Professional Documents
Culture Documents
The completion cost with project completion in the year 2016-17 is Rs. 4910
crores including escalation but with central taxes only and it comes to Rs. 5146
Crores inclusive of state taxes.
Metro rail projects need very heavy investment. Loans have invariably to be
taken to fund a part of the capital cost of the projects. These projects yield low
financial internal rate of return though their economic internal rate of return is very
high. With reasonable fair level, servicing of these loans often pose problems. To
make the project financially viable, therefore, the fares need to be substantially
increased to socially un-acceptable levels. This results in the ridership coming
down significantly, as it is sensitive to increases in the fare level. Thus the very
objective of constructing the metro rail system to provide an affordable mode of
mass travel for public is defeated. It, therefore, becomes necessary to keep the
initial capital cost of a metro project as low as possible so that the fare level of the
metro system can be kept at reasonable level.
Experience of Delhi Metro project has shown that the taxes and duties constitute
about 16 – 18% of the project cost. Following are the taxes and duties, which
have to be borne by a metro project:
• Custom Duty on all imported rolling stock and other equipment needed for the
project.
• Excise Duty on all indigenously manufactured rolling stock and other
indigenously finished goods required for the project.
• Sales Tax on all purchases made for implementation of the project whether
directly by the project implementation authority or by the contractors executing
the project.
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxii
EXECUTIVE SUMMARY
In the case of Delhi Metro project, the Union Government has granted exemption
from payment of Custom Duty and Excise Duty while the Delhi Government has
agreed to give exemption from payment of Sales Tax and Sales Tax on works
contracts. Delhi Metro Rail Corporation is also pursuing with the Government for
exemption from tax on electricity being consumed by Delhi Metro for its operation
and maintenance.
The FIRR of the project is 3.04 % .The fare structure has been estimated based
on Delhi Metro fares duly escalating the same. The fare structure for the year
2016-17 is given below.
Table 0.10
Proposed
Distance in
fare for Kochi
kms.
Metro (Rs.)
0-2 10.00
2-4 13.00
4-6 15.00
6-9 19.00
9-12 21.00
12-15 23.00
15-18 24.00
18-21 27.00
21-24 28.00
24-27 30.00
Subsequently, for the purpose of assessing returns from the project, the fares
have been revised every second year with an escalation of 5% per annum.
After examining the various options for execution of Kochi Metro Project, It has
been suggested that the project should be get executed on the funding pattern of
Delhi Metro/Chennai Metro/Kolkata Metro or on deposit terms from DMRC. This
funding pattern has been recommended due to the fact that the BOT / PPP
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxiii
EXECUTIVE SUMMARY
pattern has so far nowhere been successful.The fund requirements from various
agencyies are given in the table below.
Table 0.11
Government of India Government of Kerala Total
Particulars
% Rs/Crore % Rs/Crore % Rs/Crore
Equity by GOI & GO
16% 785.50 16% 785.50 32% 1571.00
Kerala
SD for land for land
0% 0.00 14% 672.00 14% 672.00
cost by GO Kerala
Additional SD for
Central Taxes by GOI
8% 397.60 2% 99.40 10% 497.00
(80%) & GO Kerala
(20%)
JICA Loan @ 1.40%
PA/Market Borrowing 44% 2170.00 0% 0.00 44% 2170.00
@12% PA
Total 68% 3353.10 32% 1556.90 100% 4910.00
Add: State Taxes to
be borne by Govt. Of 0.00 236.00 236.00
Kerala
Grand Total 0 3353.10 0 1792.90 5146.00
The economic appraisal of Metro Corridor from Alwaye to Petta in Kochi has
been carried out within the broad framework of Social Cost –Benefit Analysis
Technique. It is based on the incremental costs and benefits and involves
comparison of project costs and benefits in economic terms under the “with” and
“without” project scenario. In the analysis, the cost and benefit streams arising
under the above project scenarios have been estimated in terms of market prices
and economic values have been computed by converting the former using
appropriate shadow prices. This has been done to iron out distortions due to
externalities and anomalies arising in real world pricing systems. The annual
streams of project costs and benefit have been compared to estimate the net
cost/ benefit and to calculate the economic viability of the project in terms of
EIRR.
The Economic Internal Rate of Return (EIRR) for the project has then been
arrived using Discounted Cash Flow technique to the net benefit stream at
economic prices.
The cost and benefit streams arising under the above situations have been
estimated in terms of market prices and economic values have been computed
by converting the former using appropriate shadow prices.
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxiv
EXECUTIVE SUMMARY
The Economic Internal Rate of Return (EIRR) in economic terms works out to
14.2% for Alwaye-Petta Corridor of Kochi Metro. This falls to 13% and 12.9%
respectively in case of increase in cost by 10% or decrease in traffic by 10%.
With increase in cost by 10% together with reduction in traffic by 10%, the EIRR
falls to 11.8%.
Kochi Metro Project will be the biggest urban Project undertaken in Kerala state.
The Project has to be implemented through densely populated area along highly
congested routes. In spite of all efforts taken to mitigate inconveniences and
hardships to the public, certain sensitive land acquisitions and certain disruptions
in the city are unavoidable. If the Project has to go through fast, a visible positive
support to the Project from the Government, City Corporation and GCDA should
be available. Each day’s delay in completing this Project will hike up the cost of
the Project by 15 lakhs. If the Project implementation is delayed, the city will
become more and more crowded and it will be practically impossible to carry out
construction activities later on. Therefore, a carefully drawn up strategy is
necessary for implementing this Project. As a first step, Kerala State Government
should inform the Central Government of its plan to go in for Kochi Metro Project
through a Concessionaire route and the support which it would need from the
latter.
• Institutional Arrangement
Once the SPV is formed, it has to start action for implementation of the project.
There are two options in this regard; either the SPV implements/operates the
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxv
EXECUTIVE SUMMARY
project itself with funds provided by the Government or it entrusts the operation of
the project to a Concessionaire after construction.
• Implementation Programme
A suggested project implementation schedule is given below. The proposed date
of commissioning of the Alwaye-Petta Corridor with suggested dates of important
milestones is given in Table 0.12.
Table 0.12
Implementation Schedule through SPV
Completion of these two ROBs will substantially relieve the present traffic
congestion on MG Road and Baneji Road as well as on Salim Rajan Road by
diversion of traffic towards Kaloor, Pallarivattom, Kakkanad, Thammanam, Vytilla,
etc.
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxvi
EXECUTIVE SUMMARY
Since construction of Kochi Metro structures on the median of Banerji Road and
MG Road will hamper the movement of road vehicles during the execution
period, the State Government and the GCDA authorities have been apprised the
necessity for early completion of the above two ROBs.
The proposal aims to relieve traffic congestion on the major city road which has
the highest volume of traffic by creating a flyover or a grade separator to take
through traffic. The flyover will be 4582m long and is to be designed to carry 2
lanes and hence its width is kept as 8.5m supported on a central pillars. Width of
existing road at this location is not adequate to accommodate the proposed
flyover along with Kochi Metro. Besides, with the construction of Kochi Metro
which will relieve substantial amount of traffic moving on the existing road, the
need for flyover may not be necessary. It is, therefore, suggested that the State
Government may give up the proposal of fly-over at this location.
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxvii
EXECUTIVE SUMMARY
construction of Kochi Metro. Kochi Metro will be designed to cater for the
underpass.
Although as per the Planning Commission’s guidelines issued in the 10th Plan
Document, Metros have been recommended for cities with more than 3 million
population, on account of the peculiar type of developments, waterways, low-
lying areas and heavy type of developments, a Metro System is justified for
Kochi. A Light Metro with carrying capacity of about 25,000 phpdt will be
adequate. The studies have brought out the urgent need for such a Metro System
to be commenced. It is, therefore, strongly recommended that a Light Metro
System from Alwaye to Petta (25.612 km), at an estimated completion cost of
Rs. 5146 crores be taken up for execution and made operational by the year
2016.
Since the SPV set up to get the project implemented will not have the required
expertise to check and monitor the work, it will be necessary to engage
Consultant having the experience of implementation and operation &
maintenance, from the very start who will do this job on behalf of the SPV.
UPDATED DETAILED PROJECT REPORT FOR KOCHI METRO AUG 2011 xxviii