- Required RMP - Registered and Licensed Master Plumber R.A. 1378 - Plumbing Code Jurisdiction DPWH DILG DENR DOH City Mayors Officers of the Building Official
SECTION 101 TO WHOM PERMITS MAY BE ISSUED
- RMP holding a valid, unexpired and unrevoked cetificate
SECTION 102 APPLICATION OF PERMIT
- Application RMP Building Owner a. Plumbing Work b.Land - Land registration and street address c. Use or Occupancy d.Datas - Plans Computation Diagrams Drawings Technical Specs e. Others f. Signed of Owner or Permittee g. Signed and sealed by RMP - Plan and specs 6 sets
SECTION 103 PERMIT ISSUANCE
- Approved by Administrative authority - Retention of Plans 1 sets Admin 2 Applicant or owner 1 Jobsite - Validity of permit - Expiration 1 year or 365 days - if plumbing work has not yet started from the day it was issued 4 months or 120 days - if it is not started from the day it was suspended - Fees for Renewal 50% of the original fees SECTION 104 APPLICATION FOR EXISTING PLUMBING SYSTEM - Addition, Alteration or Repairs - Changes ing Building occupancy - Maintenance All Plumbing system Materials Appurtenances Existing of New - Moved Buildings
SECTION 105 INSPECTIONS
- General Admistrative Plumbing personel Plumbing Inspector - Operation of Plumbing Equipment request of inspection shoud be atleast 72 hours or 3 days before - Re inspection Fee is required No payment, no reinspection