Professional Documents
Culture Documents
Obtaining the human resource “staff” needed to execute the project. This
process is typically done early in the Executing Process Group. Project
Managers often have to “negotiate” with Functional Managers.
Answer: Acquisition.
PMP/CAPM Flashcards
The act of listening completely with all senses so as to pick up all of the
information that is being communicated. Active listening entails
paraphrasing or reciting back what is heard to ensure accurate
understanding of what has been stated.
A component of work performed during the course of the project. For the
exam, PMI uses the word activity instead of task. Schedule Network
Diagrams (i.e. PDM) often include milestones, activities, and arrows to
show sequence/dependencies. NOTE: Activities have duration, whereas
milestones do not.
Answer: Activity.
PMP/CAPM Flashcards
The time in work periods between the start and finish of a schedule activity.
(e.g. 5 days)
A list of activities that shows the activity description, activity identifier, and a
sufficiently detailed description of the scope of work, so that the project
team members can understand what work needs to be performed. Along
with a milestone list, the activity list is a key input for developing a project
schedule network diagram. (Also see Precedence Diagramming Method
(PDM.))
The time in calendar units between the actual start date of the schedule
activity and either the data date of the project schedule if the schedule
activity is in progress or the actual finish date if the schedule activity is
complete.
The procedure that includes all the activities, interactions, roles and
responsibilities needed in executing the administrative closure (i.e. Close
Project or Phase) procedure for the project; includes product verification,
contract closeout, integrated activities to collect all project records, analysis
of project success or failure (i.e. performance), gather lessons learned,
project acceptance, archive project information for future use, and releasing
the resources.
Answer: Advertising.
PMP/CAPM Flashcards
Answer: Agent.
PMP/CAPM Flashcards
Many schedule activities can have alterative methods to accomplish the work
(i.e., different size or types of machines, make-or-buy decisions, etc.)
The process of breaking down something complex into something that can
be more easily understood. For the exam, analysis is a key Tool and
Technique for processes. Analysis can be performed directly with people
(e.g. qualitative risk analysis), or with computers (e.g. quantitative risk
analysis). Also see, decomposition and progressive elaboration.
Answer: Analysis.
PMP/CAPM Flashcards
A change request that has been processed through the integrated change
control process and approved by the Change Control Board (CCB). Once
approved, changes are communicated and implemented during Executing by
the appropriate stakeholders. For the exam, “following your change control
process,” is strongly recommended.
Leads and lags maybe applied and documented to accurately define logical
relationships between dependencies. Applying leads and lags relates to the
Precedence Diagramming Method (PDM), a project schedule network
diagramming method. Starting the successor before the predecessor is
done refers to lead time. Inserted waiting time refers to lag time. Typically
requires a computer and appropriate software (e.g. MS Project).
Answer: Arbitration.
PMP/CAPM Flashcards
Answer: Architecture.
PMP/CAPM Flashcards
Contract term and condition. When one party assigns its rights or obligations
under a contract to another party.
Answer: Assignment.
PMP/CAPM Flashcards
Factors that, for planning purposes, are considered to be true, real or certain
without proof or demonstration, and involve a degree of risk. Assumptions
are identified, validated and documented in Initiating and/or in early
Planning. Assumptions affect all aspects of project planning and are part of
the progressive elaboration of the project.
Answer: Assumptions.
PMP/CAPM Flashcards
An interview in which the participants are not engaged in the interview at the
same time. Asynchronous interviews can be conducted through email or van
be prerecorded by the interviewer and provided to the interviewee at a later
time.
Answer: Authority.
PMP/CAPM Flashcards
Answer: Backlog.
PMP/CAPM Flashcards
Answer: Baseline.
PMP/CAPM Flashcards
A clear and complete understanding of how the cost estimates were derived.
This information might include adaptation procedures, assumptions,
constraints, range estimates and how much confidence can be put in the
actual estimate.
Answer: Benchmarking.
PMP/CAPM Flashcards
Answer: Bonds.
PMP/CAPM Flashcards
Answer: Brainstorming.
PMP/CAPM Flashcards
Answer: Breach/Default.
PMP/CAPM Flashcards
The approved estimate for the project or any work breakdown structure
component or any schedule activity. See also estimate. Also see BAC
below.
Answer: Budget.
PMP/CAPM Flashcards
The sum of all the budgets established for the work to be performed on a
project or a work breakdown structure component or a schedule activity. The
total planned expense for the project, as approved by the Project Sponsor,
and included in the Project Management plan.
A visual chart depicting the number of backlog items remaining at any point
in time in a project. Burndown charts are used on projects using an adaptive
life cycle.
Answer: Burndown.
PMP/CAPM Flashcards
Shows the flow of business activities using UML notation. May use vertical
swim lanes (aka: UML activity diagram).
A description of how the business analysis process will be conducted for the
project or program. The business analysis approach is documented in the
business analysis plan.
A subplan of the project management plan that defines the business analysis
approach, including the tasks that will be performed, the deliverables that will
be produced, the roles required to carry our the process, and process
decisions regarding how requirement-related decisions will be made; how
requirement priorities will be set; how changes to requirements will be
proposed, approved, and managed; how requirements will be validated,
verified, monitored, and traced; and how business analysis communication
will be preformed.
The domain of business analysis that involves planning all of the business
analysis activities and reaching the necessary process decisions required for
running an effective business analysis process for a program or project.
Documented after analyzing the Business Need. Illustrates why the project a
viable venture. The business case is an input to the Develop Project Charter
process in the Initiating Process Group. Customer satisfaction is also
important, however, it is very important the business requirements are kept.
A risk that has a chance for “profit or loss.” (i.e. Threat or opportunity) For
example, going into business you have a chance to succeed, or go bankrupt.
A process for evaluating, designing, and implementing the rules that govern
the organization, its processes, and its data.
A business analysis model that details all of the business rules and their
related attributes.
A business analysis model that details all of the business rules and their
related attributes.
Answer: Buyer.
PMP/CAPM Flashcards
The smallest unit of time used in scheduling the project. These units are
generally in hours, days, or weeks, but can also be in quarter years, months,
shifts, or even in minutes. Contrast with duration (work periods).
Answer: Capability.
PMP/CAPM Flashcards
Changes that occur during the project are documented in this project
document—often in the Scope and/or Integration sections of the Project
Management Plan. Changes should be communicated to the project team
and other stakeholders as appropriate. Even changes that have been
rejected should be recorded in the change log.
Changes that occur during the project are documented in this project
document—often in the Scope and/or Integration sections of the Project
Management Plan. Changes should be communicated to the project team
and other stakeholders as appropriate. Even changes that have been
rejected should be recorded in the change log.
The plan that defines the process for managing change on the project.
Answer: Changes.
PMP/CAPM Flashcards
Items are listed together for ease to compare (e.g. list created during Risk
Identification for analysis and response at a later time), or to ensure the
actions associated with them are managed appropriately and not forgotten.
These are outputs of the Plan Quality Management process, but may also be
documented in WBS Dictionaries and/or Work Authorization Systems
(W.A.S.).
Answer: Checklist.
PMP/CAPM Flashcards
Sometimes referred to as “tally sheets.” Used for collecting useful data (for
potential quality problems). This information may then be modeled in Pareto
charts, histograms, bar charts, etc. Checksheets are one of the 7 basic
quality tools.
Answer: Checksheets.
PMP/CAPM Flashcards
Answer: Claim.
PMP/CAPM Flashcards
A question that calls for a response from a limited list of answer choices.
Types of closed-ended questions are forced choice, limited choice, and
confirmation.
The process of finalizing all activities across all of the project process groups
to formally close the project or phase. (Sometimes referred to as
“Administrative Closure,” it incorporates the Close Procurements process.)
Any numbering system used to uniquely identify each component of the work
breakdown structure (WBS). For the exam, do not confuse
The process that documents and defines the stakeholders’ needs, required
to meet the project objectives. For the exam, having all the appropriate
stakeholders is key to collecting/eliciting requirements. NOTE: “Elicit” refers
to “drawing out” the requirements, not just “collecting” them.
Answer: Colocation.
PMP/CAPM Flashcards
How ideas or information is sent and received between two parties, defined
as the sender and the receiver. This model has included the following
components: Encode, Message, Medium, Noise and Decode. To translate
thoughts or ideas into a language that is understood by others is called
“Encode.” The “Message” is the output of encoding. The method used to
convey the message is called the “Medium.” Anything that interferes with the
transmission and understanding of the message is often referred to as
“communication blockers/noise.” To translate the message back into
meaningful thoughts or ideas is to “Decode.” For the exam, ensure you
know the components of this model.
Answer: Confidentiality.
PMP/CAPM Flashcards
Delivering results that fall within the limits that define acceptable variation for
a quality requirement. Going beyond conformance, could relate to “gold
plating.”
Answer: Conformance.
PMP/CAPM Flashcards
Anything the limits the project team’s options. This refers to the state,
quality, or sense of being restricted to a given course of action or inaction--an
applicable restriction or limitation, either internal or external to the project,
which will affect the performance of the project or a process. For example, a
schedule constraint is any limitation or restraint placed on the project
schedule that affects when a schedule activity can be scheduled and is
usually in the form of fixed imposed dates. A cost constraint is any limitation
or restraint placed on the project budget such as funds available over time.
A project resource constraint is any limitation or restraint placed on resource
usage, such as what resource skills or disciplines are available and the
amount of a given resource available during a specified time frame. Contrast
with risk.
Answer: Constraint.
PMP/CAPM Flashcards
The amount of funds, budget, or time needed above the estimate to reduce
the risk of overruns of project objectives to a level acceptable to the
organization. Also called a “reserves” or a “contingency allowance.”
Contrast with Management (contingency) reserve.
Answer: Contract.
PMP/CAPM Flashcards
Managing the contract and the relationship between the buyer and seller.
For the exam, Project Managers should be very involved in the selection of
the vendor and the type of contract, however, Contract Administrators can be
very helpful for day-to-day contract administration. Also see Control
Procurements.
Used to perform the contract closure process. Includes: the contract, product
description, requested/approved changes, deliverables, acceptance criteria,
invoices, payment records, supporting schedules, seller’s performance
reports, etc. For the exam, contracts should be in writing to be legally
binding.
The process of monitoring the status of the project to update the project
budget and managing changes to the cost baseline. Most of the EVM and
forecasting formulas are included in the Control Costs process. Formulas:
EV – AC = CV & AC / CV = CPI.
The process of monitoring the status of the project to update project progress
and managing changes to the schedule baseline. Formulas: EV – PV = SV
& EV / PV = SPI.
The process of monitoring the status of the project and the product scope
and managing changes to the scope baseline.
The approved time-phased plan plus or minus approved project scope, cost,
schedule, and technical changes. Baselines can be established for project,
WBS component, a work package, or a schedule activity.
Describes how the project costs will be planned, structured, and controlled
over the project lifecycle.
A cost reimbursable contract type where the buyer reimburses the seller for
the seller’s costs as agreed to in the contract plus an agreed upon fixed fee.
This is a cost reimbursable type contract where the seller earns additional
profits by meeting a pre-defined performance target in addition to any agreed
upon costs according to the contract. Award fees are a fixed amount,
whereas an incentive fee is set up to pay a variable amount, usually based
on early completion. If agreed upon, award and incentive monies must be
incorporated into the final, definitive budget. Earned Value Management
may also be used to measure vendor performance. For the exam, ensure
that award incentive fees have been added into your definitive budget.
A type of contract involving reimbursement by the buyer to the seller for the
seller’s actual costs, plus a fee typically representing seller’s profit. Costs are
usually classified as direct costs or indirect costs. Sometimes there are
additional fees, incentive clauses, or bonuses involved depending on the
type of cost reimbursable contract. These contract types typically provide
more risk to the buyer, and are more common when the SOW is vague. For
the exam, these contracts are considered more risky than fixed price
contracts.
Answer: Crashing.
PMP/CAPM Flashcards
This scope management process takes the project deliverables and breaks
them down to smaller components, which are more easily managed. This
process occurs after developing the Project Scope Statement, and produces
the “Scope Baseline.”
Answer: Criteria.
PMP/CAPM Flashcards
Create, Read, Update, Delete matrix used in data analysis to make sure that
every data element is supported by processes that perform the activities.
A planning technique (during the Create WBS, and Define Activities planning
processes) that subdivides the project scope and project deliverables into
smaller, more manageable components, until the project work associated
with accomplishing the project scope and providing the deliverables is
defined in sufficient detail to support executing, monitoring and controlling
the work. For the exam, this may also be called deconstruction, and relate to
progressive elaboration.
Answer: Decomposition.
PMP/CAPM Flashcards
A model that is used to divide and subdivide a high-level concept into lower-
level concepts, for example, dividing the project scope and project
deliverables into smaller, more manageable parts for the purpose of analysis.
Also known as decomposition diagram.
Answer: Defect.
PMP/CAPM Flashcards
Answer: Deliverables.
PMP/CAPM Flashcards
Answer: Dependency.
PMP/CAPM Flashcards
The exam may reference four types of dependencies defining the sequence
among activities: Mandatory, or inherent in the nature of the work being
done and unchangeable (hard logic), Discretionary, based upon knowledge
of best practices in some application area and more flexible (preferential or
soft logic), Internal, often involving dependency relationships within the
organization (prototypes), and External, involving a relationship between
project activities and non-project activities (usually unwelcome).
Quality tool; a statistical method that helps identify which factors might
influence specific variables. Usually applies to the product, by looking for the
most desirable characteristics. Typically uses a computer to compare project
management tradeoffs (e.g. senior engineers cost more, but may be able to
get the job done faster).
Rates such as staff cost per hours, material cost per foot, etc. May be
gathered from commercial databases, quotes or estimated by the team. Part
of the Estimate Costs process.
A process performed during the Executing Process Group, for improving the
competencies (i.e. training), and interaction of team members to enhance
project performance. “Team training” is considered a “direct cost” included in
the project’s budget. For the exam, this could relate to training the team to
incorporate six sigma, ISO, Agile, etc.
The process of executing the work defined in the project management plan
to achieve the project’s requirements defined in the Project Management
Plan. This may also include approved change requests, or other
considerations found during the Monitoring and Controlling Process Group.
Procedures and tools used to store, track, version, and archive documents.
The total number of work periods (not including holidays or other non-
working periods) required to complete a scheduled activity or work
breakdown structure component. Usually expressed as workdays or
workweeks. Sometimes incorrectly equated with elapsed time. Contrast
with effort and calendar dates.
Answer: Duration.
PMP/CAPM Flashcards
In the critical path method (CPM), the earliest possible point in time on which
the uncompleted portions of a schedule activity (or the project) can finish,
based on the schedule network logic, the data date, and any schedule
constraints. Early finish dates can change as the project progresses and as
changes are made to the Project Management Plan.
In the critical path method (CPM), the earliest possible point in time on which
the uncompleted portions of a schedule activity (or the project) can start,
based on the schedule network logic, the data date, and any schedule
constraints. Early start dates can change as the project progresses and as
changes are made to the Project Management Plan.
A business analysis model that shows the systems involved in a project and
how they interrelate with each other.
Answer: Effort.
PMP/CAPM Flashcards
Answer: Enhance.
PMP/CAPM Flashcards
A business analysis model that shows the business data objects involved in
a project and the relationships between those objects, including he
cardinality of those relationships.
Answer: Estimate.
PMP/CAPM Flashcards
The process of estimating the number of work periods that will be needed to
complete individual scheduled activities. NOTE: Duration is determined
before determining calendar dates.
Used in cost forecasting. The expected cost needed to complete all the
remaining work for a schedule activity, work breakdown structure component,
or the project. See also earned value management, and estimate at
completion (EAC).
The tendency to view the traits, ways, ideas, and values observed in other
cultures as invariably inferior and less natural or logical than those of one's
own group. For the exam, this may relate to Organizational Process Maturity
Model (OPM3), which ranks organizations based on their process maturity
capabilities.
Answer: Ethnocentrism.
PMP/CAPM Flashcards
Answer: Execute/Executing.
PMP/CAPM Flashcards
Answer: Event.
PMP/CAPM Flashcards
Answer: Exploit.
PMP/CAPM Flashcards
A statistical technique that calculates the average outcome when the future
includes scenarios that may or may not happen. A common use of this
technique is within decision tree analysis. Modeling and simulation are
recommended for cost and schedule risk analysis because it is more
powerful and less subject to misapplication that expected monetary value
analysis. The two, uncertain outcomes should add to 100% to perform the
calculations. For the exam, choose the potential decision that has the
highest EMV.
Answer: Fee.
PMP/CAPM Flashcards
“The product of the project.” Formal acceptance and handover of the final
product, service or result, to the customer including receipt of a formal
statement that the terms of the contract have been met, that the project was
authorized to produce.
A type of fixed price contract where the buyer pays the seller a set amount
(e.g. “lump sum.” as defined by the contract), regardless of the seller’s costs.
A type of contract where the buyer pays the seller a set amount (as defined
by the contract), and the seller can earn an additional amount if the seller
meets defined performance criteria. For the exam, award and incentive fees
“synchronize the objectives of the buyer and the seller,” and must be
included in the Definitive Budget.
Also called slack. For the exam, three types cited are: Free float: Amount
of time an activity can be delayed without affecting the early start of the
following activity (Free float = Late Finish – Early Finish). Total float:
Amount of time and activity can be delayed without delaying a milestone, or
the project’s completion date. Project float: Amount of time a project can
be delayed without delaying the externally imposed completion date or
subsequent projects. NOTE: Activities with float/slack are NOT on the critical
path.
Answer: Float.
PMP/CAPM Flashcards
Answer: Flowcharts.
PMP/CAPM Flashcards
Analyzing the expected pressures for and against a change or new idea.
Answer: Forecasts.
PMP/CAPM Flashcards
Estimate how much the project will cost at completion (EAC), how much will
it cost to complete (ETC), or using the “To Complete Performance Index”
(TCPI).
Answer: Forecasting.
PMP/CAPM Flashcards
The calculation of the early start and early finish dates for the uncompleted
portions of all network activities. (Early start + Duration = Early Finish.) A
forward pass will yield the duration of the project. A forward pass is done
prior to doing a Backward Pass.
Tool to analyze goals, problems, objectives, success metrics and high level
features.(business objective model)
Answer: Histogram.
PMP/CAPM Flashcards
The process of determining which risks may affect the project and
documenting their characteristics. Risks have probability impact, and
urgency (timing) considerations. Risks can be identified at any time, but
comprehensive risk identification.
Benefits the seller receives for aligning with the buyer’s objectives of time,
cost, quality, risk and performance (referred to as synchronization). Award
and incentive fees “synchronize the objectives” of the buyer and the seller.
Answer: Incentives.
PMP/CAPM Flashcards
Contract term and condition. Used to protect against or keep free from, loss
or damage. Should specify which party is liable for personal injury, damage
and accidents.
Relates to when the seller is not an employee of the buyer’s organization (as
stated in the contract).
Any item required by a process in order for that process to progress. These
could be outputs from previous processes. For the exam, Organizational
Process Assets, and Enterprise Environmental Factors are common.
Answer: Input.
PMP/CAPM Flashcards
Answer: Inspection.
PMP/CAPM Flashcards
Often called “soft skills.” Empathize, anticipate the needs of, acknowledge
the concerns of, communicate, facilitate, inspire, resolve conflict, negotiate,
etc. For the exam, this may also relate to “leadership skills.”
Answer: Interviews.
PMP/CAPM Flashcards
Sometimes this term may relate to “Request for Proposal” (RFP). However,
in some environments it may have a more narrow or slightly different
meaning. For the exam, and IFB typically requires a comprehensive SOW.
Billing, charges or fees for an itemized list of goods sold or services rendered
by the seller to the buyer. This is typically more labor intensive for “cost plus”
types of contracts. (NOTE: Fixed price contracts generally require less
invoicing than cost reimbursable contracts.)
Answer: Invoicing.
PMP/CAPM Flashcards
Answer: Issue.
PMP/CAPM Flashcards
Suppliers deliver goods only when they are needed. Relates to LEAN. For
the exam, JIT “forces” quality because extra materials are not readily
available.
Answer: Kaizen.
PMP/CAPM Flashcards
A method for managing knowledge work with an emphasis (JIT), and LEAN.
Work is pulled from a que. May also relate to visual process management.
Answer: Kanban.
PMP/CAPM Flashcards
“Kickoff Meetings” should be held after the Project Management Plan has
been approved. (“Project Kickoff Meetings” may be held after the Project
Charter has been approved.) The appropriate stakeholders should be
invited to the meetings. Kickoff meetings are beneficial for project team
communication, helping ensure a common understanding, team-building,
and clarification of roles and responsibilities prior to execution of the project.
For the exam, the kickoff meeting signals the beginning of Executing, and
transition from the project management staff, to the project team.
In the critical path method (CPM), the latest possible point in time that a
schedule activity may be completed based upon the schedule network logic,
the project completion date, and any constraints assigned to the schedule
activities without violating a schedule constraint or delaying the project
completion date. The late finish dates are determined during the backward
pass calculation of the project schedule network.
In the critical path method (CPM), the latest possible point in time that a
schedule activity may begin based upon the schedule network logic, the
project completion date, and any constraints assigned to the schedule
activities without violating a schedule constraint or delaying the project
completion date. The late start dates are determined during the backward
pass calculation of the project schedule network.
Answer: Lead.
PMP/CAPM Flashcards
Answer: LEAN.
PMP/CAPM Flashcards
The learning gained from the process of performing the project. Lessons
learned may be identified at any point, but should be performed at key phase
gates/stage exits/milestones. Also considered a project record, to be
included as an “organizational process asset” in the project management
information system (PMIS). For the exam, lessons learned may refer to a
meeting, or the information learned and/or documented.
What went well? What could been done differently? The causes of the
variances, the reasoning behind the corrective action chosen, and other
types of lessons learned should be documented so that they become part of
the historical database for this project and other projects of the performing
organization. The database is also the basis of knowledge management.
For the exam, this relates to organizational process assets and a project
management information system (PMIS).
A procurement document stating that the buyer intends to hire the seller. It is
not considered a contract, and is usually not legally binding.
Used to measure work performance (e.g. EVM) over the passage of time, not
by the delivery of end products.
Answer: Log.
PMP/CAPM Flashcards
Relates to contract terms and conditions. A breach so large that it may not
be possible to complete the work under the contract.
Answer: Milestone.
PMP/CAPM Flashcards
This is a list of significant events in the project and indicates whether the
milestone is optional or mandatory- possibly because it is a contract
stipulation. A list of milestones and activities are required to develop a
project schedule network diagram. Activities are performed to achieve
milestones.
Answer: Mitigate.
PMP/CAPM Flashcards
Techniques used to iterate the project cost, project schedule or project risk
using input values selected at random from probability distributions (i.e.
Monte Carlo Analysis). For the exam, this typically requires a computer.
Monitoring residual risks, identifying new risks, executing risk reduction plans
and evaluating their effectiveness throughout the project life cycle.
Performed during Monitoring and Controlling.
Answer: MoSCoW.
PMP/CAPM Flashcards
A schedule activity that has low total float. (NOTE: Critical path activities
have 0 or less float/slack.) The concept of near critical is equally applicable
to a schedule activity or schedule network path. The limit below which total
float/slack is considered near critical is subject to expert judgment and varies
from project to project. For example, if the critical path shows that the project
will take 300 days, paths that have 290 days could be considered the “near
critical path.”
Answer: Negotiation.
PMP/CAPM Flashcards
Answer: Networking.
PMP/CAPM Flashcards
Answer: Node.
PMP/CAPM Flashcards
Answer: Notice.
PMP/CAPM Flashcards
Answer: Objective.
PMP/CAPM Flashcards
A direct way to view how individuals work in their environment and how they
carry out tasks or perform processes. Sometimes called “job shadowing.”
Answer: Observations.
PMP/CAPM Flashcards
Uses only one (e.g. most likely) estimate. May increases likelihood of
padding, inaccuracy, and uncertainty. Contrast with three-point estimating.
Answer: Opportunity.
PMP/CAPM Flashcards
Answer: Output.
PMP/CAPM Flashcards
“Work expands so as to fill the time (and perhaps, money) available for its
completion.” May be a consideration for stakeholders padding their
estimates. For the exam, Parkinson’s Law is something to avoid, perhaps by
adopting three-point estimates to reduce “padding/buffering.”
The merging or joining of parallel schedule network paths into the same
node in a project schedule network diagram. Path convergence is
characterized by a schedule activity with more than one predecessor activity.
For the exam, this may also relate to “sensitive” (e.g. quantitative risk
analysis) areas within the project schedule network diagram.
Answer: Payments.
PMP/CAPM Flashcards
Accounts payable system to pay the seller. (Review, approve, and pay.) For
the exam, you may see situations where you have a contract administrator
working on your project team to help with seller payments. NOTE: Cost-
reimbursable contracts typically require more administration for payment
systems.
The process of prioritizing risks (subjectively. e.g. on a scale for 1-10) for
further analysis or action by assessing and combining their probability of
occurrence and impact on project objectives. For the exam, this may also
refer to a P-I matrix to illustrate threats and opportunities. Contrast with
quantitative risk analysis.
For the exam, relate this to Total Quality Management, quality improvement,
Edwards Deming, iterative/incremental/adaptive lifecycles, Agile, and
possibly rolling wave/progressive elaboration.
Creating a scope management plan that documents how the project scope
will be defined, validates, and controlled. For the exam, understanding
scope is key. Produces a scope management plan/scope baseline.
Meetings conducted for the purpose of evaluating risks to the project and
developing a Risk Management Plan. Teams should develop their own
ground rules. Virtual team meetings are typically more difficult than face-to-
face meetings (e.g. communication-related risks/issues).
WBS component below the control account with known work content but
without detailed schedule activities. May be documented in the Project
Charter. For the exam, this may also be related to funding limit reconciliation
when determining the budget. Also see Control Account.
Those processes performed to define and mature the project scope, develop
the project management plan, and identify and schedule the project
activities* that occur within the project. NOTE: For the exam, the subsidiary
plans (management plans) are inputs to the Project Management Plan.
Answer: Portfolio.
PMP/CAPM Flashcards
The schedule activity that determines when the logical successor activity can
begin or end. (Relates to the Sequence Activities process in Planning.)
Scope, schedule, and cost are determined early in the lifecycle. Typically
used for more formal, longer, and more comprehensive projects. Considered
to better minimize risk. Contrast with iterative and incremental lifecycles.
List of those risks that pose the greatest threat to the project. May use a
computer and software tool such as “Crystal Ball.” Risks are prioritized
based on their Probability and Impact. Also see Perform Quantitative Risk
Analysis.
Forecasting potential project schedule and cost results, listing the possible
completion dates or project duration and costs, with confidence levels. For
the exam, this topic may relate to a “Constrained Optimization Method”
(computer) project selection technique that may be used during Initiating.
Probability of achieving the project objectives under the current plan and with
current knowledge. This may be determined by Monte Carlo analysis during
quantitative risk analysis.
Used to illustrate goals and the steps required to achieve the goals.
Each procurement has it’s own statement of work which is developed from
the project scope baseline. The scope for that contract is given in enough
detail to let prospective sellers understand whether they can provide the
goods and/or services to comply with the contract’s requirements. For the
exam, the more comprehensive the SOW, the more likely the buyer will be
able to negotiate a fixed price contract.
Answer: Product.
PMP/CAPM Flashcards
The features and functions that define a product, service or result. For the
exam, it is sometimes referred to as the “Product of the Project.”
Answer: Program.
PMP/CAPM Flashcards
Project progress report includes current schedule status (such as start and
finish dates) and the remaining durations for unfinished schedule activities
(i.e. Bar or Gantt charts). Reports could be electronic or paper-based, or
even verbal.
Answer: Project.
PMP/CAPM Flashcards
A calendar with established activity dates that shows working and idle dates.
Updated to reflect any approved changes. Contrast with duration.
These documents are used to assist the Project Manager, but are often not
included in the Project Management Plan.
Total and periodic (i.e. annual or quarterly) project funding requirements are
derived from the cost baseline. For the exam, this may reflect the result of
the funding limit reconciliation. Adjusted for cost overruns or early progress.
This is an output of the Determine Budget process in the Planning Process
Group.
Aligning project objectives with the strategy of the organizations, the Project
Sponsor, and the Project Manager. This may include enlisting the
appropriate stakeholders for appropriate project-related activities.
Includes the processes that organize, manage sand lead the project team.
For the exam, this often relates to “staff.” Includes the Plan Resources,
Acquire Resources, Develop Team, and Manage Team processes.
An inclusive term that describes the sum of knowledge within the profession
of project management. As with other professions such as law, medicine,
and accounting, the body of knowledge rests with the practitioners and
academics that apply and advance it. The complete project management
body of knowledge includes proven, traditional practices that are widely
applied and innovative practices that are emerging in the profession. PMI
Standard is constantly evolving, but does not provide specific information on
how to execute projects.
A chart that shows project team members, and how they relate to each other
in a hierarchical relationship. These charts may be illustrated within the
Human Resources (Staffing) Management Plan.
The planned calendar dates for performing schedule activities and the
planned dates for meeting schedule milestones. Also relates to the schedule
baseline. Often developed and tracked using project management software.
All of the work and only the work required to deliver a product, service or
result with specified, agreed upon features and functions. Relates more to
the processes to produce the product.
Includes the processes required to ensure that all the work required, and
only the work required to complete the project successfully. Includes the
Plan Scope Management, Collect Requirements, Define Scope, Create
WBS, Control Scope, and Validate Scope processes.
The person or group that provides the financial resources, in cash or in kind,
for the project. Approves the Project Charter, the Project Management Plan,
Lessons Learned, and perhaps key product approvals. Helps determine the
risk tolerance levels.
The appropriate people are assigned to work on the project. Also see pre-
assignment.
A set of individuals who support the project manager in performing the work
of the project to achieve its objectives.
Any organizational structure in which the Project Manager has the highest
authority to assign priorities, apply resources, and direct the work of
individuals assigned to the project. However, internal stakeholders do not
have a “home” when the project is complete, and there is no allocation of
resources between projects. This may also relate to “project-based
organizations (PBOs),” whose major focus is on project-based activities.
Seller prepared documents that describe the seller’s ability and willingness
to provide the requested product or service. Considered formal and legally
binding. Maybe supplemented with an oral presentation.
Answer: Proposals.
PMP/CAPM Flashcards
Answer: Prototypes.
PMP/CAPM Flashcards
A risk that only has the chance for loss. For example, weather-related
threats. Purchasing insurance may help transfer some pure risks.
Answer: Quality.
PMP/CAPM Flashcards
One of the seven, basic quality tools. Used to gather information that can be
graphically illustrated in charts (e.g. Histograms, Pareto charts).
A rank used to distinguish items that have the same functional use, but do
not share the same requirements for quality. (e.g. Something may never
break, but may not have the grade needed for a specific application.) A
product can be a high quality l___________ (no major defects), but a low
quality g_________ (few features).
Describes how the team will implement its Quality Policy (ISO 9000, “Project
Quality System”). The organizational structure, responsibilities, procedures,
processes and resources needed to implement quality management.
Provides input to the overall project plan, and must address quality control,
quality assurance, and quality improvement for the project. (Could be formal
or informal, highly detailed or broadly framed, based on the requirements of
the project.)
Answer: RACI.
PMP/CAPM Flashcards
Used to promote and reinforce desired behavior. These should not only
focus on the team, but individuals. For the exam, this may relate to the
motivation theories.
Answer: Requirement.
PMP/CAPM Flashcards
. A table that links requirements to their origin and traces them through the
project lifecycle from beginning to end. Some of the items that may be
traced through the project are business need, opportunities, project goals,
and various project and product requirements. If a Business Analyst is
assigned to your team, they may help develop and maintain a requirements
traceability matrix.
Answer: Reserve.
PMP/CAPM Flashcards
Issue log will document stakeholder requirements, issues and concerns that
have been identified and resolved (i.e. customers agree to a follow-on
contract).
Answer: Resource.
PMP/CAPM Flashcards
Answer: Result.
PMP/CAPM Flashcards
Answer: Retainage.
PMP/CAPM Flashcards
Answer: Rework.
PMP/CAPM Flashcards
Answer: Risk.
PMP/CAPM Flashcards
Grouping risks by sources and common root causes can lead to effective risk
response (i.e. using a Risk Breakdown Structure as well as technical,
environmental and organizational sources of risk.) May include prioritization,
and be graphically illustrated in a risk breakdown structure (RBS).
Data associated with a risk needs accurate and unbiased examination of the
extent of understanding of the risk, data available about the risk, quality of
data, reliability, and integrity of the data.
An estimate of the probability that a given risk event will occur (i.e. 1% to
99%). Risks are prioritized based on probability and impact, and are
documented in the risk register.
An estimate of the gain or loss (impact) that will be incurred if the risk event
does occur (expressed as consequences, impact or amount at stake).
Commonly used with decision tree analysis. Also see Expected Monetary
Value (EMV).
The process of determining which risks might affect the project and
documenting their characteristics.
The process of deciding how to approach and plan for anything that could
impact the project positively or negatively by planning for risk management
activities, and strategies for a project.
Allocates the risk between the parties in a contract should goods or services
be lost or destroyed during the performance of a contract. On the exam, this
may be referred to as a “pure risk.”
Answer: Reassessment.
PMP/CAPM Flashcards
Project roles: who does what? Who decides what? Who has what
capabilities? These can be defined as hierarchical charts, matrix type charts
or text-based documents.
Used to show trends and variations over time. Trend analysis is used to
monitor technical performance (i.e., how many errors or defects? How many
remaining uncorrected defects? ) Also used in cost and schedule
performance (i.e. how many activities per period were completed with
significant variances?). Also see scatter diagrams, which is more commonly
cited on the exam.
Answer: S-Curve.
PMP/CAPM Flashcards
One of the seven basic quality tools. Shows the pattern of relationship
between two variables (i.e. X / Y. Regression analysis).
Shortening the project schedule duration without reducing the project scope.
Two methods are commonly employed: Crashing (adding more resources),
fast-tracking (doing tasks in parallel) learning curve (“practice makes
perfect”), and cutting scope/quality (based on priorities), are all forms of
schedule compression. Sometimes this is called duration compression.
Used to identify Early Start and Late Start dates as well as Early Finish and
Late Finish dates for the uncompleted portions of project schedule activities.
Also see project schedule network diagrams, and precedence diagramming
method (PDM).
The point in time that work was scheduled to start on a schedule activity.
This date is normally within the range of dates delimited by the early start
date and the late start date. It may reflect resource leveling of scarce
resources.
The point in time that work was scheduled to finish on a schedule activity.
This date is normally within the range of dates delimited by the early finish
date and the late finish date. It may reflect resource leveling of scarce
resources.
Answer: Scope.
PMP/CAPM Flashcards
The approved project scope statement and its associated detailed WBS and
the WBS dictionary. It provides the basis for monitoring and controlling
performance. Also relates to the information documented within the Scope
Management Plan.
The process of controlling changes to the project scope. This formal process
must be integrated with other control processes (i.e. schedule, cost, quality,
etc.). Changes, if applicable, must comply with contractual obligations.
Uncontrolled changes to scope are often referred to as scope creep.
Answer: Scrum.
PMP/CAPM Flashcards
A risk that arises as a direct result of implementing a risk response. Also see
residual risk.
Answer: Seller.
PMP/CAPM Flashcards
Quantitative risk analysis technique to determine which risks have the most
potential impact on the project. Examines the extent to which the uncertainty
of each project element affects the objective being examined when all other
uncertainties are held at their baseline values.
Answer: Simulation.
PMP/CAPM Flashcards
A defined set to techniques and tools (i.e. steps) for quality process
improvement. (e.g. reduce schedule, reduce cost, increase customer
satisfaction.) A quality standard. May also relate to 99% defect free.
Answer: Slack.
PMP/CAPM Flashcards
Goals that are well-written to meet the quality criteria of being specific,
measurable, achievable, relevant, and time-bounded.
The project selection criteria for choosing from among potential contractors
or vendors. These may include variables like need, cost, technical
capabilities, risk, lifecycle costs, production capabilities, timelines, past
performance, proprietary rights, etc. For the exam, strive for “fair and
reasonable,” and “objective” source selection criteria.
The area, on either side of the centerline (i.e. mean), of data plotted on a
quality control chart that meets the customer’s requirements for a product or
service. This area may be greater than, or less than the area defined by the
control limits. Illustrated with a solid line, higher and lower than the control
limits. Also see control limits.
A person or group who provides resources and support for the project,
program, or portfolio and is accountable for enabling success.
Answer: Sponsor.
PMP/CAPM Flashcards
Describes when and how the human resources needs of a project will be
met. See Human Resource Management Plan.
Answer: Stakeholder.
PMP/CAPM Flashcards
Answer: Standard.
PMP/CAPM Flashcards
Strategies that address negative risks, or threats that may negatively affect
project objectives. The four strategies to respond to threats are; Avoid,
Transfer, Mitigate, and Accept.
Answer: Subnetwork.
PMP/CAPM Flashcards
Answer: Subproject.
PMP/CAPM Flashcards
Answer: System.
PMP/CAPM Flashcards
A term for work whose meaning and placement within a structured plan for
project work varies by the application area, industry, and brand of project
management software. For the exam, “activity” is the term most commonly
used.
Answer: Task.
PMP/CAPM Flashcards
Answer: Templates.
PMP/CAPM Flashcards
Stopping the work (or contract) before its planned completion. Typically, this
exercised by the buyer, but it should not take place until all affected parties
have been notified.
Answer: Termination.
PMP/CAPM Flashcards
Contract term and condition. Often documented in the contract in case the
buyer must terminate the seller based on certain conditions. For the exam,
always strive to NOT terminate the seller (i.e. send a letter of default first).
Answer: Theory Z.
PMP/CAPM Flashcards
Answer: Threat.
PMP/CAPM Flashcards
Contract term and condition. A phrase used to notify the seller that time is
extremely important and that any delay may be considered a material
breach. In these situations, delivery is strictly binding.
Any project schedule network diagram drawn in such a way that the
positioning and length of the schedule activity represents its duration.
Essentially, it is a bar chart that includes schedule network logic.
Answer: Tool.
PMP/CAPM Flashcards
Answer: Traceability.
PMP/CAPM Flashcards
Answer: Training.
PMP/CAPM Flashcards
Answer: Transfer.
PMP/CAPM Flashcards
Answer: Triggers.
PMP/CAPM Flashcards
Answer: UML.
PMP/CAPM Flashcards
The person or organization that will use the project’s product or service (e.g.
end user). Also see “customer.”
A business analysis model that shows all of the in-scope use cases for a
project and which actors have part in those use cases.
Any changed or repaired items are inspected and will either be accepted or
rejected before notification of the decision is provided. Rejected items may
need to be re-worked.
The results of quality control are deliverables that can be verified as correct,
and then validated as complete (e.g. Validate Scope). Also see accepted
deliverables and validate scope.
The assurance that a product, service, or system meets the needs of the
customer and other identified stakeholders. It often involves acceptance and
suitability with external customers. Contrast with verification.
Answer: Validation.
PMP/CAPM Flashcards
A creative approach used to optimize project life cycle costs, save time,
increase profits, improve quality, expand market share, solve problems,
and/or use resources more effectively.
Answer: Variance.
PMP/CAPM Flashcards
Comparing planned scope, schedule, and cost variables with actual scope,
schedule, and cost variables and resolving the variances.
Are assumptions still valid? Has the risk changed, or can it be retired? Have
Risk management policies been followed? Can contingency reserves be
modified? These are some of the goals when using this performance
information gathered throughout the project.
Cost estimating technique that assumes what a project should cost based on
analysis of the responsive bids from trusted, qualified vendors. For the
exam, this may relate to the Estimate Activity Resources process.
Answer: Verification.
PMP/CAPM Flashcards
A system that is used to track the history of revisions, often but not always
related to software.
A group of persons with a shared objective who fulfill their roles with little or
no time spent meeting face to face, sometimes separated by great distances.
For the exam, these present additional communications issues related to
language, culture, time zones, technology, motivation, etc.
Contract term and condition. Statements declaring that rights under the
contract may not be waived or modified other than by express agreements of
the parties. Project Managers can intentionally or unintentionally give up a
right in the contract through conduct, inadvertent failure to enforce or lack of
oversight.
Answer: Waivers.
PMP/CAPM Flashcards
Contract term and condition. A guarantee of quality for the goods or services
delivered under the contract, usually restricted to a limited time period.
Answer: Warranties.
PMP/CAPM Flashcards
Answer: Workaround.
PMP/CAPM Flashcards
A subsystem of the overall project management system. May take the form
of a WBS Dictionary, but used to perform and check the work during
Executing and Monitoring and Controlling, respectively. It is a collection of
formal documented procedures that defines how project work will be
authorized to ensure that the work is done according to the identified
documents, tracking system, acceptance criteria, and defined approval levels
needed to issue work authorizations. Also see WBS Dictionary.
WBS from previous projects can be saved (usually in the PMIS) and then
modified and reused on future projects. Many application areas of
performing organizations have standard templates. The PMI Practice
Standards for WBS Publication provides industry-specific templates that can
be tailored to specific projects. NOTE: The WBS and the WBS Dictionary
information may be stored outside these.
OVERVIEW QUESTIONS: What are some key words for Monitoring and
Controlling?