You are on page 1of 13

NAMA JESSICA CHATERINE PURBA

NIM 1870031008
KELAS P2K TEKNIK INDUSTRI

SOAL NO.1
Break-Even Analysis for WILLOW FURNITURE COMPANY

Fixed Cost ($) 8000 Units Revenue Fixed Total Cost Profit
Variable Cost ($) 65 40 7200 8000 10600 -3400
Revenue ($) 180 80 14400 8000 13200 1200
Analysis in Units 300 120 21600 8000 15800 5800
160 28800 8000 18400 10400
Total Cost ($) 27500 200 36000 8000 21000 15000
Total Revenue ($) 54000 240 43200 8000 23600 19600
Profit ($) 26500 280 50400 8000 26200 24200
BE in Units 69.57 320 57600 8000 28800 28800

SOAL NO.2
Break-Even Analysis for RETREAD TIRE COMPANY

Fixed Cost ($) 60000 Units Revenue Fixed Total Cost Profit
Variable Cost ($) 9 1000 25000 60000 69000 -44000
Revenue ($) 25 1500 37500 60000 73500 -36000
Analysis in Units 12000 2000 50000 60000 78000 -28000
2500 62500 60000 82500 -20000
Total Cost ($) 168000 3000 75000 60000 87000 -12000
Total Revenue ($) 300000 3500 87500 60000 91500 -4000
Profit ($) 132000 4000 100000 60000 96000 4000
BE in Units 3750 4500 112500 60000 100500 12000
Break-Even Analysis for WILLOW FURNITURE COMPANY
70000
60000
50000 Revenue
40000 Fixed
Total Cost
cost

30000
Profit
20000
10000
0
40 80 120 160 200 240 280 320
-10000

Break-Even Analysis for RETREAD TIRE COMPANY


150000

120000

90000 Revenue
Fixed
60000 Total Cost
cost

30000 Profit

0
1000 1500 2000 2500 3000 3500 4000 4500
-30000

-60000
NAMA JESSICA CHATERINE PURBA
NIM 1870031008
KELAS P2K TEKNIK INDUSTRI

PROGRAM LINIER SOAL NOMOR 1 (HAL 62)


Products Produk 1 Produk 2
Profit per unit 8 2
Resources Available Usage Left Over
Pon 4 5 20 2 18.33
Sumber Daya 2 6 20 20 0.00

Production Variable
Produk 1 0.42
Produk 2 0.00
Profit 3
Microsoft Excel 14.0 Answer Report
Worksheet: [Tugas Op. Riset.xlsx]PROGRAM LINIER
Report Created: 22/01/2020 06:47:49
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: Simplex LP
Solution Time: 0,047 Seconds.
Iterations: 1 Subproblems: 0
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0,000001, Use Automatic Scaling
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative

Objective Cell (Max)


Cell Name Original Value Final Value
$B$15 Profit Produk 1 3 3

Variable Cells
Cell Name Original Value Final Value Integer
$B$13 Produk 1 Produk 1 0.42 0.42 Contin
$B$14 Produk 2 Produk 1 0.00 0.00 Contin

Constraints
Cell Name Cell Value Formula Status Slack
$E$10 Sumber Daya Usage 20 $E$10<=$D$10 Binding 0
$E$9 Pon Usage 2 $E$9<=$D$9 Not Binding 18.333333333
NAMA JESSICA CHATERINE PURBA
NIM 1870031008
KELAS P2K TEKNIK INDUSTRI

PROGRAM LINIER SOAL NOMOR 2 (HAL 63)


Products Produk 1 Produk 2
Profit per unit 6 4
Resources Available Usage Left Over
Perakitan 1 (Jam) 10 10 100 23 76.67
Perakitan 2 (Jam) 7 3 42 42 0.00

Production Variable
Produk 1 2.33
Produk 2 0.00
Profit 14
Microsoft Excel 14.0 Answer Report
Worksheet: [Tugas Op. Riset.xlsx]PROGRAM LINIER 2
Report Created: 22/01/2020 06:58:27
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: GRG Nonlinear
Solution Time: 0,047 Seconds.
Iterations: 3 Subproblems: 0
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0,000001, Use Automatic Scaling
Convergence 0,0001, Population Size 100, Random Seed 0, Derivatives Forward, Require Bounds
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative

Objective Cell (Max)


Cell Name Original Value Final Value
$B$15 Profit Variable 0 14

Variable Cells
Cell Name Original Value Final Value Integer
$B$13 Produk 1 Variable 0.00 2.33 Contin
$B$14 Produk 2 Variable 0.00 0.00 Contin

Constraints
Cell Name Cell Value Formula Status Slack
$E$10 Perakitan 2 Usage 42 $E$10<=$D$10 Binding 0
$E$9 Perakitan 1 Usage 23 $E$9<=$D$9 Not Binding 76.666666667
onNegative
NAMA JESSICA CHATERINE PURBA
NIM 1870031008
KELAS P2K TEKNIK INDUSTRI

PROGRAM LINIER SOAL NOMOR 3 (HAL 63)


Products Gandum Beras
Price per unit 0.05 0.03
Resources Available Usage Left Over
Vitamin A (mg) 8 6 48 68 -20
VItamin B (mg) 1 2 12 12 0

Production Variable
Gandum 0.00
Beras 11.32
Harga Minimal 0.34
Microsoft Excel 14.0 Answer Report
Worksheet: [Tugas Op. Riset.xlsx]PROGRAM LINIER 3
Report Created: 22/01/2020 07:16:20
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: Simplex LP
Solution Time: 0,031 Seconds.
Iterations: 2 Subproblems: 0
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0,000001, Use Automatic Scaling
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative

Objective Cell (Min)


Cell Name Original Value Final Value
$B$15 Profit Variable 0.00 0.34

Variable Cells
Cell Name Original Value Final Value Integer
$B$13 Gandum Variable 0.00 0.00 Contin
$B$14 Beras Variable 0.00 11.32 Contin

Constraints
Cell Name Cell Value Formula Status Slack
$E$10 VItamin B (mg) Usage 12 $E$10>=$D$10 Binding 0
$E$9 Vitamin A (mg) Usage 68 $E$9>=$D$9 Not Binding 20
NAMA JESSICA CHATERINE PURBA
NIM 1870031008
KELAS P2K TEKNIK INDUSTRI

SOLUSI KOMPUTER UNTUK MASALAH TRANSPORTASI


(HAL 234-235)

DATA PERMASALAHAN
Jumlah yang Jumlah yang
Cerobong Butir Gandum Pengggilingan Biaya Penggilingan
Ditawarkan Diminta Cerobong Butir
Gandum
Kansas City 150 Chicago 200
Chicago A
Omaha 175 Omaha 100 Kansas City $6
Des Moines 275 Des Moines 300 Omaha $7
Total (Ton) 600 Total (Ton) 600 Des Moines $4

The Wheat Shipping Example


Mills Grain
Grain Elevators Supply
Chicago St. Louis Cincinnati Shipped
Kansas City 25 0 125 150 150
Omaha 0 0 175 175 175
Des Moines 175 100 0 275 275
Demand 200 100 300 600
Grain Shipped 200 100 300
Cost 4525
Biaya Penggilingan Formulasi Model Program Linier

Cincinnati Meminimumkan Z = $6X1a + 8X1b + 10X1c + 7X2a + 11X2b + 11X2c + 4X3a + 5X3b + 12X3c
St. Louis B C
$8 $10 Batasan :
$11 $11 X1a + X1b + X1c = 150
$15 $12 X2a + X2b + X2c = 175
X3a + X3b + X3c = 275
X1a + X2a + X3a = 200
X1b + X2b + X3b = 100
X1c + X2c + X3c = 300
c + 4X3a + 5X3b + 12X3c
Microsoft Excel 14.0 Answer Report
Worksheet: [Tugas Op. Riset.xlsx]MASALAH TRANSPORTASI
Report Created: 22/01/2020 07:51:39
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: Simplex LP
Solution Time: 0,031 Seconds.
Iterations: 8 Subproblems: 0
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0,000001, Use Automatic Scaling
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative

Objective Cell (Min)


Cell Name Original Value Final Value
$B$17 Cost Chicago 0 4525

Variable Cells
Cell Name Original Value Final Value Integer
$B$12 Kansas City Chicago 0 25 Contin
$C$12 Kansas City St. Louis 0 0 Contin
$D$12 Kansas City Cincinnati 0 125 Contin
$B$13 Omaha Chicago 0 0 Contin
$C$13 Omaha St. Louis 0 0 Contin
$D$13 Omaha Cincinnati 0 175 Contin
$B$14 Des Moines Chicago 0 175 Contin
$C$14 Des Moines St. Louis 0 100 Contin
$D$14 Des Moines Cincinnati 0 0 Contin

Constraints
Cell Name Cell Value Formula Status Slack
$B$16 Grain Shipped Chicago 200 $B$16=$B$15 Binding 0
$C$16 Grain Shipped St. Louis 100 $C$16=$C$15 Binding 0
$D$16 Grain Shipped Cincinnati 300 $D$16=$D$15 Binding 0
$F$12 Kansas City Shipped 150 $F$12=$E$12 Binding 0
$F$13 Omaha Shipped 175 $F$13=$E$13 Binding 0
$F$14 Des Moines Shipped 275 $F$14=$E$14 Binding 0