Professional Documents
Culture Documents
1
Typical Reasons for Cable Faults
Final Results
2
Virtual & non-countable Costs
Servicer failures during normal operation leads to unuasual “Stress“ of whole
Network & could provoke further Cable Faults
4
Different Maintenance Strategies
6
Why testing Cable Installations?
Why performing Cable Tests on service-aged & new Installations?
■ Introduction
■ Acceptance/ commissioning testing
■ Condition Monitoring
■ Summary & Conclusions
8
Introduction
9
Introduction
By example of MV cables:
Unfortunately not....
10
Introduction
11
Introduction
12
Introduction
13
Introduction
14
Introduction
Poor cable
preparation
15
Introduction
16
Agenda
■ Introduction
■ Acceptance/ commissioning testing
■ Condition Monitoring
■ Summary & Conclusions
17
Acceptance/ commissioning testing
Recommended procedure:
Outer sheath integrity test
VLF test at 3U0 and 0.1Hz for 15 minutes (IEC standard)
Offline PD Diagnosis
18
Acceptance/ commissioning testing
19
Acceptance/ commissioning testing
PD Characteristics at different excitation voltages
continuous AC Cosine
Damped AC
sinusoidal rectangular
20
Acceptance/ commissioning testing
PD Characteristics at different excitation voltages
21
Acceptance/ commissioning testing
Expert knowledge needed
22
Acceptance/ commissioning testing
Expert knowledge needed
23
Acceptance/ commissioning testing
Trending limits
24
Acceptance/ commissioning testing
Case Study 1
25
Acceptance/ commissioning testing
Case Study 1
26
Acceptance/ commissioning testing
Case Study 1
27
Acceptance/ commissioning testing
Case Study 1
Summary:
28
Agenda
■ Introduction
■ Acceptance/ commissioning testing
■ Condition Monitoring
■ Summary & Conclusions
29
Condition monitoring
30
Condition monitoring
Offline PD diagnostics
Offline dielectric diagnostics e.g. tanDelta measurement*
31
Condition monitoring
Case Study 2
32
Condition monitoring
Case Study 2
tanDelta results
Local problem in L3
33
Condition monitoring
Case Study 2
PD Mapping @ Uo PD Mapping @ Uo
VLF Sinus 0.1Hz VLF CR 0.1Hz (210Hz)
34
Condition monitoring
Case Study 2
35
Condition monitoring
Case Study 2
Summary:
36
DAC available for HV cables also?
37
Summary and conclusions
Commissioning testing:
Withstand testing only is not sufficient as a commissioning test
PD diagnostics are strongly recommended and widely applied
Excitation voltage should be comparable to operating frequency
Condition monitoring:
For condition monitoring in addition a tanDelta diagnosis is needed
A tanDelta diagnosis can also identify local problems
38