Professional Documents
Culture Documents
Abstract—25 kV, 50 Hz single-phase AC supply has been that the transformers in electric traction substations, feeding
widely adopted in the long-distance electrified railway systems in the contact line, are connected between two phases of the
many countries. Electrical locomotives generate harmonic transmission grid. This generates current loading at the 110 kV
currents in railway power supply systems. Single-phase traction voltage level at the point of connection of the electric traction
loads also inject large unbalance currents to the transmission system, thus creating voltage drops at the transmission branch
system and cause voltage unbalance subsequently. As the amount impedances, which leads to voltage unbalance.
of rail traffic increases, the issue of power quality distortion Besides voltage and current unbalance, electric railway
becomes more critical. system also causes voltage and current harmonic distortion at
Harmonic currents and unbalanced voltages may cause negative
the point of connection due to operation of power electronics
effects on the components of the power system such as
overheating, vibration and torque reduction of rotating
used for train control and drive systems [4]. In order to
machines, additional losses of lines and transformers, calculate the distorted voltages and currents caused by electric
interference with communication systems, malfunctions of traction at the point of connection to the transmission grid, a
protection relays, measuring instrument error, etc. model of diode locomotive was created using the EMTP-RV
Therefore, the harmonic current flow must be assessed exactly in software. The calculated harmonic voltages and currents were
the designing and planning stage of the electric railway system compared to the values measured at the electric railway
(ERS). Harmonic current flow through the contact line system substation.
has to be accurately modeled to analyze and assess the harmonic
effect on the transmission system. II. ELECTRIC LOCOMOTIVES WITH DIODE RECTIFIERS
This paper describes the influence of electric railway system on Majority of electric locomotives in Croatian electric
power quality in 110 kV transmission system. Locomotives with railway system 25 kV, 50 Hz are equipped with DC motors
diode rectifiers were analyzed. Electric railway system was
and diode rectifiers. Diode rectifier bridge causes current
modeled using EMTP-RV software. Currents and voltages were
calculated in 110 kV and 25 kV network. Power quality
waveform distortion and as a consequence voltage distortion
measurements were performed on 110 kV level in 110/35/25 kV in transmission power system.
substation and analyzed according to IEC 61000-3-6. Diode locomotive consists of an autotransformer, diode
Keywords: Electric Railway System, Power Quality, Modeling, rectifiers and four DC motors. The autotransformer 25/1.06
Measurement kV connects contact wire with diode rectifiers and DC motors.
Figure 1 shows the electrical scheme of diode locomotive.
Contact wire
I. INTRODUCTION
Constant technological development requires the
Lm
electrification of main railway lines due to the advantages of
25/1.06 kV i''
electric traction over diesel traction, such as: increase in D1 D2
speed, safety, efficiency and environmental acceptability. Autotransformer U' U''
u'
However, electric railway system has a negative influence
on facilities to which it is connected and on surrounding D3 D4
facilities. The negative influence of the electric railway system
is manifested in the form of unbalanced loading [1] and
generation of harmonic voltages and currents [2]-[3] at the
point of connection. Unbalanced loading occurs due to the fact Fig. 1. Electrical scheme of the diode locomotive
Figure 2 shows voltage U” and current i” waveforms network is represented by Thevenin equivalent (impedance in
entering the diode rectifier [5]. Diode rectifier has one series with voltage source). The positive and zero sequence
commutation over one semi-period of voltage. impedance was calculated from single-phase and three-phase
The Figure 2 also shows conducting sequence of individual short-circuit currents.
diodes in the rectifier bridge as well as commutation when all Figure 4 shows a 25 kV catenary system which consists of
diodes simultaneously conduct in a short time period (in Fig. 2 a messenger wire and contact wire.
this time period is enlarged). The catenary system was modeled using a frequency-
u dependent J. Marti model which is based on the
approximation of the line characteristic impedance Z(ω) and
U'' propagation function A(ω) by rational functions of the higher
u'
order. Ground resistivity was assumed 100 Ωm.
D2, D3 D1, D4
Messenger wire
t
D1, D2
D3, D4
i''
IM Contact wire
-IM
Rails
Fig. 2. Diode rectifier voltage and current waveforms
kontaktna_mreza
Ulaz2 Izlaz2
DEV1
Tr0_6 RL10 ?i
RL21 25kV RL22
25 +
+VM p+ + + Ulaz1 Izlaz1
p+ 1060 s1+ s1+ 870 DC3
+VM
?v 0.027,5.033mH
m15
4.5,15.9mH 0.004,28.58uH
model in: kontaktna_mreza_rv.pun p- s1 RL23 s1
Ulaz2 Izlaz2
R18
+ FDline2
11
+ ?i 0.004,28.58uH
AC3 m23 0.5,4mH + FD s2 RL24 s2
RL27
+ +A 1 2 DEV3
1060 s3+ + s3+ ?i
+
RL11
?i c 0.004,28.58uH +
+
0.027,5.033mH
50
Ulaz2 Izlaz2
DC motors
Diode rectifier
bridges
TABLE I
PARAMETERS OF THE CATENARY SYSTEM
R5
0
R7
R4
+
+
D5 ?vi 0.001
+
+
7.5
D7 ?vi 0.001
7.5
+
C6
125uF
?v
+
0.7
0.7
C3
+
C5
0
1.33uF
1.33uF
D6 ?viR6
+
0.7 0.001
C4
0
R3
+ +
7.5
1.33uF
110 kV transmission
transmission 110
110 kV transmission
transmission
line - line
Gojak 1 line -line
Gojak 2
PQ1 PQ2
110 kV
110/35 kV 110/35 kV
Yy0 Yy0
20 MVA 20 MVA
1,20
TABLE II 1,00
CURRENT AND VOLTAGE THD AT 110 KV AND 25 KV LEVEL
0,80
110 kV 1.63 %
41.83 % 0,40
25 kV 2.06 %
0,20
TABLE III
0,00
CURRENT AND VOLTAGE HARMONICS AT 110 KV AND 25 KV LEVEL 2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
number U (V) I (A) U (V) I (A) Fig. 13. 3rd voltage harmonic at 110 kV level
1st 35280 194 89560 40.1
3rd 125.1 35.2 251.2 11.4 During 95 % time of the week the maximum value of third
5th 116.7 31.0 234.4 6.4 voltage harmonic was 0.9 % in phase L2 and L3 and 0.3 % in
7th 107.7 10. 5 216.4 4.2 phase L1. Besides the 3rd voltage harmonic, the 3rd current
21st 421.0 26.7 931.4 5.5 harmonic was also increased in L2 and L3 phases of electric
23rd 462.0 26.7 841.8 5.5 railway drains. Fig. 14 shows 3rd current harmonic in phase L2
of both railway substation transformers. The 3rd current
V. MEASUREMENT OF POWER QUALITY harmonic is characteristic for diode and thyristor electric
locomotives.
Power quality parameters were measured for the period of
5th voltage harmonic in all three phases is approximately
seven days in 110/35/25 kV substation shown in Fig.12 [10]. equal (Fig. 15) due to the fact that the 5th harmonic is
characteristic for the loads in distribution network as well as
for the railway system. During 95 % of the week, the According to Fig. 18 it can be concluded that the increased 9th
maximum value for all phases was 0.6 %. current harmonic in phase L2 and L3 of electric railway drain
causes increase of 9th voltage harmonic in the same phases at
TR1 – phase L2 TR2 – phase L2
8,00 110 kV level.
7,00
1,75 TR1 – phase L2
TR HŽ 1 - Ih9 RMS L2 10' A
TR2 – phase L2
TR HŽ 2 - Ih9 RMS L2 10' A
3. harmonik struje u fazi odvoda HŽ 1 i HŽ 2 [A]
6,00
1,50
5,00
4,00
1,00
3,00
0,75
9th 9.current
2,00
0,50
1,00
0,25
0,00
2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto 0,00
Datumand
i Vrijeme 2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
Date time 00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
rd Date
Datumand time
i Vrijeme
Fig. 14. 3 current harmonic in phase L2 of the both electric railway
transformers at 110 kV level Fig. 18. 9th current harmonic in phase L2 of the both electric railway
transformers at 110 kV level
Phase Uh5
L1RMS L1 10' Phase L2 Phase L3
%Un
0,80
3n harmonics are specific for diode and thyristor
locomotives. During 95 % of the week the maximum value of
the 21st voltage harmonic in phase L2 and L3 was 0.5 %, while
0,60
0,40
in phase L1 was zero (Fig. 19). The 21st current harmonic is
0,20 shown in Fig. 20.
0,00
2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto Phase L1 Phase L2 Phase L3
1,20
Date and time
0,80
0,60
3,50
5. harmonik struje u fazi odvoda HŽ 1 i HŽ 2 [A]
electric railway system (A)
5th current harmonic from
3,00
0,40
2,50
0,20
2,00
1,50 0,00
2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
1,00
Date and time
0,50
Fig. 19. 21th voltage harmonic at 110 kV level
0,00
2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
Datum and
Date i Vrijeme
time TR1 – phase L2 TR2 – phase L2
1,00
th
Fig. 16. 5 current harmonic in phase L2 of the both electric railway
transformers at 110 kV level
harmonic from electric
harmonik struje u fazi odvoda HŽ 1 i HŽ 2 [A]
0,80
0,60
(%) of the 1 st harmonic
0,20
2121.
st
0,50
0,40
0,00
0,30 2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
0,20 Date
Datumand time
i Vrijeme
0,10
Fig. 20. 21th current harmonic in phase L2 of the both electric railway
0,00 transformers at 110 kV level
2009-vlj-03 2009-vlj-04 2009-vlj-05 2009-vlj-06 2009-vlj-07 2009-vlj-08 2009-vlj-09 2009-vlj-10
00:00:00, uto 00:00:00, sri 00:00:00, čet 00:00:00, pet 00:00:00, sub 00:00:00, ned 00:00:00, pon 00:00:00, uto
Date and time The comparison between measured values and planning levels
Fig. 17. 9th voltage harmonic at 110 kV level for harmonic voltages according to [12] is shown in Table IV.