You are on page 1of 6

Name : _______________________ EC.

No _________________

Date : __________________

1. What is “Black Start” facility in case of GT ?


2. As per latest contract with State electricity board and CPP, how much power can be drawn from state electricity
GRID?
3. Emergency power system is designed for feeding power to all LT drives of black start GTs in case of total power
failure condition : (True / False).
4. All 33 kV breakers at CPP can be opened from local and remote both when it is selected to :-
a. Remote mode
b. Local mode
c. Off mode
b. Any mode
5. Important point to be kept in mind while shutdown of grid transformer is,
a. Islanding of 33 kV board
b. Load shedding
c. Adjustment of generation / load
d. All of above
6. Before charging a out going 33 kV feeder on 33 kV board at either of MRS at CPP, clearance
is to be taken from
a. From downstream side sub station where this feeder is feeding the
power
b. From Plant manager
c. From SE (steam generation & distribution)
d. None of these
7. Before actually 33 kV cable Tie is closed at CPP 33 kV board, it’s all required parameters for
synchronizing are checked by
a. A check-synchronizing relay mounted on cable tie breaker
automatically
b. The operating personnel through 7SJ600 relay mounted on cable
tiebreaker
c. SE (power generation & distribution) on EDMS
d. None of these
8. Sikka and Theba bay breakers at 132 kV switchyard can be operated from back up panel
( True/False )
9. GT and STG Incomers on 33 kV board at CPP can be operated from EDMS / remote.
(True/False)
10. The principle of 220 V battery charger is to :-
a. Convert AC to DC
b. Convert HT to LT
c. Convert DC to AC
d. None of these three
11. General schematic of any UPS in CPP is same as that of battery charger : (True / False)
12. Incase of failure of UPS-B at CPP UPS unit, all load will be transferred to,
a. UPS-A
b. Static bypass UPS-A
c. Static bypass UPS-B
d. Manual Bypass
13. Total 220 V battery chargers in CPP are :-
a. Two
b. Three
c. Four
d. Five
14. In DC system battery bank is meant for :-
a. Feeding battery charger
b. Feeding load continuously
c. Feeding load whenever AC supply fails
d. Feeding load & battery charger both
15. On start command in case of GT # 4 at CPP, its diesel engine starting drive gets DC power
from :-
a. GT # 4 125 V service charger
b. GT # 4 rectifier unit
c. GT # 4 MCC
d. None of these
16. Total number of 125 V battery chargers in CPP are :-
a. Four
b. Six
c. Eight
d. Twelve
17. 24 V battery bank for CPP GT # 4,6 & 7 ratchet drive is kept in field near respective GT.
( True/False )
18. In CPP, how many GTs have diesel Engines as starting device?
a. 1
b. 2
c. 3
d. 4
19. All GT and STG MCC at CPP are having following facility,
a. Manual paralleling
b. Auto change over
c. Both a and b
d. None
20. Under which condition FCB of GT-1 and GT-4 will not open at CPP ?
a. Generator differential operation
b. Over fluxing operation
c. Reverse power operation
d. None
21. GT-1 MCC control supply is,
a. 220 V DC
b. 125V DC
c. 230 V AC
d. 115V AC
22. Under normal operation of GT (M/C on load), what is the current drawn by its AOP?
a. 60 Amp
b. 45 Amp
c. 30 Amp
d. Not applicable
23. The class of winding insulation of generators in CPP is :-
a. F
b. A
c. Y
d. E
24. Number of poles in rotor in STG Jeumont generator at CPP is:
a. 2 pole
b. 4 pole
c. 6 pole
d. 8 pole
25. Operation principle of WTI, OTI and PRD in Transformers is same : (True / False).
26. Why transformer rating is always defined in VA / KVA / MVA?
27. Transformer core is laminated to reduce
a. Hysteresis loss
b. Eddy current loss
c. Copper loss
d. All of above
28. What is the current rating of LT side of GRID transformer at CPP ?
a. 800 Amp
b. 789 Amp
c. 289 Amp
d. 886 Amp
29. Reduction in oil level of transformer will give alarm through,
a. MOGL
b. OTI
c. WTI
d. Buchholz
30. Balloons in transformer conservator are provided for,
a. Saving transformer oil
b. isolating atmospheric air from oil
c. Pressure control
d. none of above
31. Why OLTC is provided in Grid transformer only at CPP and not in other transformers ?
32. What is the function of Lightening Arrester ?
33. What types of Circuit breakers are used in CPP, their location?
34. Direct cable connected TIE at CPP 33 kV board can be switched on from EDMS as well as from GCP : (True /
False).
35. What is the rated current capacity of generating breakers?
36. Bus current transformers in case of CPP 33 kV system is installed in:-
a. Bus coupler panel
b. In each incomer panel
c. In bus PT panel
d. None of these
37. Main earthing connection bar for CPP 33 kV boards :-
a. Entering through cable box
b. Entering through breaker panel
c. Externally going to the top of board
d. None of these
37. What is the normal operating air pressure of switch yard breakers & what is the cut in pressure of it’s air
compressor?
38. What is the fault level at CPP 132 kV Switch yard bus?
a. 25 kA
b. 40 kA
c. 50 kA
d. 60 kA
39. Switch yard 132 kV Grid transformer breaker can be synchronised from EDMS. (True / False)
40. For connecting two 33 kV boards directly through cables, total number of cable Ties in CPP are: -
a. One
b. Two
c. Three
d. Four
41. Earth switch and isolators in CPP 132 kV switchyard are provided with,
a. Electrical Interlock
b. Mechanical Interlock
c. Soft interlock
d. all of above
42. In CPP we have following motor starters,
a. DOL
b. Star-delta
c. Auto transformer
d. All of above
43. All CPP HT motor feeders are rated for,
a 415 V
b 3300 V
c 6600 V
d 11000 V
44. Auto change over time of PCC at CPP is,
a. Greater than MCC
b. Less than MCC
c. Less than 6.6 kV bus coupler
d. Same as MCC
45. How many trip coils is used in CPP switchyard 132 kV circuit breaker?
a. One
b. Two
c. Three
d. Four
46. Charging of all four Grid transformers is not possible from MRS-II : (True / False).
47. To import power from state electricity network when there is total power failure condition, under voltage relay of
132 kV Tie breaker need to be bypassed : (True / False).
48. Control supply rating of CPP 6.6 kV board all breakers is same. ( True/false )
49. At CPP HRSG MCC Incomer is having Siemens make ACB. (True / False)
50. What are the protections provided for 33 kV feeder/incomer?
51. What is differential protection? Is it used anywhere for motor protection in CPP?
52. At CPP, interposing CT used for 33 kV bus differential protection is placed at 33 kV board inside 33 kV bus
chamber : (True / False)
53. In case of earth fault on Bus bar, which protection will operate?
a. Generator E/F
b. Feeder E/F
c. Bus-bar differential Vend
d. none of the above
54. Describe use of AFV, FV, AMV & MV P&B relay in CPP?
55. List out different protections provided in Generators?
56. At CPP STG will not trip but only generator breaker will trip when reverse power protection alone has operated : (
True / False)
57. LGPG relay is used for grid transformer protection at CPP : (True / False)
58. Distance protection for transmission line connecting Reliance at CPP is thorugh :
a. RADHD
b. REL 100
c. RADSS
d. RAICA
59. Lockout relay is mounted on each and every 33 kV as well as 6.6 kV breaker panel at CPP. (True / False)
60. REF protection is provided in CPP 2 MVA transformers : (True / False)
61. Augment fan motor’s are provided with Instantaneous E/F protection (50) at CPP. (True / False)
62. What is full form of ELDMS?
63. At CPP MRS 33 kV breaker will trip on failure of it’s control supply : (True/ False)
64. Starting of each GT starting drive (HT drive) in CPP is possible from :
a. DCS
b. LCS place nearby respective drive
c. EDMS
d. None of above
65. Low forward power relay is provided for all generators at CPP : (true / False)
66. Largest rated LT motor in CPP is :
a. CCW pump motor
b. LP process pump motor
c. NP Off-base fuel pump
d. Augment air fan of HRSG
67. Following motors does at CPP not have speed-control facility,
a. HRSG HP dosing pump
b. Aux boiler dosing pump
c. GT Hi-tech dosing pump
d. none of above
67. Which system among following at CPP while in operation do not need aux oil pump running? (GT, STG, HP
process pump, HHP BFW pump, TFD & IAC).
68. HI moisture content inside steam turbine’s generator casing at CPP is possible in any season : (True / False)
69. Fresh air blowers at all HVAC packages are operating in auto mode : (true / False)
70. 24 V battery bank at CPP for GT-4, 6 & 7 ratchet drive is kept in field near respective GT (True / False).
71. What is the recent modification carried out at CPP in EDG for increasing reliability?
72. Note down the power sources of all CCW drives at CPP ?
73. At CPP on EDMS primary load shedding blocking on it’s own is possible due to any generator breaker ON
feedback loss : (True / False).
74. Which Bus coupler normally remains in ON condition at CPP ?
75. CPP PMCC-16 incomer breaker can be closed from EDMS? (True / False).
76. Pmax setting of each machine at CPP in EDMS depends on what factor?
77. Write down the actions to be taken on GT-1 tripping?
78. DC lube oil pump in STG is required to avoid STG tripping in case of AC lube oil pump outage. (True / False).
79. Bus coupler closure at downstream plants are inhibited in case of Load shedding operation through EDMS from
CPP :
a. To help downstream for locating fault
1. To help CPP end for locating fault
2. To help EDMS panel engineer to note down affetced loads
3. None of above

80. Bearings of all HT drives of CPP are grease lubricated : (True / False)
81. Why DC control supply is used for switchgear controls?
82. In case of total power failure condition, manual intervention is not required for restoring power to CCW pumps
from their respective source : (True / False).
83. Manual paralleling and auto changeover logic at CPP 33 kV board is not used normally but can be used when
power is being restored from zero (True / False).
84. Deluge for CPP fuel tanks can be operated from EDMS OS : (True / False)
85. What is the basic law which governs CPP 33 kV Bus differential protection?
86. Resetting & de-blocking of PLS in case of EDMS is same : (True / False)
87. PLS operation alarm is available on CPP F & G panel also : (True / False)
88. Before grid transformer shutdown at CPP, particular 33 kV switchboard islanding is must : (True / False).
89. Power load shedding priority on CPP EDMS are :
a. 5
b. 10
c. 12
d. none of above
90. DP set by operator on EDMS is taken into load shedding program calculation correctly can be seen by EDMS
operator : (True / False)
91. 2nd scanner fan of each Auxiliary Boiler at CPP is fed from emergency MCC-13 : (True / False)
92. At CPP fuel pumps 51 A and 53 A are fed from emergency MCC-13 of respective MRS : (True / False)
93. How many different types of control supplies are used in CPP MCCs? List out all with location?
93. While synchronizing a grid transformer on 33 kV side locally (i.e. from 33 kV breaker side),
voltage and frequency of both sources are matched by changing: -
a. Voltage & frequency of grid transformer (to be synchronized) from
it’s 33 kV breaker
b. Voltage & frequency of grid transformer (to be synchronized) from
it’s 132 kV breaker
c. Voltage & frequency of machine in operation on that 33 kV board
d. None of these
94. Both EDG sets will start in auto in case of total power failure by sensing :-
a. U/V ON 6.6 kV bus of S/S 961-10
b. U/V ON 6.6 kV bus of MRS-1
c. U/V ON 6.6 kV bus of MRS-2
d. U/V ON 33 kV bus of MRS-1
95. There is no need of filling check sheet while isolating a transformer at CPP EDG building because it is a
emergency transformer. (True/False)
96. What is the rating of UPS installed in CPP CCR?
a. 60 KVA
b. 100 KVA
c. 50 KVA
d. 40 KVA
97. 125 V battery charger for GT # 1,2,3,5 & 8 has :-
a. One float & one boost charger
b. One float & two boost chargers
c. Two float & one boost charger
d. Two float & two boost chargers
98. 220 V DC system is for the control of :-
a. Steam Turbine controller (Turbolog)
b. Gas Turbine controller (Mk-V)
c. DCS system
d. HT / LT panels & some MCCs
99. For CPP UPS : Both UPS-B and Bypass mains are supplied from,
a. Miscellaneous MCC
b. Black start GT MCCs
c. Directly from PCC
d. Emergency LT system
100. Phase sequence of incoming AC source is important in case of 125 V battery charger’ this
statement is :-
a. True
b. False
c. None of these