtask. Be sure to identify the
predecessor tasks and roll up the hours from each set of tasks to their major task.
WORK BREAKDOWN STRUCTURE
PROJECTED SCHEDULE
System
30 Search Internet 2 8/12/2022 8/18/2022
31 Librarian Assistance 2 8/29/2022 9/8/2022
32 Print Receipt For Patron 2 9/9/2022 9/16/2022
33 Check In Functionality P
34 Scan Bar Code 2 9/17/2022 9/28/2022
35 Print Receipt For Patron 2 9/29/2022 10/9/2022
36 Overdue Fines Functionality P
37 2 10/10/2022 10/18/202
Jovanovic, P., & Beric, I. (2018). Analysis of the available project management