Professional Documents
Culture Documents
Schedule Risk Analysis ICEAA 2016 PDF
Schedule Risk Analysis ICEAA 2016 PDF
Design changes
Staffing Manufacturing problems
Contracting problems
Customer (government) not supportive
Cannot get subcontractor under contract
William Cashman, “Why Schedules Slip…”
Air Force Institute of Technology (AFIT) Master’s Thesis, 1995
30d
Design Unit 1
350
180 85% 237 85% 233
Cumulative Frequency
Cumulative Frequency
250
60% 230 60% 228
120
55% 229 55% 227
Hits
Hits
50% 227 200 50% 226
100
45% 226 45% 226
5% 216 5% 218
0 0% 215 0 0% 215
215 220 225 230 235 240 215 220 225 230 235 240
Distribution (start of interval) Distribution (start of interval)
Cumulative Frequency
Cumulative Frequency
250
60% 227 60% 228
250
55% 226 55% 228
Hits
Hits
200 50% 226 50% 227
5% 218 5% 219
0 0% 215 0 0% 212
215 220 225 230 235 240 215 220 225 230 235 240
Distribution (start of interval) Distribution (start of interval)
If we can get into trouble with this simple schedule, we can get into
trouble with real project schedules
85% 23 Sep 11
200
80% 21 Sep 11
75% 19 Sep 11
180
70% 18 Sep 11
Cumulative Frequency
60% 15 Sep 11
140
55% 14 Sep 11
Hits
80% Target is
120 50% 13 Sep 11
45% 11 Sep 11
100
9/21
40% 10 Sep 11
35% 09 Sep 11
80
30% 07 Sep 11
60 25% 06 Sep 11
20% 05 Sep 11
40
15% 03 Sep 11
10% 01 Sep 11
20
5% 29 Aug 11
0 0% 17 Aug 11
29 Aug 11 18 Sep 11 08 Oct 11
Distribution (start of interval)
Start
Finish
Design Unit 2 Build Unit 2 Test Unit 2
90% 02 Oct 11
85% 29 Sep 11
250
80% 28 Sep 11
75% 26 Sep 11
80th
70% 25 Sep 11
200
65% 24 Sep 11
percentile is
Cumulative Frequency
60% 23 Sep 11
55% 22 Sep 11
now Sept 28
Hits
45% 20 Sep 11
40% 19 Sep 11
35% 18 Sep 11
100
30% 17 Sep 11
25% 16 Sep 11
20% 15 Sep 11
50
15% 13 Sep 11
10% 12 Sep 11
5% 09 Sep 11
0 0% 30 Aug 11
08 Sep 11 18 Sep 11 28 Sep 11 08 Oct 11 18 Oct 11
Variation:7
Cumulative Probability
One Path Schedule
900
85% 26 Nov 11
“Shoulder” is at
70% for a 30%
80% 21 Nov 11
75% 16 Nov 11
800
likely risk
70% 20 Oct 11
65% 04 Oct 11
700
Cumulative Frequency
60% 30 Sep 11
55% 27 Sep 11
600
50% 25 Sep 11
400
40% 21 Sep 11
35% 19 Sep 11
in the Failure Mode
30% 17 Sep 11
300
25% 16 Sep 11
20% 14 Sep 11
200
15% 12 Sep 11
10% 10 Sep 11
100
5% 07 Sep 11
0 0% 28 Aug 11
28 Sep 11 17 Nov 11 06 Jan 12
Distribution (start of interval)
Variation:46
Cumulative Probability
If taking 10 Days Longer in Build reduces probability to
10%, can save 46 days for an 80th percentile company
Software
Designing
Technology
State-of-
the- Art
Software
© 2016 Hulett & Associates, LLC Coding 34
Effect of Correlation
Design 1.0 .9 .8
Build .9 1.0 .7
Test .8 .7 1.0
100%
Cumulative Probability
High
60%
correlation 50%
subtracts 40%
5 days at 30%
the P-20
Variation:5
20%
10%
0%
14 Aug 12 19 Aug 12 24 Aug 12 29 Aug 12 03 Sep 12 08 Sep 12 13 Sep 12 18 Sep 12 23 Sep 12 28 Sep 12 03 Oct 12 08 Oct 12 13 Oct 12 18 Oct 12 23 Oct 12
Not likely to be much help for real schedules that have parallel paths
Design 1.0 .9 .8
Code .9 1.0 .2
Test .8 .2 1.0
Motivational bias
– Some people do not want to cooperate
– Others want to bias the results, usually so the project looks good.
They have their own agenda
Cognitive bias
– Even people who want to respond accurately may find it difficult at
first
– Thinking about things going wrong is not easy
Ceiling Amount
Likelihood
Risk Denied
Element Cost
Range
Unbiased Range
Anchored on
Most Likely
Likelihood
Activity Duration
3
Triangle
Trigen
2
0
190 220 250
Recognized
High Range
Activity Duration
Original Distribution
Dramatic
Event
Likelihood
Element Cost
Can tell which activities are crucial, but not directly which
risks are driving
Makes poor use of the Risk Register that is usually available
Cannot decompose the overall schedule risk into its
components BY RISK
– Ability to assign the risk to its specific risk drivers helps with
communication of risk causes and risk mitigation
Four risk drivers are specified. The first is a general risk about engineering productivity,
which may be under- or over-estimated, with 100% probability. It is applied to the two
Design activities
With this risk, the Construction Contractor may or may not be familiar with the technology,
the probability is 40% and the risk impact if it happens is .9, 1.1 and 1.4. It is applied to the
two Build activities
Activity 1 Activity 2
Activity 1 Activity 2
Activity 1 Activity 2
Risk 1 1.2 factor Risk 2 1.05 factor Use (1.2 x 1.05 = 1.26) Factor,
multiply the two
Risks in series often lead to very long durations, especially if there are many risks on the activity
This is an example of the simulation strategy for a project with 8 risks. It requires 8 + 7 + 6
+….+1 or 36 separate simulations. This would take a long time by hand. At this point only
Polaris has automated the process.
© 2016 Hulett & Associates, LLC 89
Schedule Risk Tornado
with Risks Prioritized by Days Saved
Target for Mitigations is 178 days, risk-by-risk. Uncertainty alone accounts for 130 days.
Total schedule contingency to ©P-80
2016 Hulett & Associates, LLC
is 308 days. 91 91
Risk Mitigation Workshop(s)
Mitigation Establish this project as top priority - needs top management action and
Action commitment
10/20/201
Post -Mitigated parameters 15% 95% 100% 115% $1.99
7
Cost
Risk Owner: S. Smith Days saved
Saved
Date of
Within 1 month Results 94 $0.14
Action:
Risk Action Cost of
Risk is not completely
B. Blake mitigated. Cost saved is the reduction of cost contingency reserve$0.02
held
Owner: Mitigation
for schedule risk. For Net Cost Saved subtract the $20 million cost of mitigation
The high priority risk has been mitigated. The finish date moves to 20
October 2017 from 22 January 2018, about a 3-month improvement
© 2016 Hulett & Associates, LLC 94
Partially Mitigate all Risks – Finish Date
Pre-mitigation results
One risk mitigated
Mitigating all risks (Here, just reducing the probability by half) moves the P-80 date
back to 10 August, 2017 for a total mitigation time of about 5 months.