80. Bearings of all HT drives of CPP are grease lubricated : (True / False)
81. Why DC control supply is used for switchgear controls?
82. In case of total power failure condition, manual intervention is not required for restoring power to CCW pumps
from their respective source : (True / False).
83. Manual paralleling and auto changeover logic at CPP 33 kV board is not used normally but can be used when
power is being restored from zero (True / False).
84. Deluge for CPP fuel tanks can be operated from EDMS OS : (True / False)
85. What is the basic law which governs CPP 33 kV Bus differential protection?
86. Resetting & de-blocking of PLS in case of EDMS is same : (True / False)
87. PLS operation alarm is available on CPP F & G panel also : (True / False)
88. Before grid transformer shutdown at CPP, particular 33 kV switchboard islanding is must : (True / False).
89. Power load shedding priority on CPP EDMS are :
a. 5
b. 10
c. 12
d. none of above
90. DP set by operator on EDMS is taken into load shedding program calculation correctly can be seen by EDMS
operator : (True / False)
91. 2nd scanner fan of each Auxiliary Boiler at CPP is fed from emergency MCC-13 : (True / False)
92. At CPP fuel pumps 51 A and 53 A are fed from emergency MCC-13 of respective MRS : (True / False)
93. How many different types of control supplies are used in CPP MCCs? List out all with location?
93. While synchronizing a grid transformer on 33 kV side locally (i.e. from 33 kV breaker side),
voltage and frequency of both sources are matched by changing: -
a. Voltage & frequency of grid transformer (to be synchronized) from
it’s 33 kV breaker
b. Voltage & frequency of grid transformer (to be synchronized) from
it’s 132 kV breaker
c. Voltage & frequency of machine in operation on that 33 kV board
d. None of these
94. Both EDG sets will start in auto in case of total power failure by sensing :-
a. U/V ON 6.6 kV bus of S/S 961-10
b. U/V ON 6.6 kV bus of MRS-1
c. U/V ON 6.6 kV bus of MRS-2
d. U/V ON 33 kV bus of MRS-1
95. There is no need of filling check sheet while isolating a transformer at CPP EDG building because it is a
emergency transformer. (True/False)
96. What is the rating of UPS installed in CPP CCR?
a. 60 KVA
b. 100 KVA
c. 50 KVA
d. 40 KVA
97. 125 V battery charger for GT # 1,2,3,5 & 8 has :-
a. One float & one boost charger
b. One float & two boost chargers
c. Two float & one boost charger
d. Two float & two boost chargers
98. 220 V DC system is for the control of :-
a. Steam Turbine controller (Turbolog)
b. Gas Turbine controller (Mk-V)
c. DCS system
d. HT / LT panels & some MCCs
99. For CPP UPS : Both UPS-B and Bypass mains are supplied from,
a. Miscellaneous MCC
b. Black start GT MCCs
c. Directly from PCC
d. Emergency LT system
100. Phase sequence of incoming AC source is important in case of 125 V battery charger’ this
statement is :-
a. True