INITIAL VERTICAL STATIC LOAD TEST

Client ALPLA INDIA PVT. LTD. Diameter of Pile : 700 mm

Agency ROHAN BUILDERS INDIA PVT. LTD. Length of Pile : 11.2 mtr
Pile ID TEST PILE NO. 2
CIVIL CONSTRUCTION WORKS FOR PROPOSED
Name of Work
PRODUCTION FACILITY

Design Load 169.00 MT Date of Casting : ###

Test Load 422.50 MT Date of Testing : ###

FIELD OBSERVATION DATA

Actual DIAL-GAUGE READINGS Settelment


Duration
Sr. No. Clock Time Load, Average Reading
(min)
MT A B C D mm

1 12:15:00 0:00:00 0.00 0.30 0.32 0.27 0.18 0.27 0.000

12:15:00 0:30:00 84.50 0.40 1.43 0.45 0.23 0.63 0.36


2
12:45:00 0:00:00 84.50 0.45 1.55 0.52 0.25 0.69 0.425

12:45:00 0:30:00 169.00 1.90 2.71 1.34 1.30 1.81 1.55


3
13:15:00 0:00:00 169.00 1.93 2.74 1.39 1.31 1.84 1.575

13:15:00 0:30:00 253.50 2.09 3.11 2.01 2.22 2.36 2.090


4
13:45:00 0:00:00 253.50 2.25 3.26 2.22 2.40 2.53 2.265

13:45:00 0:30:00 338.00 3.90 4.40 3.11 3.54 3.74 3.470


5
14:15:00 0:00:00 338.00 3.92 4.42 3.13 3.56 3.76 3.490

6 14:15:00 1:00:00 422.50 4.48 5.08 4.22 4.10 4.47 4.203

24 Hours Reading
Actual DIAL-GAUGE READINGS Settelment
Duration
Sr. No. Clock Time Load, Average Reading
(min)
MT A B C D mm

1 12:15:00 0:00:00 0.00 0.30 0.32 0.27 0.18 0.27 0.000

14:15:00 1:00:00 4.48 5.08 4.22 4.10 4.47 4.203

15:15:00 1:00:00 4.70 5.30 4.38 4.29 4.67 4.400

16:15:00 1:00:00 4.77 5.44 4.49 4.35 4.76 4.495

17:15:00 1:00:00 4.80 5.52 4.50 4.40 4.81 4.538

18:15:00 1:00:00 4.88 5.75 4.59 4.52 4.94 4.668

19:15:00 1:00:00 4.96 5.82 4.71 4.55 5.01 4.743

20:15:00 1:00:00 5.05 5.88 4.78 4.61 5.08 4.813

21:15:00 1:00:00 5.09 5.61 4.83 4.69 5.06 4.788

22:15:00 1:00:00 5.16 5.70 4.89 4.75 5.13 4.858

23:15:00 1:00:00 5.23 5.76 4.96 4.80 5.19 4.920

0:15:00 1:00:00 5.30 5.81 5.02 4.86 5.25 4.980

1:15:00 1:00:00 5.35 5.88 5.06 4.89 5.30 5.028

1 2:15:00 1:00:00 422.50 5.41 5.94 5.11 4.93 5.35 5.080

3:15:00 1:00:00 5.46 5.99 5.16 4.98 5.40 5.130

4:15:00 1:00:00 5.51 6.02 5.21 4.99 5.43 5.165

5:15:00 1:00:00 5.56 6.08 5.27 5.03 5.49 5.218

6:15:00 1:00:00 5.61 6.13 5.32 5.08 5.54 5.268

7:15:00 1:00:00 5.66 6.19 5.38 5.14 5.59 5.325

8:15:00 1:00:00 5.70 6.25 5.43 5.19 5.64 5.375

9:15:00 1:00:00 5.75 6.31 5.48 5.25 5.70 5.430

10:15:00 1:00:00 5.81 6.38 5.54 5.31 5.76 5.493

11:15:00 1:00:00 5.86 6.42 5.60 5.34 5.81 5.538

12:15:00 1:00:00 5.87 6.43 5.61 5.35 5.82 5.548

13:15:00 1:00:00 5.87 6.43 5.61 5.35 5.82 5.548

14:15:00 1:00:00 5.87 6.43 5.61 5.35 5.82 5.548


Actual DIAL-GAUGE READINGS Settelment
Duration
Sr. No. Clock Time Load, Average Reading
(min)
MT A B C D mm

1 12:15:00 0:00:00 0.00 0.30 0.32 0.27 0.18 0.27 0.000

Rebound Readings

1 14:15:00 0:00:00 422.50 5.87 6.43 5.61 5.35 5.82 5.548

2 14:15:00 0:30:00 338.00 5.30 5.99 5.03 4.93 5.31 5.045

3 14:45:00 0:00:00 338.00 5.23 5.93 5.02 4.90 5.27 5.003

4 14:45:00 0:30:00 253.50 4.50 5.11 4.95 4.15 4.68 4.410

5 15:15:00 0:00:00 253.50 4.42 5.08 4.94 4.11 4.64 4.370

6 15:15:00 0:30:00 169.00 3.65 4.56 3.68 3.71 3.90 3.633

7 15:45:00 0:00:00 169.00 3.62 4.31 3.65 3.64 3.81 3.538

8 15:45:00 0:30:00 84.50 2.90 3.21 3.07 2.90 3.02 2.753

9 16:15:00 0:00:00 84.50 2.88 3.18 2.04 2.20 2.58 2.308

10 16:15:00 0:05:00 0.00 1.85 2.05 1.75 1.58 1.81 1.540

11 16:20:00 0:00:00 0.00 1.85 2.05 1.75 1.58 1.81 1.540


Actual DIAL-GAUGE READINGS Settelment
Duration
Sr. No. Clock Time Load, Average Reading
(min)
MT A B C D mm

1 12:15:00 0:00:00 0.00 0.30 0.32 0.27 0.18 0.27 0.000


8
INITIAL VERTICAL STATIC LOAD TEST
Client ALPLA INDIA PVT. LTD. Diameter of Pile : 700 mm

Agency ROHAN BUILDERS INDIA PVT. LTD. Length of Pile : 11.2 mtr
Pile ID TEST PILE NO. 2
CIVIL CONSTRUCTION WORKS FOR PROPOSED
Name of Work Date of Casting : ###
PRODUCTION FACILITY
Design Load 169.00 MT Date of Testing : ###
Test Load 422.50 MT

LOAD VS. SETTLEMENT GRAPH

Load, MT

0.00
0.36
Settlement, mm

1.54
1.55
2.09
2.31

3.47
3.54

4.20
4.37

5.00
5.55

Gross Settlement, mm 5.548


Net Settlement, mm 1.540
Rebound, mm 4.008 9