You are on page 1of 53

This manual is an output from a project funded by the UK Department for International Development

(DfID) for the benefit of developing countries. The views expressed are not necessarily those of DfID.

PICO HYDRO FOR VILLAGE POWER


A Practical Manual for Schemes up to 5 kW in Hilly Areas

Phillip Maher and Nigel Smith


Disclaimer

The authors accept no responsibility for injury or death resulting from incorrect manufacturing,
installation or operation of equipment described in this manual. All electrical and mechanical installation
and repair work should always be supervised and checked by a qualified and experienced technician or
engineer.

Edition 2.0
May 2001
AKNOWLEDGEMENTS CONTENTS
1 Introduction ........................................................................................... 1-1

The authors would like to thank Professor Alexandre Piantini from Universidade de São Paulo, Brazil for 2 The Basics of Pico Hydro ............................................................................ 2-1
his valuable inputs in Section 16 on lightning protection of isolated distribution systems.
3 Identifying Your First Scheme....................................................................... 3-1
In addition, Ing. Mauricio Gnecco from Fundacion Desarollo de Technologias Appropriadas in Colombia
provided useful ideas about the content and presentation and Dr Arthur Williams from Nottingham Trent 4 Planning a Pico Hydro Scheme ....................................................................... 4-1
University proof-read the first drafts which helped shape the manual into its current form.
5 Ownership and Viability............................................................................... 5-1
Photographic contributions from Ghanashyam Ranjitkar, Energy Systems, Nepal, Drona Raj Upadhyay,
Intermediate Technology Development Group, Nepal and Teo Sanchez, ITDG Peru were also gratefully 6 Scheme Layouts ....................................................................................... 6-1
received.
7 Site Surveying......................................................................................... 7-1

8 Pico Hydro Designs.................................................................................... 8-1

9 Generating Electricity ................................................................................ 9-1

10 Flow Management ................................................................................... 10-1

11 The Penstock ........................................................................................ 11-1

12 The Powerhouse ..................................................................................... 12-1

13 Selecting The Loads ................................................................................ 13-1

14 The Distribution System ........................................................................... 14-1

15 Domestic Wiring..................................................................................... 15-1

16 Lightning Protection of Pico Hydro Schemes...................................................... 16-1

17 Testing, Commissioning and Operation ............................................................. 17-1

18 Fault-Finding ........................................................................................ 18-1

19 Appendicies .......................................................................................... 19-1

20 Useful References and Addresses ................................................................. 20-1

21 Glossary ............................................................................................. 21-1

22 Index ................................................................................................ 22-1


Introduction

Scope
1 INTRODUCTION The focus of this manual is the implementation Readership
of hydro technology for the electrification of Finally, this manual is aimed at everyone with an
easily learned. This keeps some equipment
small villages in hilly or mountainous regions. This interest in pico hydro or rural electrification. It
What is Pico Hydro? costs in proportion with local wages.
constrains the scope of the designs to turbine is particularly intended for those who are
Pico hydro is hydro power with a maximum • The number of houses connected to each
and generator units which are suitable for thinking about this technology for the first time.
electrical output of five kilowatts. Hydro power scheme is small, typically under 100
medium to higher head sites (more than 20m It seeks to inspire sufficient confidence to
systems of this size benefit in terms of cost and households. It is therefore easier to raise
metres) and AC generation as low voltage DC encourage local implementation by “first-time”
simplicity from different approaches in the the required capital and to manage
systems cannot easily convey electricity over hydro engineers. With this in mind, criticisms
design, planning and installation than those which maintenance and revenue collection.
more than a few metres. Many aspects of the from readers would be welcomed to allow the
are applied to larger hydro power. Recent • Carefully designed pico hydro schemes have a
implementation methods described however, are guidelines and procedures to be refined and
innovations in pico hydro technology have made it lower cost per kilowatt than solar or wind
common also to other designs including those updated in the light of further experience.
an economic source of power even in some of the power. Diesel generator systems, although
suited to low head sites and to those which
worlds poorest and most inaccessible places. It is initially cheaper, have a higher cost per
benefit individual consumers rather than small
also a versatile power source. AC electricity can kilowatt over their lifetime because of the
communities.
be produced enabling standard electrical associated fuel costs.
appliances to be used and the electricity can be
distributed to a whole village. Common examples Complementary Publications
Hindrances to Market Development
of devices which can be powered by pico hydro Complementary manuals have been written to
The principle reasons why the market for pico
are light bulbs, radio’s, televisions, refrigerators help encourage more widespread adoption of
hydro remains untapped are that pico turbine-
and food processors. Mechanical power can be pico-hydro technology. A manual for
generator units are not available in many
utilised with some designs. This is useful for manufacturers, “The Pico Power Pack –
countries. Where they are available, few people
direct drive of machinery such as workshop Fabrication and Assembly Instructions” aims to
know how to design and install complete schemes.
tools, grain mills and other agro-processing stimulate local production of recommended
equipment. This manual explains how to select designs and therefore help to reduce the
Aims problems of availability which exist in many
and install pico hydro systems for hilly and
This manual aims to help overcome these countries.
mountainous locations.
problems by providing clear instructions for
design and installation of schemes on a local The “Starting a Business Using Water Power”
The Market level. Designs are recommended which emphasise guide encourages applications for income
On a global scale, a very substantial market simplicity, low maintenance and long life generation and community benefit using pico
exists in developing countries for pico hydro expectancy. The induction generator is one hydro. In particular, proven examples of
systems (up to 5 kW). There are several reasons example of technology which is becoming successful commercial applications are Figure 1-1 Pico hydro resources are abundant – the flow
for the existence of this market. increasingly incorporated into low cost / high described. By encouraging local entrepreneurs to in a spring is often sufficient to generate electricity.
reliability schemes of this size. It is especially use pico hydro as the source of power for a (Jarcot, Mustang, Nepal)
• Often, small communities are without suitable for direct-drive with small Pelton business, the technology can be more readily
electricity even in countries with extensive turbine runners which can rotate at the required financed even in areas where development loans
grid electrification. Despite the high demand speed. The operation of induction motors as or subsidies are not available to rural people.
for electrification, grid connection of small generators is described and full instructions are
communities remains unattractive to utilities given for the electrical connections.
due to the relatively low power consumption.
• Only small water flows are required for pico The penstock pipe and distribution cable are
hydro so there are numerous suitable sites. A often the most expensive components in pico
small stream or spring often provides enough hydro electrification projects. Cost saving
water. approaches to the civil works and distribution
• Pico hydro equipment is small and compact. systems play an important part in successful
The component parts can be easily implementation and these are also described.
transported into remote and inaccessible
regions.
• Local manufacture is possible. The design
principles and fabrication processes can be

pmaher 31/05/01
1-1 pmaher 31/05/01
1-2
The Basics of Pico Hydro

D. The power in the jet, called hydraulic power mechanical power is converted to electricity.
Some power is also lost in the penstock. Water in
2 THE BASICS OF PICO HYDRO or hydro power, is transmitted to a turbine
contact with the walls of the pipe is slowed down
runner which changes it into mechanical power.
by friction. This power loss is expressed in
A. Water Supply The turbine runner has blades or buckets which
(usually a spring metres of head loss. Its value is typically up to
cause it to rotate when they are struck by
or a small canal)
B. Forebay Tank
Pico Hydro Power System water. The turbine is a general name that usually
20%-30% of the total head. Before the losses in
the pipe are taken into account, the drop is
or Reservoir refers to the runner, the nozzle and the
referred to as the gross head and after losses
surrounding case. The runner typically spins 1500
Flow have been subtracted it is called the net head.
times each minute. The turbine is attached to a
(litres per second)
generator. The purpose of the generator is to
F. Mechanical Load EFFICIENCY
Head E. Electronic convert rotating power into electrical power.
Controller e.g. Grain Mill Efficiency is the word used to describe how well
(metres) C. Penstock Pipe This is how the water flowing in a small stream
the power is converted from one form to
(100 to 500 metres) can become electricity.
another. A turbine that has an efficiency of 70%
AC Electricity
220V 50Hz or will convert 70% of the hydraulic power into
110V 60Hz E. An electronic controller is connected to the mechanical power (30% being lost). The system
generator. This matches the electrical power efficiency is the combined efficiency of all the
H. Electrical Loads that is produced, to the electrical loads that are processes together. The system efficiency for
D. Turbine and Generator Water escapes
such as lightbulbs, along tailrace connected. This is necessary to stop the voltage electricity generation using pico hydro is
radio and TV from going up and down. Without a load typically between 40% and 50%.
are connected
inside the house. controller, the voltage changes as lights and
other devices are switched on and off. i.e. as a rough estimate, if there is found to be
2.8 kW of hydraulic power in a small stream, the
POWER electricity which could reasonably be expected
G. The Distribution
System connects Power is measured in Watts (W) or kilowatts is:
the houses in the (kW). There are 1000 W in 1 kW. Pico Hydro 2.8 x 45% = 2.8 x 0.45 = 1.26 kW
village to the Power has a maximum electrical power output of
generator. 5 kW. It is important to say which type of power
you are referring to when discussing a hydro Example 1 Calculate the hydraulic power
Fluorescent lamps
use less power power project as there are three types and they in a small stream
will all have a different value. The water power
The Hydraulic Power in a stream can be
Figure 2-1 Components of a Pico Hydro System (or hydraulic power) will always be more than the
calculated when the Head and the Flow have
mechanical and electrical power. This is because,
A pico hydro system makes use of the power in B The water is fed into a forebay tank. This is as the power is converted from one form to
been measured. The formula to calculate
falling water. Figure 2-1 shows the layout of a sometimes enlarged to form a small reservoir. A Hydraulic Power is as follows:
another, some is lost at each stage as illustrated
pico hydro system. Each of the components has reservoir can be a useful energy store if the in Figure 2-2
been described in more detail below. water available is insufficient in the dry season. Power = Head (metres) x Flow (litres/sec) x9.81
For advice on design and construction of forebay Hydro Power Electrical Power

A The source of water is a stream or sometimes tanks, read Section 10.2.


(from the Penstock) (from the generator)
Power Loss What is the Power in a stream if the head is 60
Power Loss from Generator
= 20 to 30% m and the flow is 10 l/s?
an irrigation canal. Small amounts of water can in Penstock
=up to 30% Mechanical Power Power Loss
also be diverted from larger flows such as C The water flows from the forebay tank or (from the turbine)
from Turbine
Power = 60 x 10 x 9.81
= 30%
rivers. The most important considerations are reservoir down a long pipe called the penstock.
= 5886 watts (W) or 5.9 kilowatts (kW)
that the source of water is reliable and not At the end of the penstock it comes out of a Figure 2-2 Some power is lost at each stage during the
needed by someone else. Springs make excellent nozzle as a high-pressure jet. See Section 11 for conversion from a water jet to electricity
sources as they can often be depended on even in help with choosing the right penstock. The The biggest loss usually occurs when the power in
dry weather and are usually clean. This means design of pico hydro system described in this the jet of water is converted into rotating, F. The Mechanical Load is a machine which is
that the intake is less likely to become silted up manual is suitable for places where there are connected to the turbine shaft often using a
mechanical power by hitting the turbine runner.
and require regular cleaning. For more hills or mountains. In fact, a drop (or head) of at pulley system so that power can be drawn from
On a well-designed and constructed scheme
information about the water source and intake, least 20 meters is recommended. A drop of 20 the turbine. The rotating force of the turbine
approximately one third (30%) of the power of
look at Section 10.1. metres or more also means that the amount of runner can be used to directly turn equipment
the jet will be lost here. The losses can be much
water needed to produce enough power for the higher on poorer quality schemes. A further 20% such as grain mills, or woodwork machinery.
basic needs of a village is quite small. to 30% will be lost in the generator when the Although approximately 10% of the mechanical

pmaher 31/05/01
2-1 pmaher 31/05/01
2-2
The Basics of Pico Hydro Planning a Pico Hydro Scheme

power is lost in the pulley system, this is still a Example 2 Calculate (i) the net head, (ii) and money to the project. If there are skilled
very efficient way of using the power. More people within the community that can help with
power is available because none is lost in the
the useful mechanical power and 3 IDENTIFYING installation then this is a further benefit.
(iii) the electrical power which
generator or in an electric motor. For advice on 5. Close to a road or other major route:
mechanical loads look at Section 13.4.
could be generated from the YOUR FIRST By choosing a popular location it will be easy to
stream described in Example 1 encourage people to visit the project and to
G. The Distribution System connects the
Use the following assumptions: 25% of the head SCHEME spread the news about your capabilities.
is lost as friction in the penstock, the turbine is
electricity supply from the generator to the
65% efficient and the generator is 80% If you are starting up in the pico hydro business
houses. This is often one of the most expensive
efficient? or starting a programme of community pico 3.3 Achieving Maximum Publicity
parts of the system. Section 14 gives detailed
hydros it is important to carefully select the Invite an important local person to open the
information on how to design the distribution
system and choose the correct size of cable.
(i) Calculate the net head first scheme as this will act as a focus for scheme and encourage the local press to
If 25% of the head is lost as friction in the pipe future interest. When identifying the site for come to the opening by producing a carefully
the head loss is 0.25 x 60 = 15m. If 15m are lost your first scheme it is important to maximise the written press release (it is worth spending a
H. The Consumer Loads are usually connected then the useful head ( or net head ) is gain and minimise the pain! The following hints few dollars getting a marketing expert to
inside houses. Electrical load is a general name = 60 - 15 = 45 m and tips will help. help with this).
which refers to any device which uses the
Produce an eye-catching leaflet or flyer to
electricity generated. The type of electrical The net hydraulic power available at the turbine give to people and to encourage them to use
loads that are connected on a pico hydro scheme is now less than the hydraulic power using the 3.1 General Location you to install a scheme for them.
will partly depend on the amount of power that is total (gross) head: 1. Accessible to you: Put up some nice signs to direct people to the
generated. Fluorescent lights are preferred Look for sites in districts that that you can get scheme.
because they use much less power for an Power = Net Head x Flow x 9.81 to easily so that your travel costs are minimised Encourage the owners of the scheme to start
equivalent amount of light as filament light bulbs = 45 x 10 x 9.81 and you can visit easily if problems occur. small enterprises using the pico hydro power.
do. This means that more lights can be connected = 4414 W 2. Accessible to customers/funders: A highly illustrated, easy to read booklet on
to the same generator. More information on Select districts that are near to where many of ‘Water Power for a Village Business’ is
choosing light bulbs and other electrical loads is
(ii) Calculate the mechanical power your future customers are based and close to available from the same source as this
given in Section 13.1. project funders to make it easy for the people
If the turbine is 65% efficient the mechanical manual.
power produced will be: that are key to your future business to visit you.

Power (Mechanical)
=net hydraulic power x turbine efficiency 3.2 Specific Location
= 4414 x 0.65 1. No major technical challenges:
= 2870 W Identify a site that is not too challenging
technically, i.e. no complicated civil works
(ii) Calculate the useful electrical required to transport water, ample flow, and a
power head that is well suited to available, well proven
If the generator is 80% efficient, then the turbine technology.
electrical power available for lighting and other 2. Close proximity to consumers:
purposes is: Short distribution lines keep costs low, are
easier to construct and maintain.
Power (Electrical) 3. Small number of consumers:
=mechanical power xgenerator efficiency Select a site where the number of customers will
= 2870 x 0.8 be small, as the power capacity can then be small,
= 2295 W or 2.3 kW reducing risk. Also the smaller the number of
consumers the easier it is to organise and
manage the project.
4. Well organised and motivated community:
It is very important that the recipients of the
power are a harmonious community, with no
major divisions, highly motivated towards having
a pico hydro and prepared to contribute labour

pmaher 31/05/01
2-3 pmaher 31/05/01
3-1
Planning a Pico Hydro Scheme Planning a Pico Hydro Scheme

these to decide on a suitable tariff and STEP 10 DETAILED SURVEY STEP 15 DETAILED COSTING
connection cost (see Section 5.3)
4 PLANNING A PICO Conduct a detailed site survey. Make a realistic cost assessment of the major
scheme components and obtain written
HYDRO SCHEME STEP 5 DEMAND SURVEY B
Is the available net head sufficient to meet quotations.
Examine what existing activities that require requirements? Will the penstock be excessively
This section gives an overview of what is
expenditure on energy or which take large long? Can it be shortened by the use of a Scheme components: penstock, turbine and
required to implement a pico hydro project for
amounts of time to carry out would benefit from channel? Can the flow be relied on throughout generator unit, distribution system, civil works
village electrification. This allows the developer
hydro power? the whole year or is storage required? Use local and additional items. Add at least 5% for
to fully understand what is involved beforehand.
knowledge. If in doubt, wait until the end of the contingencies (unforeseen additional costs)
The order of the steps is important to ensure
that the implementation is well organised.
STEP 6 SIZING AND COSTING dry season and check flows. Constantly be on the look-out for cheaper
Estimate the size of generator required to meet suppliers but do not cut corners which will
the energy demand. Estimate the cost based on reduce the quality of the scheme. Negotiate
STEP 1 COST AND AVAILABILITY
information collected at STEP 1. STEP 11 FINALISE POWER OUTPUT discounts based on the quantity of materials
Establish the source of key components which will be required.
particularly the turbine-generator and controller Modify the original estimate of generator size
Determine the range of head / flow / power
STEP 7 VIABILITY CHECK based on accurate assessment of site hydraulic
potential (available power in the stream). STEP 16 FINANCIAL VIABILITY
outputs of available equipment. Obtain Choose the most favourable size of scheme using
approximate cost of total scheme from turbine- the demand survey and power estimate. Then Use cost assessment to check if the scheme is
generator supplier and / or other schemes. compare the likely annual income with the capital It may seem tempting to implement a larger still financially viable. Compare forecast income
Otherwise assume a cost of $3,000/kW. cost. A rough guide to financial viability is: scheme than has initially been planned if the site from electricity tariff with loan repayment
• if the annual income <10% of the capital cost characteristics allow. There are a number of costs.
Visit other schemes and suppliers of turbines- then the scheme is not viable. reasons why it is preferable to keep the size of
generator equipment, pipe, and cable. These will • if the income is 10-25% of the capital then the scheme small, even if the site has potential If not, look where the major costs are occurring
be the most expensive components. the scheme could be possible . for a larger turbine/ generator combination: and see if they can be reduced. Seek cheaper
• if the annual income is more than 25% of the • Small schemes cost less and easier to estimates for cable, water pipe. Consider a
capital cost then the scheme is viable. implement different size of scheme or connecting more
• If mistakes are made with the installation of consumers and use energy efficient lamps so
STEP 2 INITIAL OVERVIEW
STEP 8 HEAD & FLOW a small scheme, then they are cheaper to revenue/repayment levels are increased.
Determine whether there is: correct
a) local desire for electricity or mechanical Decide on a suitable combination or combinations
• Maintenance and repair costs will be lower
power, b) willingness to pay, of head and flow to produced required power
from available turbine-generator. Assumptions STEP 17 CONSUMER CONTRACTS
c) local ability to manage a scheme,
about the system efficiency should also be made. STEP 12 SCALE MAP Agree consumer contracts for electricity supply
d) grid electricity available or planned
If in doubt assume an overall efficiency (water Draw a scale map of the site which include the amount of monthly tariff and
power to electrical power) of 45%. the number of light-packages provided in each
STEP 3 POWER ESTIMATE STEP 13 SCHEME LAYOUT house.
STEP 9 VILLAGE MEETING Sketch scheme layout, using the site plan map as
Make a preliminary estimate of the heads and
Present the findings of the survey to the the basis. Write on lengths of penstock, any STEP 18 ORGANISE FINANCE
flows in the area to determine whether there is
likely to be sufficient power for a pico hydro. community at an open meeting to which local canals and each different section of the Arrange finance based on supply contracts.
government staff and local development distribution system if one is required. Draw to
organisations should also be encouraged to scale.
STEP 4 DEMAND SURVEY A attend.
Present all information as estimates. STEP 14 REVISE LAYOUT STEP 19 ORDER MATERIALS
Estimate the number of houses within a radius of
Overestimate the costs and underestimate the
1km from the water supply and, of those, which Look for alternative layouts that could allow the Order materials and equipment and deliver to
power available. Suggest options for ownership
are willing to pay for an electricity supply. length of the penstock or the distribution site
(individual, group, community) and explain the
system to be reduced so that costs can be cut.
responsibilities and funding possibilities. Only
1km radius is the distance over which the This may involve repositioning the powerhouse or STEP 20 INSTALLATION
proceed to the detailed survey when there is
electricity can most easily and economically be the use of canals.
local agreement on ownership and funding. Install scheme
transmitted. Make assumptions about the Consider requirement for payment for survey.
capital, maintenance and operating costs and use

pmaher 31/05/01
4-1 pmaher 31/05/01
4-2
Planning a Pico Hydro Scheme Ownership and Viability

STEP 21 OPERATOR TRAINING 5.2 Cost Breakdown


Train local operator in operation and maintenance 5 OWNERSHIP AND Scheme costs can be divided into capital costs
and running costs:
and safety of the system and the owners in
management of the scheme. VIABILITY Capital Costs – The capital cost is the total cost
of purchasing and installing all of the scheme
5.1 Ownership Options components. The capital cost is raised through a
Management training should cover collection of 5.2 Cost Breakdown
combination of one or more of the following:
repayment or tariff and repayment of credit. 5.3 Tariff Setting
5.4 Consumer Agreement private funds, bank loans, government subsidy
Also the operation of a maintenance fund to
5.5 Demand Survey and charitable donations. If no other data is
ensure that scheme continues to operate.
available, $3000/kW can be used as a
5.1 Ownership Options conservative figure for the total capital cost of
STEP 22 CONSUMER TRAINING a pico hydro scheme, excluding house wiring,
There are two main ownership options for pico
Provide information and training to consumers building work and distribution poles.
hydro schemes:
about safety and usage of electricity.
Community Ownership- consumers of the power
Running Costs - In order to collect the tariff
pay for the scheme and any net income goes back
STEP 23 COMMISSION SCHEME and repay the loans it is essential that the
to the community
scheme remains operational once installed. The
Entrepreneur Ownership- one or more
running costs are those costs associated with the
entrepreneurs pay for the scheme and receive
operation and maintenance. The wages of the
the profit from sales of power.
scheme operator vary from country to country
although US$ 30 to US$ 50 per month is typical,
Other models such as Government Ownership are
as the job is normally considered to be part-time
less common for pico hydro schemes. The
and this salary can be supplemented with other
requirements for viability vary depending on the
income. The salary will also depend on the number
ownership model. In the case of Community
of individual consumers as a distribution system
Ownership, viability is assessed in terms of
for a scheme with many houses connected will
whether the quality of life improvements and
require more maintenance than one with fewer
financial savings over other energy sources are
houses. On very small schemes, the operator may
greater than the cost of the scheme. In the case
have a free lamp instead of receiving wages.
of Entrepreneur Ownership, viability is measured
mainly by the return on investment for the
Maintenance costs arise because of the need to
entrepreneur. Each ownership model has
repair or replace damaged and worn components
advantages and disadvantages.
in order to keep the scheme operating reliably.
These can be assumed to be a fixed proportion
Pro’s and Con’s
Usually the benefits are more evenly distributed
of the total capital cost (e.g. 4-6% per year).
C.O.
with a higher proportion of households receiving a The exact figure depends upon equipment and
connection. installation quality and attention given to
E. O. Profit motive usually ensures that maintenance and maintenance. If in doubt, assume 6%.
repair is given more attention, income-generating
end-uses for the power are a priority, management
by an individual rather than a committee is more
5.3 Tariff Setting
straight-forward. However, poorest community The tariff is the amount that consumers are
members may be excluded because of higher charged for their electricity service. For pico
tariff’s.
hydro schemes the tariff is usually a fixed
Table 5-1 Comparison of Community Ownership (C.O.) amount which is charged each month. This is
with Entrepreneur Ownership (E.O.) of pico hydro
made possible by the use of load limiters instead
schemes.
of electricity meters as these prevent the
A demand survey and financial viability consumer from drawing more current than they
calculations are very important to establish have subscribed to, as explained in Section 15.3.
whether or not a pico hydro scheme is viable and How the tariff level is set depends on the type
to determine the most appropriate scheme size. of scheme ownership and how the scheme is
financed. Provision must be made to increase the
tariff to compensate for price increases
pmaher 31/05/01
4-3 pmaher 31/05/01
5-1
Ownership and Viability Ownership and Viability

(inflation). Linking the rise in tariff to other Community scheme with no capital available • What a light package is and the implications 1. How many houses are there within a 1km
price rises, such as national electricity tariffs, Often rural households lack sufficient disposable of a limited electricity supply (e.g. what radius of the source of water / proposed
may make this process easier. The use of ‘light funds to pay for pico hydro and under these appliances can and cannot be connected if a generator site?
packages’ enables the consumer to see a directly circumstances a loan, usually from a bank, should socket for an electric plug is provided) 2. Within this area, how many people are
link between the level of service which they be considered. A realistic payback period for the • The costs per light package (Connection prepared to pay for electricity and how
receive for the tariff which is paid. loan should be determined. This is usually charge, cost of house wiring, monthly tariff) much?
Light Packages between 3 and 15 years. Having determined a and how the monthly tariff will change with 3. What activities currently occurring would
A light package is an electricity supply that is suitable payback period, banks and other credit time. benefit from pico hydro power?
sufficient for one lamp and possibly a radio. The sources should be approached to establish the • If the electricity will be provided between
advantage of this system is that the cost of the repayments required per $1000 borrowed and particular times of the day (e.g. 4pm to 11pm)
the terms of the loan especially regarding then this should be stated. How many houses are there?
service can be easily compared to the benefit
obtained. If tube lighting is used, a single light collateral. • During the dry season the times may vary The number of houses within a 1km radius will
package may typically provide 15W. Load limiters due to reduced availability of water. probably be known by local people and can be
are fitted which limit the power supplied to that Having found the best credit deal, the steps • The labour contribution required to checked by walking around the area. 1km is
required for the number of light packages to determine the tariff in this case are as construct the powerhouse, penstock, intake usually the economical distance over which
chosen. The consumer pays a fixed monthly fee follows: and distribution poles. electricity from a pico hydro unit can be
per light package. 1. Determine the capital cost per light package transmitted. For some countries recent
as before. (e.g. $45) EXPLAIN THE ADVANTAGES and Ordnance Survey maps are available. Map scales
Community-owned scheme with no bank loan 2. Calculate the monthly loan repayments for DISADVANTAGES of 1:50,000 may have individual houses marked.
In this case the consumers pay a one-off fee each $1000 borrowed and from this work out When finding out who is interested in receiving If a map can be expanded on a photocopier, this
which pays for the capital cost of the scheme the repayment for $1. (e.g. if $30 per month an electricity connection, it is important to makes it easier to identify features in a
and a small monthly tariff which covers operation for $1000 borrowed then 30/1000= $0.03 explain the advantages. The main advantages of particular area and to mark on additional houses
and maintenance. per $1 borrowed. ) electricity for most people in rural communities that are not shown. A map of a rural community
3. Calculate the monthly repayment per light are: living near to a small hydro resource in Kenya is
package by multiplying the capital cost per • improved lighting for cooking and study shown below.
The costs to the consumers can be estimated
as follows: light package by the monthly repayment for • better air quality because no kerosene lamps
1. The connection cost per light package is $1. (e.g. 0.03x45 = $1.35 per light per • less money spent on batteries or kerosene Potential
month). • less risk of fire pico hydro
calculated using data from other pico hydro
site
schemes or by assuming $3000/kW excluding 4. Add maintenance costs, calculated as before The ability to demonstrate electric tube light in
1km
house wiring. For example, if the scheme cost and an allowance for the operator wages to local houses is very advantageous. One method of
square
is $3000/kW and each light package is 15W obtain the total monthly tariff per light doing this is by using a pre-charged “emergency
Black dots
then the capital cost of one light package will package. light” (see Section 13.1)
indicate
be $45. This must be paid up-front to allow A disadvantage of the pico hydro scheme for houses
the scheme components to be purchased. Entrepreneur-owned scheme lighting and other small loads is that the
House wiring must also be paid for. The entrepreneur needs to determine the return consumers must make a commitment to pay the
on investment that they require for a pico hydro tariff every month. This differs from other It is sometimes possible to supply power to
2. Estimate the maintenance costs of the
scheme to be sufficiently profitable and a energy types such as kerosene and small houses that are further away by using a
scheme. This will be $0.23 per package per
worthwhile investment. For example, this may be batteries which are bought whenever funds are transformer although this adds cost and
month if the maintenance fund is 6% of the
10% above the cost of a bank loan. This can be available. complexity. Battery charging for people more
capital cost ($3000/kW) as recommended
used to calculate the monthly cost per light than 1 km from the generator is an additional
above.
package in a similar way to that described above. possibility (see Section 13.1). The best place for
3. Estimate the monthly cost of operator wages
The survey will then determine whether there 5.5 Demand Survey the generator is usually as near to the centre of
and divide by the approximate total number
are sufficient households willing to purchase the the village as possible. The position of the
of light packages to find the operation cost The demand survey is a very important step for
light packages at this rate. generator also depends on the water source. For
per light package. For example if most schemes. It enables the developer to find
more advice on selecting the best site and the
approximately 100 light packages are out how many light packages are required at the
5.4 Consumer Agreement scheme layout, read Section 6.
expected to be subscribed to and the wages tariff and connection fee which have been
will be $30 per month, the operator cost per Before the demand survey is conducted the calculated and hence the correct size of scheme
package will be 30/100 = $0.3 terms of the consumer agreement should be
How many people will pay for electricity?
to be installed. The following questions will need
4. Add the operator costs to the maintenance clearly established. This will help to clarify to be answered in order to proceed with the 1. Conduct a survey of households within a 1km
cost to obtain the running cost per light exactly what benefit the consumers will receive scheme design: radius of the best generator location. Obtain
package which will be payable by the and at what cost and level of labour contribution. name, address and the number of light packages
consumers each month. Key points to explain are as follows: that would be purchased using the tariff level

pmaher 31/05/01
5-2 pmaher 31/05/01
5-3
Ownership and Viability Ownership and Viability

and one-off fee / house wiring cost which have Calculate a tariff for a 15W light package for 2. Scheme financed through bank credit. Per light package +house wiring this is a monthly
been calculated. This can be done through each financing option and decide which is the repayment of $59 x 31/1000 = $1.83
community meetings or visiting the houses most viable. The interest rates at local banks have been
individually. The consumers must make a firm investigated. One bank is prepared to lend the Similar repayments can be calculated for
commitment to the supply agreement and sign for 1. No bank loan capital required at an annual interest rate of repayment terms of 10 years and 15 years
the number of packages which they will subscribe Assuming the capital cost of the installed system 25%. This is the best deal. They require the land
to. is $3000/kW, the capital cost per 15W light registration papers of community members as Summary of tariff costs for one lamp package:
2. Use the results of the survey to decide on the package is 15/1000 x 3000 = $45. collateral.
power required to supply the total number of The annual repayments (R) for each $1000 Loan repayment 5 10 15
light packages and size the scheme. The costs for the house wiring of a light package borrowed can be calculated using the following period years years years
of this size have been investigated in Addis formula: Repayments for $1.83 $1.38 $1.27
Ababa. Component details and costs for the i (1 + i ) n scheme and house
house wiring and load limiter are as follows: R = L×
What other activities could benefit? (1 + i ) n − 1 wiring
Item Specification Cost $ Maintenance (6%) $0.23 $0.23 $0.23
Other activities, normally done by hand or using
diesel engines can use pico hydro-power instead. Bulb + holder 9W CFL 8.22 L = loan amount (e.g. $1000) Operator cost $0.25 $0.25 $0.25
Planning uses for the hydro system during the Switch In line 0.60 i = interest rate (e.g. 25%) Total monthly tariff $2.31 $1.86 $1.75
day, when energy is not needed for lights, is Socket Wall Mounted 0.72 n = number of years of repayment
called increasing the load factor. Improving the Cable 0.75mm² x 5m 0.60 Comments
amount of time that the hydro system is ‘busy’ Fuse + Holder 3A / 220V 0.60 Operator and maintenance costs are calculated
can help to lower the cost per light package. Load limiter PTC Thermistor 0.97 The repayments have been calculated for loans as before. The interested is assumed to be
However, the extra income should only be Switch 220V Isolation 0.97 taken over 5, 10 and 15 years. calculated annually and unchanging for different
included in the calculations if these businesses Plastic Box 75 x 50 x 25mm 1.20 For 5 years the annual repayment is : repayment periods. In reality the interest rates
will be established from the beginning of the Seal for box Printed Label 0.12 are usually lower for longer repayment periods
project. Popular uses for pico hydro-power in Total $14.00 0.25(1 + 0.25) 5 and for larger sums.
addition to lighting include: R = 1000 × = $372
The annual maintenance costs will be calculated (1 + 0.25) 5 − 1
• agro-processing including threshing and milling as 6% of the capital costs. Per Light package this
• battery charging is
• ice-making and refrigeration Over 5 years this is a total repayment of $1860
45 x 0.06 /12 = $0.23 per month.
• power for tools in a workshop.
Use Section 13 to find out how other activities Similarly,
The operator is expected to be paid $30 per
could be powered by pico hydro. The for a 10 year term
month. It is expected that each of the 60 houses
complimentary publication “Starting a Business the annual repayments are $280
will take an average of two light packages each.
Using Water Power” gives more income- (total repayment = $2,800 )
That gives an operator cost per light package of
generating ideas. 30/120 = $0.25
for a 15 year term
Example of Viability Calculations: the annual repayments are $259
So for this option the consumer will need to pay
(total repayment = $3,887 )
At a village in Ethiopia, Africa, there is the following per light package:
interest in developing power from an irrigation
Based on the annual repayments it is now possible
canal. There is up to 4.5 kW electrical power
One-off fee $45.00 to calculate the monthly tariff per light package:
available all year round at this site. The
House wiring $14.00
community leaders want to know how much it
Monthly maintenance $0.23 The capital cost for one light package is $45 and
will cost to install the scheme and connect to
Monthly operator cost $0.25 the house wiring cost is $14. Assuming that bank
60 houses.
credit is used to pay for 100% of the scheme
There are two possibilities: For example, a consumer subscribing to 2 costs including house wiring (but excluding poles
1. the community funds all the costs packages would have to pay 2x[$45 + $14] = $118 and building works) then the monthly tariff is
themselves initially and a monthly tariff of approximately calculated as follows:
2x[$0.23 + $0.25] = $0.96.
2. the community borrow the capital costs For a five year loan repayment
from a bank and just fund the house- Monthly repayment costs per $1000 borrowed
wiring themselves = 372 / 12 = $31

pmaher 31/05/01
5-4 pmaher 31/05/01
5-5
Scheme Layouts Scheme Layouts

get longer. Remote areas will have more At this site, there is sufficient water in the • The cost of this pipe is likely to be the most
limited access for transportation of building stream all year round to supply approximately significant scheme cost with this layout. See
6 SCHEME LAYOUTS materials. This may affect the design of civil 100W of electricity to each of 25 houses. Section 11 for advice on choosing a penstock.
6.1 What factors decide the layout? works such as intakes, canals and reservoirs. However, there is a considerable distance
6.2 Examples of Scheme Layout between the water source and the nearest 6.4 Layout 2: Short Penstock, Long
6.3 Layout 1: Long Penstock, Short Cable • Water supply and irrigation projects houses in the village (approximately 800m) and Cable
6.4 Layout 2: Short Penstock, Long Cable
In some cases it is possible to combine a pico during the dry season, some water is taken from
6.5 Layout 3: Using a Canal
6.6 Layout 4: Low Pressure Pipe and Storage hydro scheme with other local initiatives such lower down the stream and used to irrigate farm
as the development of domestic water supply land. A map of the site has been drawn and is
6.1 What factors decide the layout? or new irrigation systems. This may affect shown in Figure 6-1
decisions regarding the layout. Contour lines have been added which join
Since decisions regarding the scheme layout will
together places of the same height. There is 10m
affect the power output, reliability, cost and
The task facing the layout designer usually difference in height between each of the
convenience of the service, it is worth
involves several compromises. The most obvious contour lines increasing away from the river
considering several options to make sure that
layout for a particular site may not be the best which flows through a valley.
the best layout is chosen.
and other options should be considered. Note: In figures, each dot represents 5 houses.
As the stream is some distance from the village
The factors requiring consideration when
The length of the penstock pipe and the length there are a number of possible layouts to
selecting the best layout are as follows: = Penstock pipe = Intake = Power house
of the distribution cable, in particular, must be consider. The main points of each layout have = Tailrace = Cable = Group of 5 houses

carefully judged. It will be helpful, when been summarised to allow a quick comparison to
• Location of the houses in relation to the
considering different layouts, if the local cost be made. Figure 6-3 Layout 2 Short penstock and long distribution
water
for different sizes and types of plastic pipe and system. Water rights are not affected.
If the houses are a long way from the
cables are available. This will allow rough 6.3 Layout 1: Long Penstock, Short In this design, the cost and the head losses will
turbine, the scheme is likely to be expensive.
Reduce this cost by careful planning.
estimates to be made for quick comparison. Cable both be reduced because the penstock is
shorter. The water in the tailrace rejoins the
Detailed designs are not required at this stage, original stream so irrigation is not disrupted
• Power requirement
but it will be helpful if the designer has read and • Distribution cable will be expensive and needs
The power generated depends on how much
understood Sections 10, 11 and 14 before making careful selection to minimise the cost and
water is taken (flow rate) and the number of
final layout decisions. avoid a large volt drop.
metres which it falls (head). These are both
affected by the layout. • The powerhouse is a long way from the village
which may be very inconvenient.
6.2 Examples of Scheme Layout For advice on designing and costing the
• Water rights
Checking water rights and negotiating water Figure 6-1 A map of the site is essential when planning distribution system, consult Section 14.
usage with everyone affected is an important the layout. On this map, points of the same height have

part of the planning process. Questions such been joined with contour lines. = Penstock pipe = Intake = Power house
6.5 Layout 3: Using a Canal
= Tailrace = Cable = Group of 5 houses
as the following should be asked:
Whose land will be used for the scheme? Figure 6-2 Layout 1 has a short distribution system
Who else uses the water and for what Groups of 5 houses
saving on cable cost. However, a longer penstock will be
purpose? Spring more expensive.
Clear agreements should be reached before 800 metres
In Layout 1, a long penstock brings water to a
any installation work begins. This will avoid
Stream convenient powerhouse in the village keeping the
disputes that could affect the operation of
Water taken distribution system short. The civil works are
the scheme after commissioning. here for kept to a minimum, because the intake is also the
irrigation
Flow of River forebay tank.
• Cost and availability of different
• Water in the tailrace is not returned to the
components Contour
lines
original stream and therefore irrigation is = Penstock pipe = Intake = Group of 5 houses = Forebay Tank
The layout affects the cost and the power = Tailrace = Cable = Power house
affected. Water rights will be an important = Canal

output. The major challenge of the layout Four different scheme layouts are considered in issue with every layout except with Layout 2.
designer, is to keep the penstock and the the following example of a typical hillside Figure 6-4 Layout 3 Use of a canal replaces the need for
• Much of the head will be lost unless a
distribution system as short as possible. Both a long distribution system or penstock.
electrification project. penstock of large diameter is used.
the cost and power losses increase as they

pmaher 31/05/01
6-1 pmaher 31/05/01
6-2
Scheme Layouts Site Surveying

In this layout, the water is brought nearer to 7.2 Obtaining the Necessary Equipment.
the village using a canal. A lot of manual work is
required to dig a long canal like this but the 7 SITE SURVEYING A variety of equipment to help determine the
head and flow is discussed in this section. Some
penstock and distribution cables can both be 7.1 Power from a stream methods require practice in order to be used
short and will therefore cost less. 7.2 Obtaining the Necessary Equipment.
accurately. Methods have also been included
7.3 Measuring the Head
• An earth lined canal will require regular which involve no specialist equipment or training
7.4 Measuring the Flow
maintenance enabling anyone to be able to estimate the power.
• A concrete lined canal will be more reliable
7.1 Power from a stream
but expensive particularly at remote sites For head measurement, the water-filled tube
• Canals should be avoided in areas which have The amount of power that can be provided by a
method is the lowest cost though time
landslides stream depends on two things. These are called
consuming. Use of digital altimeters and Abney
Section 10.2 gives information about designing a the head and the flow.
Levels has also been described. Where available,
small canal. these methods can provide a relatively quick and
1) The head, measured in metres (m), is the
accurate alternative if used correctly. Digital
6.6 Layout 4: Low Pressure Pipe and vertical drop from the top of the penstock to
altimeters are becoming more widespread and
Storage the bottom. The greater this drop, the greater
lower in cost though a quality one cost about
the power and the higher the speed of the
$200.
turbine. It is important not to confuse this
height with the penstock (or stream) length.
The flow measurement techniques described are
the bucket method and the float method. The
2) The flow, measured in litres per second
float method is much less accurate but very easy
(l/s), is the amount of water which flows past
to perform. Use of the digital conductivity
you in one second when you stand by the
meter in what is called the ‘salt gulp’ technique
stream.
of flow measurement has also been included. At
Hydro-Power is calculated by multiplying the many sites this method is much more practical
head and flow by the force of gravity. The unit and accurate than the others. Like the digital
of power is the Watt (W). 1000 Watts = 1 altimeter, conductivity meters are gradually
= Penstock pipe = Intake = Group of 5 houses = Reservoir kilowatt (kW). Since the force of gravity is becoming more widely available and have a similar
= Tailrace = Cable = Low pressure pipe
fairly constant (9.81m/s2), the formula for
= Power house
cost.
Figure 6-5 Layout 4. A modified version of the last Hydro Power can be written as follows:
layout The canal is replaced with a low-pressure pipe. Hydro Power (W) =head (m) x flow (l/s) x 7.3 Measuring the Head
The forebay has been enlarged to add a means of energy 9.81
storage. The techniques, summarised in Table 7-1, differ
in terms of cost, complexity, and accuracy.
Layout 4 is almost the same as 3 but the canal is Example Calculate the power in a stream Generally, the lower the head, the more critical
replaced by a piece of low-pressure pipe and the
The maximum head of a stream on a farm in the accuracy of the measurement.
forebay is enlarged to form a small reservoir. A
suitable low-pressure pipe is often sold as Western Nepal is 70 meters. The flow that has
been measured is 5 litres per second. What The head should be measured at the most likely
drainage pipe. This type of pipe is considerably
hydro power is available in this stream? place for the penstock. This means that the site
cheaper per meter than penstock pipe.
layout will have been studied and possible places
• Maintenance is reduced as there is no canal
Answer: Power = head x flow x gravity for the power house and forebay tank will be
• A pipe is easier to install than a canal.
= 70 x 5 x 9.81 under consideration. Don’t forget, keep the
• More building materials, labour and
= 3433 W or 3.4 kW penstock as short as possible to obtain the
maintenance are required for the reservoir
required head. The head required for a pico
and extra pipe must be purchased.
hydro project like the ones described in this
• A reservoir allows easier management of It is important that the head is carefully
manual (medium to high head) will need be at
water resources during the dry season and measured. In some places the flow is clearly
least 20 metres and ideally 50 metres or more.
smaller pipe to be used to bring the water more than is needed. If this is true then
from the stream. accurate flow measurements are not required. If
Section 10.3 explains how to design a small there is doubt about any of the calculations then
reservoir. the measurements should be repeated. It is
better to underestimate the head and flow
rather than to overestimate them.

pmaher 31/05/01
6-3 pmaher 31/05/01
7-1
Site Surveying Site Surveying

Method Cost Accuracy Time Difficulty Equipment Required No. of Digital Altimeters The Abney Level.
People
The Abney Level (or Clinometer) is a hand held
1 Water-filled Low ($20) Accurate with Takes time Easy to Plastic tube, tape 2 or more
plastic tube practice (3-6hrs) learn measure, wooden pegs,
sighting meter. It requires skill to use but once
notebook and pencil mastered can measure heads with an accuracy of
2 Altimeter Medium / +/-1m to +/-5m quickest No skill Digital altimeter, 1 (though +/- 5%.
High. ($200 depending on model method (less required wooden pegs, notebook better
each) Borrow (greater accuracy is than 1hr) and pencil with 2)
With this method, the angle of the slope is
or hire if possible using 2
possible altimeters)
measured. The linear distance is also measured
3 Abney Level Quite low. Accurate with Quite slow Practice Abney Level, long tape 2 and using simple trigonometry, the height
Borrow or hire practice (up to 2hrs required measure, two sticks difference between two points is calculated.
if possible depending on (1.5m), pegs, notebook When these are added together the total head is
experience) and pencil
obtained.
Table 7-1 A comparison of methods to measure Head in eye level and the expected level in the forebay. Procedure for head measurement using an
metres Record that one reading has been taken and Abney level
stand still. Figure 7-1 Head measurement using a digital altimeter in
Step 1: Two posts are needed which are 1.5 to
Water-filled Tube Kenya
1.6 metres in length or the distance from ground
This is the cheapest method of head Step 2: The assistant now moves downhill past Digital altimeters are the most convenient way to to eye level, (they must be the same but their
measurement to learn. No specialist equipment is your position keeping the water in the tube by measure the head at a site. Height is calculated exact length is not important). The first is held
required. A piece of clear, plastic tube, about 20 holding a thumb over the end. As they walk using changes in air pressure. All that the user at the proposed location of the turbine and the
metres long with a diameter of 10 or 12 mm, is further down, lower your end of the tube until has to do is to record one reading at the second about 30m towards the intake. A clear
the main piece of apparatus. the water in your end is at the level of the soles proposed forebay location and one at the site of line of site is necessary so this may affect the
of your shoes. The assistant stops walking the turbine in order to determine the head. The route taken. A brightly coloured ribbon or
Fill the tube with water so that when the two downhill when the water reaches eye level. second reading should be taken as quickly as similar object is useful to identify the top of the
ends are held together, the water level is about Record that a second reading has been taken possible to prevent atmospheric changes in sighting post
30cm from the top. The water inside the tube pressure (changing weather) from affecting the Step 2: The distance between the top of the
will always find the same level on either side. A Step 3: The process is repeated until one side readings. two posts is measured and recorded (distance d).
plastic funnel will help to pour in the water. of the tube is held in the expected location of Some Abney levels have a built-in range finder
Bubbles in the tube should be avoided as they the turbine. The number of reading taken are The best way to remove weather effects is by and this can be used instead of a tape measure.
can cause inaccurate readings. They should be then totalled up. This is multiplied by the using two identical altimeters and to take Step 2: The angle between the tops of the two
removed where possible by allowing them to rise average height (to eye level) in metres of the measurements at the same time. One altimeter siting posts is carefully measured using the level
out of the tube (very small bubbles don’t two people who took the measurements. to give remains in the same position, either at the top or and recorded. Both posts should be held straight
matter). the total head. The procedure should be the bottom of the slope to check the effects of with the level resting on top of one.
At least two people are required for this method repeated two or three times until you are sure changing weather. The other is used to calculate Step 3: The process is repeated up the hill until
but more can help with taking measurements and that the head measurement is accurate. Good head. Meanwhile any changes in head caused by the proposed intake level is reached.
recording the results. marking at the forebay site and the powerhouse atmospheric conditions are noted and then Step 4: The heights between each pair of points
position enable the same section of hillside to be adjustments can be made to the final figure. It are calculated using the sine rule and added
Procedure measured again. If the head is more than is easy to repeat the test several times in order together to give the total head.
Step 1: One person holds each end of the tube required then an intermediate position, can be to check the head. If the altimeters can be
and does not allow the water to spill out. Begin found. The distance between the two marker zeroed, zero both at the same time. Agree the
by matching the water level in the tube to the points should be measured to decide the length time required for the person who carries the Position of
Abney level
nce d Sighting

height h
expected water level of the forebay tank which of penstock required. second altimeter to move to their new position.
should be marked by a stick. Your assistant Using watches take the new readings on both dista post
should remain still, holding their end of the tube A variation of this method is to seal one end of altimeters at the same time. The two readings
at this point. Meanwhile, move downhill carefully can be subtracted to give the head. An accuracy angle A
the tube with a pressure gauge. The pressure at
holding your thumb over the end of the tube as each measuring point is recorded and the sum of of at least +/- 5m is expected with digital
Level
you go so that the water doesn’t spill out. Once the total pressures can be used to calculate the altimeters although +/- 1m should be possible
post
your eye level is approximately the same as the overall head. The pressure gauge must be with some. Height h = d x sin (A)
expected water level in the forebay, raise the calibrated before use so that the readings are
tube to head height and take your thumb off the trustworthy. A tall building an long tape measure Figure 7-2 Calculation of the height between two points
end.. Adjust your position as necessary so that can be used for calibration. using an Abney Level
the water level in the tube matches exactly your

pmaher 31/05/01
7-2 pmaher 31/05/01
7-3
Site Surveying Site Surveying

Method Cost Accuracy Difficulty Time Equipment required Number of STEP 2: Find a place to measure the flow. 3. Build a simple weir and use a piece of pipe
people
This can be difficult. You need to find a method
1 Bucket Method Negligible Reasonable / poor Not 10 minutes + Bucket and 2
( only suitable for depending on method difficult time to block stopwatch of directing the water in the stream into the
flows less than / experience stream if bucket. It is important that as little as possible
about 10 l/s) required escapes. If some does escape, estimate a
2 Float Method Negligible Poor although Not 30 minutes A float (piece of 2 percentage and add on to the measured flow.
reasonable accuracy Difficult wood), tape measure,
STEP 3: Take the measurements.
in smooth parallel- stopwatch
sided channels Using a stopwatch or ordinary watch with a
3 Salt Gulp Analysis High Medium to high Requires 1 hour Conductivity metre, 1 or more second hand, record how long the bucket takes
($200). accuracy with care to Salt weighed into to fill to the marked level. Repeat this at least 3
Borrow / practice (±5%) perform bags, bucket,
times and average the results. If you find that
hire a meter calculator
the bucket fills in less than 5 seconds, your
Table 7-3 Suitable methods of measuring small flows (<50l/s) results will not be very accurate. For more
help the surveyor estimate the flow throughout accuracy it is better to use the largest container The Float Method.
the year. Three methods of flow measurement which you can find or try another method of It works well in canals or channels. It can also be
are explained which are particularly suitable for measuring the flow. used in rivers and streams although with less
the measurement of small flows (less than 50 STEP 4: Work out the flow in litres per accuracy Two pieces of information are needed
litres per second) The methods are summarised second. to calculate the flow by this method. The first is
in Table 7-3. If the bucket holds 15 litres and takes 8 seconds the cross-sectional area of the water flowing in
to fill then the flow is 15/8 l/s or 1.87 litres per the stream or channel. The second is the speed
The Bucket Method second that the water is flowing. This is measured using
A simple method of finding small flows ( up to a float and timing its travel between two points a
Suggestions of methods to divert water into known distance apart.
about 10 l/s) is to use a bucket and a watch. In
the flow measuring container
fact any large, waterproof, container is suitable,
1. Natural Waterfall
providing that you can first find its volume in Procedure
litres. A 15litre bucket is suitable for the STEP 1: Find the cross-sectional area (CSA).
Figure 7-3 Head measurement using an Abney Level in
smallest flows (3 litres per second or less) and The difficulty of measuring the cross-sectional
Nepal
larger ones for bigger flows. area depends on the type of flow under
Station No. Distance D Angle A D x sin(A) consideration. Estimating the CSA in a smooth-
1 31.5 m 14º30’ 7.89 m sided channel is much easier than in a shallow,
STEP 1: Find the volume of the bucket (if
2 29.0 m 7º15’ 3.66 m rocky stream.
unmarked).
Take a smaller container with a known volume. A
11 23.1 m 10º20’ 4.14 m
one litre water bottle is a good example. Fill the To estimate the area at a particular point,
Total head 57 metres
bucket with water using the smaller container measure the width and then take depth
Table 7-2 Using an Abney level, the distances and angles measurements at regular intervals across the
and count how many litres you have added. Mark
are recorded at several points between the turbine and
the level in the bucket clearly when the maximum flow. Plot the depth measurements on squared
intake position so that the total head can be calculated 2. Build a weir from available materials and use
as shown above. number of complete litres has been added. paper as shown in Figure 7-5. Join them up with
a wooden channel, a corrugated sheet or a
straight lines to the width that is marked along
piece of stem from a banana plant to channel
1 litre one axis to create an enclosed area. The area can
7.4 Measuring the Flow the water
be estimated by counting the number of squares
The accuracy to which the flow needs to be that are enclosed. Multiply the number of
measured depends on the site. A demand survey squares by the area which one square represents
and estimates of the head help to determine the in m2. Repeat these measurements in the middle
required flow. In many cases, the flow available and at the other end of the length over which
will be more than is needed for the scheme, since the float is being timed (approximately 10
the flows for pico hydro are small. The most 20 litres metres). Three values of the CSA will allow an
critical time of year is towards the end of the average to be calculated.
dry season when rain has not fallen for some
time. This is the best time to measure the flow.
Local people will be able to say if the water level Figure 7-4 Use a small container of known volume to find
the volume of a larger one.
in the stream is typical for that time of year and

pmaher 31/05/01
7-4 pmaher 31/05/01
7-5
Site Surveying Site Surveying

float method is limited because of the


Width requirement for correction factors and the
difficulty of measuring the cross-sectional area The travel of the float
is timed between two
of many streams. points of a known
distance apart (L)
Depth AREA (m2)
Example Calculate the Flow using the
Float Method
Figure 7-5 Squared paper can be used to help estimate What is the flow in a small channel where the 1.
the cross-sectional area
following information has been obtained?
STEP 2: Measure the speed of the flow 1) The water in the channel is 25 cm deep, the
(surface velocity). sides of the channel are approximately square
2.
A length (L) of 10 metres between the marking and the width is 40 cm. The side are quite Measure the depth at several
points through the stream. Use
points should be sufficient. Begin to time the smooth Length L these measurements to work
out the cross-sectional area
float when it passes the first marker and stop as 2) When a stick was floated down a 20m section 3. in square metres. Repeat in the
middle and at the opposite end
soon as it passes the second. Repeat at least of the channel it took a) 36 b) 40 and c) 44 of the length (L). Then estimate
the average cross-sectional are
three times for consistent results. For the test, seconds
choose the straightest section of stream with
the most even cross-sectional area. Answer:
Figure 7-6 The float method of flow measurement
(i) Cross sectional area of the water in the
This method is accurate to within 5% if
STEP 3: Calculate the flow in litres per channel
performed carefully. It relies on the fact that
second = 0.25 x 0.4 The Salt Gulp Method the conductivity of water in a stream will rise
The flow is the product of the average stream = 0.1 m2
This method requires more complicated when salt is added. The flow rate is determined
area and the average velocity (or average speed) (ii) Average time taken
calculations than the others but is easier to by measuring the speed and concentration of a
of the flow: Since the water moves more quickly = (36+40+44)/3
carry out. With some practice however, it can be cloud of salty water as it passes downstream.
on the surface than in other parts of the = 40 seconds
the most convenient, rapid and accurate method
stream, an additional factor must be introduced Average surface velocity
of measuring flow in a stream. Procedure:
which takes this difference into account. The = 20metres/40seconds
difference between the surface velocity and the = 0.5 m/s
A portable digital conductivity meter and some STEP 1: Add the salt solution to the stream
average stream velocity depends on the type of
means of accurately weighing salt are required. A known mass of salt is mixed with some water in
stream. Guideline “velocity correction factors” (iii) Correction Factor for a smooth channel
Digital conductivity meters are becoming more a bucket until fully dissolved. The amount of
are given below. The table also gives an indication = 0.85
widespread and it is hoped that they will water in the bucket doesn’t matter but once the
of the accuracy that can be expected. (iv) Flow = Area x velocity x correction factor
eventually be available in all areas where pico salt has been added then the water must not be
= 0.1 x 0.5 x 0.85
hydro development is taking place. Access to a spilt. Record the mass of salt added, to the
Type of stream Velocity Accuracy = 0.0425 m3/s
computer is useful. A spreadsheet allows the nearest gram. All the salt water solution is then
correction The flow in litres per second
factor
results to be rapidly converted into a flow rate. tipped into the stream. The mass of salt used
= 0.0425 x 1000
A rectangular channel with 0.85 Good Otherwise a calculator and graph paper are depends on the size of the flow. As a rough
= 42.5 litres per second.
smooth sides and bed required to calculate the results. estimate, use approximately 25g of salt for
A deep, slow moving stream 0.75 Reasonable every 5 litres per second of flow (the flow will
A small stream with a smooth 0.65 Poor
have to be guessed on the first occasion).
bed
A quick, turbulent stream 0.45 Very poor
STEP 2: Record the conductivity change
A very shallow, rocky stream 0.25 Very poor downstream. The conductivity meter probe is
placed in a swiftly moving area of flow, 25 to 30
The equation to calculate the flow is: metres downstream of where the salt solution is
added. The normal conductivity level of the
Q = Aave x Vsurface x Correction Factor
where
water is recorded. This is called background
Q= Flow rate (m3/s) conductivity. As soon as the conductivity
Aave= Average cross-sectional area (m2) readings begin to climb, record them every 5
Vsurface= Surface velocity (m/s) seconds. This will usually happen 2 or 3 minutes
Figure 7-7 Portable conductivity meter and carefully after the salt water has been tipped in upstream.
Divide the answer by 1000 for a flow rate in
weighed bags of salt If, within 15 minutes, the conductivity has not
litres per second. Clearly, the accuracy of the

pmaher 31/05/01
7-6 pmaher 31/05/01
7-7
Site Surveying

reached at least twice the background level, Note: The mass of salt must be converted to
then the procedure must be repeated with a milligrams (grams x 103) before being used in the

Site Surveying

-6
Conductivity Conductivity
greater quantity of salt. Readings continue to be

(seconds) Ohm x 10 Ohm x 10


equation.

Change
recorded every five seconds until the

2
5.9
5.1
4.6
4.1
3.7
3.3
3.1
2.6
2.4
2.2
2.1

1.9
1.8
1.8
0.7
0.7
0.6
0.6
0.6
0.5
0.5
0.5
0.4
0.4
0.4
0.4
0.3
0.3
0.3
0.2
0.2
0.2
0.2
0.2
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
2140
-1
conductivity has returned to its background
level. This will normally be after a further 10 to

29.9
36.2
35.1
34.3
33.8
33.3
32.9
32.5
32.3
31.8
31.6
31.4
31.3
31.2
31.1

29.9
29.8
29.8
29.8
29.7
29.7
29.7
29.6
29.6
29.6
29.6
29.5
29.5
29.5
29.4
29.4
29.4
29.4
29.4
29.3
29.3
29.3
29.3
29.3
29.3
29.3
29.3
31
31
-6
15 minutes. If possible select a scale on the

Reading
meter that is just sufficient for the maximum

-1

Total
conductivity to be read. This may mean loss of
the first set of results.

230
235
240
245
250
255
260
265
270
275
280
285
290
295
300
305
310
315
320
325
330
335
340
345
350
355
360
365
370
375
380
385
390
395
400
405
410
415
420
425
430
435
440
445
Time
The meter readings are typically given in micro
Siemens (µS) which are units of conductivity
(ohms-1 x 10-6).

-6
Conductivity Conductivity

Ohm x 10
Increase

14.5
22.5
33.7
46.2
58.8
71.3
85.7
98.9
110.2
119.4
125.9
127.6
125.7
121
115.2
110.4
100.9
90.4
79.6
70.8
68.5
55.2
48.6
40.2
32.9
28.3
24.8
20.7
18.1
15.1
12.4
0.1
0.1
0.1
0.1
0.1
0.3
0.6
1.1
2.3
4.3
8.8

11
9.3
7.9
-1
STEP 4:Plot a graph of changing salt

7-9
concentration against time

100
29.2
29.3
29.3
29.3
29.3
29.3
29.5
29.8
30.3
31.5
33.5
38
43.7
51.7
62.9
75.4
88
100.5
114.9
128.1

38.5
37.1
139.4
148.6
155.1
156.8
154.9
150.2
144.4
139.6
130.1
119.6
108.8

97.7
84.4
77.8
69.4
62.1
57.5
54
49.9
47.3
44.3
41.6
40.2
-6
These readings should be plotted on squared

(seconds) Ohm x 10
paper as a graph of conductivity against time.

Reading
-1
The shape of the graph allows the results to be
evaluated. A smooth curve with a peak value at

100
105
110
115
120
125
130
135
140
145
150
155
160
165
170
175
180
185
190
195
200
205
210
215
220
225
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
least twice the level of the background
conductivity, indicates that the procedure has

Time
been successful. If the curve is badly skewed or
the readings are uneven then the procedure will
need to be repeated.

STEP 5: Calculate the area under the curve


The area under the curve must be established in

Figure 7-8 Results from the ‘salt gulp’ method of flow measurement can be analysed
order to calculate the flow rate. This is done
either by counting the squares underneath the

Thulo Phako, Basantapur, Eastern Nepal


curve or by summing the results using a

250
spreadsheet. If you count the squares then the
axis scale must be taken into account.

Area under curve = Total of condutivity change x time period


Flow Rate = mass of salt in mg x factor k / area under curve

4.77 litres per second

200
microSiemens
STEP 6: Calculate the flow rate

ohm-1/mg l-1
milligrames
The equation for calculating the flow rate is as

Flow in Forebay, Thulo Phako, Basantapur


Seconds
metres
follows:

20th May 1998

2338 watts
Power Available = Flow Rate x Head x Gravity

150
°C
M × k −1
Q=

22
50

5
25000
29.2

2.04

10698

Time (secs)
7.30 am
A
where:
Q = flow rate (l/s)

100
Salt Gulp Flow Measurement
M = mass of salt (mg)

Time period between results


k-1= conversion factor (ohm-1/mg l-1)

Background Conductivity
A= area under curve (s x 10-6 x ohm-1)

quickly using a spreadsheet.


50
Conversion Factor k
Water Temperature:

Area under curve =


Mass of salt used :
The conductivity is converted into salt

Power Available =
concentration by multiplying by a conversion

pmaher 31/05/01
Flow Rate =
factor that takes water temperature into

Net Head:
Location:

account. The conversion factor, k-1 has units ohm-

0
180

160

140

120

100

80

60

40

20

0
Time:
Date:

1
/mg l-1 and assuming a water temperature of
Salt Concentration (ohms -1 x 10-6)

22°C, the value of k-1= 2.04.

pmaher 31/05/01
7-8
Pico Hydro Designs Pico Hydro Designs

America. The turbine runner is also a small Pelton Type of Pico Type of Amount of Number of Possibility for Easy access Cost
wheel but a 12V DC car or truck alternator is Hydro electricity power houses which can using mechanical to nozzle and
8 PICO HYDRO used as a generator. The turbine is coupled to System Produced generated be electrified power turbine
the alternator using a pulley belt and mounted on Peltric Set AC 500-5000W 1 to 300 No No Low Cost
DESIGNS a simple steel-angle frame that is easy to
Colombian DC 50 - 500 W 1 or 2 Yes Yes Very Low
8.1 The ‘Pico Power Pack’ manufacture. An installation of this design in
Alternator Cost
8.2 Inspiration for the ‘Pico Power Pack’ shown in Figure 8-2. Since the turbine shaft is
8.3 The Turbine
System
horizontal, it is also possible to run other
Pico Power AC 500-5000W 1 to 300 Yes Yes Low Cost
machines with hydro-power in addition to the Pack
8.1 The ‘Pico Power Pack’ generator. This design has been used to provide
The ‘Pico Power Pack’ is a new design of pico the energy source for a mechanical refrigerator,
Table 8-1 This table compares three designs of pico hydro system
hydro-power system. It is low cost, reliable and for example. No extra control system is required
suitable for electrification of remote villages. other than the voltage regulator which is already
For information on how to manufacture this included with the alternator. Since DC (direct The ‘Pico Power Pack’ components are shown in
design, a complimentary publication entitled “The current) is generated, no frequency regulation is Figure 8-4. The generator is mounted
Pico Power Pack - Design and Manufacture” has required but the electricity must be used close horizontally on a steel angle base frame. Since
Light-weight Pulley on
been prepared. to or at the powerhouse. AC (Alternating Current) is generated, the removable extended
system is suitable for electrifying houses that case. shaft for
8.2 Inspiration for the ‘Pico Power Pack’ are up to one kilometre away from the output to
powerhouse, like with the ‘Peltric Set’. The
Rigid side-plate mechanica
The Peltric Set: Different pico hydro systems to support case drives
removable case makes it easy to inspect the and seal
have been developed in several countries to help
turbine and the nozzle and to clean them when
solve the growing demand for rural Induction
necessary. Location of
electrification of remote communities. The directly- coupled Motor
Peltric Set and FDTA pico hydros in particular Pelton runner used as a
The generator shaft is extended at the opposite Generator
provided the inspiration behind the development
end from where the turbine is attached. This
of the ‘Pico Power Pack.’ The ‘Peltric Set’ was
allows a pulley to be fitted. Small machines such Vertical
developed at Kathmandu Metal Industry in Nepal adjustmen
as mills, grinding wheels or saws can be driven Steel angle
and is shown in Figure 8-1. A vertically mounted of nozzle
with a pulley. In this way, the hydro-power can base frame
induction generator is directly coupled to a
be used for a wider range of productive
Pelton turbine. The turbine casing also forms the
purposes. The extra money made through running
base for the generator which makes the design
a small business using pico hydro-power, makes
simple and economical with material. AC
it easier to repay the cost of the scheme. Figure 8-4 The Pico Power Pack generates AC electricity
electricity is Figure 8-2 A Colombian manufacturer (right) installs a DC
and allows mechanical equipment to be driven.
generated which pico hydro system.
means that the
The pico power pack combines the low-cost Table 8-2 Suitability of different turbine designs for
power can be
steel-angle base and horizontal shaft of the pico hydro
distributed
Colombian alternator unit with the simple design
economically over
of a Pelton turbine directly driving an induction Turbine Name Head Range Cost for 5kW Maintenance Damage by Silt
hundreds of
motor used with the Peltric Set. The three Pelton Medium and Low Simple and robust so low Little effect from silt
metres. There are
designs are compared in Table 8-1. high maintenance
approximately 500
Cross Flow Medium and Low / Medium More turbine maintenance Little effect from silt
units of this type (Michel-Banki) low required than Pelton
electrifying Turgo Medium and Medium - more Low maintenance Little effect from silt
villages in Nepal at high complex than pelton
the present time. Propeller Low Low / Medium More maintenance More problems with silt
required than Pelton over time
Figure 8-1 The ‘Peltric Set’ has provided many rural Pump-as- Medium and Low More maintenance More problems with silt
villages with an economical electricity supply in Nepal
Turbine low required than Pelton over time
Francis Medium High - uneconomic at More complicated to Not for use with heavily
Low Cost DC System: A different system has
5 kW maintain silt-laden water
been designed at FDTA (Fundacion Desarollo de Figure 8-3 Installed Pico Power Pack
Technologias Appropriadas) in Colombia, South

pmaher 31/05/01
8-1 pmaher 31/05/01
8-2
Pico Hydro Designs Generating Electricity

8.3 The Turbine The correct size of Pelton Turbine Runner 9.2 Electrical Standards
This is the part of the system which harnesses
the hydro power and turns it into mechanical
The size of a Pelton wheel or ‘runner’ is measured
using the ‘pitch circle diameter’ (p.c.d.). This is
9 GENERATING National electrical standards should be followed.
In some countries, special standards for micro
(rotating) power. Several different designs of
turbine have been developed. Some of their
twice the distance from the centre of the jet to
the centre of the runner.
ELECTRICITY hydro and/or isolated village electrification have
been agreed. These standards should be followed
characteristics are compared in Table 8-2. The 9.1 Safety Warning even if they disagree with the recommendations
9.2 Electrical Standards
type of turbine that is used in the Pico Power The size of the turbine runner for a pico hydro given here. Please read the disclaimer at the
9.3 Earth-fault protection
Pack is the Pelton wheel. system is usually no more than 200mm p.c.d.. 9.4 Generator Options front of this manual.
This distance is used because this is the place 9.5 Using 3-Phase Induction Motors as Single-Phase
The Pelton Turbine where the jet strikes the buckets and Generators. 9.3 Earth-fault protection
9.6 Electronic Load Control
The Pelton turbine runner is used for many small- determines how fast the runner rotates. An earth fault occurs, for example, if a live wire
9.7 Alternatives to load control
scale hydro power systems if the head is more 9.8 Selection and Sizing of Generator, Capacitors, Cable and becomes loose inside a device and touches its
than 20 metres. It is relatively low cost to The smaller the runner becomes the faster it Protection Equipment metal case. An RCD (Residual Current Device)
manufacture but tough enough to last a long will rotate. This means that direct coupling to 9.9 Installation and Connection will disconnect the supply if a fault like this
time. The case and nozzle are also simple to build the shaft of the generator is possible. This causes a large enough current to flow to the
and even a very small Pelton turbine can work reduces the cost of the parts and makes the ground (i.e. if the case is earthed or someone
system simple to install as pulleys and belts are 9.1 Safety Warning touches the case and makes a path to earth). It
very efficiently converting most of the hydraulic
power into mechanical power to turn the not required. Electricity can be extremely dangerous. If a can also disconnect the supply if someone
generator. person comes into contact with a live wire or accidentally touches a live wire causing current
faulty equipment with a voltage higher than 50V, to be conducted through them to the ground.
it is possible for them to receive a fatal electric This reduces the risk of fatal electric shocks
shock. The electricity generating system though these can still occur if someone touches
Pelton
Runner described here is designed to operate at mains both line and neutral and is insulated from the
voltage (120V or 220V AC depending on the earth. The RCD required is one with a residual
p.c.d. line
national standards). Anyone carrying out tripping current of 30mA. It should be
Nozzle electrical installation work at these voltages connected directly to the generator as shown in
must be supervised by a qualified and Figure 9-7.
experienced electrician. In addition the following
safety instructions must be strictly followed:
• Before attempting any installation or
Water Jet maintenance, ensure that the generator is
not turning and that the flow control valve on
the penstock is firmly closed. Hang a label on
Figure 8-5 Locally Manufactured Pelton p.c.d.180 mm Figure 8-6 The Nozzle directs the water jet on to the
(Sri Lanka) the valve to warn others if maintenance is
p.c.d. line of the turbine runner
done outside the powerhouse (e.g.
How It works ”Maintenance in progress – do not operate!”).
100

A Pelton turbine has one or more nozzles that 90 200mm pcd • Earth all metal cased equipment with a
160mm pcd
direct pressurised jets of water onto specially 80
suitable earth connection (see 9.3)
70

shaped buckets that are fixed to a wheel. The 60


120mm pcd
• Never touch any electrical equipment with
Head (m)

buckets absorb the force of the water jet and 50


wet hands.
40
push the wheel round at high speed, often at 30
• Install all equipment according to
1500 revolutions per minute. The bucket shape 20 manufacturer’s instructions. Figure 9-1 3-phase RCD
is designed to divide the jet into two halves and 10
• Do not adjust or attempt to repair equipment
then to deflect the water away smoothly to stop
0
0 500 1000 1500 2000 2500 3000 3500 unless trained to do so. In addition to an RCD, earth electrodes are
it interfering with the jet or with the other
Best Efficiency Turbine Speed (rpm)
• Notices that warn of the danger of high required to allow the RCD to function. These are
buckets. A cut-away section allows the next voltages should be clearly positioned on the metal conductors that are in close contact with
bucket to move further round into position while Figure 8-7 Graph showing the operating range of three door of the powerhouse, on the case of the the soil and provide a low resistance path for the
the first is still in contact with the jet. Pelton runner diameters controller and on the front of each load current to the ground. Connection to an earth
limiter. electrode is required near the generator. Earth
electrodes are also required if any of the
electrical loads have metal cases (electric
cookers, for example). The resistance of the

pmaher 31/05/01
8-3 pmaher 31/05/01
9-1
Generating Electricity Generating Electricity

earth should not be greater than 1kΩ if an RCD coil of wire can be buried underneath the robust and very reliable. However, they are not It is important that capacitors of the correct
with a 30mA tripping current is used. foundations. Do not bury under the foundations the only generators that are used for hydro type are chosen and properly connected
Measurement should be carried out with an if the soil type is very dry as the resistance is power projects. Different generators have been otherwise the generator could fail to operate or
earth tester. The manufacturer’s instructions unlikely to be low enough. compared in Table 9-1. Situations where it may overheat. The manufacturer who supplies the
should be carefully followed to ensure accurate Method 3 A third method is to use a copper be more practical to consider other generators turbine and generator
results. Earth testers are expensive (typically plate measuring at least 500mm x 500mm. This in addition to the induction generator include the should also supply
$600 to $1000). Consider hiring or borrowing should be buried in a hole at least one metre following: capacitors of the
unless you do a large number of schemes. deep in an area which remains moist. 1. Very low cost power systems for battery correct size. If the
charging or lighting only in a single dwelling next individual components
Three methods of installing an earth electrode to the powerhouse. Consider a DC generator. are bought separately,
are described: 2. Schemes required to power motor loads then follow the advice
Method 1 The easiest electrode to install is greater than 15% of the generator rating are given in Section 9.8.
usually a 1 metre copper-coated steel rod that is best supplied by synchronous generators. For
Figure 9-5 Power
driven into the ground near to the powerhouse. more information about motor starting using Capacitors suitable for
The electrode is connected to the neutral induction generators, read Section 13. connection to induction
terminal at the generator using a low-resistance generators
heavy-gauge copper cable (e.g. SWG 10mm²) and 9.5 Using 3-Phase Induction Motors as
a brass, connecting nut that slides over the rod Single-Phase Generators.
and allows the cable to be clamped in place. Two
Purpose built induction generators are expensive Single Phase
shorter rods can be used and connected Supply to
but three-phase induction motors can be used as Induction
Loads
together if it is not Generator
Figure 9-3 Installation of a copper-plate earth generators when run in reverse. These are mass- Windings
possible to drive the electrode, Multiple earth cables have been soldered in
produced and so are quite cheap and easily
rod 1 metre into the place to reduce the resistance and increase the
reliability.(Nepal)
available.
ground. They should
For most small electrification projects, a single-
be spaced at least
phase supply is required. It is quite easy to
two metres apart 9.4 Generator Options Figure 9-6 Single-phase supply from 3-phase motor
produce a single-phase supply from a three-
and connected with
phase motor. This is done by connecting unequal
the same earth
amounts of excitation capacitance across the
cable.
winding of the machine as shown in Figure 9-6.
Cover (e.g.large, This is called C-2C because across the second
flat stone )
generator phase, twice the amount of
Serviceable Plastic capacitance is connected. On the third phase no
50 cm cable connection drainage
made to rod pipe capacitors are connected.

to earth
connected device Type of Source Typical Cost for Speed (rpm) Disadvantages Advantages
Generator 3kW Machine Options
Induction Standard Low: 1000, 1500, Needs correctly sized Widely available, slow speed
Figure 9-4 3-Phase Induction Motor (7.5 kW) with industrial $200 - $250 3000 capacitors connected to ranges, robust simple
1 metre

Copper earth
rod driven into double-ended shaft, used as a generator. (Nepal) motor used as a operate as a generator. Poor construction. Can withstand
the ground generator motor starting ability overspeed. Cheaper than
Induction generators and synchronous synchronous generators
generators produce AC power. Alternating Synchronous Commonly used Low – medium: 3000, Brushes and slip rings wear out Higher efficiency than
current (AC) and direct current (DC) are - Brushed with petrol or $300 - $500 sometimes and require replacement. Must induction at part-load and
explained in the Appendix. The main advantage of diesel engines. 1500 be strengthened for over- better motor starting
speeding capability
AC is that the power can be transmitted over
Synchronous Occasionally High: 1500, 3000 Not widely available. Repairs As synchronous-brushed but
Figure 9-2 A 1m copper-coated steel rod can provide a quite long distances. This makes AC suitable for - Brushless used with $600 - $1000 are often complex / expensive. with better reliability
suitable earth electrode. village electrification projects because the diesel engines Must be strengthened for

Method 2 A second method is to use a loose coil electrical loads (such as light bulbs) are usually over-speed
quite spread out and often a long way from the DC Car or truck Not Applicable Car > 2000, Not suitable for village Very low cost, no controller
made of about 10 metres of SWG 10 bare copper alternator Max. output ≈ truck > 1200 electrification. Restricted required.
wire. This should be spread out and buried in a generator.
500W range of appliances. Brushes
hole about one metre deep. If the soil is damp Induction generators are good for providing and slip rings wear out
where the powerhouse is constructed, then the electricity in remote areas because they are
Table 9-1 Comparison of Generators suitable for use with Pico Hydro Turbines

pmaher 31/05/01
9-2 pmaher 31/05/01
9-3
Generating Electricity Generating Electricity

strongly recommended. This is explained in more


9.6 Electronic Load Control detail in Section 15.3.
This switch is used to The IGC keeps the The ballast load is If the voltage and frequency are not kept at the
Total
disconnect the voltage constant switched on and off by right level then the user loads connected to the Power
1000W
distribution system when the load on the the IGC. It uses the generator can be damaged. Power
sent to
before the generator is power not required by Too High Too Low Ballast
generator changes. = 400W
Voltage Motors, televisions and Most appliances
switched off. other loads
radios can be damaged. have reduced
the lifetime of performance or fail
lightbulbs and heaters to operate
becomes shorter.
I.G.C. User Load
Frequency Will not usually cause Can cause internal e.g. 600W
Ballast Heater
problems with most circuits to overheat
consumer loads. Except and fail in radios,
speed dependant motor TV’s and motors.
loads.
User load Figure 9-8 Division of power between user load and
Table 9-2 Effect of voltage and frequency variation on ballast
isolation
Ballast trip lamp loads
switch
L The Ballast
The ballast meter The speed of the turbine changes when the load
To user load
N indicates how much The ballast is an essential part of the electronic
connected to the generator changes. For
power is used by the control system. Great care must be taken with
example, if more lights are switched on then the
A 3-phase induction ballast load. the choice and connection of the ballast. The
speed of the turbine will decrease. Since this
motor is used as a most common source of problems with induction
Over-volt trip lamp change of speed affects the voltage and
generator generator controllers is with the ballast.
frequency, the load on the generator must be
kept constant or the flow of water through the
Air heaters
Induction Generator Motor nozzle must be adjusted. The most reliable
3-Phase Convection heaters are the best type of ballast
protection Capacitors
method of controlling the load and keeping the
L RCD to use for pico hydro schemes. They are usually
switch These capacitors are voltage and frequency constant is by using an
reliable and have the longest life. They are sold
needed to make the electronic load controller.
as electrical room-heaters. Designs that can be
induction motor work
mounted on the wall are the safest type. A low-
as a generator. The speed of an induction generator can be kept
cost ‘DIY’ design of ballast using cooking rings is
near constant by using an IGC (Induction
shown in Figure 9-9. This will work as a radiant
2C N Generator Controller). This device sends any
heater when wall mounted on a suitable frame.
unused power to a ballast (or dump load) so that
The cable insulation and frame must be able to
Earthing Point the total load on the generator remains constant.
withstand very high temperatures. Radiant
For example, if the generator produces 1000
heaters generally have a shorter life than
A Motor Watts and the total load connected by the
A copper earth electrode is convection heaters because they operate at a
Protection Switch consumers is only 600W then the IGC will
The Residual Current higher temperature.
required to allow RCD’s and control the switching on and off of the ballast so
Device gives earth- protects the
lightning arrestors to work. that the remaining 400W is also dissipated. If
fault protection generator and Water heaters are often used as ballast loads
It is essential to have an the consumer load changes at any time, the IGC
improving consumer capacitors from although experience has shown that these often
earth connection near to will automatically adjust the power diverted to
safety. overload. cause problems on small schemes and therefore
the powerhouse. the ballast so that the voltage and frequency are
they are not recommended. Cheap water-heating
kept constant.
elements and steel ballast tanks often corrode
rapidly. The temperature requires monitoring and
The IGC cannot, however, prevent the generator
cold water must be introduced to the tank
from becoming overloaded. For example, if the
before the water boils. Automatic flow control
generator is producing 1000W but more than
systems can be designed to achieve this but they
1000W of load is connected then the voltage will
are complicated and are not cost-effective for
fall and the IGC is unable to prevent this. To
pico hydro.
Figure 9-7 Connection of generator and controller avoid overloading, the use of load limiters is

pmaher 31/05/01
9-4 pmaher 31/05/01
9-5
Generating Electricity Generating Electricity

Ballast trip: The ballast is automatically 9.8 Selection and Sizing of Generator, increased frequency in order to generate at 245
Steel angle
frame disconnected if the ballast is too large or if the Capacitors, Cable and Protection Volts.
ballast connections are shorted out. The ballast The terminal box of many induction motors

350mm
Cooking
Equipment
Ring trip lamp(s) will light. allows connection in a star or delta pattern giving
Figure 9-7 shows how the generator, capacitors
Lightning protection: Many IGC designs contain the possibility of two voltage ranges. The voltage
Wire mesh controller and ballast are connected. The are a
1100mm
guard a varistor that minimises the risk of damage to range for star and delta is given on the
number of considerations when specifying a
the controller due to indirect lightning strikes. nameplate. Either of the following is suitable for
Figure 9-9 Low cost ballast using electric cooking rings motor to use as a generator.
Meters a 220V scheme:
Low Cost Ballast Design The IGC will function without meters fitted. Either 380-415V star / 220-240V delta
a) Voltage range: The voltage rating of the Or 220-240V star / 127-139V delta
A ballast of this design should be mounted on the However, these enable the user to maximise
three-phase induction motor to be used as a
wall. The cables must be protected using a heat- their use of the power available and are helpful
single-phase generator must be carefully
for identifying the cause of electrical problems. Note: Motors of 3kW and above are often
resistant sheath and connections made to the selected. If the rating is too high, the generator
Ballast meter: This meter indicates the wound for 660–720V star/ 380–415V delta.
heating elements from below. will be unstable. If the rating is too low it will
percentage of power being dissipated in the These are not suitable as 220–240V generators.
not be possible to achieve the required
ballast load. It is the most useful meter because Most manufacturers will supply motors wound to
Calculating the power dissipated generator voltage without overheating the
it indicates how much spare capacity there is and the voltage you require, with a longer delivery
Cooking rings are available with a range of power windings.
how close the generator is to being overloaded time.
ratings and are cheap and robust. By connecting Motor Rating (kW)
two rings in series the voltage is halved and the (when the controller is functioning normally but U1
Type of 0.55 - 1.1 1.5 - 3.0 4.0 - 7.5 W2 U1
lifetime is considerably extended. Since the the meter reads zero).
motor
voltage is halved with series connection, the Voltmeter: This is useful for setting the
2 pole VGEN+6% VGEN+3% VGEN
current is also halved and so the power operating voltage on the controller and for
4 pole VGEN+9% VGEN+6% VGEN+3%
dissipation is therefore quartered. For example, observing the voltage if the generator becomes W1 U2
overloaded. It should be rated for 300V AC and 6 pole VGEN+12% VGEN+9% VGEN+6% V2 V1
a ballast to dissipate 3.0kW would require 8 W1 V1

rings rated for 1.5kW. That is four pairs of connected to the supply output terminals so that Table 9-3 Recommended motor voltage. STAR DELTA

series connected rings across the controller or it is protected by the over-voltage trip.
Note that the operating voltage of the
two of the units shown in Figure 9-9. Figure 9-11 The two voltage ranges are possible with
generator (VGEN) is usually set slightly higher
9.7 Alternatives to load control many induction motors by connecting the windings in
than the national single-phase voltage to allow 'Star' or 'Delta'
V/2 x I/2 = P/4 = 375W dissipated per ring if It is tempting to operate the generator with no for the voltage drop on the distribution system.
series connected in pairs. 8 x 375W = 3.0kW. load controller present. Two options are Table 9-3 shows the recommended motor b) Frequency: The frequency rating should be
available. voltage, in relation to the generator voltage, for the same as that required by the loads (i.e. 50Hz
The connection of the cooking rings for this Fixing the Load different motor sizes and speeds. This will give or 60Hz). For a direct drive system, the
example is shown in the circuit diagram below. One method of controlling the voltage and stable operation and a near optimum efficiency. generator speed must be matched to the turbine
frequency is to have a load connected that The reason why smaller and slower speed speed. Note that the generator speed is always
exactly matches the output of the generator. generators require higher motor voltage ratings about 10% higher than the motor speed. Shaft
However a fixed load is difficult to achieve if is to compensate for their lower power factors. speeds for common sizes of induction generator
IGC Ballast more than one consumer is connected and The acceptable limits for the voltage rating are given in the table below. Select a machine
Connections appliances, such as refrigerators, that are +/-6% of the recommended voltage. with the correct number of poles.
continually switch on and off cannot be used. It Example: If a 4-pole 3kW motor is to be used to No. of poles 50 Hz 60Hz
is not recommended generate 245 Volts, using Table 9-3, the 2 3.120 rpm 3,750 rpm
Manual Control of the Turbine Speed recommended motor voltage is 245V +6%, i.e. 4 1,560 rpm 1,875 rpm
3 kW ballast using 8 cooking rings 6 1,040 rpm 1,250 rpm
rated for 1.5 kW each. Manual control requires the presence of an 260 Volts. The acceptable limits of motor
operator to correct the flow of water to the voltage are 245V (recommended value –6%) and Table 9-4 Examples of induction generator shaft speeds
Figure 9-10 Electrical connection of cooking ring ballast 275V (recommended value +6%).
(4 pairs of series connected rings) turbine and control its speed whenever the load
is changing. This method is not recommended for The effect of increasing the voltage of the c) IP Number: Select a motor which is IP 55.
Protection features of the IGC achieving good voltage and frequency regulation motor can be achieved by increasing the The IP number is a measure of how easily liquid
Over-voltage trip If the voltage rises too high, and is costly in the long term due to operator frequency by the same percentage. Varying the or dust (e.g. flour) can enter the machine. IP 55
then the supply will automatically be wages. frequency has drawbacks as shown in Table 9-2. models are resistant to either and therefore
disconnected to protect the consumer loads. The However, small increases of up to about 6% are suitable for hydropower applications.
over-voltage trip lamp(s) will light to indicate acceptable. For example, if 230 Volts is a
this condition. standard voltage available for the 3kW motor d) Insulation Class: Always select the
described above, this can be used at 6% highest available winding insulation class. The

pmaher 31/05/01
9-6 pmaher 31/05/01
9-7
Generating Electricity Generating Electricity

two most common types are B and F. Class F has the precise current rating of the generator. where: Additional electrical protection
a longer life than Class B. For the same Typical current ranges for motor protection π = 3.1416 1. A lightning arrestor should be fitted close to
operating temperature, Class F insulation will last switches are 2-4A, 4-6A, 6-10A, 10-16A, 16-20A, f = frequency of the generator (Hz) the powerhouse. This will protect the generating
four times as long as Class B. 20-24A. For the 2.2kW motor in the example, a k depends on the voltage rating of the motor equipment from high voltages caused by nearby
6-10A motor protection switch would be ideal. which is used. As described earlier, the lightning strikes and act in addition to the
d) Power Rating: Estimate the maximum The alternative to the motor protection switch is acceptable limits for the motor voltage rating varistor that protects the IGC (see Section 16).
electrical power output, Pmax, by calculating the the Miniature Circuit Breaker (MCB). However, are +/-6% of the recommended value (given in
hydraulic power and assuming an overall these have the disadvantage of being only Table 9-3). The multiplying factor, k, can be 2. The cables in the powerhouse must be
efficiency of 50% (unless actual efficiencies are available with fixed current ratings and so found from Table 9-6: protected from mechanical damage by using
available). Use Pmax and the generator voltage cannot be set to the line current of the motor. cable conduit. The conduit must be fixed to the
(VGEN) to work out the operating current. Recommended voltage is k = 0.35
Figure 9-13 Miniature generator connection box and to the controller/
Circuit Breaker used (as in Table 9-3)
capacitor casing with threaded fittings. This
Recommended voltage k = 0.3
Pmax provides an additional layer of insulation,
I op = 1.1 × +6% is used
VGEN Current rating Recommended voltage
prevents the cables from being pulled
k = 0.45
-6% is used accidentally out of their connection boxes and
where Iop = maximum operating current of the cable
provides a watertight connection.
VGEN = generator voltage The cable current Table 9-6 Values of multiplying factor, k.
rating should be at
3. An isolation switch is needed to disconnect
The (rated) line current of the motor, Iline, must least 40% greater The value of C, as calculated above, should be the distribution system as the generator must
be greater than or equal to the operating than the maximum rounded up to the nearest 5µF and the 2C (2 x be started and stopped without user load
current: current rating of the calculated value, C) rounded down to the connected. Also it may be necessary to
Iline ≥ Iop the Motor nearest 5µF. It will probably be necessary to disconnect the user loads when driving
Protection Switch adjust these values further in order to obtain mechanical loads. A mains switch or an MCB can
Example: A 2-pole generator is to be used on a or MCB. Conduit should be used for the the exact frequency required. The total be used as an isolation switch.
pico hydro with a maximum electrical power powerhouse wiring. The current ratings given, capacitance C and 2C should be made up of a
output of 1,500 Watts. The national voltage is apply to single-core, PVC insulated cables which number of individual capacitors. This will allow
220 Volts and the generating voltage 220V + 6%, conform to BS 6004, BS 6231 and BS6346. some adjustment of the C-2C to be made during 9.9 Installation and Connection
i.e. 233V, calculate Iop: CSA of copper Current capacity installation. The voltage rating of the capacitor In addition to Figure 9-7 the following guidelines
Iop = 1.1 x 1500/233 = 7.1 Amps. cable (mm2) (Amps) should be comfortably greater than the should be used when installing and connecting the
1.0 mm2 13.5A maximum generator voltage, e.g. capacitors generator and additional electrical equipment.
A 2.2kW 2-pole motor is available which, when 1.5 mm2 17.5A should be rated for 380V AC if generating at Connecting the generator
delta connected, has a voltage rating of 240Volts 2.5 mm2 24A around 220V. They should preferably have a
(the recommended voltage as given in Table 9-3), 4.0 mm2 32A As described under “Generator Selection” in
screw fitting underneath to allow them to be
and a line current of 7.6 Amps. This motor is 6.0 mm2 41A Section 9.8, an induction motor with either of
securely mounted (see Figure 9-5). The ‘motor-
ideal for use at this site. 10.0 mm2 57A the following connection possibilities is suitable
run’ type of capacitors should be used as these
for a 220V scheme:
Over-current protection Table 9-5 Current carrying capacity of single-core are rated for continuous use. ‘Motor-start’
The generator electric cables enclosed in conduit capacitors are only designed for intermittent use
a) 380-415V star / 220-240V delta
windings and and are therefore not suitable. For information
Selection of Capacitors b) 220-240V star / 127-139V delta
cables must be about connection of the capacitors, see Section
The excitation capacitors (C-2C) required to 9.9.
protected from
enable a 3-phase induction motor to work as a Using motor a), the metal links should be
excessive
single-phase generator will determine the arranged in the terminal box to give the delta
currents. These Selection of the IGC
frequency of the electricity produced. The connection. Using motor b), the links are
can cause them to
capacitance required to generate at a particular The power rating for the controller must be arranged to give the star connection. This is
overheat and fail.
frequency varies between one motor and another equal to or greater than the maximum electrical illustrated in Figure 9-14. The three cables to
High currents
and depends on whether the motor voltage rating power output of the generator, Pmax. A good the RCD are tightened under the terminal
also damage the
is higher or lower than the recommended value in quality IGC from a reputable manufacturer must washers at the generator.
capacitors.
Table 9-3. The basic rule for calculating the be used as it cannot be repaired by the operator.
Figure 9-12 Motor
Protection Switch required capacitance C is as follows:
For maximum I line
protection a motor protection switch should be C ( µF ) = k ×
VGEN × 2πf
used as the tripping current can be adjusted to

pmaher 31/05/01
9-8 pmaher 31/05/01
9-9
Generating Electricity Generating Electricity

Motor windings Problem Solution


W2 U1 A IP 44 only Use IP 55 which have Most large capacitors have two connections on
No seal on better protection against each side and cables may either be soldered in
W2 U2 V2
B
connection box liquid and dust
place or attached using suitable connectors that
C Loose connections Tighten connections every 6
W1 U2 U1 V1 W1 are usually clamped onto the end of the wires
V2 V1 causing over-heating months and use ‘shake-
DELTA Metal links across here proof’ washers at terminals with the aid of crimping pliers. Connectors and
for DELTA connection
D Lack of colour coding Cables of different colours the appropriate tool should be used if they are
should be used to avoid available as soldering is impractical in isolated
Metal links here
U1 only for STAR wiring errors. locations and prevents on site adjustment.
connection
E Pipe used as conduit Use cable conduit and
W2 U2 V2 Damaged capacitors are also difficult to replace
conduit connectors to
terminal box. (see photo) if the connections are soldered. When crimping,
U1 V1 W1 ensure that the connections are very tight, both
W1 V1 Table 9-7 Problems with generator connections
STAR between the wire and crimp and crimp and
Terminal box of induction motor Installation of the RCD capacitor terminal.
This should be mounted on the wall between the Follow these instructions for IGC installation:
Figure 9-14: Make sure the metal links are arranged • IGC must be installed vertically, in a well-
generator and controller. Ideally it should be Installing the IGC.
correctly in the terminal box to give STAR or DELTA
enclosed in a purpose built housing with a ventilated and dry location.
connection with the correct voltage range. The IGC is normally housed in a metal case that
transparent front allowing the operator to see • Connect according to labelling of terminals
is mounted on the powerhouse wall. The case
when a trip occurs. and label all connecting wires.
Connect the earth electrode to any of the three should preferably have a hinged door and be
• The case must have ventilation holes that
terminals if the delta connection is used. For a large enough to comfortably accommodate the
Connecting Capacitors allow a flow of cool air to pass over the
star connected motor, use any of the three capacitors in addition to the IGC circuit board.
finned heat sinks of the IGC. The air vents
separate terminals but not the star point Connect the 3-phase RCD (2C, L, N) and motor
should be above and below the IGC, covered
attached to the metal links. The earthed protection switch as shown in Figure 9-7. The
with wire mesh and a solid protective cover
terminal becomes the neutral (N) and the capacitor connections will depend on the number
raised above the surface that prevents entry
remaining two terminals are labelled live (L) and of capacitors that are used. For example, a
of dripping water (as shown in Figure 9-18).
2C. It does not matter which way round L and 2C particular generator requires C=52µF, 2C=104µF.
• Check that no cables are touching the heat
are as this will be determined when the The capacitors available are 5µF, 15µF and 30µF.
sinks as the insulation could be damaged
generator is commissioned. Rounding C up to 55µF and 2C down to 100µF
when the controller is operating.
allows these to be used and connected as shown
• If housed in a metal case, then the case must
in Figure 9-16. The 100kΩ / 2Watt resistors are
be earthed.
used to discharge the capacitors if the
• The ballast heater must not be installed
A protection switch or RCD trip, preventing shock.
underneath the IGC but above or at the side.
The case must be locked, with a ‘high voltage’
B 2C 30µF 30µF 30µF
5µF warning label on the door. A second label should
5µF
100K/2W
state that the box must not be opened unless
Connections
from MCB
2C
the IGC has been isolated from the Generator
L 30µF
15µF 5µF 5µF
Connection
Connect Water guard
C from RCD
C to IGC

100K/2W
N
D
Figure 9-16 Suitable connection of capacitors if C= 52µF
Wire mesh
Connecting several capacitors of different sizes
E
together, to make up the total values of C and
2C, enables small adjustments to be made and Figure 9-17 Correctly installed IGC and Capacitors
Controller Case
Figure 9-15 Connections inside generator terminal box. allows the frequency to be corrected when the
Several problems have been identified and solutions given generator is commissioned. Removing small The trip lamps on the IGC may be mounted are
in the Table 9-7 amounts of capacitance increases the frequency. usually mounted the circuit board and in the door Figure 9-18 Suitable design of air vent for controller and
of the metal case. capacitor casing. A vent should also be provided at the
If the C capacitance is reduced by a certain bottom of the case to allow air-flow over the components
value then 2C should be reduced by
approximately twice that value.

pmaher 31/05/01
9-10 pmaher 31/05/01
9-11
Flow Management Flow Management

Filters 10.2 Canals


10 FLOW wire filter a) to forebay

flushing pipe
MANAGEMENT metal clip wire mesh coil

10.1 The Intake concrete weir


b) to turbine
10.2 Canals
10.3 Forebay Tanks
10.4 Reservoirs holes drilled in pipe
(half nozzle diameter)

10.1 The Intake


Figure 10-5 Filter designs for a) intake and b) penstock
The intake of pico hydro schemes can be a simple
and inexpensive arrangement. Non-permanent Figure 10-2 An intake using a small concrete weir is Filters are required to prevent pipes that are
Figure 10-6 Canal installed in a difficult location
solutions are favoured over elaborate weirs due useful if the flow is very low during the dry season used for pico hydro installations from becoming supplying a small hydro scheme for local electrification
to their lower cost and greater flexibility. The blocked with materials such as silt, wood and (Peru)
Construction of Small Concrete Weirs
effect of floods must always be considered when leaves. There are two situations where a filter is
designing the intake. The proportions for small concrete or masonry A canal can be a low cost method of conveying
required:
weirs should follow approximately those given in water from a source some distance to a more
Pipe intake – for ample flows 1. the intake pipe leading to a canal, forebay or
Figure 10-3. Often large stones cemented favourable intake position. For some sites, this
Boulders used to divert part of a river flow into reservoir as illustrated above.
together can be used for the construction of the can really improve the economic viability by
a simple canal or submerged length of pipe as 2. the entrance to the penstock pipe (see
weir. The strength of the structure is reducing the length of penstock and cable
shown in Figure 10-1 are often sufficient. With Section 11).
significantly improved by using a gabion. This is a required. At other sites a canal is an expensive
such simple and inexpensive solutions, storm For the first case, the size of the holes in the
wire cage that holds the structure together. It addition and can often require regular
damage can be repaired with local materials. filter is not important. The only thing to
is particularly useful where strong flows are maintenance due to leaks, soil erosion and
Though careful construction is required to consider is how to prevent the pipe from
expected. The wire mesh is usually made from 2 landslides.
prevent frequent repair being necessary. The becoming blocked. One method of building a
or 3mm diameter wire with a mesh size of 50mm suitable filter is to use a tube of wire mesh. The
pipe must sometimes be quite long to ensure that
to 100mm. Using a canal and deciding on the route it should
the entrance is higher up than the exit to the tube can be fixed to the pipe with a metal clamp
take, are decisions that must be considered
canal. Flexible pipe is easier to use than rigid such as a jubilee clip.
0.4 x h carefully. The following factors are important:
pipe and it should be anchored in the flow with rock concrete
• Local experience and history with building and
large stones. The entrance should be raised In the second situation, when the filter is
managing similar water systems such as
slightly off the bed of the river or stream. This positioned at the entrance to the penstock, it is
irrigation canals.
h (m)

will prevent silt or debris from blocking the important that the holes in the filter are smaller
• The availability of cheap / free labour to dig
entrance. than the nozzle at the other end. Actually, they
and maintain the canal
flushing intake pipe should be about half the diameter of the nozzle
pipe • Soil type, lining requirements and cost of
0.50m

water level 0.7 x h to be sure that any particles that enter the pipe
transporting materials such as cement.
can not cause a blockage at the other end. (If
• The cost of other options such as a longer
Figure 10-3 The construction of a weir should follow the the nozzle becomes blocked then there is a
above proportions. penstock / longer distribution cable compared
intake pipe river bed danger that the penstock will burst due to the
to the cost of a canal. The use of low-
sudden pressure.) A filter with small holes can
Figure 10-1 The simplest intake design is a pipe anchored pressure pipe to convey water to the intake
in the flow be made out of a piece of plastic or metal pipe
may also be a lower cost alternative.
that is capped at one end. Lots of holes are made
• Could a new canal serve a dual purpose,
using a correctly sized drill. It is important that
Weir intake – for low flow sites irrigating land during the dry season in
the total area of the number of holes drilled is
A small weir can be constructed out of concrete addition to supplying the turbine?
more than the area of the pipe to make sure that
to ensure that all the available water is diverted • Are there any existing (or abandoned)
enough water can be drawn in. The filter is
during the dry season. This may be a practical irrigation canals that could be directly used
threaded or clamped over the pipe to ensure a
solution at some sites. The flexible pipe, which or improved or extended if necessary?
tight seal.
removes the water, is set into the weir. The If the canal is lined with concrete or stones and
foundations and the sides of the weir should be cement, then its strength and reliability will be
joined to solid rock to prevent water from improved. However, such a lining will increase the
leaking round and eventually undermining the Figure 10-4 A concrete weir can be used to form a small cost considerably. In many remote areas this will
structure. reservoir (Nepal). not be practical because of the difficulty of

pmaher 31/05/01 pmaher 31/05/01


10-1 10-2
Flow Management Flow Management

transporting building materials. Lining a canal 2. Design of canal cross-sectional area (A) Seepage (Figure 10-7) or small wooden aqueducts (Figure
also increases its efficiency. Water can travel at Earth lined canals loose a significant proportion 10-8) can sometimes be used to bridge difficult
higher speed without causing the sides to erode Naturally, the canal cross-sectional area must be of the water due to seepage. In sandy soil areas sections of the route.
so for a particular volume flow rate, the bigger than the cross-sectional area of water expect at least 5% to be lost through seepage
dimensions can be reduced (see Table 10-1). needed to give the flow required. The extra per 100m (e.g. 0.5 l/s for a flow rate of 10 l/s)
Canal design height (called the freeboard allowance) is usually Providing additional water is available, it is worth
about 30%. This reduces the risk of the canal sizing the canal for a larger flow rate than that
The flow of water in a canal depends on:
walls being damaged by overfilling. required by the turbine. Assume that an
• The speed or velocity of the water
The sides of an earth canal should slope additional 10%-20% will be required. This will
• The cross-sectional area of water
outwards. This reduces the risk of the walls allow for some loss through small leaks as well as
The equation for flow rate is
collapsing due to the erosion caused by the flow seepage. Sometimes water in the canal will also
Q = vA
of water. It is possible to construct a canal with be used for a number of purposes such as
where:
Q = flow rate (m3/s) vertical walls if it is strengthened by lining the irrigation or domestic supply. The requirements
(multiply by 1000 for flow in litres per second) sides with stones and cement or with concrete. should be taken into consideration at the design
v = velocity (m/s) In this case the top and bottom dimensions are stage. Figure 10-8 A wooden aqueduct can be used to transport
A = Cross-sectional area of water (m2)
the same. However, masonry and concrete linings water in the canal across uneven ground
Canal Construction.
are expensive and are rarely cost-effective for
1. The velocity of water flowing in a canal (v) The route taken by the canal must be carefully
pico hydro schemes.
depends on the slope of the canal and the selected. If possible the following areas should canal
‘roughness’ of the material which has been Top be avoided:
used to line it. • Excessively porous ground
There is an upper limit to the velocity for H • Rocky areas which prevent excavation
different building materials. Above this value the • Steep and unstable sections
sides can quickly become eroded.
Bottom
Canal material Max. velocity to avoid Sealing the canal with clay or concrete in porous
erosion in shallow canals areas may be an option but large rocky outcrops stone wall
Sandy soil 0.4 m/s In order to simplify the process of canal design, should be avoided. Steep sections and storm
Clay soil 0.6 m/s suitable dimensions for the cross sectional area gullies are also difficult but in many rural areas,
Concrete / masonry 1.5 m/s are given for different flow rates in the ingenious solutions have been found. Canals have,
Table 10-1 Velocity limits for shallow canals (<0.3m following table. The head loss is the drop for been successfully constructed in some very
deep) 100m of canal. If the required length of canal is difficult locations (see Figure 10-6 and Figure
200m then multiply the head loss by 2 and build 10-9). These require careful planning, local
From Table 10-1 it is apparent that for earth
with this drop over its length. motivation and persistence but not necessarily
lined canals, the maximum velocity of the water
Canal lining and minimum dimensions great expense.
is much less than for those with a durable lining.
10 l/s Sandy soil Clay soil Concrete/
If the water contains silt then there is also a masonry
lower limit to the velocity of 0.3 m/s. This is to Height H 13 cm 15 cm 15 cm
prevent the silt being deposited and blocking the Top Width 59 cm 44 cm 29 cm
canal. If the water is clear then the lower limit Bottom Width 6 cm 13 cm 29 cm
is not important. A low velocity means that the Head Loss 1.6 m 1.3 m 1.4 m
(100m length)
drop required over the length of the canal is
20 l/s
small. For this reason, the canal dimensions given Figure 10-9 and Figure 10-10 show a raised canal that
Height H 19 cm 22 cm 21 cm
in Table 10-2 have been calculated using a design runs on a narrow ledge underneath a vertical rock face.
Top 84 cm 62 cm 42 cm
The canal has a masonry lining and is supported by a high
velocity of 0.3 m/s. This allows the head loss in Bottom 9 cm 18 cm 42 cm stone wall underneath.
the canal to be reduced and maximises the head Head Loss 1.0 m 0.8 m 0.9 m
available for the penstock. (100m length) Low Pressure Pipe
30 l/s Figure 10-7 A length of pipe can be used to bridge a An alternative method to convey water to the
In the following examples of canal dimensions a Height H 23 cm 27 cm 25 cm difficult gulley with a small canal. The pipe is secured intake is to use low-pressure, plastic pipe. This is
Top 103 cm 75 cm 51 cm with rocks on either side.
roughness of 0.07 has been assumed. This is available in some countries as drainage pipe. Low-
Bottom 11cm 22 cm 51 cm
suitable for a shallow canal with some vegetation. Head Loss 0.8 m 0.6 m 0.7m When crossing a storm gulley, for example, it is pressure pipe is cheaper than penstock pipe
The roots of vegetation growing along the canal (100m length) particularly important to allow adequate drainage because the walls are thinner. It will often be a
cause some friction but they are useful because for rainwater that could otherwise destroy the cheaper alternative than a concrete lined canal.
Table 10-2 Suitable minimum canal dimensions for
they support the sides. different flow rates and lining materials sides of an earth canal. Short lengths of pipe

pmaher 31/05/01 pmaher 31/05/01


10-3 10-4
Flow Management Flow Management

• type of ground and soil the silt. This is rarely necessary for pico hydro
• cost of labour and local skills providing that a sluice gate or a flushing pipe is
However, it is highly recommended that all included (see Figure 10-13). This makes the job
designs include an overflow facility and some of cleaning out the silt much easier.
means of draining to allow the tank to be
cleaned. Overflow
Figure 10-13 Suggested design of forebay tank fed from If the forebay becomes full, the water must
escape without causing damage. The overflow can
Direction of flow be a notch or channel cut into the lowest wall of
in irrigation canal the forebay (see Figure 10-15). An alternative
method is to use a pipe that combines the
Figure 10-11 Land drainage pipe overflow and the flushing facility. This is
illustrated in Figure 10-13. The vertical pipe can
be removed from the elbow to flush out the Figure 10-15 Construction of stone forebay (Kushadevi,
Some consideration needs to be given to the Flushing Pipe Nepal)

1.0m
best diameter and the slope of the pipe since tank. This example shows a forebay that is fed
this will affect the flow rate and head loss. See by an irrigation canal although the water could
Section 11. equally well be provided by a low-pressure pipe.
The flow can be diverted into the forebay when
10.3 Forebay Tanks required. Otherwise the water always continues
Penstock Pipe to flow down the canal.
Whichever method is used, the overflowing
water should be directed away from the forebay,
Height preferably into another stream or a ditch.
0.5m

difference
(100mm) Forebay Construction
Providing that labour is available a small forebay,
using stones and clay as a seal, is not expensive Figure 10-16 The flow of water into the forebay is
to construct. The intake to the penstock is controlled by a sluice gate. An overflow is cut into the
an irrigation canal. wall on the downhill side so that excess water is returned
easier to secure if stones are used in the
to the stream without undermining the masonry. A
Depth of Water construction of the walls. If the forebay flushing pipe, sealed with a wooden bung has been
The depth of water in the forebay tank should frequently overflows then the clay will be quickly incorporated at the lowest part of the tank.
be sufficient to cover the penstock by 4 times eroded and will require regular repair.
its diameter. The penstock should also be Cement and stones or concrete are used to
approximately one diameter clear of the bottom. construct forebays with a longer life and greater 10.4 Reservoirs
erosion resistance. A suitable method for
Example cementing stones or bricks to line a forebay,
canal or reservoir is shown in Figure 10-14
What depth should the overflow in the forebay
be set at if the penstock is 75mm in diameter?
Figure 10-12 A small forebay is suitable where flow is
Answer Mortar for cementing stone
sufficient throughout the year together during construction
Depth above penstock = 4x75 = 300mm
of civil structures should be
The forebay tank provides a sufficient depth of Depth below penstock = 75mm mixed to the ratio of 1:4
water to ensure that the top of the penstock is Penstock diameter = 75mm (cement to sand).
always covered. In some cases the penstock is Therefore approximate depth of overflow A more water resistant
extended to the intake and then no forebay is = 300+75+75 = 450mm cement, ratio 1:2, can then
required. A forebay is required where a canal is be used for pointing
Silt between the stones and Figure 10-17 A small reservoir provides low-cost energy
used or if water from more than one source is preventing leaks. storage which can be useful during the dry season.
Since the water in the forebay tank is slow
collected. (Sankhuwa Sava, Eastern Nepal)
moving, silt falls to the bottom where it forms a
The design of the forebay may vary depending on The forebay can be enlarged to form a small
thick layer of mud. This can block the penstock
factors such as: Figure 10-14 Masonry techniques for pico hydro civil
reservoir if the flow during the dry season is
if it is allowed to become too deep. Larger hydro structures
• accessibility of location insufficient to operate the turbine continuously.
schemes often have desilting basins to remove
• availability of building materials

pmaher 31/05/01 pmaher 31/05/01


10-5 10-6
Flow Management The Penstock

For example, water is stored up during the day for two hours of mechanical power to drive a saw turbine. The higher the pressure, the thicker
and night when the turbine is not in constant use in the workshop during the mornings. the pipe walls must be and the more expensive it
and then released to provide power for evening 11 THE PENSTOCK becomes. The pressure of the water in the
lighting. How big does the reservoir need to be? 11.1 How the penstock works penstock depends on the head. If pipe with a
Flow in during driest period = 2 l/s 11.2 Penstock Selection pressure rating which is too low is used, then
11.3 Connecting the Nozzle
Water storage can add a useful degree of Flow into penstock = 5 l/s there is risk of a burst. If the pressure rating is
11.4 Penstock Installation
flexibility and security to the scheme if either Maximum period of operation = 5 hrs too high then money has been wasted. The ideal
of the following are true: Shortfall in supply during this period penstock will be low pressure at the intake and
11.1 How the penstock works
1) The water will be collected from more than = 5 - 2 = 3 litres per second thicker at the nozzle where the pressure is
one source, some of which is likely to be The penstock is simply a long pipe that fills with greatest.
intermittent. The reservoir must have enough capacity to water. The weight of the water in the pipe Selecting the correct pressure rating
2) The water is or will soon be used for other supply an extra 3 litres per second during the provides the required pressure at the nozzle to
The pressure at any point in the pipe can be
purposes apart from hydro-power, such as period of operation. drive the turbine. This pipe may run directly
easily calculated if the head at that point is
irrigation. Volume of water required as storage: from the water source to the turbine or from
known. Refer to Figure 11-1 in order to
the end of a canal that brings the water closer,
understand how the pressure in the pipe changes
The storage requirements are easily calculated if 5hrs = 5 x 60 x 60 saving on the cost of a longer pipe. A filter is
with the head.
the flow required by the turbine and the lowest = 18000 seconds connected at the intake end. At the turbine,
Plastic pipe has a built in safety factor of
expected flow into the reservoir are known. The Volume = 18000 s x 3 litres per second there is a valve used for turning the water flow
between 1.5 and 2.5 to allow for pressure surges.
manufacturer should provide information about = 54000 litres or = 54 m3 on and off. After the valve is the nozzle which
This means that the pipe can be used up to the
the flow requirements of the turbine. The (1 cubic metre = 1000 litres) concentrates the water into a high-pressure jet.
manufacturers pressure rating (providing that
reservoir should be sized according to the
the joins between the lengths have been
minimum expected flow. This must be measured What dimensions should the reservoir be in 11.2 Penstock Selection
correctly made and the pipe is firmly anchored
during the driest part of the year using one of order to store 54 m3? The penstock is often the most expensive
or buried). The flow control valve must be turned
the techniques described in Section 0. component of a pico hydro scheme. It is
slowly on and off to minimise sudden pressure
Alternatively it must be estimated by relying on The reservoir will be allowed to fill up overnight therefore important that the pipe used is
surges. If these guidelines are followed and the
local knowledge. so that the saw can be driven in the morning. carefully chosen.
pipe is used up to the manufacturers pressure
There are three things to consider when buying
rating then costs will be kept to a minimum
The ground is rocky at the proposed site of the pipe for the penstock:
without a safety compromise.
Example Storage Capacity of a Reservoir reservoir and it is unfeasible to dig a reservoir • the material
that is more than 1.5 m deep. • the internal diameter - depends on the
A 1.5kW turbine and generator have been
Suitable dimensions would therefore be 1.5 length and flow rate. The importance of pipe diameter
selected for the site in Western Nepal
metres depth x 6 meters width x 6 metres • the pressure rating - depends on the net The diameter is important because it affects the
described in the example on page 7-1. The head
length. head. power available to the turbine. The larger the
has been measured at the site and found to be
1.5 x 6 x 6 = 54 m3 diameter, the more power there will be. Although
70 meters after friction losses in the penstock
The Pressure Rating the pipe may appear smooth, it has some surface
have been taken into account.
An alternative solution for this village is to roughness that slows down the water. This
supply the reservoir with water from a spring slowing down is called ‘frictional loss’. The
In order to generate this power with this head
that is some distance away. They can transport Pressure (bar) = Head(m) x 0.0981 frictional loss is expressed in metres of head
the turbine manufacturer recommends a flow of 10m
approximately 1 litre per second though a narrow Use at least 2 bar Pressure here loss and is greater when the speed of the water
5 litres per second. Measurements of the flow in pipe for this section = 20 x 0.098
but inexpensive pipe from the second source 20m = 1.96 bar is greater. The water speed and therefore the
the nearest stream to the village have been (low pressure)
during the driest period. What is the new Pressure here frictional loss increase if either the turbine
taken during the driest part of the year, after 30m = 40 x 0.0981
storage capacity required? nozzle is made larger or the penstock diameter
several weeks of no rain and found to be only 2 Use at least 4 bar Penstock = 3.92 bar
pipe for this section (medium pressure)
Pipe is made smaller. Frictional loss also increases in
litres per second. This is also the lowest flow 40m
[Answer = 36 m3 so suitable dimensions would be proportion with the penstock length. If a pipe of
that has been observed in the stream according Pressure here
1.5m x 6m x 4m] 50m = 60 x 0.0981 larger diameter is used then the frictional loss is
to local knowledge (thought to be reliable as far Use at least 6 bar
= 5.89 bar
(high pressure) less but the price increases significantly.
pipe for this section
back as 10 years). During the rest of the year, 60m Typically, if the diameter of a pipe is doubled,
however, a flow exceeding 5 l/s is available. X
Nozzle then the price is increased four times. The
Storage will be required for the dry periods to
frictional loss however is about 30 times less!
enable the scheme to supply electricity to the Figure 11-1 Penstock pressure rating
village for 5 hours of lighting in the evenings and
The penstock is designed to convey water under
pressure in a safe and efficient manner to the

pmaher 31/05/01
10-7 pmaher 31/05/01
11-1
The Penstock The Penstock

Selecting the Optimum diameter Head loss is required which will be approximately three materials have been compared in Table “butterfly” or “globe” valves that allow the flow
20% of 70. 11-2. to be reduced more rapidly. Grease should
First, find out the flow rate required for the
70 x 0.20 = 14 metres regularly be applied to the threaded stem of the
turbine. This information should be provided by
The values in the table are for pipes of 100m in 11.3 Connecting the Nozzle valve to prevent corrosion and eventual seizing.
the manufacturer. If not, use the method based
length. We require 300 meters therefore the The turbine nozzle should be threaded on the
on the nozzle diameter which is described in the
values in the table must be multiplied by outside to allow the valve to be screwed into
complimentary manual for manufacturers of the
300/100 = 3 place. The manufacturer should supply a
Pico Power Pack. Also needed, is the total length
Looking along the column for a flow of 6 l/s and compatible valve with the turbine. PTFE tape or
of pipe required (the distance taken by the pipe
calculating the head loss: paste is very useful to help lubricate and
from the forebay to the turbine) and the total
300 m of 50mm pipe = 3 x 17.07 = 51.21 metres waterproof threaded connections and should be
head available.
300 me of 63mm pipe = 3 x 5.48 = 16.44 metres applied if available. Similarly on the penstock
300 m of 75 mm pipe = 3 x 2.36 = 7.08 metres side, a suitable threaded connector is required.
Look at Table 11-1. First find the flow rate
This may be provided on a reducer as illustrated
nearest to the one required in the left-hand
Clearly the best choice is 63mm (2.5”) pipe which Figure 11-2 Reducer, gate valve and nozzle in Figure 11-2 which can then be attached to a
column. The recommended compromise between
gives a head loss near to 14 metres A gate valve is recommended to turn on and off larger penstock diameter using a flange coupling
friction loss and cost of pipe is 15%-20%
the water supply to the turbine. These are (see Figure 11-10).
frictional loss. All the head losses given are for
100 metres of pipe. These figures must be b) If HDPE pipe of only 100mm and 50mm widely available and because they take more time Table 11-1 Head Loss per 100m length for different
multiplied by [required pipe length / 100] in diameter were available, what would be the most to close, they reduce the likelihood of large diameters of plastic pipe at different rates of flow

order to give an estimate of frictional loss at the cost-effective combination? ‘surge pressures’ from developing in the penstock
site. This loss should normally be no more than Answer: that can cause it to burst. This can occur with
25% of the total head. If the head loss is 20%, 80 metres of 50mm pipe (for high pressure
then the net head will be 80% of the gross section )
= 0.8 x 17.07 = 13.6 metres Flow ( l/s ) Internal Pipe Diameter (Nominal Bore)
(total) head:
220metres of 100mm pipe (for low pressure
50mm (2”) 63mm (2.5”) 75mm (3”) 88mm (3.5”) 100mm (4”)
NET head (available to turbine) section)
= GROSS head (total head) = 2.2 x 0.58 = 1.28 metres
Total head loss = 13.6 +1.28 2.0 2.28m 0.75m 0.33m 0.15m 0.08m
– head loss due to friction
= 14.9 metres
4.0 8.03m 2.62m 1.13m 0.52m 0.28m
Sometimes a head loss different to 20% should Penstock Materials
be chosen. For example, if the gross head For pico hydro schemes, the penstock pipe is
available at the site is scarcely enough to run the 6.0 17.07m 5.48m 2.36m 1.09m 0.58m
usually made from plastic. HDPE (High Density
turbine, then a penstock only resulting in a 10% Polyethylene) is used in many countries. It is
8.0 29.09m 9.31m 3.97m 1.83m 0.98m
frictional loss could be considered. Alternatively, particularly suitable because it is both flexible
if the distance between the site for the and weather resistant. This type of pipe is 10.0 44.19m 14.05m 5.98m 2.73m 1.48m
powerhouse and the forebay tank is long and usually coloured black. Internal diameters up to
head is more than necessary, a loss of 30% could 75mm (3”) are flexible enough to be coiled up 12.0 61.9m 19.69m 8.38m 3.82m 2.05m
be tolerated if it meant a significant saving in which makes transportation easier. Common
cost with sufficient power still being provided. internal diameters (or ‘nominal bore’) used for
Penstock Transport to Installation Joining sections Lifetime Roughness
pico-hydro are 50mm, 63mm, 75mm, 90mm,
Material site
Example :Selecting penstock diameter 100mm and 110mm.
Dia. 75mm or less Easy because Requires skill to fusion Very weather Low so not much
HDPE
a) Which is the diameter of penstock that will can be coiled flexible weld resistant and head loss.
give a head loss of around 20% and be the most Alternative materials are PVC (Polyvinyl-chloride) tough
and steel. PVC is widely available for use as PVC 6m lengths only More difficult Easy with pipe Degrades in Low so not much
cost effective. The following information is
because quite connectors and PVC sunlight unless head loss
known: domestic waste pipe. However, PVC pipe and
rigid cement but high cost painted
The turbine selected requires a flow rate of 6 fittings for domestic use are rated for low Difficult in Rigid and heavy Welding or bolting Corrodes Medium for new
Steel
litres per second pressures only and therefore not suitable for remote areas therefore flanged sections gradually and pipe becoming
The gross head is 70 meters penstocks. Low-pressure PVC pipe is suitable for because of difficult together. Not cost- requires worse with
use in the forebay (flushing pipe and overflow). weight effective for pico hydro maintenance corrosion
The penstock will be 300 meters in length
Steel is commonly used for larger hydro when Table 11-2 Comparison of penstock materials

Answer: the flow and pressure in the pipe are higher. The

pmaher 31/05/01
11-2 pmaher 31/05/01
11-3
The Penstock The Penstock

entering the pipe sections. The penstock should When a bead has formed all the way around on
11.4 Penstock Installation follow a downhill course where ever possible and both pipe sections, the plate is removed and the
must at no point be higher than the penstock two lengths are forced together. An even weld
STEP 1 LAYING OUT entrance in the forebay. In some situations it will ‘bead’ around the whole circumference indicates
be necessary to lay the pipe in a trench to a successful join. The pipe must not be moved
maintain the correct gradient. In other areas until the joint is completely cool. Teflon is a heat
the pipe will require supporting above ground proof, non-stick material which is available in
level. How this is achieved will depend on the size fabric form. A Teflon bag can be used to cover
of pipe and the height above ground. This is when the hot plate and prevent the plastic pipe from
the advantages of HDPE pipe become apparent. sticking during the initial softening. The plate
Its flexibility means that it is considerably should be at 220ºC for softening HDPE. Heat
easier to install than either PVC or steel. temperature indicating crayon (‘Thermochoc’ in
Nepal) are available which change colour when
Figure 11-7 The metal plate is heated in a small fire the correct temperature has been reached. A
small amount is applied to the plate during
First the plate is heated over the embers of a heating. The correct plate temperature is often
small fire learned by experience however, as the crayons
Figure 11-3 Delivering pipe sections to the site. are not always readily available.
Check that the pipe that has been delivered is
the correct type and length. The route for the STEP 4 CONNECTING TO THE
penstock from the intake to the generator TURBINE NOZZLE
should have been marked out and vegetation
cleared where necessary. Lay out the pipe Figure 11-5 Pipe sections that span gaps must be
sections along the proposed route, making an supported at the correct height.

initial check that the quantity ordered is Pipe above 75mm in diameter requires more
sufficient support than smaller sizes. Initially, sticks can
be used to help bridge difficult areas.
STEP 2 PREPARING THE ROUTE
Figure 11-8 Both sides of the pipe are held against the
hot plate.

The two ends of pipe are inserted into either


side of the jig with the heated plate in between.
Figure 11-10 Penstock connection using flanges
The plastic is allowed to soften evenly at the end
of both sections by holding the lengths firmly in The connection between the penstock and the
place. turbine is important because it is here that the
water is at its highest pressure. Sometimes the
penstock is connected directly to the gate valve
Figure 11-6 The supports must be suitably reinforced that controls the flow. A reducer is usually
before filling the pipe.
required as the penstock diameter is generally
Before the pipe is filled with water, more secure larger than the valve. A suitable method of
foundations, using stones and mud for example, connecting a plastic penstock to a steel reducer
must be constructed. is illustrated in Figure 11-10. An HDPE pipe
flange fitted with a steel ring has been fused to
STEP 3 JOINING THE PIPE the end of the penstock. This can then be
Figure 11-4 The penstock can be laid in a trench and securely bolted to the reducer after inserting a
HDPE pipe sections can be joined at the site
then buried when the installation is complete to secure it gasket.
using hot fusion. The tools required are a steel
The pipe can be laid on the surface of the ground An ‘Excel’ software program has been developed
plate with diameter slightly larger than the pipe
providing that obstructions such as rock and Figure 11-9 The plate is removed and the two sections to help design the penstock and calculate the
being joined and a jig to support the two are brought together forming a neat bead around the
branches have been cleared. Care should be head loss in different pipe sections. For a copy
sections. pipe.
taken to prevent mud, stones and debris from of the program, please contact the editorial
address.

pmaher 31/05/01
11-4 pmaher 31/05/01
11-5
THE Powerhouse THE Powerhouse

in a similar way. Soil dug out of the trench Windows: • The roof must be watertight and pitched to
should not be used for this purpose. improve drainage.
12 The • A footing is then required on which the walls
• Essential to provide light and ventilation.
• Not facing the prevailing wind direction. • It should preferably be made of a fire-proof
will stand. This should be twice the width of material such as clay tile or corrugated steel
POWERHOUSE the walls and stepped up at the top as shown
• Should be secured with wire mesh or wooden
shutters to prevent unauthorised entry (not and definitely be waterproof.
12.1 Construction in Figure 12-2. Suitable materials for the necessarily with glass.) • It should extended beyond the walls to
12.2 Layout footing are concrete, brick and stone • Window area should be 1m2 for every 10m2 of prevent water from entering the window
12.3 Planning the Installation. depending on what material is used for the spaces.
floor space.
walls. • Ventilation spaces should also be left under
Door:
12.1 Construction Floor: the eaves to allow circulation of air if the
• The door to the powerhouse should open windows are closed.
• Raised above ground level to prevent flooding outwards for safety and should be lockable.
during heavy rainfall. • It must be large enough to allow access for all Sealed with mortar
• Lined with concrete to ensure secure equipment including possible future
under eves
on this side
Wooden poles for
foundations for the turbine and generating acquisitions. support of corroga
iron roof.
equipment. • It should prevent entry of rainwater.
• Sloped towards the tailrace so that any
Tailrace:

3.00m
spillage drains away.
• The tailrace should be lined with concrete to

2.00m
• Large enough area to allow for all round
a depth of 100mm inside the powerhouse.
access to turbine, generator and control
equipment. If any mechanically-driven • The concrete lining should extend a minimum
of 1m outside the powerhouse and must be
machinery such as grain mills are also housed
leak proof in order to protect the powerhouse Concrete floor
or likely to be in the future, then the floor (100mm) on a bed
foundations. of gravel or sand.
area should be increased accordingly. Depth determined by
nature of ground

FOUNDATIONS AND FLOOR Figure 12-5 Recommended powerhouse construction


OF POWER HOUSE
methods
Figure 12-1 Typical stone powerhouse in Nepal
Wall from cement blocks,
A good design of powerhouse will protect the bricks or stone
12.2 Layout
turbine, generator and other equipment over its
lifetime, which should be a minimum of 15 years. Concrete Floor ( 100mm)

The construction of the powerhouse will vary Small stones Flow out
depending on local availability of materials, local
preferences and the local climate. However, Tailrace
Controller
cutting costs by building an insubstantial Ground Level Filling of sand Shelf
or fine soil Grain mill
powerhouse is false economy. Constant
Figure 12-3 Power house under construction, Nepal
maintenance and repair work will be required Footing of Ballast Heater
1m bricks or large stones
otherwise the life of the generating equipment Roof:
Concrete, brick or stone
will be considerably reduced. Equally, an over- Window grill with
Nail through Corrugated sheets
built powerhouse will be more expensive than Firm soil or rock at ridge overlap twice
wooden shutters
base of trench
necessary. The following guidelines will help to
construct a building that will be a suitable Figure 12-2 Recommended construction of foundations
compromise between cost and quality for most and floor
Wooden
Batten Location of
locations. Walls: turbine and
generator
Foundations: • Should be at least 2m high at the lowest point Penstock
• A foundation trench should be dug down to and constructed to allow roof to be pitched. Cement bricks used for construction
of walls: 400mm x 200mm x 200mm
solid rock or otherwise to a depth of one • Should be thick enough to allow adequate Flow in

metre below each wall. It should be twice as protection from storms. Provision should be Figure 12-6 Suggested layout for powerhouse components
wide as the intended wall. Any soft areas at made for mounting control box, ballast
the bottom of the trench should be dug out equipment, capacitor box etc. Suitable
and filled with stone or concrete. The Figure 12-4 Suggested techniques for assembly of
methods are the use of wooden panels and
corrugated steel roof
trenches should be levelled as far as possible built in shelving.

pmaher 31/05/01
12-1 pmaher 31/05/01
12-2
Selecting The Loads

problems with domestic


6. Commissioning

Resolve any electrical


types of electric lighting which are most

Cover penstock with

Train operators and

distribution system

Table 12-1 The installation has been divided into six phases to help the developer plan the order of activities. Work down the columns and then across the table, some activities can
Check operation of
commonly used for domestic purposes.
THE Powerhouse

13 SELECTING THE

connections.
turf or soil

managers
Incandescent lighting. Light bulbs of this type
LOADS use a filament made of wire that heats up and
13.1 Electrical loads gives off light when a suitable current is passed
13.2 Motor-driven loads through.

Connect the distribution system


Check penstock and fittings for

Test run turbine and generator


to check for correct operation

Check operation of mechanical


13.3 How to avoid problems with motor starting

Check correct operation of


13.4 Mechanical end-uses Bulb
13.5 Pulleys and Belts
5. Testing

controller and ballast.

to the load controller


13.6 Procedure for choosing pulleys and belts:
Gas
13.7 Belt tensioning and supporting fixtures
The LOADS are the devices which are connected
Filament
to a pico hydro system and which work as a
result of the power generated by the turbine.

loads
leaks
They can be divided into electrical and
mechanical loads.
necessary. Otherwise lay pipe to necessary and cover particularly

Connect protection devices such


Line the forebay or reservoir as

12-3
stone and cement and complete
any building work at the intake
Bayonet fitting
Lay the penstock pipe in position Connect penstock sections and

Screw fitting
Connect excitation capacitors,
load controller, ballast and
necessary with concrete or

13.1 Electrical loads


4. Connection

Figure 13-1 Incandescent lamps


negotiating any difficult ground join to flow control valve

Support penstock where

as RCD(s) and lightning


protection devices to Electrical loads use the electricity produced by Incandescent light bulbs are commonly used
the generator. Many kinds of electrical loads can because they are cheap and easily available.
if made of PVC.

be used with a pico hydro system. A few common However, they have quite a short lifetime and
generators

electrical loads are listed below. They have been

arrestors
make inefficient use of the electricity. The
divided into two groups: those that use a motor problem is that only 8 to 12 % of the electrical
and those which do not. There are additional energy is converted to light. The rest escapes as
considerations when connecting motor driven heat. Although there are a few lighting
Assemble turbine and generator

structure and built supports for

Excavate and position the earth


Construct the walls and roof of
Position intake and dig canal if

mechanically driven machinery

loads to a pico hydro scheme. These are


marked if forebay is required

load-limiters. Connect service


3. Construction and

forebay area which has been

applications which use this waste heat such as


electrode. Attach a cable to

Position domestic loads and

cables to main distribution


explained in Section 13.2.
such as rocky outcrops or

chicken hatcheries, in most cases light bulbs of


base frame on support
Assembly

this type are a highly inefficient way of using the


Non-motor driven loads, for example: electricity which has been generated. In
the powerhouse

• Lighting addition, constant heating and cooling of the


sunken areas

powerhouse

• Battery chargers filament eventually causes it to burn out and


system.

• Radios then the bulb has to be replaced.


• Televisions
Motor driven loads, for example: Tubular Fluorescent Lighting. This type of lamp
Make any final adjustments to
or
foundations for the powerhouse,
Clear the site and construct the
site taking into account any late

turbine and generator. Consider

Identify a suitable location for

together, erecting poles where


materials and equipment at the

• Food processors and liquidisers has electrodes at either end of the tube. These
allowing correct positioning of

if earth connection is in base.

an earth connection near the


powerhouse. (Unless earth is
vegetation for the penstock

• Refrigerators
Connect distribution cables
forebay
digging a shallow channel if

be carried out in parallel with others which will save time.

release small particles called electrons which


buried in the foundations)
2. Preparation

Clear a path through the


Order deliver and store

• Ventilation Fans cause ultraviolet light to be produced from the


reservoir and excavate

• Workshop tools (grinding wheels, drills, saws, argon gas that is held inside. UV light is
planners, sanders)
of

converted into visible light by a fluorescent


modifications

coating on the inside of the glass.


positioning
necessary

necessary
12.3 Planning the Installation.

The type and number of electrical loads that can


Fluorescent powder
be connected depends on the amount of
electricity being generated. The following
sections discuss the technical considerations for
Ensure that sufficient gradient
Finalise the design particularly

Check site plan including length


concerning the locations of the

design, and mark out positions

and size of distribution cable


of powerhouse, penstock and

exists for water to flow into

each type of load more carefully.


Make minor adjustments to

forebay or reservoir from

Distribution System

Lighting Glass seal


required before delivery

Electrodes
powerhouse, forebay or
1. Planning

forebay or reservoir
reservoir and intake

pmaher 31/05/01

Lighting is often the primary use of the


intake pipe or canal

electricity that is generated from a pico hydro


system. The provision of electric lighting in an Figure 13-2 Tube lights
unelectrified rural community can improve the
Tube lights require an electrical circuit called a
quality of life by a large margin. There are three
ballast in order to control the electric current

pmaher 31/05/01
13-1
Selecting The Loads Selecting The Loads

flowing through the lamp and to give a high therefore have an adverse effect on the life of f = frequency (Hertz)
voltage at the electrodes. An inductive ballast (a the windings or circuitry because of over- Figure 13-3 0182
. × 0.87
coil of wire on an iron core) was commonly used heating. Small rises in frequency or reductions in Metalised
C= = 2.27 µF
6.3 × 220 × 50
up until recently when electronic ballast’s were the rated voltage will probably be tolerated. Polypropylene
To fully power factor correct this fluorescent
developed. Electronic ballast’s can operate at a Lighting Capacitors
for power factor lamp, a capacitance of 2 micro-Farads (µF)
higher frequency and this helps to improve the The lifetime of CFL’s and tubes is also reduced if correction of should be connected across the supply. Under
performance and increase the life of the lamp. they are switched on and off many times. This fluorescent lamps correction of the power factor is recommend
makes them unsuitable for places where a light is when the precise value of capacitance for full
Compact Fluorescent only required for a short period e.g. a cupboard power factor correction is not available (see
Lamps (CFL’s)- or a toilet. note.)
These have been
developed more Power Factor Correction of Fluorescent Lamps. b) In order to power factor correct four lamps
recently and are The term ‘power factor’ is explained in Appendix per house then the capacitance required is
already widely A on Electricity. Power factor correction means 4 x 2.27 = 9.08 µF. Two 4µF capacitors
available. They work in to adjust the power factor of the system nearer
Example Capacitance required for power connected in parallel across one of the lamps is
the same way as to one. The power factor already has a value of
factor correction of inductive loads the best solution in this case. If capacitors of
fluorescent tubes Electronic one for incandescent lamps so no correction is only one or two sizes are available, then connect
except that the tube ballast required. For fluorescent lamps which contain A pico hydro scheme has 100 houses connected
inside to the appropriate number of lamps to bring the
is narrower and folded inductive ballast’s, the power factor can be as to a 2.5 kW generator. In each house there is a
power factor to 1. Always connect capacitors
over several times. low as 0.5. This has two impacts on a scheme 20 W fluorescent tube. The power factor of
directly across the inductive load, otherwise
The electronic or where large numbers of the lamps (50+) are these tubes (according to manufacturers’
there will be too much capacitance connected
inductive ballast is connected: information) is 0.5. If the scheme operates at
when other lamps are switched off.
usually contained in the base of the lamp. The 1. Power losses in the cable increase due to 220V and 50 Hz :
Note: Do not over correct the power factor.
design allows the lamp to be fitted to a large amounts of reactive power which are a) What value of capacitance should be
This will reduce the supply frequency and
conventional socket, with either a bayonet (BS) drawn. connected to each tube to bring the power
increase the current in the wiring.
or Edison screw (ES) fitting. You can usually tell 2. Low load power factor causes the generator factor up to a value of 1?
if an inductive ballast is fitted as the lamps are frequency to rise and could cause de-excitation b) If the capacitance is considerably cheaper
Voltage Rating of Capacitors
heavier. of the windings of the induction generator. This when purchased in larger units and each house
The price of capacitors depends on the voltage
would cause the generator to stop working until has four 20W fluorescent tubes, what size of
rating as well as their size. (i.e. the number of
Reliability of Fluorescent Lamps some of the lamps are disconnected. capacitor should be chosen to correct the
Electronic circuitry in fluorescent lamps makes micro farads) The voltage rating of capacitors
Power factor can be improved by connecting complete domestic lighting circuit?
them sensitive to the quality of the electricity should be at least that of the loads to which
capacitors across the inductive loads. The
supply. If the voltage and frequency vary by they are connected. Capacitors with higher
amount of capacitance required will depend on a) How much current does each fluorescent tube
large amounts then it is possible that the lamps voltage rating than the load will have a longer
the number of fluorescent lamps which are require?
will be less reliable and have a shorter life. lifetime. For small loads such as lights, which are
connected. Ideally each house with fluorescent Power
Otherwise their life should be at least 5 to 10
I= used intermittently and for short periods, it is
lamps should have its own capacitors. Larger V × cos φ
times longer than an ordinary light bulb. It is best to choose capacitors with the same voltage
capacitors cost less per micro Farad ( F) than 20
therefore important that the voltage and I= . A
= 0182 rating (i.e. 220V) as these will be the cheapest
smaller ones so it is wise to power-factor
frequency are kept near their rated values. 220 × 0.5 option. For power factor correction of larger
correct all the lamps in one house with a single
loads such as motors it is worth spending more
capacitor. Metalised polypropylene lighting
What capacitance is required to power factor on capacitors with a higher voltage rating. For
The rated value of voltage and frequency is the capacitors that are available in size from 4 F are
correct given this current value? example, capacitors rated at 415V would be a
value that the device has been designed for. This ideal for power factor correction of small
good choice for a 220V motor.
is written on the side of the bulb. lighting loads.
I × sin φ Advantages and disadvantages of the three
C=
6.3 × V × f types of lamps are compared in Table 13-1.
The life of a ballast (and hence the lamp for Although it is difficult to estimate the size of
CFL’s because the ballast cannot be replaced the inductive loads on a system until it is built,
separately) will be reduced if the frequency is the approximate amount of power factor C = Capacitance required (Farads)
less than the rated value (50 or 60 Hz) or if the correction required should be estimated at the I = Current rating of device (Amps)
voltage is higher than the rated value (110V, initial planning stages and priced in to the cos φ = Power factor
120V, 220V etc.). Both these conditions cause scheme costs. V = nominal voltage (Volts)
the amount of current drawn to increase and will

pmaher 31/05/01
13-2 pmaher 31/05/01
13-3
Selecting The Loads Selecting The Loads

Advantages Disadvantages Multiply the amp-hours by the battery voltage to


Incandescent Low cost, widely available therefore easy to ! Low efficiency, made worse if the voltage falls. Charging Lead-acid Batteries Safely get Watt-hours.
lamps replace. Therefore, not the best choice when the power
• Explosive gases are produced during the
Not damaged by low voltage operation available is limited.
Power factor of 1 ! Short life-span (750-1000 hours) charging of vented lead-acid batteries so the Example
Fluorescent Relatively Low cost ! Require different socket (can also be an advantage, presence of flames or sparks nearby is
How long could a 12V 60Ah motor vehicle battery
Tubes Widely available see below*) extremely dangerous and must be avoided.
(ordinary type) Good efficiency so a good choice for village ! Larger than other types of lamp for the same output. be used to power a black and white television
• Charge batteries in a well ventilated area
lighting using pico hydro ! Must be disposed of carefully as contains mercury which requires a 40W 12V DC supply before
• Use gloves and goggles when handling to
Long life-span (5000-8000 hours) vapour. recharging if the maximum depth of discharge is
! A separate ballast is required. This will require avoid burns from sulphuric acid which forms
20%.
periodic replacement in addition to the tube. the electrolyte. Wash any spillage’s
! May require power factor correction. immediately with clean water.
! Not suited to frequent on/off switching. Answer:
• Even quite flat batteries can cause a fire if
Compact Very good efficiency and are a good choice for ! Initial cost is more than previous types although Storage capacity of battery
Fluorescent a scheme where the voltage and frequency are prices are falling.
the terminals are accidentally shorted out
= 12 x 60 = 720 Watt-hours.
Lamps (CFL’s) correctly controlled. ! More sensitive to variations in the supply which can with a cable or other metal conductor.
Useful capacity before recharging =
Fit into standard sockets affect lifetime and performance. • Always disconnect the charger before
Ballast is usually contained in the lamp. ! Require careful disposal (contain mercury vapour).
=720 x 20% = 144 Watt-hours
disconnecting the batteries under charge.
Very long life-span (8000-10000 hours) ! May require power factor correction Hours of TV viewing (40W TV)
! Not suited to frequent on/off switching. Battery performance = 144 / 40 = 3hrs 30mins
Table 13-1: Different types of electric lighting compared
Lead acid batteries should not be fully Emergency Lighting
discharged as this damages them. Motor vehicle
*A pico hydro scheme which provides lighting can become overloaded if CFL light bulbs fail and are then replaced by incandescent A product sold for emergency lighting has
batteries are only intended for shallow
lamps (these are cheaper). An additional advantage of tube lighting is that there is less temptation to replace with incandescent recently become available in many countries. This
bulbs since the sockets will also require changing to allow them to be connected. discharging and ideally should not be discharged
is a tube light with a built in battery and
Batteries store low-voltage dc electricity which by more than 20% of their capacity. A small
charging unit. In areas where the grid is
is different from the higher voltage ac battery charge indicator (quite cheaply available
Battery Charging unreliable, these lights are popular because they
electricity which is produced by the generator. in some countries) is useful to monitor this.
can be used during power cuts and then plugged
Battery chargers are useful in rural areas that Deep-cycle batteries can be discharged up to
Two common types of rechargeable batteries, into the mains for recharging when the grid
are not grid -connected. Using hydro-power as a 80% of their capacity without damage.
used for providing power to small electrical comes back online. They can also provide a useful
charging source, they can be left running for
appliances in remote areas, are lead-acid and lighting solution in rural areas and be charged
long periods and, depending on their design, may The reliability of a battery reduces the more it
nickel-cadmium (Ni-Cad). Lead-acid batteries are when required from an induction generator.
charge several batteries at the same time. is cycled (charged and discharged). Generally a
used to provide 12V electricity in most motor Since they are also portable, they remove the
Batteries can be used by people who live too far new, good quality motor vehicle battery will fail
vehicles and often used for lights, radios and need for torches.
away to be connected directly to the generator. after 200 cycles to 50% of its capacity. A
TV’s in rural homes because they have relatively
A battery allows the use of simple electrical suitable depth of discharge for a motor vehicle
high energy storage and are widely available.
loads and can be recharged when required for a battery is therefore is 20%. This will prolong its
There are different types of lead-acid
small payment that is much less than the cost of useful life. Deep-cycle batteries can be cycled
batteries. The older motor vehicle type, allow
disposable batteries. many more times, typically 1000-2000 times at
the electrolyte to be topped up with distilled
water. Modern designs are maintenance free and 80% depth of discharge. This means that they
sealed to prevent spillages. A more expensive will last many times longer than a motor vehicle
type of lead acid battery is the deep-cycle battery even though they are more expensive
battery. If available, these provide a more initially.
reliable and long lasting form of energy storage
than motor vehicle batteries. Ni-Cad are the opposite to lead acid in that they
perform better and last longer if fully
discharged before re-charging. This is Figure 13-5 Example of emergency lighting sold in Kenya
Nickel Cadmium batteries are more expensive with 2 x 8W fluorescent tubes and plug for recharging
per unit energy stored and used to power small advantageous as no charge monitoring required (Cost = $35).
electrical goods such as torches and radios. They and the natural tendency is to use batteries until
give a smaller voltage than lead-acid batteries they are fully discharged. Radio and Television
but are easier to handle and more reliable. Battery Capacity After lighting, radios or televisions are probably
Capacity indicates how much energy a battery the most common domestic loads. The main
Figure 13-4 Battery charging with hydro power (Peru) Battery chargers convert the electricity from can store. A 60 amp-hour battery can deliver one considerations when operating these loads from
AC to DC and prevent overcharging which is amp for 60 hours or 20 amps for 3 hours. a pico hydro system or other isolated electricity
important to maintain the life and reliability. supply are as follows:

pmaher 31/05/01
13-4 pmaher 31/05/01
13-5
Selecting The Loads Selecting The Loads

• Operating at under-frequency or over- the system. These problems can be minimised by c) Starting different types of loads
voltage is harmful. The life of internal careful planning. The type of load connected, affects how easy a Many money-making activities which are useful to
components such as transformers will be motor is to start. The turning force (or torque) the community such as grain milling, need
shortened due to excess current. 13.3 How to avoid problems with motor required, for example to start turning a mill is mechanical power. In areas that are serviced by
• Small increases in frequency should not be starting different from the force required to begin a national electricity grid, the mechanical power
harmful turning a fan. A high starting torque is needed to is usually provided by electric motors. It is still
To avoid problems with motor starting, the
• Protect expensive televisions with a separate start the mill in order to overcome the friction possible to run some motors using the electricity
following should be considered:
voltage regulator. of the grinding wheels. generated with a pico hydro plant, but there are
a) the size of motor which is connected to the
• Operating from a DC supply such as batteries significant constraints on this as explained in the
generator
will not cause damage providing that previous section.
b) the type of motor which is connected For some types of machines that are easy to
electricity at the correct voltage is supplied Fortunately with pico hydro-power, there is also
c) the type of load which is driven by the start, like fans, the motor power can be
and the TV or radio is designed to work with an opportunity to drive mechanical loads directly.
motor increased to 20% of the generator power.
batteries. The mechanical energy of the turbine runner can
d) the length and size of cable between the Machines that can be sized for 20% of the
be transferred directly to the loads without
motor and generator. generator output include the following;
conversion into electricity. This is usually
a) Size of motor • Fans
achieved by means of pulleys and belts. The main
• Grinding wheels (for tool sharpening)
Motors use much more power at starting than advantage of using mechanical power directly is
• Electric drills
13.2 Motor-driven loads when running. Also when switched on they cause that much larger loads can be driven than would
an initial drop in voltage which reduces their otherwise be possible with electrical motors. For
Many modern appliances are driven by electric
starting torque. If too large a motor is switched d) Position of the motor a comparison of electrical and mechanical drives,
motors. However, connecting motor driven loads
on , the starting torque will be insufficient to The motor is likely to be one of the largest look at Table 12.2.
to an isolated electricity supply requires
turn the shaft. single loads in the distribution system. It is If the mechanical power is used directly by
additional considerations. The main differences
What is the largest motor that can be started important the voltage is kept within the required linking the end-use machinery with pulleys and
between a motor and other common types of
using a pico hydro system? range. If the motor is situated near to the belts to the turbine, then it is possible to drive
electrical load are that the current required can
Use this general rule to decide: generator then it will benefit from a higher equipment requiring almost the full rated power
vary greatly:
Max. Motor power = 10% of Generator power voltage. This will reduce starting problems. If of the turbine. A small efficiency loss occurs in
• during motor starting, much more current is
For example, the largest motor that could be the motor is a long distance from the generator, the belt drive. This will be, at most, 10% of the
required than when the motor is running.
started and driven by an induction generator the cable to connect it will be expensive and power in the turbine shaft if the pulleys and
• the current required by a motor can vary
producing 2.5kW is: 10% of 2500W = 250W there will be a lower starting voltage. belts are correctly sized and tensioned. This
during use depending on the load connected.
leaves 90% of the power to drive the load.
For example, a motor connected to a saw will
b) Type of motor 13.4 Mechanical end-uses Compare this with the maximum size of induction
draw more current when a plank of wood is being
Universal motors are used in many small and In addition to supplying domestic electrical loads motor that ca n be driven, calculated on Page 13-
cut than when the saw blade is spinning freely.
hand-held appliances, such as electric drills. such as lighting, pico hydro-power can be put to 6.
Alternatively, a motor driving a fan will draw a
They are compact, available in smaller sizes than good use during the daytime. The power can be
constant amount of current when the fan is
induction motors and easier to start. The type of used to make money and quickly repay the loan
running because the load on the fan does not
motor that is used for most loads requiring more that was taken to help buy the equipment.
change.
than about 200W is the induction motor. This is
A number of undesirable things can happen if the Electrically Driven Machines Mechanically Driven Machines
the same type that is used as a generator for
wrong size of motor is used with a particular Ease of Starting Difficult or not possible except for relatively Excellent , since turbine torque is highest at
the Pico Power Pack. Capacitors are often
generator: small motors. zero speed.
connected to help induction motors to start and Efficiency low (50% of turbine power) High (90% of turbine power)
• the motor will not start and the generator
to improve the power factor whilst running. The Location Very flexible Very inflexible (must be located next to the
de-excites.
motors are then classified depending on which turbine)
• the supply voltage dips sharply when the
capacitors have been connected. The type of Maintenance and Repair More complicated therefore maintenance and Simple to maintain and repair.
motor is started. When the motor is running repair needs are greater
induction motor which is used, should consider
the voltage is lower than its rated value Cost Cost may be lower than mechanical equivalent if Pulleys, belts and tensioning equipment must be
the load that is being driven
indicating that the scheme is overloaded. device is mass-produced. The cost of cable and included. Locally produced machinery may be
Type of motor Characteristics Suitable loads power factor correction must be included. more expensive than mass-produced electrical
• the MCB in the powerhouse may trip and Capacitor start High starting Fridge appliances.
disconnect the all the loads, if the machine torque compressors, mills,
which the motor is driving becomes jammed Capacitor run Good power Grinding wheels, Table 13-2 Comparison of electrically and mechanically driven loads
Being unable to start the motor, or tripping the factor/ low drills, fans
starting torque
circuit breakers whenever the motor is in use,
Capacitor start Best all round Saws, planers,
may cause frustration and disillusionment with and run performance

pmaher 31/05/01
13-6 pmaher 31/05/01
13-7
Selecting The Loads Selecting The Loads

Example : Calculate the mechanical power deeper in to the pulley and can therefore get (revolutions per minute), more commonly at 1500 Minimum pulley diameter
available to drive a load. more grip. The differences in size between the rpm and sometimes even 3000 rpm. That is 50 A final consideration when selecting the pulleys
two types are illustrated in Figure 13-6 complete turns in one second! Most machines is that particular sizes of induction motor
The power in the turbine shaft is 3.5 kW connected to the turbine need a slower speed
The efficiency of the belt drive is 90% specify minimum pulley diameters that can be
V-Belts than this. A small flourmill for example, may connected. This is because a higher belt tension
Answer require only 500 or 600 rpm. The difference in
90% of 3.5 = 3.5*0.9 = 3.15 kW
10mm 13mm 17mm
(and therefore a greater bearing load) is
speed between the shafts is called the speed required for smaller pulleys. Common sizes of
Power available = 3.15 kW

6mm

8mm
Z A ratio. It is calculated as follows:

11mm
B induction motor and the corresponding minimum
Some examples of mechanical loads which are
pulley diameters are shown in the following table:
commonly driven by hydro-power are listed in Wedge Belts Speed ratio= turbine shaft rpm / load shaft rpm
Table 13-8. Typical power requirements and 10mm 13mm 16mm
Induction Common Power Minimum pulley
speeds for small loads (suitable for use with
The speed of the turbine shaft will depend on motor ratings (kW) diameter (mm)
some pico hydro systems) have also been given. SPZ

8mm

10mm
SPA SPB

13mm
the site conditions and the type of generator frame size 4 pole 6 pole
Before purchasing mechanical equipment, consult D80 0.37 / 0.55 / 0.75 71 71
used. Usually the manufacturer selects the
manufacturers’ information and ensure that the D90S&L 0.75 / 1.10 / 1.50 71 71
operating speed. It is advantageous to use the
power output of the turbine is sufficient. The D100L 1.50 / 2.20 / 3.00 71 71
Figure 13-6 Cross-sections of different belt sizes generator and controller as an over-speed
choice of equipment will determine the pulleys D112M 2.20 / 4.00 90 71
controller. If the mechanical load requires less D132S 3.00 / 5.50 90 85
and belts required. Read the next section V-belts are named Z, A, B in increasing order of
power than is available from the turbine, the D132M 4.00 / 5.50 / 7.50 112 95
carefully to make sure these are appropriately size and similarly wedge belts are named SPZ,
excess power will be delivered to the generator
selected. SPA and SPB. V-belts and wedge belts of the Table 13-4 Minimum pulley diameters
and controller. If the mechanical load requires
same size range (Z and SPZ for example) can
all the turbine power then the speed will fall by Power per Belt
13.5 Pulleys and Belts both be used on the same pulley. However, care
about 10% as at this speed the generator will not The amount of power that can be transferred
Pulley belt drives are used to link mechanical must be taken not to confuse the two types. V-
excite and there will be no electrical load. depends on the thickness of the belt (whether it
equipment to the turbine shaft where the belts are generally much cheaper than wedge
A speed reducing drive means that a small pulley is an SPZ, SPA, Z or A for example) and also on
equipment has a different operating speed to belts which can make them appear attractive to
is fitted to the generator shaft and a larger one the size of the smallest pulley. Larger pulleys
that of the turbine. use when a spare is required. However, if a
to the mechanical load. This will mean that the transmit more power because there is more
wedge belt is replaced with a V-belt then there
Note: Direct drive of mechanical loads larger pulley will turn more slowly so that the contact area with the belt and less chance of it
is a strong possibility that the drive will no
If the load can be directly driven from the load, such as a mill, doesn’t spin too fast. A speed slipping. Wedge belts can transmit more power
longer work because the belt will slip.
generator shaft then no pulleys and belt are increasing drive is the opposite way round: A than V-belts. The power that can be transmitted
required. These are the considerations: In order for pulleys and belts to function
large pulley drives a smaller one, making it spin by one belt is shown for different sizes of pulley
• Turbine speed must match the load speed correctly and have a long lifetime, they must be
faster. Certain types of saw, for example, may and belt in Table 13-5 and Table 13-6
• Turbine must have the same centre point as carefully selected. The following questions must
require a speed increasing drive.
the load. (Is it practical to position the load be answered to allow the correct pulley and belt
A turbine shaft speed based on the number of
near the floor?) combination to be selected:
generator poles should be used to calculate the Z Rated Power (kW) per belt for small pulley of
• Disengaging the load from the turbine is more • How much power does the load require?
speed ratio. The number of poles (usually 4 but various pitch diameters (diameter in mm)
complicated. • How fast does the turbine shaft run when rpm 71 80 85 90 95 100 106
sometimes 2, 6 or 8) can be found on the
Direct drive is practical with particular loads in driving the generator? turbine
information plate on the side of the generator. 4
• What is the required running speed of the shaft
certain circumstances (e.g. grinding wheels) but pole generators are most commonly used. 1000 0.7 0.8 0.9 1.0 1.1 1.2 1.3
this is seldom the case. load shaft? Number Approx. Design Speed of Turbine 1500 0.9 1.1 1.3 1.4 1.5 1.7 1.8
• What is the centre distance between the two of Poles Head (m) / Generator Shaft (rpm)
3000 1.5 1.9 2.1 2.3 2.5 2.8 3.0
shafts? 2 >80m 3000
Two types of pulley belt are commonly associated
• How many hours per day will the load be in 4 25 - 80 1500
with hydro power schemes, the V-belt and the A Rated Power (kW) per belt for small pulley B
use? 6 <25 1000
flat belt. V-belts are the most suitable for pico of various pitch diameters ( diameter in
• What is the diameter of the turbine shaft? Table 13-3 Generator shaft speeds and head range for mm)
hydro. They are smaller, lighter, easier to install
• What is the diameter of the machine shaft? direct drive rpm 90 100 112 125 132 140 140
and maintain, and lower in cost compared with
turbine
flat belts. For more information about selection of design
shaft
Speed Ratio turbine shaft speed, please read the notes in 1000 1.1 1.4 1.8 2.1 2.3 2.6 2.9
V-belt drives are an efficient and robust method By choosing appropriate pulleys, the speed which Appendix B. 1500 1.5 1.9 2.4 2.9 3.2 3.5 3.9
of transmitting power between the turbine and one shaft spins can be different from the other. 3000 2.3 3.0 3.8 4.6 5.0 5.5 5.3
other machinery. Wedge belts are a more This is useful for a pico hydro system. The speed Table 13-5 Power per belt tables for V-belt drives
modern version of the V-belt. They can transmit of the turbine may be around 1000 rpm
more power because they wedge themselves

pmaher 31/05/01
13-8 pmaher 31/05/01
13-9
Selecting The Loads Selecting The Loads

SPZ Rated Power (kW) per belt for small pulley of L= 2302. A belt of 2300mm will be a suitable
STEP 2 Installation Allowance
various pitch diameters ( diameter in mm) (min. decrease in centre distance
required to install belt) length.
rpm 71 75 85 95 112 125 140 Look at ‘Power per Belt’ tables (Table 13-5 and
turbine Table 13-6). Select the minimum pulley diameter
shaft The new centre distance can now be calculated
and belt type suitable to deliver the required
1000 0.8 0.9 1.2 1.4 1.9 2.2 1.7 using a belt of 2300mm
power. (Check Table 13-4 to make sure that at
1500 1.1 1.3 1.6 2.0 2.7 3.2 3.7 CentreDist. = A + A 2 − B
3000 1.8 2.1 2.8 3.5 4.7 5.5 6.4
least the minimum pulley size for the generator
Centre Distance where
is used) The belt tables include a service factor
Take-up Allowance L
SPA Rated Power (kW) per belt for small SPB of 1.1 assuming that the load will be in use for 10 (Min. increase in centre distance A= − 0.3925( D + d )
required to retension belt) 4
pulley of various pitch diameters (mm) hours a day or less. For further information on and
rpm 90 100 112 125 132 140 140 sizing, consult Appendix C. ( D − d )2
turbine Figure 13-7 Measurement of centre distance B=
shaft
8
1000 1.4 1.8 2.3 2.9 3.2 3.5 4.1 STEP 3 New Centre distance = 799mm (A=402.3,
1500 1.9 2.5 3.2 4.0 4.5 5.0 5.5 Select another pulley from those available to Example Selection of suitable belt drives B=4512.5)
3000 2.9 4.0 4.7 6.7 7.4 8.2 8.5
give the speed ratio required to within ±10%. If 1) What is a suitable pulley and belt
Table 13-6 Power per belt tables for Wedge belt drives it is not possible to obtain the correct ratio 2) What are the centre distance adjustments
combination if the following is known?:
using the pulley sizes that are locally available, which are required for belt installation and
Single-belt drives or multiple-belt drives Power to be transmitted = 3.6 kW
look at the power per belt tables again and make re-tensioning?
More than one wedge belt is often used to Speed of turbine shaft = 1500 rpm
another selection, using the next pulley size up Consulting Table 13-7for an SPA belt of length
increase the power that can be transferred using Speed required by load shaft = 550 rpm
for the smallest pulley. 2300mm:
a pulley of fixed diameter. However, for pico Approximate centre distance = 800mm
a) For installation : a reduction of centre
hydro applications it is recommended that only Maximum Usage = 10 hrs per day
distance by at least 25mm should be possible.
single-belt drives are used. This is for the STEP 4 Step 1 Pulley ratio = Turbine speed / load
b) A minimum take-up allowance of 40mm in
following reasons: Calculate the required belt length using the speed
addition to centre distance will allow the belt to
• There is usually no cost saving with multiple approximate centre distance (see Figure 13-7) = 1500 / 550
be re-tensioned if it stretches.
belt systems at this power range. and diameters of the two pulleys. = 2.73:1
Further Questions:
• If more than one belt is required, then the (D − d ) 2 Step 2 Design Power = Load power + 10%
L = 2C + . (D + d )
+ 157 1) What combination of pulleys and belt would be
belts must be very carefully ‘matched’ (i.e. be
4C = 3.6 kW + 0.36 kW suitable to transmit 2kW between the following
exactly the same size) If there is any
where: turbine and load shaft:
difference in the size then this can cause one = 4.0 kW
L= pitch length of belt in mm Turbine shaft speed = 1500rpm Load shaft speed
of the belts to fail more quickly.
C= centre distance in mm Step 3 Select belt and pulley from Table 13-5 = 2000 rpm Usage for a maximum of 3 hours per
• If one belt breaks, it is usually good practice
D= pitch diameter of large pulley in mm and Table 13-6 day.
to replace all the belts at the same time. A
d= pitch diameter of small pulley in mm The closest match to this power requirement is a 2) A SPZ belt of length 1500mm. Is this suitable
multiple belt system cannot be run if one or
In order to determine the centre distance SPA belt using a 125mm diameter pulley on the for transferring a mechanical load of 1kW? The
more or the belts is missing so multiple-belt
required for, available belt lengths and pulley turbine shaft. The power per belt is 4.0 kW (at centre distance is approximately 600mm.
systems have the same maintenance
combinations, use the following formula: 1500 rpm ).
requirements and reliability as single-belts
Step 4 The diameter of the driven pulley can 13.7 Belt tensioning and supporting fixtures
systems.
2 also be calculated: A ratio of 2.73 is required Correct tensioning of belt drive is important for
• Coupling and uncoupling of the turbine shaft CentreDist. = A + A − B
and the turbine shaft pulley is 125mm diameter reliability and efficiency. Under-tensioning
from the mechanical load is more difficult where Pulley diameter required = 125 x 2.73 = 340mm creates slippage. This generates excessive heat
with multiple belt systems.
L The nearest size to this is 315mm. that shortens the life of the belt. Over-
• One belt simplifies the selection of the best A = − 0.3925( D + d )
4 The ratio is now 315/125=2.52 tensioning also shortens belt life and increases
pulley combination.
and This gives a load speed of 1500/2.52=595rpm the load on all the bearings. The life of the
If this is acceptable then use this combination. bearings will be reduced if the load on them is
13.6 Procedure for choosing pulleys and ( D − d )2
B= If not then repeat the procedure using a too high. Some means of adjusting the centre
belts: 8 different pulley size or different belt. distance (the distance between centre of the
Step 5 What belt length is required for a two shafts) is required for installation of the
STEP 1 centre distance of approximately 800mm? belt and to adjust the tension. The tension can
Find the required pulley ratio: (D − d ) 2 easily be measured using a spring balance. This
L = 2C + . (D + d )
+ 157 procedure is described in Appendix C with
Speed ratio= turbine shaft rpm / load shaft rpm 4C
L= 2*800+(315-125)2/4*800 + 1.57(315+125) methods for allowing the tension to be adjusted.

pmaher 31/05/01
13-10 pmaher 31/05/01
13-11
Selecting The Loads The Distribution System

electrification. For further information about


Belt Pitch Installation Allowance Take-up AC electricity, consult Appendix A.
Length (mm) Allowance 14 THE For more detailed information on distribution
(mm) Z A B (mm)
systems consult the Mini-Grid Design Manual
410 to 530
SPZ
20
SPA SPB
5
DISTRIBUTION (ESMAP Technical Paper 007). This excellent
reference is currently available free of cost
530 to 840
850 to 1160
20
20
25
25
30
30
10
15
SYSTEM from the World Bank.
1170 to 1500 20 25 30 20 14.1 Introduction
1510 to 1830 20 25 30 25 14.2 Drawing a Plan The design of the distribution system needs to
1840 to 2170 20 25 30 30 14.3 Layout Patterns
2180 to 2830 20 25 30 40
satisfy the following criteria:
14.4 Selecting Cable for Village Electrification
2840 to 3500 20 25 30 50 14.5 Distribution Poles • all the consumers who are to be included in
3520 to 4160 20 25 30 60 14.6 Installation of the Distribution System the electrification scheme will receive a
4170 to 5140 20 25 30 70 14.7 Protection of the distribution system connection
5220 to 6150 25 30 65 14.8 Sizing the cables
• a voltage drop of 10 % or less will be
14.9 Design of a distribution system to supply a workshop
Table 13-7 Installation and Take-up Allowances (see maintained at the furthest point from the
Figure 13-7) generator
Type of Machine Speed Power required • the distribution system will operate safely
(rpm) h.p. kW and reliably without presenting a danger to
Milling people.
200mm 600 3 2.2
225 550 4 3.0
280 550 6 4.2
Thresher 450mm dia. drum 1100 4-5 3.0-3.6
Woodworking
14.2 Drawing a Plan
Circular Saw dia. 200mm 2800 1 0.75 The first step in the design of the distribution
Band saw wheel dia. 300mm ------ 1 0.75 system is to draw an accurate, scale plan of the
Hand Feed Planer (surfacing 3000 1 0.75
area. The water source (stream) will be
only 600mm width of blade)
represented, in addition to the houses that will
Centre Lathe ( Med. Duty, 500- 0.5 0.375
160mm) 2000 be connected to the generator.

Table 13-8 Examples of mechanical loads and their


typical requirements
It is important that this plan is drawn to scale.
This means that the distances between each of
the houses and the stream need to be measured
Figure 14-1 Installation of a village distribution system accurately and drawn in the correct position. If
(Kushadevi, Nepal)
this plan is wrong then it will be difficult to work
out how much cable will be needed and where to
14.1 Introduction route the cable.
The distribution system is the name given to the
cables, poles and associated equipment that The following steps enable the plan to be
deliver the electricity produced by the produced:
generator to the houses and other buildings
where it is required. STEP 1
On a piece of paper, mark North, East, South
The cost of a village distribution system is likely and West.
to be one of the largest costs of the whole pico
hydro project. This cost can however, be
STEP 2
minimised by careful design.
Indicate with an arrow at the side of the paper
The methods described in this section are the general direction uphill. If the village
limited to the design and installation of single- crosses a valley, draw two arrows pointing in
phase AC distribution systems for village different directions to show the opposite sides.

pmaher 31/05/01
13-12 pmaher 31/05/01
14-1
The Distribution System The Distribution System

STEP 3 STEP 9 B Radial spread; central powerhouse with scheme. On larger schemes, carefully consider
houses in all directions different routes for connecting the houses.
Draw the stream from which water for the The map will be improved if the rough sketch is
Forebay Tank
hydro scheme will be taken. redrawn a couple of times. Try to get the Reference
House 1
100m 14.4 Selecting Cable for Village
relative positioning of the houses correct and
Electrification
STEP 4 estimate the distances between them. This map Spur A N
will be more valuable if care is taken to draw it The cable required to supply the houses with
Draw in carefully, any roads, footpaths, rivers, electricity, will be a significant part of the total
accurately. Walk around the village several
woods and other prominent landmarks. scheme cost. It is therefore important that the
times, if necessary, and show your sketch to
other people to get their opinion. Add as much most cost-effective cable is chosen.
STEP 5 detail as possible particularly about distances Key issues
Decide on the layout of the scheme (Page 6-1). between the houses. When selecting cable for village electrification
Powerhouse
Mark the proposed locations of the intake, the Spur D Spur B projects, the key issues can be summarised as
forebay or reservoir, penstock and the STEP 10 Reference
House 4
Reference
House 2 follows:
powerhouse. Write on the length of the Spur C • Cost: Both the direct cost of the cable and
Draw the map out one more time, but this time
penstock. the indirect cost of poles and fittings need
draw it to scale. Spending time at this stage to
plan carefully could save large amounts of money Reference consideration. The indirect costs are usually
House 3
STEP 6 on cable. Draw in the penstock, powerhouse, and greater if non-insulated cable is used
Figure 14-2 Radial spread distribution system
Mark the position of four houses that are going four reference houses. because the conductors have to be held
to be connected to the distribution system, This is the most convenient arrangement. If the under the correct tension to keep them
choosing the ones that are furthest away from powerhouse is in the middle of the houses, then spaced apart and insulators used so that
STEP 11
the generator. Choose one in each direction, the distribution system can be kept as short as they do not contact with the poles.
Now add the other houses, carefully. Be sure to possible. Running cables to houses in different • Voltage drop: The voltage at the end of the
North, East, South and West, if possible and use
position each one in the correct position relative directions from the powerhouse also has the cable will be different from that at the
a compass. These are going to form the
to the others. advantage that the network can be maintained generator. This is mainly because the cable
reference points for the system layout.
Sometimes there are no houses in one or two and repaired more easily. Switches can be used has a resistance. The resistance depends on
directions from the generator. If this is the STEP 12 to isolate the individual spurs. These can be the cable thickness and the type of
case, choose three or four houses that are both Once the final copy of the map has been drawn in located centrally in the powerhouse. MCB’s are conducting material from which the cable is
furthest away from the generator and from each this way, it is time to consider the best method suitable for this purpose (see Section 0). The made (e.g. copper or aluminium).
other. to connect the houses to the generator. cable diameter required for the main • Lifetime / reliability: The cable will be
Note: Hand-held GPS (Global Positioning distribution lines will be smaller because the exposed to the weather throughout the year.
Systems) are becoming widely available at prices total load current is divided amongst several Some of the factors which affect the life
STEP 7
of about $200. These can make drawing the plan spurs. and reliability are diameter, conductor
Number each of the reference houses 1,2,3,4. material, type of insulation and the number
much easier.
Then draw in all other houses that will be C: Random distribution in one or two directions of strands which are wound together to make
connected to the generator. Try and get their the complete cable. Stranded cable should
location on the plan as accurately as possible. Do 4
Forebay Tank always be chosen, the more strands the
Reference
not connect up the houses with lines House 1
better.
14.3 Layout Patterns
representing cables at this stage. • Safety: The safety of local people can be
Spur A
Look at the following examples of distribution
affected by the choice of cable. Cable with a
layouts and consider which is most like the layout
STEP 8 tough insulation such as cross-linked
of houses on the plan which you have drawn.
Walk in as straight a line as possible from the Reference Spur C polyethylene is safest. Pole design and
House 2
Powerhouse
correct tensioning also affects safety
8

proposed location of the powerhouse to each of A: Houses grouped together with the
1

the reference points in turn. Count the number Spur B particularly when using non-insulated cables.
generator some distance away
of paces and calculate the exact distance in • Security: It is easier for people to make
This is a very common situation with hydro-power
Reference
metres by first measuring the length of 20 Spur D illegal connections to non-insulated cable.
schemes. Consider if it is possible to reposition House 3
normal paces. Mark these distances on the map the powerhouse using the suggestions in 100m
and their compass bearings. Include the distance Section 6 so that the long distance to the village
from the generator of any intermediate houses is reduced. Obviously the cost saving in cable will Figure 14-3 Distribution system in two directions
that lie on or very close to the path that is need to be balanced against the additional The shortest route to connect up all of the loads
walked. expense of extending the penstock or the canal to the generator may be obvious on a small
to the forebay.

pmaher 31/05/01
14-2 pmaher 31/05/01
14-3
The Distribution System The Distribution System

Types of cable degradation such as cracks in the insulation. If • Safety: Safety depends on factors such as not interfering with the cables. However, in
The conducting material that the cable is made necessary, sections of the cable should then be the material and method of installation as lightning prone areas, live trees should not be
from is likely to be either copper or aluminium. replaced. Dark-coloured insulation usually well as the pole height. used to support cables (see Section 16). A direct
Copper Cable: degrades less than lighter colours. • Weight: Poles made from heavy materials strike on a tree that has been used to support
Copper cable is made of separate strands of such as concrete are difficult to transport part of the distribution system will cause a large
wire. The number of strands and the thickness Aluminium Cable: and handle. voltage to be conducted to the cables. This can
of each, determine the overall resistivity and 1. ACSR Aluminium cable is commonly result in significant damage to equipment and
cost. The number of strands vary but typical reinforced with galvanised steel. This is Poles can be a very expensive part of the injury to people.
values for small cables are 3,7,16,24,30,32 and referred to as ACSR (Aluminium Cable Steel distribution system, and as a consequence the
50 strands. Different copper cables are Reinforced). It is popular because of its cheapest option is often taken, even though this
identified by a numbering system. The first is relatively low cost and high strength. The may prove to be more expensive in the long term 14.6 Installation of the Distribution
the number of wire strands in the cable and the aluminium cables are given names that due to the need for frequent replacement. System
second is the gauge which gives a measure of the correspond to a particular equivalent CSA of Wood is usually the preferred choice for poles,
thickness of each strand. Cable number 7,16 for copper. This allows different cables to be although reinforced concrete and steel are Pole Installation
example, has seven wires of 16 gauge. compared in terms of their resistance. sometimes used where wood is scarce. Properly Distribution poles should be spaced between 25
There are two common gauge systems: SWG 2. ABC. Aerial Bundle Conductor is aluminium treated and maintained quality wood poles have a metres and 40 metres apart.
(Standard Wire Gauge) and AWG (American alloy cable with XLPE insulation. This is life of at least 40 years. However, poles made
Wire Gauge). They use different gauge systems recommended where available as it is strong, from unseasoned and untreated wood can fail in Pole Height Service connections Guy wire supports
(to wire) are made at the pole the last pole in the line
for particular cross-sectional areas (CSA), so highly resistant to sunlight and usually very less than 12 months, particularly in hot and
care should be taken to ensure that the two cost-effective. humid areas. Poles must be seasoned (dried) and 3.0m or
5.0m or Sag: 80 to 250mm
systems are not confused. 3. Aluminium equipment wire is also available in treated. In dry climates, seasoning can be done 5.8m
some areas. This is low cost but is not by natural air circulation, but kiln drying or Buried depth
Hand drawn copper is better than the annealed suitable for use as distribution cable because steam conditioning is required in humid climates. 1 - 1.5 metres.
Span: 25 to 40 metres
(flexible) copper found in most equipment wire of its low strength. To properly treat poles, pressure or hot/cold
because it has approximately 60% more soak methods are used to force creosote or
Figure 14-4 Required installation practice for distribution
strength. 14.5 Distribution Poles other preservatives into the wood. poles
Unfortunately these methods are not well suited
for treating a small number of poles due their The first and last poles in a line should be stayed
However, insulated annealed copper equipment
complexity and expense. A cheap approach is to with guy wire. Any poles on corners or bends
wire has been used on many pico hydro schemes
paint or soak the lower portion of the pole using should also be stayed. Minimum ground
in Nepal because it is widely available in
creosote or old engine oil, though this is much clearances should be according to national
convenient sizes. The only reported problem has
less effective than properly treating the standards. If there are no standards available
been where a small, three-stranded cable broke
complete pole. then the minimum ground clearance is 3.0m over
inside the insulation which made the fault
open ground, 5.5m along motorable road and 5.8m
difficult to locate. Firstly, it is recommended
An effective low-cost method with bamboo poles across motorable road. The poles should be
that cables with a larger number of strands are
is to place the cut ends of freshly-felled bamboo spaced approximately every 25m and at a
used to minimise this risk. Equipment wire is not
in a container of preservative and to leave them maximum of 40m. Note different requirements
designed to support its own weight over long
in a sunny place for 4 – 5 days. Natural for poles over 5 meters in Table 14-1. Since
spans. To prevent the cable from stretching a
transpiration will cause the preservative to bamboo poles of appropriate diameter are
galvanised steel or iron support wire should be Key issues
diffuse from the base of the bamboo to the unlikely to be available for poles which are 5
used around which the cable is wrapped. Most
The important issues regarding selection of metres and above, hardwood poles should be
insulated copper cable has PVC insulation which is leaves.For more information on poles and pole
distribution poles are as follows: used.
less weatherproof than the XLPE (Cross-linked treatment consult the Mini-Grid Design Manual.
• Cost: The cost of the poles may be quite
Polyethylene) insulation which is commonly found
substantial or very little and depends on Ground clearance 3.0m 5.0m 5.8m
on cables intended for outdoor use. Sometimes, the main trunk of a living tree is
whether local materials are suitable or if Min. pole dia. 100mm 125mm 125mm
used to support cables in rural areas. Only Buried Length 1.0m 1.5m 1.5m
poles must be purchased and transported
Note on PVC cable insulation healthy, mature trees should be used and the Maximum span 40m 35m 35m
from further away.
Some types of PVC cable insulation degrade in foliage should be cleared to at least 1.5m in all Material options Bamboo or hardwood hardwood
• Lifetime: The materials used and how the hardwood
sunlight. Also it becomes brittle at sub-zero directions around the cable. Also the lower
poles are installed and maintained will affect
temperatures. If PVC coated cable is used for branches should be removed to discourage Table 14-1 Requirements for distribution poles
how long they last.
the distribution system, the operator should children from climbing the tree. Regular checks
periodically check the cable for signs of should be made to ensure that further growth is

pmaher 31/05/01
14-4 pmaher 31/05/01
14-5
The Distribution System The Distribution System

time, indicating if adjustments are required. This loop of slack wire can be formed where a alternative to splicing cables. Insulated cable
is likely, as cables will stretch over time with connection is made. need not be stripped back as an electrical
Pole their own weight. contact with the conductor is made when the tap
Corner poles Guy wire
Identifying the live and the neutral can be a splice is clamped shut with pliers. It is essential
Sag
Distribution Insulated Sighting
problem if conductor with the same colour to use tap splices of the correct size to minimise
cable coupling line
Pole insulation is used for both. If different coloured damage to the cables and ensure a good
Tensioning Wooden boards nailed
Guy wire nut to posts for sighting insulation is unavailable, use coloured insulating connection.
Stay rod tape at the beginning and end of cable coils used
90º for the live line. This will allow it to be easily
Figure 14-6 Sighting method of sag measurement identified during installation.

For long pole spans, a ‘return wave’ method can


Connecting spurs to the main conductor
be used to obtain the correct sag. This is
described in the Mini-Grid Design Manual (see If a copper cable is to be connected to an
Figure 14-5 Use of guy wires to support poles and help aluminium cable, special bimetallic connectors are
tension cables
Page 20-1).
required that separate the conductors to
Cable installation prevent electrolytic attack on the aluminium
Lengthening cables
Sag: The distance between the poles determines conductor.
The cable lengths can be joined by using crimp-
the amount of sag that is required. The sag is type cable connectors and by twisting stranded
not critical for insulated cables providing that a An alternative method of joining the cables is
cables together (see Figure 14-7)
minimum sag of 80mm is allowed to prevent shown in Figure 14-8. If the distribution cable is
Distribution cable
excessive tensioning. The maximum sag for insulated then the insulation must be carefully (insulated)
Crimp type cable connectors, consist of a
insulated cables is 250mm. stripped back. Solder should be applied to the
compressible metal tube (or splice) that slides Service Cable
For non-insulated conductors, it is important to join using a soldering iron (preferably gas
over the ends of the conductors and is
measure the sag more carefully in order to powered) and then the join should be re-
compressed (crimped) using a special tool. It is
prevent the risk of conductors making contact insulated with tape. Figure 14-9 and Figure 14-10: Use of a tap splice to
essential to use connectors that are specified connect the service cable to an insulated distribution
with each other especially during windy for the diameter of cable used and to use a cable
Main line
conditions. The requirements for sag of ASCR crimping tool suitable for the size and type of
cables with various pole spans are presented in connector. If the correct connector and the
Table 14-2.
14.7 Protection of the distribution system
right tool are used the connector should be able
Cables expand in hot weather and therefore the Lightning
to support the full tension of the cable. The Tap wire
sag is greater. When installing cables in cold connectors are cheap, though for cables above It is very important that consideration is given
weather, aim to achieve close to the minimum 6mm2 the tools are quite expensive. to protecting the distribution system from
sag, and in hot weather aim for close to the lightning. Even indirect strikes some distance
maximum sag. Figure 14-8 Suitable method of connecting tap wires to away from the cables can cause very high
1. distribution cables
voltages to be induced in the cable that can
Strip back
insulation Service Connections damage equipment. Consult Section 16.3 and
Span (m) 20 25 30 35 40 at least 5cm
incorporate the recommended measures at the
Min. sag (mm) 20 30 45 50 75 The service cable runs from the house to the
2. initial stages of designing the distribution
Max. sag (mm) 70 100 150 200 250 main distribution line. A good, weather-resistant,
Twist strands
from the two cables electrical connection is required, between the system.
Table 14-2 Sag requirements for ACSR firmly together

3. distribution system and the service cables. The


Cover the join completely
methods described for connecting spurs to the Excess Current
by tightly wrapping
Sighting method of sag measurement insulation tape around.
main line can be used for connecting the service The cables are protected from high currents
A method of measuring the cable sag is to using 4.
cables. (these could be caused by a short circuit) by
straight wooden boards nailed to the poles as either a Motor Protection Switch or MCB inside
shown in Figure 14-6. The boards are fixed at Figure 14-7 Twisting stranded cable A convenient and more rapid method of the controller in the powerhouse. The minimum
the correct height for the cable sag and sighted connecting the copper service cable to insulated cable sizes are determined by the current rating
from another pole one span back. The cable is Insulated copper cables can be joined by
copper conductor is to use a small, plastic of this protection although cable sizes will
tensioned until the sag is aligned with the boards twisting. However, the cable joins must never
connecting device called a ‘tap splice’ shown in usually be larger to minimise the volt drop (see
as shown. One advantage of this method is that take the tension of the cable. Both cables should
Figure 14-9. These are available in sizes for Section 14.8). If several spurs begin at the
if the wooden boards are left in place, it is easy be wrapped around the pole or another fixture
various cable diameters between 0.5mm2 and powerhouse, it is preferable to connect an MCB
to determine if the cable sag increases over such as a bracket to prevent this. In this way, a
6mm2. They provide a low cost and safe for each spur so that the individual sections can

pmaher 31/05/01
14-6 pmaher 31/05/01
14-7
The Distribution System The Distribution System

be isolated if necessary. Additional MCBs may be branches of the distribution system where only a Example: Calculating % volt drop: Squirrel - 13 1.31 0.16
required if the current carrying capacity of the few houses with small loads are connected. Gopher - 16 1.06 0.20
Weasel - 20 0.85 0.24
smallest cables used at the ends of the Generator voltage = 220 Volts Rabbit - 30 0.57 0.37
distribution system are less than that of the CSA of copper cable Cable resistance = 0.0061 Ohms per metre Dog - 55 0.31 0.67
existing MCBs. Current capacity (Amps) Length of distribution = 150 meters Add US $0.11 per metre to ASCR for average cost of D
1.0 mm2 17A Length of Cable = 300 metres irons and insulators (not required for insulated cable)
1.5 mm2 22A Load Current = 5 Amps Table 14-4 Sample of cable specification from Nepal
Installation procedure for distribution 2.5 mm2 30A
system 4.0 mm2 40A Volt drop = Current x Total resistance of cable Method 1: Consumer loads clustered together
6.0 mm2 51A at the end of the distribution cables
Step 1: Using the guidelines for pole spacing and = 5 x (0.0061 x 300)
Table 14-3 Current carrying capacity of single This method will tend to oversize the cable
the map of the distribution system, work out how = 9.15 Volts
core insulated copper cables in free air. because the current is slightly overestimated.
many poles will be required and where they % volt drop
The cable is therefore likely to be more
should be positioned. = 9.15/220 x 100
By calculating the voltage drops across the expensive than necessary. However, it is the
Step 2: Calculate how many poles will require = 4.1%
distribution system, it is possible to find the most straightforward method for a rapid design
supporting with guy wires (including corner poles, Calculating the best size of cables for a
best sizes of cable to use. of distribution system.
see Figure 14-5). distribution system increases in complexity, the
Step 3: Avoid routing distribution cable along more houses are connected. The best method is
exposed ridges where the risk of damage from Explanation of voltage drops: to treat each individual branch or spur
wind and lightning strikes is greatest. The consumer voltage drop is the difference in separately. However, this is very time-consuming N
Step 4: Dig holes and lay out poles along voltage between the generator voltage and the because of the number of separate calculations B
intended route voltage in a consumers house. This difference is which must be made. Computer programmes allow Penstock 200m
A C D
Step 5: Erect all poles along chosen route due to the resistance and inductance of the this to be done much more rapidly. (350m) 450m 400m
except for those that will be supported by guy cable through which the electric current flows. Powerhouse
200
wires. The volt drop due to inductance is usually small Note: Save Money on Cable by Raising the E
Step 6: Beginning at the powerhouse, and and for simplicity can be neglected, enabling the Generator Voltage
installing the thickest first, suspend the cable volt drop to be calculated using Ohms Law: If the voltage at the generator can be raised to
from each pole in turn. If non-insulated cable is the upper voltage limit (i.e. national voltage + 6%) Figure 14-11 Distribution system with load "clusters" at
Volt (drop) = Current x Resistance (of cable) the end of spurs
used, ensure that cables are correctly fitted to then even greater savings in the cost of the
insulators. distribution cable may be possible. The voltage Consider the simple distribution system in Figure
Step 7: Use people to pull the cable taught, A small volt drop is acceptable. If the voltage in range across the system is now +6% of the 14-11. The loads have been grouped together at
achieving approximately the correct tension a house is too low however, electrical loads that nominal value at the generator and -6% of the B, D and E and the distances from the
while attaching the cable to each pole. are connected (e.g. tube lights) will not work voltage at the terminals of the furthest house. A powerhouse A and from node C, have been
Step 8: At the end of a run of poles, dig a hole properly. An acceptable minimum voltage is 6% total volt drop across the cables of 12% is carefully measured. All that remains is to size
and fix the end pole in position with a guy wire to below the national voltage. For example, if the therefore possible. This means that a cable of the cable for the distribution system to give the
support it. national voltage is 220V, for a 6% volt drop the smaller diameter can be used while still keeping lowest acceptable voltage at B, D and E and
Step 9: Measure the sag and adjust tension as consumer voltage would be: the volt drop within acceptable limits. therefore to minimise the cost.
required in order to set within the correct 220 – (0.06 x 220) = 206.8 V
limits. At 207 V, electrical loads designed for 220V will Two manual approaches to sizing the distribution
Step 10: When distribution system is complete, still function normally. Houses that are furthest cable based on the volt drops are described
connect service cables. Leave a loop of slack from the generator will have the largest volt below. Both methods make assumptions about the What is the best cable to use if
cable where the cables enter the building. This drop because the current has to flow through position of the loads. This helps to reduce the • the load at each point (B,D and E) is 1kW
prevents rainwater from running down the cable more cable to reach them. Choose cables that number of calculations that are necessary. single phase,
into the building. ensure a minimum voltage of 6% below national
• the nominal voltage is 220V, and
voltage at the furthest houses. This keeps the Cable CSA CSAcable Ohms / Cost: • the power factor is 1 (for explanation of
14.8 Sizing the cables distribution system cost to a minimum and type strand mm2 1km US$/m
power factor, see Appendix A)
ensures that voltages in other parts of the mm2
The cables in a distribution system are likely to
Insulated Copper
be different diameters in different places. This system are acceptable.
3,20 0.6567 1.9701 8.63 0.09
is because some parts of the system will carry 7,22 0.397 2.779 6.12 0.15 A-B
more current than others parts and the cables 7,20 0.6567 4.5969 3.70 0.19 Current (I) flowing along A-B (using I=P/V)
will therefore need to be larger in diameter. It 7,18 1.1675 8.1725 2.08 0.33
1000/220 = 4.545Amps
7,16 2.0755 14.528 1.17 0.69
would be a waste of money to use large cables on
Aluminium (ACSR) CSA in mm2 copper equivalent

pmaher 31/05/01
14-8 pmaher 31/05/01
14-9
The Distribution System The Distribution System

a) Try 7,16 insulated copper cable. (see Table Cable Resistance = 800 x 0.0037 = 2.96 Ohms
14-4) Cable Cost = 800 x 0.19 = US $152 The current I, is assumed to be constant for Note: An Excel spreadsheet has been created to
Total length of conductor required is 2 x 200m = Line Current = Load Connected / Nominal Voltage each house. It is calculated by dividing the total allow accurate design of village distribution
400m. Resistance (Ohms per metre) = 0.0012 = 1000 / 220 = 4.54 A available power (assuming a 6% power loss in the systems with greater ease. Please contact the
Cable Resistance = length x resistance per metre Voltage Drop = 2.96 x 4.545 = 13.45 V distribution system) by the nominal voltage and editorial address via email for a copy.
= 400 x 0.0012 = 0.48 Ohms % voltage drop = (13.45/220)*100 = 6.1 % then by the total number of houses. Each house (Email address: phillip.maher@ntu.ac.uk )
Cable Cost = 400 x 0.69 = US $276 Total Voltage Drop A-D = 4.8 + 6.1 = 10.9 % is assumed to have an identical load and to be
Voltage Drop = I x R = 0.48 x 4.545 = 2.18V spaced equally along a particular section of
% Volt Drop = (2.18/220)*100 = 1%. C-E Same as A-B (1kW load and 200m long) distribution line, as shown in Figure 14-12 The
Voltage drop = 5% total voltage drop at the end of the line can be
Since we are aiming for a total drop of 12% of Cost of cable = US $60 calculated as follows: 14.9 Design of a distribution system to
the nominal value (see Note, P.14-8), this cable Total Voltage Drop A-E = 5.0 + 6.1 = 11.1% supply a workshop
can clearly be reduced in diameter Vdrop = (5+4+3+2+1) I.R1 This section has been included to illustrate the
Cost Comparison approach to sizing and connecting motor loads to
b) Try 7,22 insulated copper cable (see Table The cost of this distribution system is compared. Where, R1 = cable length (i.e. 2 x distance a small induction generator. The example used is
14-4) 1) Using all 7,16 insulated copper = (200 + between houses) x cable resistance per metre for a workshop but the principles can be applied
Cable Resistance = 400 x 0.0061 = 2.44 Ohms 200 + 450 + 400)*2 = 2500 x 0.69 to other types of motor loads connected to a
Cable Cost = 400 x 0.15 = US $60 = US $1725 Re-analysing the previous example in this way, distribution system.
Voltage Drop = 2.44 x 4.545 = 11.08V 2) Using all ‘squirrel’ ACSR= 2500 x 0.16 + 1250 and assuming that each 1kW load is actually 10
Percentage volt drop is 5% which is still within x 0.11 (0.11 = cost of D irons and insulator per houses evenly spaced, and that the cable is used Example
the acceptable limits. Reducing the cable more meter along the section i.e. half the cable length) as calculated in Option 3 above (mixed
A particular village has a pico hydro site with the
than this becomes impractical because the cable = US $537.50 conductors) then the voltage drops are as
potential to produce 4.4kW of electrical power.
strength will not normally be sufficient. 3) Using mixed conductors as calculated above: follows:
The intention is to use the electricity for
A-B = US $60 (Cu)
evening lighting. Some members of the
A-C A-C = US $144 + 450 x 0.11= US $193.50(ACSR) I= 100/220 = 0.4545
community are also very interested in
Although no load is directly attached to C the C-D = US $152 (Cu) A-B : R1 = 2x200/10 x 0.0061 = 0.244
constructing a workshop to produce wooden
cable must be sized separately since the C-E = US $60 (Cu)
furniture. This could potentially be very useful
currents flowing are different from C-D and C-E. Total for 3) = US $465.50 Vdrop = (10+9+8+...+1) x 0.4545 x 0.244
as it would provide a daytime load and add to the
The voltage drop A-C must be added to the = 6.1V = 2.8%
income generated from the pico hydro scheme.
Voltage drop of C-D and C-E. The value at the Clearly if the loads change, recalculation is
end of the line must not exceed 12%. required based on the new current value along A-C : Same as before as no loads are connected
The carpenters would ideally like to be able to
each section. Although this process can be time in this section.
use the following machines
a) Try 7,22 insulated copper consuming, particularly for more complex Vdrop = 1.17 x 9.09
• band saw
Cable Resistance = 900 x 0.0061 = 5.49 Ohms distribution systems, careful planning at an early = 10.63 V = 4.8 %
• plane
Cable Cost = 900 x 0.15 = US $135 stage will be rewarded with potentially
• lathe
Line Current = Load Connected / Nominal Voltage significant savings in cost. C-D : R1 = 2x400/10 x 0.0037 = 0.296
• circular saw
= 2000 / 220 = 9.09 A
• pillar drill
Voltage Drop = 5.49 x 9.09 = 50 V Method 2: Equally Spaced Consumer Loads Vdrop = (10+9+8+...+1) x 0.4545 x 0.296
• hand drill
Percentage voltage drop = 22.7% so cable = 7.4V = 3.3%
• grinding wheel
diameter must be larger. 5I 4I 31 2I I

The community is aware that the mechanical


C-E R1 = 2x200/10 x 0.0061 = 0.244
I I I I I power produced by the turbine is greater than
b) Try Squirrel ACSR (see Table 14-4)
the electrical power and it would be useful if the
Cable Resistance = 900 x 0.0013 = 1.17 Ohms Vdrop = (10+9+8+...+1) x 0.4545 x 0.2.44
workshop machines could be driven directly using
Cable Cost = 900 x 0.16 = US $144 = 6.1V = 2.8%
Figure 14-12 Equally spaced consumers belt drives. Unfortunately the sides of the valley
Line Current = Load Connected / Nominal Voltage
are steep and the flat area for building the
= 2000 / 220 = 9.09 A The second method of voltage drop calculation Reassessment of the cable requirements will be
powerhouse near the river is limited. In addition,
Voltage Drop = 1.17 x 9.09 = 10.63 V assumes that the loads connected to a particular possible based on the above voltage drops which
access with timber for sawing into planks would
Percentage voltage drop = (17.2/220)*100 = 4.8 branch of the distribution system are equally are much less than those calculated by the
be difficult if the workshop was in the same
% must be added to voltage drop C-D and C-E spaced along its length. This is slightly more previous method.
building. A flat area of land 200m uphill from the
complicated than the method shown above but is
proposed generator site has been identified
C-D Try 7,20 insulated copper (see Table likely to give a more accurate picture of the
which would make a good location for the
14-4) expected voltage drop.

pmaher 31/05/01
14-10 pmaher 31/05/01
14-11
The Distribution System The Distribution System

workshop. However, this will mean using for one motor to reach its running speed
workshop machines that are driven by electric Hand held power tools usually do not use before starting the next.
motors. induction motors and can often be sized up to • Power factor correct the motors as
The carpenters would like to know the following: 25% or more of the supply capacity. This would explained in Section 13.3.
1) Which of the machines listed above could be enable a 1kW hand-held drill for example, to be • Each machine should be connected to the
operated? connected in the workshop. supply through a circuit breaker. This will
2) What would be the cost of a distribution protect the motor windings from high
cable from the generator to the workshop? 2) What is the cost of a suitable distribution currents. Motor start MCB’s should be
3) What other considerations are important? cable? specified and rated slightly higher than the
The distribution cable required is 200m in normal rated current of the motor.
Answer length. All of the load is at the end of the cable Adjustable protective motor switches can
1) Which machines can be used? and a maximum voltage drop of 6% is permissible. also be used (see Figure 9-13). These allow
All the machines that are listed can be run using the tripping current to be adjusted to the
the power supplied by the pico hydro generator Assume that all the power produced by the precise current rating of the motor for
if they are selected carefully. Small, workshop generator, may be consumed by loads in the maximum overload protection. Use Table
tools are usually powered by single-phase motors. workshop. The motors are small in relation to the 14-5 as a guide for 240V supplies. Circuit
A single-phase supply is the simplest to generate generator but their power factors are uncertain. breakers are not normally used for hand-held
and will therefore be the most appropriate to Calculate the maximum current that the tools. These are protected by a consumer
transmit the electricity from the generator to generator can supply at the rated voltage and unit with a suitably rated MCB and a fused
the workshop. Before sizing the supply cable, use this to size the cable. plug.
research the available workshop machines that
run on single-phase power. Maximum generator current (@240V)
Electric motors up to a certain size only can be = 4400 / 240 = 18.3Amps Motor size Amp range of MCB (240V)
connected to small induction generators (see 1/3 HP (250W) 2 – 4 Amps
Section 13.3). It is important to know what the The length of cable is 200m x 2 (phase and ½ HP (375W) 2 – 4 Amps
starting current requirements are for these neutral) = 400m 2/3 HP (500W) 2 – 4 Amps
machines so that the generator is not ¾ HP (560W) 4 – 6 Amps
overloaded. Generally, non- of these machines From Table 14-4, and selecting Squirrel cable 1 HP (750W) 4 – 6 Amps
are under load when first switched on. They will (smallest ASCR), calculate volt drop:
Table 14-5 Protective motor switch ratings for different
only be used when the normal operating speed machine sizes
has been reached. For this reason, they can be Cable Resistance = 400 x 0.0013 = 0.52 Ohms
classed as low-starting torque loads and sized up
to 20% of the supply capacity. Voltage Drop = 0.52 x 18,3 = 9.5 V

Supply capacity = generator capacity – power loss Percentage voltage drop = (9.5/240)*100 = 4 %
in distribution cable.
Cable Cost = 400 x 0.16 + 200 x 0.11
Assume that the power loss is 6% and then size ($0.11 = average cost of D-irons and insulators
the cable to deliver the power with no more than per metre of cable)
6% volt drop. = US $86

Supply capacity = 4.4kW – 6% = 4.1kW 3) What additional considerations are there?


Additional considerations are as follows:
So, the largest motor which can be connected in • Do not purchase the workshop machines until
to the workshop to power one of the machines the turbine and generator are installed and
listed is the electrical output is checked.
• Do not start the machines simultaneously as
20% x 4.1kW = 820W the combined power requirement may exceed
the generator capacity and trip the overload
For example, machines that have induction protection in the powerhouse. The motors
motors up to 1 horse power (750W) can be should be started on after another, waiting
operated successfully using this generator.

pmaher 31/05/01
14-12 pmaher 31/05/01
14-13
Domestic Wiring Domestic Wiring

Consumer protection using an RCD live, the RCD will operate and disconnect the
3 metres
To Load Limiter
supply, protecting the user. Otherwise there is a
15 DOMESTIC The risk of a dangerous electric shock by a
person accidentally coming into contact with a
Live
Neutral
risk of electric shock. This is explained in Figure
15-4
WIRING bare cable is minimised by the use of an RCD.
RCD’s must be used on all pico hydro schemes. Mains socket 1. Faulty live wire
touches metal
15.1 Main Issues Ideally each household should have its own RCD. In-line case and makes
switch L it live L
15.2 Wiring Harness
However RCD’s are expensive and therefore it is Supply RCD
15.3 The Load Limiter Load
15.4 Load limiter design usual to share an RCD between several N N
households or on small schemes just to have an Compact
Fluorescent lamp
3. RCD disconnects the circuit
after detecting change in Earth connection
RCD in the powerhouse. The level of protection is neutral current. to metal case

just as high with just an RCD in the powerhouse, Figure 15-3 Circuit diagram of a typical wiring harness
though it is more inconvenient as a fault in one 2. Current is conducted to earth,
and by-passes the neutral wire.
house trips the supply to all houses. This is
Design of Wiring Harnesses
explained in Figure 15-2. This device cannot Figure 15-4 Protecting consumer loads using an RCD
however, remove the danger of a serious shock if Flexibility: Many new consumers will want to
someone touches both conductors at the same change the position of their light bulbs after
they are first installed. This is partly due to a If earthing is required, an electrode should be
time. Local people should therefore be warned provided near to the consumer house. For
about the dangers of touching the cable, lack of experience with electricity. If spare
cable is provided and the sockets are already information about earth electrodes, see Section
particularly when non-insulated cable is used for 9.3. The earth cable from the electrode is
distribution. connected, then the lights can be positioned in a
variety of ways without risk to the consumer. connected to a spare section of the connection
Figure 15-1 Installation of domestic wiring circuit (Nepal) The harness is installed by strapping the cables block in the service box and the cable junction
Supply box. The domestic cable should be of the twin
L L
securely to suitable wooden beams. Unused cable
is coiled up and suspended out of the way. The and earth type. A 3-pin plug and socket is then
15.1 Main Issues RCD
amount of cable provided will depend on the size used to connect the device to the supply. The
N N 1. A person
The main considerations for house wiring are: 3. In a fraction of a second, accidentally earth wire should be connected internally to the
the RCD disconnects the supply touches a live wire. of the local houses.
• Consumer safety and a dangerous electric shock metal case of the device.
is avoided. Load connected: The number of plug and light
• Reliability 2. The person is standing in water
bulb sockets connected to the harness will
and conducts easily to earth.
• Versatility in terms of positioning Current flows though them
depend on the power that the consumer has
and back to the earth electrode.
• Limiting the size of the connected load subscribed to. A typical harness such as the one
• Keeping the cost low illustrated in Figure 15-3, has one plug socket
Figure 15-2 The danger of electric shock from a bare
• Ease of installation cable is reduced by fitting an RCD. and two light sockets. The connected load could
A 3 pin plug
is used to
connect a
be 2 CFL’s lights (9W each) and a radio metal-cased
Safety 15.2 Wiring Harness appliance
connected using the 2-pin socket (2W) giving a
The greatest risk to consumer safety is from The metal case
This is a “ready-to-install” domestic circuit. It is total of 20W. This load is used to determine the is connected to
electric shocks and fires. These risks are the earth wire
assembled by a trained person, is safe and load limiter current rating (see Section 15.4).
minimised as follows:
reliable, and contains all the necessary Cable: The current rating of the cable used for
1) Connect an RCD
components (load limiter, light bulb sockets, wiring harnesses and all fixed domestic wiring, Figure 15-5 Metal-cased devices should be earthed
2) Provide an isolation switch for each house
electrical sockets, etc.). should be at least 40% higher than the current
3) Earth all metal cased electrical devices
The use of wiring harnesses is particularly rating of the fuse or MCB protecting the house To Load Limiter
4) Use correctly-sized double-insulated cable
suitable for village electrification using pico wiring (see Section 15.3 and 15.4). It should also Live
and a wiring harness for house wiring
hydro. Rural houses rarely require complicated be double insulated for additional consumer Neutral
5) Make sure there is no exposed wiring
domestic circuits. People who receive an safety. Earth
6) Position sockets out of reach of small
electrical connection for the first time usually
children
do not have many electrical appliances which to Consumer Earthing
7) Use a suitably sized fuse or MCB to
connect. In many cases the only devices used will There is no need for a consumer earth to be
3-pin socket
protect all wiring. for metal-cased
be light bulbs and a radio or television. provided unless metal-cased appliances are likely devices
8) Give advice about electrical safety and
Consumers who use many loads will benefit more to be used.
position a danger notice on the load limiter
from a fixed wiring circuit as this is likely to be Consumer loads that have metal cases such as
9) Don’t allow hot light bulbs and cookers to
more cost-effective. cookers, must have an earth connection. Then, if
touch materials that burn easily. Figure 15-6 An earth connection must be provided if
a wiring fault develops making the metal case metal cased loads are likely to be connected.

pmaher 31/05/01
15-1 pmaher 31/05/01
15-2
Domestic Wiring Domestic Wiring

15.3 The Load Limiter 15.4 Load limiter design to identify whether the fuse wire is still intact.
Conventionally the consumer is charged for their A low cost design of load limiter is shown in 1) The first consideration is the current rating Ceramic fuses, however, have higher breaking
electricity consumption by means of an Figure 15-7 (Fuse Irated) The fuse must be designed to blow capacity. A fuse with a glass case should
electricity meter that records the number of below the PTC maximum current (PTC Imax). The preferably be selected, if available with
Panel-mounting
kilowatt-hours drawn from the supply. This is not fuse holder or current rating must however be well above the sufficient current rating and breaking capacity.
in-line fuse holder guaranteed ‘no trip’ current of the PTC (Int).
appropriate for pico hydro schemes as it does Positive
Temperature 4) The voltage rating of the fuse must be
not prevent overloading of the small generator Coefficient
or encourage consumption of electricity during
Thermistor PTC Int< Fuse Irated < PTC Imax greater than or equal to the voltage rating of
(PTC)
“off-peak” periods such as at night when Panel-mounting the generator (i.e.250V or 125V as necessary)
mains switch 2) The second consideration for fuse selection is
electricity is still available and often goes to (Double-pole with Varistor (metal
insulated lever L N N L oxide varistor) the breaking capacity. This is the current at 5) The final consideration is the size of fuse.
waste. A better option is a limited current and casing) for lightning
connection, where the consumer pays a fixed mov
protection of which there is a danger of the circuit reforming This depends on the dimensions of the fuse
electronic loads
monthly fee that allows them to draw a current Terminal block (See Section 15) because of arcing across the fuse contacts. The holder. Ensure that new fuses are always
up to a prescribed limit on a continuous basis. Plastic box with breaking capacity must be greater than the identical to those being replaced.
screw-on lid
This prevents overloading and encourages ‘off- (50mm x 75mm) highest continuous overload current that the
peak’ power consumption. A load-limiting device generator is able to produce. The highest 6) Fuse Type: Fast-acting fuses should be
Supply from
prevents the consumer drawing more current
distribution To junction box continuous current occurs when the generator is selected as delay types are too slow to protect
system
than they subscribe for by temporarily overloaded. This is typically twice its operating the PTC.
disconnecting them. Some types of load limiter current (Iop). Size the fuse as follows, so that
Figure 15-7 A load limiter should connect the service
reconnect automatically, others must be manually wire from the distribution system to the domestic wiring
there is no danger of the breaking capacity being
reset. The use of load limiters is strongly in the house. A PTC is used as a load limiter if less than exceeded: Note: Bypass prevention
0.5 Amps is drawn. Some form of protection is required to stop the
recommended for the following reasons:
• Load limiters are less expensive and more Breaking Capacity ≥ 3.0 x Iop load limiter from being bypassed. Suitable
Selection of PTC’s
easily installed than electricity meters. methods are using a seal or a small padlock on
The PTC has a current level at or below which, it
Consumers cannot draw more power than 3) Fuses are available with glass and ceramic the service box to discourage tampering.
is guaranteed not to trip (Int). This is used to
they have subscribed to. cases. The advantage with glass is that it is easy
determine which PTC should be used to limit a
• The collection of revenue from the scheme is particular load.
simplified if the tariff is a fixed amount each The switch allows safe rewiring of domestic
month. circuits and increases the ease of fault
• The total consumer load can be matched to detection by allowing the domestic circuit to be
the generator output. This means that the isolated easily from the supply. A fuse must be
generator will not become overloaded and the connected in series with the switch in the live
system voltage and frequency will be and sized to protect the PTC from high currents
maintained. that could cause it to fail.
• Domestic wiring is automatically protected A double-pole switch is used to ensure that both
from high currents the live and neutral can be disconnected. A
single-pole switch would make faults that caused
The type of load limiter used, depends on the the RCD to trip difficult to isolate because the
amount of current which is drawn: neutral would still be connected. A double-pole
If less than 0.5 Amps is drawn use a PTC switch also offers greater protection to loads
(Positive Temperature Coefficient Thermistor) from lightning strikes, provided that consumer
If more than 0.5 Amps is drawn use an MCB or disconnect their loads using the switch during
an Electronic Current Cut-out (ECC). storms. The current rating of the switch should
be at least two times the rating of the fuse. The
If a PTC is used then a fuse and an isolation voltage rating must be greater than or equal to
switch are also required. The fuse prevents the the generator voltage rating.
PTC from being damaged by high currents. The
switch allows safe rewiring in the house and
Selection of Fuses
makes fault-finding easier.
There are five considerations for fuse selection
to include in a load limiter of the design
described.

pmaher 31/05/01
15-3 pmaher 31/05/01
15-4
Lightning Protection Lightning Protection

This is a very rough guide. To obtain an accurate result from a direct strike, they are still becomes an excellent conductor above the
estimate about the risk of lightning, talk to dangerous, particularly for electronic equipment. threshold. They are faster acting and usually
16 LIGHTNING people from the community where the Voltages are induced both between live and clamp to lower voltages than spark-gap
distribution system will be installed to find out if neutral and neutral and earth. The “line-to- arrestors, therefore providing better protection
PROTECTION OF local lightning is frequent or rare. neutral” voltage surge can be reduced by twisting for electronic equipment such as TVs, CFLs with
the cables together if insulated conductors are electronic ballasts, and generator controllers.
PICO HYDRO This section deals with lightning protection from used. For low current ratings, they are very cheap
direct and indirect strikes on the distribution (about $1) as they are mass-produced for use in
SCHEMES lines. domestic appliances. However, for the higher
16.1 Direct Lightning Strikes 16.3 Lightning Arrestor Types current ratings designed for use on overhead
16.2 Indirect Lightning Strikes 16.1 Direct Lightning Strikes Spark-gap lines, they are expensive ($50 to $100)
16.3 Lightning Arrestor Types especially when compared to spark-gap devices.
No equipment exists that provides full The conventional lightning arrestor consists of a
16.4 Protection of Powerhouse Equipment
16.5 Protection of Consumer Loads protection in the event of direct strikes. For spark gap for the lightning to arc across and a Powerhouse Distribution Consumer
this reason it is essential that the risk of direct series resistance to limit the flow of current System Loads
Ballast
Lightning can cause death and injury and damage strikes is reduced as much as possible by careful after the voltage surge. They are generally Load Lightning
Induction isolation Arrestor Lightning Mains switch
to buildings and equipment. Measures must be routing of the distribution system. The risk of slower acting than more modern arrestors and do Generator
RCD
switch on 1st pole Arrestor at consumer
L connection
IGC L L
taken to minimise these risks, especially in areas direct strikes is reduced if the distribution is not clamp the voltage at as low a value. They
of high lightning activity. run through a large area of trees as there is a offer reasonable protection to electrical
N N N

good chance that lightning will strike a tall tree equipment such as wiring and motors but little
500m max.
Earth L
Risk Estimation some distance away rather than the cables protection to electronics. Prices are typically
Connection
Varistors may
Weighting Factor A: Degree of Isolation themselves. When the number of trees is small, $10 to $20. Select the voltage rating so that also be connected
across the consum
it is best to keep the distribution at least 10m the arrestor does not operate under normal
supply if a PTC is
Structure located in a large area 0.4 Extra varistors
N used.
away as the lightning may jump across from a voltage conditions but comes into operation if
connected
of structures or trees of the across output
tree which is struck. This is because cables the voltage exceeds maximum setting of the
terminals of IGC.
same or greater height e.g. in a
provide a lower resistance path to earth. over-voltage trip on the IGC (see Section 9.6). It
forest
is important the voltage rating is low enough to Figure 16-2 Connection of lightning arrestors to prevent
Structure located in an area with 1.0
Avoid routing the distribution along exposed protect the generator but not so low that the
damage to electrical equipment and reduce danger to
few other structures or trees of electricity consumers
ridges, particularly in lightning prone areas. If it arrestor is triggered by fluctuations in the
similar height
is essential to do this, then use buried, armoured generator voltage (for example, this can happen
Structure is completely isolated 2.0
or exceeding at least twice the
cable. Whenever possible, route the distribution if the load is suddenly disconnected). The life of 16.4 Protection of Powerhouse Equipment
in valleys. lightning arrestors can be shortened if they are A lightning arrestor is connected line-to-neutral
height of surrounding trees
triggered in this way. on the first distribution pole immediately outside
Note on Overhead Ground Wires (OGW) the powerhouse as shown in Figure 16-2. A
Weighting Factor B: Type of Country
Some people have recommended the fitting of an single-pole load isolation switch is used instead
Flat country at any level 0.3
overhead earthed wire, above the line and of a double-pole one so that the neutral is
Hill country 1.0
neutral conductors with the aim of conducting earthed even when the load is isolated. This
Mountain country between 300m 1.3
lightning discharges to earth. This is not ensures that there is always a path to earth.
and 900m
recommended for low voltage distribution Whenever possible during lightning storms, the
Mountain country above 900m 1.7
networks. The reason is that the lightning may distribution system should be disconnected using
jump between this wire and the line and/or this switch and the generator shut down.
Try to identify on the map (Figure 16-4) the
neutral causing a dangerous voltage on these
number of thunderstorm days per year in the
conductors. This approach only works on very Protection of the IGC
region closest to you. Multiply by Weighting
high-voltage transmission systems due to the
Factors A and B and use the following table to A varistor is fitted (soldered) to the IGC circuit
much larger air gap between the OGW and the
estimate the risk of lightning. board to protect the more sensitive electronic
conductors and frequent earthing of the OGW.
Figure 16-1 Spark gap lightning arrestors components. It is recommended that in medium
Risk Estimation by number of and high risk areas, additional varistors are
16.2 Indirect Lightning Strikes Varistors
thunderstorm days per year fitted to provide extra protection. These should
An indirect strike is where lightning strikes Varistors have neither a spark gap or series be connected in parallel across the output
High Risk More than 100
close to the distribution line as this will induce resistance. They consist of two electrodes terminals as shown in Figure 16-2. Several
Medium Risk 25 to 100
high voltages in the cables. Whilst these separated by a material that is a good insulator devices connected in parallel allow greater
Low Risk Less than 25
voltages are not as high as the ones which can below a certain threshold voltage and which

pmaher 31/05/01
16-1 pmaher 31/05/01
16-2
Lightning Protection Lightning Protection

current handling to reduce the voltage across that do not contain electronics are reasonably
the sensitive electronic components in the IGC. well protected by spark-gap arrestors. However,
loads that contain electronics, such as TV’s,
The additional varistors should have a voltage radios and CFL’s are much more sensitive and
rating at least 25% above the rated voltage of require varistors for protection. The best
the distribution system. This will avoid them protection is provided by pole mountable
being damaged under normal operating varistors with current rating of more than
conditions. However, their voltage rating should 50,000 Amps as these can withstand very high-
be less than the voltage rating of the soldered energy discharges.
varistor. If they are damaged then they can
easily be replaced on site as they are not A cheaper alternative that works particularly
soldered. For example, if a varistor with an AC well with PTC themistor load-limiters (see Figure
voltage rating of 420V (usually the case) is 15-7) is to fit a disk-type varistor between line
already fitted to the IGC then additional and neutral on the load side of the limiter and
lightning protection can be achieved by have a pole mounted spark-gap arrestor. In the
connecting devices with 320V rating. event of lightning induced surge, the varistor will
clamp the voltage in the house, with the
16.5 Protection of Consumer Loads additional voltage being dropped across the PTC.
It is difficult to specify the number of lightning Once the voltage is high enough, the spark-gap
arrestors required for a scheme as it depends on arrestor will operate and conduct most of the
many factors, including the frequency of current. Note that this puts extra stresses on
lightning, expense of replacing damaged the PTC. However, these are cheaper to replace
appliances and the cost of the arrestors. than most domestic appliances. Figure 16-4 Map showing thunderstorm days per year
Electrical guidelines for micro hydro in Nepal throughout the world (based on World Meteorological
During stormy weather, consumers should be records for 1955)
state that the maximum distance of a consumer
from an arrestor is 500m and less in areas where encouraged to disconnect their supply via the
the risk of lightning strikes is high. When mains switch at the entrance to their house.
selecting the precise location to protect a Note the use of a double pole switch at the
number of consumers, preference should be consumer service entrance to isolate the live and
given to points in the system which are near to the neutral (Section 14.4). This is the most
areas where lightning is more likely to strike. secure method to prevent damage to delicate
loads such as CFL’s. Where the consumer
When fitting arrestors, the neutral is normally premises require an earth, it is important that
earthed at the lightning arrestor to minimise the the consumer earth is separate from the earth
neutral to ground voltage surge, as this can cause to which the lightning arrestor is connected and
the insulation to break down. This is not preferably 10m or more away. This is because
achievable when an RCD is fitted in the high currents to earth can result in dangerous
powerhouse, as earthing the neutral will cause voltage potentials close to the earth connection.
the RCD to trip. However, the neutral can be Earthed
earthed through an additional lightning arrestor, Consumer
as shown in Figure 16-3. Load

Selection of Lightning Arrestors


The neutral-to-ground lighting arrestor can be a
conventional spark-gap type, since it is only
required to prevent insulation breakdown. min. 10m

The selection of the line-to-neutral lightning


arrestor depends on the type and value of the
Figure 16-3 Ensure that the consumer earth
loads to be protected. Loads such as electrode (if used) is at least ten metres from
incandescent light bulbs, motors and heaters the neutral-earth arrestor electrode.

pmaher 31/05/01
16-3 pmaher 31/05/01
16-4
Testing, Commissioning and Operation Testing, Commissioning and Operation

This voltage should rise to approximately the • To measure the frequency use a frequency 17.6 Commissioning the distribution
same voltage as the generator. meter or use a tachometer and calculate
17 TESTING, • Check the ballast meter to ensure that the from the speed (generator shaft rpm’s) as
system.
• Check all distribution poles and cables to
reading is greater than zero. This indicates follows:
COMMISSIONING that the controller and ballast are
ensure that they have been installed safely
paying particular attention to ground
functioning. If no voltage is produce or the Number of poles Frequency (Hz)
AND OPERATION ballast meter reading is zero, refer to 2 Shaft speed / 63
clearance and cable sag.
• Check all house wiring has been safely
Section 18. 4 Shaft speed / 31.5
installed and that consumers have been
17.1 Final Checks • Adjust the position of the nozzle plate to 6 Shaft speed / 21
instructed about the dangers of electricity.
Check the following before starting the turbine give the highest ballast reading.
• If inductive loads such as tube lights or
• Calculating frequency from the speed is
for the first time. motors are connected, measure the
17.3 Generator connection accurate to about 5%.
• The generator, motor protection switch and frequency when these are operating. If
There are two possible connections for the • The frequency can be adjusted by altering
connecting cable have been correctly sized frequency is too high then apply power
generator. Only one is acceptable. Continuous the amount of capacitors connected.
(Section 9.8) factor correction to the significant inductive
operation with the wrong connection is likely to Removing capacitors increases the frequency.
• The generator, capacitors, controller, loads.
damage the generator. Twice the amount of capacitance must be
ballast, RCD, motor protection switch and
• Note the ballast reading when the valve is added or removed from the 2C as from C
earth-electrode have been connected 17.7 Operation
fully open. (see Figure 9-7).
according to Figure 9-7 and manufacturers To start the generator:
• Close the valve and remove the cover on the • If the turbine will be operated over a range
instructions. • disconnect the consumer loads.
generator terminal box when the generator of flows, then check the frequency over the
• All connections are tight and cable insulation • open the flow control valve slowly until fully
has stopped rotating. whole range and correct if necessary.
has not be stripped back further than open or desired power output is achieved.
• Reverse the connections labelled “L” and “2C” Note that changing the frequency will effect the
necessary (no bare cable should be exposed • connect consumer loads.
(see Figure 9-7). power output as it will change the turbine
at connection blocks). • If a large amount of power is being
• Replace the cover, start the turbine by fully efficiency and generator efficiency. The change
• The turbine and generator are free to dissipated in the ballast, consider reducing
opening the valve. is best observed by reading the ballast meter
rotate. the flow in order to reduce the temperature
• If the new ballast meter reading is greater with no user loads connected.
• Any moving parts such as pulleys and belts of the ballast and increase its life.
have safety guards to protect people in the than before then this is the correct
connection. If not, restore the connections
17.5 Size of ballast load
powerhouse. To stop the generator:
• The motor protection switch and RCD are to their original position after closing the The ballast meter should read between 40% and
• disconnect the consumer loads
switched on. valve and waiting for the generator to stop. 100% when no user loads are connected.
• slowly close the flow control valve until it is
• The tailrace is free from obstruction Note: That with the correct connection the • If below 40% then the ballast is too large
completely closed.
• The penstock joints are watertight and the generator will run more quietly less hot. and should be replaced by a smaller one. For
penstock is anchored or buried. example, some of the resistive elements (e.g.
• The penstock filter is free from debris. 17.4 Adjusting voltage and frequency. the cooking rings) can be disconnected.
• The voltage (indicated by the voltmeter) is • If 100% then check that all elements are
17.2 Start-up set by the controller. Adjust the setting on heating up. If some elements are cold, check
the controller by following manufacturers connections and, if possible, the resistance
• Disconnect user loads connected to the
instructions in order to obtain the required of the element.
distribution system using the mains switch
value. • If all the elements are working and the
located near the controller (Note: MCB and
The frequency value should be 49 Hz to 52.5 reading is still 100%, increase the size of the
RCD should be in ON position). •
Hz for a 50 Hz system (59 Hz to 63 Hz for a ballast load without exceeding the maximum
• Open the gate valve near the nozzle slowly to
60 Hz system). rating for the controller or generator.
about half full flow. Wait 60 seconds to allow
Do not operate below the minimum • If this is not possible, then operate the
any soil and air in the penstock to be flushed •
frequency values given. The life of the turbine at reduced power output.
out.
generator and other devices connected will Alternatively increase the capacity of the
• Turn off the valve and remove the turbine
be reduced. controller and/or the generator.
cover. Inspect the nozzle for any
obstructions. If any are found, disconnect • A frequency slightly above these ranges will
the nozzle to remove them. not usually have a detrimental effect unless
• Replace the cover and slowly open the valve. speed dependant motor loads such as pumps
• The generator should excite and this will be or fans are connected.
indicated by a reading on the volt meter.

pmaher 31/05/01
17-1 pmaher 31/05/01
17-2
Fault-finding Fault-finding

RCD operates Current leaking to ground either • Disconnect consumer loads and restart to
18 FAULT-FINDING in powerhouse or elsewhere establish if the fault is in the powerhouse. If
in powerhouse check wiring of earthed
Problem Possible Causes Solution
devices (e.g. controller casing) to locate
No voltage/low power Insufficient turbine power • Check water supply, nozzle and generator
earth fault.
output speed.
• If fault is elsewhere in the system,
Wiring fault • Check wiring and MCB and RCD are switched disconnect all earthed consumer loads
on. • Check lightning arrestors for short to ground
Capacitor values incorrect • Check capacitors are connected as shown in by temporarily disconnecting.
the wiring diagram. Individual house Load limiter tripped • disconnect all domestic loads and wait for 5
• Check capacitor values are correct for minutes. Reconnect less loads than before
without power
generator.
load limiter fuse blown • check fuse.
Generator has lost residual • Disconnect consumer load. When generator is
Wiring fault • check service wire connection
magnetism stationary, connect a battery of 6V or more
• check domestic wiring
across any two generator terminals for one or
Group of houses Wiring fault • check distribution cable connected to the
two seconds. Re-start with no user load
without power houses for a fault
connected.
Ballast loads not connected • Check for loose or missing connections All houses without Wiring fault • check wiring of main consumer switch in
Over-voltage trip properly (ballast meter reads • Check that any switches in the ballast circuit power (generator, powerhouse
operates 100%) are on. controller and ballast • check first section of distribution cable for
• Check that all ballast loads become hot. If breaks .
working normally)
not, measure resistance and replace if •
necessary.
Further notes on fault finding:
Generator output higher than IGC • Operate turbine at reduced power output or
rating replace IGC with one of higher rating
Controller damaged and fails to • Check whether fault is due to incorrect wiring 1. Loss of Residual Magnetism
deliver power to ballast (ballast of IGC. If not, then replace circuit board. If consumer loads are left connected when an
meter does not operate or only induction generator is stopped it is likely that
over a limited range), the residual magnetism will be lost. This small
Ballast trip lamp lit Ballast short circuited • Check resistance between ballast leads and magnetic field is required to build up the
between each ballast lead and earth to test
excitation currents and allow the induction
for short circuits. Repair or replace faulty
generator to work at the voltage required. If
wiring / ballast loads.
excitation does not occur, then the voltage (and
Ballast load too large • Check that the power rating of ballast is less
than or equal to the power rating of the IGC. power) will be approximately zero when the
Light bulbs flicker Response speed of controller • Alter setting of response speed turbine is rotating. If this is the case, then a dc
incorrect. potentiometer on circuit board. power source such as a battery should be
Ballast load much greater than • Reduce capacity of ballast load. connected across any two of the generator
generator rating. terminals before starting the turbine. A 6V, 9V
Uneven turbine output • Check turbine for misalignment, damage or or 12V lead acid battery would be suitable for
blockage. this or several large torch batteries connected
• Check for badly worn bearings. in series and should be connected for 1-2
Motor protection switch Generator connection incorrect • Check generator connections. seconds only. Note: Care must be taken when
operates using lead acid batteries not to short-circuit the
Too much excitation current • Reduce the amount of capacitance connected. terminals as the battery can explode!
(motor protection switch operates
even when turbine operating at
reduced power output) 2. Check for damaged capacitors
Too much load current (motor • Increase rating of motor protection switch Ideally check the capacitor value with a
protection switch operates with and generator if necessary. capacitor meter. Otherwise the operation of
turbine operating at full power • Operate turbine at reduce power output capacitors can be verified with a multimeter -
output) • Avoid overloading the generator
measure the resistance (should be high and
Short circuit in distribution • Isolate sections of the distribution system
increasing as capacitor is charged by meter
system until the fault is found. Alternatively measure
battery) A low resistance indicates that the
the resistance at different sections to
identify the fault. capacitor is damaged and it should be replaced.

pmaher 31/05/01
18-1 pmaher 31/05/01
18-2
Appendices Appendices

Direct current system (dc)


1) Power required by load is 200W
19 APPENDICIES 2) Voltage is 12V dc Current

Appendix A Basic Electricity V oltage


Pow er

I = P/V
0

Voltage, Current, Power = 200/12 π

= 16.7 Amps
Electricity is a very convenient form of energy.
High current means high losses in electric cables φ = − 90°

It can be generated in one place and then


because of the cable resistance.
transported to where it is needed. At the flick Series = 2 x voltage
of a switch, it can be made to do useful work Connection of one battery Figure 19-4 If the load is a pure inductor, then the
AC Waveforms current lags the voltage by 90°. The average power
such as create light, heat or run motors. The
The AC voltage which is produced by a consumed is still = 0 Watts
driving force that causes electricity to flow is
synchronous or induction generator has
called the voltage. The electricity flow itself is
approximately the same shape as a sine wave.
known as current. Electrical power is a
When a load is connected, the current will have a
combination of voltage and current. The power,
Parallel
similar shape and the same period ( period = time
measured in watts or kilowatts is used to
Connection for one complete wave ). The frequency is the Voltage Power C urrent

describe the rate at which the energy is used.


= 2 x current number of complete waves in 1 second. For 0
π

of one battery example, the complete wave shown in Figure 19-2 φ = −30°

Resistance is repeated 50 times in one second if the


Figure 19-1 Series and parallel connection of batteries
The amount of current which flows depends not frequency is 50 Hertz.
only on the voltage which is driving but also on
the resistance of the material through which it Direct current at 12V can be produced using a If the load is purely resistive (for example a
is passing. Materials such as copper have a low car alternator. The maximum power however, is heater or light-bulb), then the current then the
Figure 19-5 General circuits are combinations of
limited to about 500W. resistance, capacitance and inductance. Here the current
resistance allowing current to pass easily. These current will alternate at exactly the time as the lags the voltage by 30° as the load is both resistive and
are called conductors. Materials that have a high voltage. The current and voltage are said to be inductive. The power factor (cosφ
φ) is close to 1 and the
resistance, such as most plastics, are called Alternating current (ac) is used to describe “in phase” amount of reactive power consumed is small but must still
insulators. electricity that is repeatedly changing direction. be supplied by the generator.
The rate at which this happens is called the
Real and Apparent Power
AC and DC Electricity frequency. Induction generators and synchronous V oltage

generators produce ac electricity. One major The basic formula for power is current times
Direct Current (dc) is the type of electricity Pow er voltage:
advantage of ac is that the electricity can be
that is stored in a battery. The current flows
generated at a much higher voltage, e.g. 120V or 0
φ = 0° π /2 π 3π / 2
from positive (+) to negative (-) if the battery is
220V than that of dc systems using batteries. Current
19.2 Power (apparent) = I x V
connected to a load. Battery voltages vary. For However, for ac circuits this is not the whole
example, they may be 1.5V, 6V, 9V or 12V. If two story as this is only the apparent power. To
Higher generator voltage means that the current
batteries are connected in a line (series), then calculate the real power an additional factor is
required to deliver a certain power is less. If the
the voltage is doubled. If both batteries are Figure 19-2 AC waveforms can be approximated to a sine needed called the Power factor.
current is less then the power losses in cables
connected in parallel then the currents capability wave. If the load is a pure resistor, then the current
are also less. This means that with ac, it is Using the Power factor (Pf) the real power can
which flows is in phase with the generated voltage
is doubled. Never short the terminals of a be calculated:
possible to transport electricity efficiently over
battery as they explode.
long distances.
Power (real) = V x I x Power factor
The time over which a particular current can be V oltage

The following ac and dc system have been


produced, also varies from battery to battery. Real power is measured in Watts (W) and
compared for a supply to five 40W light bulbs: Pow er
Current

For example, a sixty amp-hour (Ah) battery could apparent power in Volt-amps (VA).
Alternating current system (ac)
produce one ampere of current for sixty hours
1) Power required by load is 200W
0

or twenty amperes for three hours. Only π


The reason for this difference is that there are
2) Voltage is 220V ac φ = 90°
batteries with identical voltage and amp-hour two types of electrical loads; resistive loads and
I = P/V
rating should be connected together in the same reactive loads. With resistive loads the current
= 200/220
circuit. For more information about battery is in phase with the voltage as shown in Figure
= 0.91 Amps Figure 19-3 If the load is a pure capacitor, then the
types, see Section 13.1. 19-2 and in this case the power factor=1 and the
current leads the voltage by 90° and the average power
consumed = 0 Watts real power equals the apparent power. Reactive

pmaher 31/05/01
19-1 pmaher 31/05/01
19-2
Appendices Appendices

loads may be either inductive or capacitive. Appendix C Turbine Operating Speeds for A useful guideline is to use the synchronous
Purely reactive loads draw current consume no Mechanical Loads speed of the motor. This will be slightly less than
net power as shown in Figure 19-3 and Figure the operating speed when the generator is being
Apparent Power S (VA)
19-4 as for half a cycle the power dissipated is A Operating speed under driven (synchronous speed + 3% slip) This will
heavy mechanical load

Power (kW)
positive and for half a cycle it is negative. In Reactive (synchronous speed - 10%) mean that under normal conditions of operating
these cases the power factor=0 and real Power Q Pelton turbine B Operating speed under the mechanical load electricity will not be
speed characteristic light mechanical load
power=0. The combination of resistive and (VAR) under changing load (syncronous speed) generated, but the turbine will still be deliver
Pmax
C Operating speed when
reactive requirements of a particular circuit is φ generator only is connected maximum power. The synchronous speeds for 2
(syncronous speed + slip)
referred to as the impedance. A leading power pole (3000rpm), 4 pole (1500rpm) and 6 pole
factor (p.f. > 1.0) indicates that a load is more Real Power P (Watts) (1000rpm) induction machines have been used in
capacitive than inductive. A lagging power factor So the “Power per Belt” tables (Table 13-5 and
(p.f.<1.0) indicates that the load is more P= S x cosφ Table 13-6)
inductive than capacitive. (Power factor = cosφ)
Appendix D: Additional Notes on Belt
When the power factor equals 1.0, then the net and Sizing
A B C Speed (rpm)
requirement for reactive power is zero and only
S = P2 × Q2 Figure 19-7 Ideal operating speeds of Pelton turbine The guidelines given in Sections 13.5 and 13.6 are
resistive power is supplied. Power factor
under different load conditions sufficient for approximate matching of pulleys
correction means to bring the power factor Figure 19-6 Power triangle showing relationship between and belts to loads. However, the following two
closer to one and reduce the reactive power real and apparent power. If the speed of the turbine for driving the
factors have not been taken into account in the
consumption. In practice this usually means mechanical load is carefully chosen, then it is
“Power per Belt” tables.
connecting capacitors in parallel with an inductive possible to allow the induction generator to be
Power Factor Correction used as a brake for the mechanical load thus
load to raise the power factor.
Circuits which have a lagging power factor 1) Long belts can deliver more power than short
regulating its speed. This reduces wear and has
caused by inductive loads (see Figure 19-4) such ones.
Since the reactive power does not show up on an advantages during processes such as milling, for
as electric motors or fluorescent lamps, require 2) A pulley ratio which is speed reducing (a
electricity meter, domestic consumers are not example, producing a more evenly ground flour.
a supply of reactive power. For small loads small pulley is driving a larger one) can also
normally charged for reactive power. However Any surplus power, not required by the
connected to the electricity grid, this does not deliver more power than a drive which has
this extra reactive power must still be provided mechanical load will be dissipated in the
present a problem as the reactive power can two pulleys of equal size.
by the generator. So to prevent a pico hydro generator or ballast, preventing the load and
system from becoming overloaded, power factor easily be supplied. However, this may not be the turbine from over-speeding.
case with small stand-alone induction generators. Ratio SPZ SPA SPB
correction is often an important consideration
Power factor correction is sometimes necessary The operating speed of an induction generator is 1:1 >550 >760 >1050
for the developer.
in these situations to allow the most efficient typically the synchronous speed +3%. This is the 2:1 >600 >850 >1150
use to be made out of the power available. speed when electrical power is delivered to the 3:1 >600 >850 >1200
A power factor of 1.0 means that a load is purely
resistive. No reactive power is used and real and controller and consumers. At about 10% below 4:1 >650 >900 >1260
apparent power have the same value. If the The term “power factor correction” means to the synchronous speed, there is no net 5:1 >650 >950 >1260
power factor is less than one, then the load is increase a lagging power factor towards 1 so that generation of electricity. Table 19-2 Add 5% to power per belt if Centre
partly inductive. Power factors of some typical the amount of reactive power required by a Distance (mm) is greater than the above value.
loads are given in the following table: circuit is reduced (see Figure 19-5.). This can be The use of an induction generator controller
achieved by connecting capacitors across the The pulley belt can be sized to a greater level of
regulates the turbine speed under both varying
load. Capacitance causes the current to lead the accuracy if Table 19-2 and Table 19-3 are used.
Load Power factor mechanical and electrical load conditions. When
voltage rather than lag behind. This can be For a belt which is longer than the values given in
the mechanical load is reduced causing the speed
Incandescent lamp 1.0 understood by comparing Figure 19-3 and Figure Table 19-2 (values in mm), 5% can be added to
of the turbine to increase, the controller begins
Fluorescent lamps 0.5 - 0.7 19-4. The net effect of this is that the total the power. For example, If an SPZ belt is used
to divert the excess power to the ballast. This
Motors 0.2 - 0.95 reactive power requirement of the circuit is on a pulley system that has a ratio of up to 2:1,
increases the load on the turbine and therefore
reduced. Additional considerations are the the power can be increased by 5% when the
Table 19-1 Variation of power factors for common loads is able to control its speed. The action is similar
availability and cost of suitable capacitors and centre distance is greater than 600 mm.
to a mechanical brake.
how much capacitance to connect. These may
Power Triangle
determine to what extent the power factor can So what speed should be chosen as the design
The relationship between real and apparent
be corrected. However, it is important to avoid speed for the turbine shaft when sizing a pulley
power and power factor can be summarised in a
over-correction of the power factor. Selection system for a mechanical drive?
“power triangle.”
of capacitors for power factor correction is
explained in Section 13.1.

pmaher 31/05/01
19-3 pmaher 31/05/01
19-4
Appendices

SPZ SPA SPB


rpm’s of
turbine
shaft 20 USEFUL REFERENCES AND ADDRESSES
1000 0.15 0.39 0.81
References:
1500 0.23 0.58 1.21
3000 0.46 1.17 2.42
1. Harvey, A. et al. ‘Micro Hydro Design Manual,’ Intermediate Technology Publications, 1993.
Table 19-3 Additional kW per belt if Ratio is 1.95
or greater and turbine pulley smaller than the load 2. Inversin, A. ‘Mini Grid Design Manual,’ ESMAP, World Bank, 2000.
pulley

If the pulley ratio is 1.95 (1.95:1) or greater,


then the power can be increased by the amount Editorial Address
shown in Table 19-3. For example, if an SPA belt Micro Hydro Research Group
is chosen and the turbine speed is around 1500 Department of Electrical and Electronic Engineering
rpm, the power which that belt can deliver The Nottingham Trent University
increases by 0.58 kW if the ratio is 1.95 or Burton Street
more. Nottingham
NG7 4BU

Tel. +44 (0) 115 848 2885


Fax: +44 (0) 115 948 6567
Email: phillip.maher@ntu.ac.uk
Web: http://eee.ntu.ac.uk/research/microhydro/picosite

Intermediate Technology Publications


103-105 Southampton Row
London WC1B 4HH

Tel: +44(0) 171 436 9761


Fax: +44(0) 171 436 2013
Email: orders@itpubs.org.uk
Web: http://www.oneworld.org/itdg/publications.html

ESMAP
C/o Energy, Mining and Telecommunications Department
The World Bank
1818H Street, NW
Washington, DC 20433
U.S.A.

pmaher 31/05/01
19-5 pmaher 31/05/01
20-1
Head the vertical drop of a water in a stream or in the penstock; measured in metres
21 GLOSSARY Induction Generator Controller – and electronic device used to keep the voltage and frequency steady
IGC

Abney level a device used for measuring the incline of a slope; can be used to calculate the head Incandescent lamp simple lamp with a wire filament

ac alternating current; electric current which changes direction at frequent intervals .e.g. at 50Hz or Induction generator source of ac electricity
50 times per second
Induction motor electrical machine which can be used to drive mechanical loads
Altimeter a device which uses air pressure to calculate difference in vertical height between two points
Intake point where water enters the penstock
Ballast load usually an electrical heating element which consumes any unused power produced by the generator
Lighting package an electricity supply suitable for one lamp and possibly a radio
Battery used for storing dc electricity; re-chargeable batteries (e.g. lead-acid, Nickel Cadmium) can be used
to light houses which are too far from the generator to have a connection Lightning arrestor a device which allows current surges caused by lighting strikes to be conducted away to ground

Belt drive system for transferring rotating mechanical power from one shaft to another using pulley wheels and Load a device which uses the power produced by the generator
belts
Load control a system to keep the amount of load on the generator constant
Bucket method method of flow measurement using a bucket of known volume and a stopwatch
Load limiter a device which prevents too much current being taken by a consumer
Canal can be a practical and low cost method in some rural areas of transporting water to the forebay and
reducing the length of penstock required Low-pressure pipe can be used as a cost-effective alternative to a canal to bring water to the mouth of the penstock

Capacitor electronic device used to allow induction motors to work as generators; also used for power factor MCB Miniature Circuit Breaker; alternative safety device to the fuse with the advantage that it can be
correction; capacitance is measured in micro Farads ( F) reset after tripping due to a short circuit or overloading

CFL Compact Fluorescent Lamp; energy efficient light bulb requiring less power than other varieties Meter device which displays the level of generator voltage or ballast power

Current the rate of flow of electrons through a circuit; measured in Amps Motor Protection Safety device which disconnects if too much current is drawn. Unlike an MCB, which operates at only
one current level, the tripping current can be selected from a range, e.g. 6 to 10 amps.
Switch
dc direct current; electric current flowing in one direction
Over-voltage trip protection circuit built into the IGC which automatically disconnects the supply to protect the
consumer loads if the voltage rises too high
Demand survey Assessment of the power requirements and ability to pay of a community

Pelton turbine rotating wheel with buckets around the outside which absorb the power of a water jet and convert it
Distribution system wiring system which connects houses to the generator
into rotating mechanical power; most Pelton designs require a head of 20 metres or more to work
efficiently
Distribution pole supports for distribution cable

Peltric Set design of pico hydro unit which is popular in Nepal


Domestic wiring electrical system inside a house

Penstock pipe containing water under pressure: brings water from forebay to powerhouse
Earth-fault a wiring fault allowing current to leak to the ground

Pico hydro hydro power with a maximum electrical output of 5kW


Efficiency the word used to describe how ell the power is converted from one form to another; it is the ratio of
the output power to the input power expressed as a percentage; the efficiency of a pico hydro
p.c.d. pitch circle diameter; diameter line around a Pelton turbine at the centre of jet interaction
system is usually about 45%.

PTC Positive Temperature Coefficient Thermistor; electronic device which can be used as a low-cost form
Emergency lighting tube light with rechargeable battery which can be switched on when the electricity supply fails
of load limiting

Energy storage energy storage may be required if the flow of water cannot be guaranteed to be high enough
Power measurement of energy supply and demand; given in Watts(W) or Kilowatts(kW); may be hydraulic
throughout the year; batteries and reservoirs are examples of how energy can be stored
power, mechanical power or electrical power.

Flow measurement of the quantity of water flowing past a point in one second; measured in metres per
Power factor reducing the reactive power requirements of loads such as induction motors and fluorescent lighting
second or litres per second and used to calculate the hydraulic power
by connecting capacitors of certain value across the supply.
correction
Forebay structure which is sometimes used for pico hydro at the start of the penstock ensuring that the
Powerhouse building which contains the turbine, generator and any directly driven mechanical loads
water is sufficiently deep

RCD Residual Current Device; used to disconnect the supply in the event of an earth
Frequency the switching backwards and forwards of alternating current; measured in Hertz (cycles per second)
fault

Fuse electrical safety device which prevents damage to circuits or appliances caused by short circuits or
Reservoir small scale energy storage; sometimes used during the dry season if flows are insufficient; water
overloading

pmaher 31/05/01
21-1 pmaher 31/05/01
21-2
collected during the day so that the turbine can be run in the evening for lighting

Resistance property of materials related to how well they conduct electric current e.g. plastic has a high
22 INDEX
resistance and is called and insulator, copper has a low resistance and is called a conductor; Abney Level (Clinometer), 7-1, 7-3 mechanical, 2-3, 9-9, 12-3, 13-1, 13-7, 13-8, 13-
resistance is measured in ohms (!)
Ballast Heaters, 9-5 12
Salt Gulp method of flow measurement by adding salt to the water and measuring the conductivity change
Battery charging, 5-4, 9-3 Meters
Stand-alone system Electricity system which is not connected to the National Grid Canals, 6-3, 10-1, 10-2, 10-4 ballast meter, 9-6
Capacitance voltmeter, 9-6
Transformer A device with allows the voltage of an ac circuit to be changed up or down by a fixed amount
excitation, 9-3 Miniature Circuit Breaker (MCB), 9-8, 9-9, 13-6,
(e.g. 240v to 12v) Sometimes the distribution voltage is raised so that houses further than 1km from
the generator can be connected. Higher voltage reduces losses in the cables.
power factor correction, 13-2, 13-3, 13-4 14-3, 14-7, 14-13, 15-3, 17-1, 18-1
Turbine nozzle restricts the flow of water at the end of the penstock to produce a high velocity jet Current, 8-2, 9-1, 9-8, 13-3, 14-8, 14-9, 14-10, Over-voltage trip, 9-6, 18-1
15-3, 18-2 Pelton turbine, 1-1
Valve device used to regulate the flow of water in the penstock. A gate valve is preferred Distribution Peltric Set, 8-1, 8-2
cable, 14-1, 14-3 Penstock
Voltage measurement of “electrical pressure” which is required in order for current to flow around a circuit;
measured in volts (v) layout, 14-2 diameter, 11-1
poles, 14-1, 14-4 materials, 11-2
Voltage drop loss of voltage across the distribution system because of the cable resistance. A voltage drop of up service connections, 14-7 pressure rating, 11-1
to ±6% is acceptable
Distribution System, 2-3, 14-1 Penstock Filters, 10-2
Domestic Wiring, 15-1 Pico hydro, 1-1, 2-1, 2-2, 4-1, 5-4, 8-1, 8-2, 9-3
Earth-fault protection, 9-1 Pipe
Efficiency, 2-2 drainage, 6-3, 10-4, 10-5
Energy storage, 6-3, 10-6, 13-4 flushing, 10-6, 11-2
Flow measurement, 7-1, 7-4, 7-9 Pitch circle diameter (p.c.d.), 8-3
Forebay tanks, 2-1, 6-2, 7-1, 7-2, 10-5, 11-2 Positive temperature coefficient thermistor
Frequency, 9-5, 9-7, 17-2 (PTC), 15-3
Fuses, 15-3, 15-4 Power
Head measurement, 7-1, 7-2 electrical, 2-2, 2-3, 4-1, 9-8, 9-9, 14-11
IGC hydraulic, 2-2, 2-3, 8-3, 9-8
installation of, 9-11 mechanical, 2-2, 2-3, 4-1, 8-2, 8-3, 10-7, 13-7,
Induction Generator Controller (IGC), 9-5 13-8, 14-11
Induction generators, 1-1, 9-3, 9-5, 9-7, 14-12 Power factor correction, 13-2, 13-3, 13-4
Induction motors, 1-1, 8-1, 9-3, 9-8, 9-9, 13-6, Powerhouse, 12-1
13-7, 13-9, 14-12 Reservoirs, 2-1, 6-3, 10-1, 10-2, 10-6, 10-7, 12-3
Intake design, 10-1 Residual current device (RCD), 9-1, 9-2, 9-9, 9-
Lighting 10, 15-1, 15-2, 17-1, 18-1, 18-2
compact fluorescent, 13-2, 13-4 Safety, 9-1
emergency, 13-5 Salt Gulp Method, 7-4, 7-7
incandescent, 13-1, 13-4 Scheme
packages, 5-2 layout, 6-1
tube, 7-2, 13-1 Scheme layout, 6-1
Lightning Arrestors, 9-9, 12-3, 18-2 Survey
Load Control, 9-1, 9-5 demand, 5-1
Load limiters, 15-3 site, 7-1
Loads Turbine nozzle, 2-1, 2-2, 8-2, 8-3, 9-5, 10-2, 11-1,
consumer, 2-3, 14-10 11-2, 11-3, 17-1, 18-1
electrical, 2-2, 2-3, 9-1, 9-2, 13-1, 13-4, 13-7, Voltage, 9-5, 13-3, 14-3, 14-9, 14-10, 14-12
14-8 Voltage drop, 14-8, 14-11
Water source, 2-1, 5-3, 6-2, 11-1, 14-1

pmaher 31/05/01
21-3 pmaher 31/05/01
22-1

You might also like