Professional Documents
Culture Documents
Project Report and providing pre-construction services in respect of 2 laning of Final Detailed Project Report
Churachandpur -Tuivai road section (length- 162Km) on NH-102B in the State of Financial Analysis
Manipur. Package - IIIA
CHAPTER - 11
FINANCIAL ANALYSIS
11.1 General
The financial viability analysis for the proposed road forms the basis for assessing whether the
project is attractive enough for private sector participation. The analysis ascertains the viability
of the investment proposal on BOT format. A provision of maximum 40% government grant is
also considered if the project fails to achieve the desire result on BOT format. The financial
analysis covers aspects like financing through debt and equity, loan repayment, debt servicing,
taxation, depreciation, etc. The viability is evaluated in terms of the Project IRR [Financial
Internal Rate of Return (FIRR) on total investment] and the Equity IRR (FIRR on equity
investment), using discounted cash flow analysis, where both costs and revenues have been
indexed to take account of inflation.
Base Cost
The base cost for financial analysis comprises the cost to the BOT concessionaire and excludes
the cost to executing authorities. It includes civil construction cost and pre-operative expenses.
The base cost is at 2019 prices.
Other Cost
With a view to account for inflation, Financial Cost comprising processing fee, sponsor’s
contingency etc, Interest during construction, the base costs have been escalated at a rate of 25
The construction is phased over three years (2020-2022). Cost Phasing would be 30%, 40% &
30% over 3 years.
Under BOT arrangement the permissible maximum limit of viability gap funding is 40% of capital
investment.
Grant, Loan & Equity Requirement - during construction (Rs Crore)
Total
Equity 294
Government Grant 654
Loan / Debt 686
IDC 125
Total Project Cost 1759
125,
7% 294, 17%
Equity
IDC
The fees structure / toll rate has been taken from National Highways Fee (Determination of
Rates and Collection) Rules, 2008 and Amendment Rules, 2014 (dated 16 th January 2014) –
For structures more than 60m, 10 times of the length has been considered
For Bypasses, 1.5 times of the length considered
Toll Rate for 2007-08 base year for 4-Lane National Highway,
Toll Rate for 2-Lane National Highway is 60% of that of 4-Lane National Highway (refer sub rule
3 of Principal Rule 4)
Toll Rates are revised based on WPI as per Rule 5 of (Determination of Rates and Collection)
Rules, 2008 and modified subsequently.
The return on the proposed investment is not enough even after a VGF of 40% on the TPC as
equity support. Thus the project fails on the financial viability.
11.8 Conclusion
The project fails to generate the desired level of return, even with a grant of 40% on TPC. Thus
the project does not qualify to be implemented on the BOT - Toll mode. It’s recommended
that the project to be implemented through EPC mode.