Page 1 EnSE 503

Specifications and Contracts


Plumbing – Chapter 14
1. Benedicto A. Scope of Work
14-A Material Requirements
A. Plastic Pipes Nos. 1, 2, 3,and 4

2. Cruz S. 14-A Material Requirements


A. Plastic Pipes Nos. 5, 6, 7, and 8

3. Cua H. 14-A Material Requirements


A. Plastic Pipes No. 9
B. Septic Tank Nos. 1, 2, and 3

4. Escano M. C. Plumbing Fixtures and Nos. 1, 2, 3, and 4a


Fittings
K. Water Test on System No. 1 and 2

5. Escober E. C. Plumbing Fixtures and Nos. 4b, 4c, and 4d


Fittings

6. Garcia E. D. Bathroom and Toilet Nos. 1, 2, 3, 4, 5, 6, and 7


Accessories

7. Guimbaolibot R. E. Special Plumbing Fixtures Nos. 1, 2, 3 and 4

8. Jalac K. E. Special Plumbing Fixtures Nos.5 and 6


F. Roof Drains, Overflow No. 1
Pipes and Steel Grating

9. Justo L. F. Roof Drains, Overflow Nos. 2, 2a, 2b, 2c


Pipes and Steel Grating

10. Lazo M. F. Roof Drains, Overflow Nos. 2d, and 2e


Pipes and Steel Grating
G. Fire Protection System Nos. 1, 2, and 3

11. Lominoque C. G. Fire Protection System Nos. 4, 5, 6, and 7

12. Manabat L. G. Fire Protection System No. 8


14-2 Construction
Requirements
A. Installation of Soil, Waste, Nos. 1 and 2
Drain and Vent Pipe
Page 2
13. Nagum E. A. Installation of Soil, Waste, Nos. 3, 4, 5 and 6
Drain and Vent Pipe
J. Drainage System Test No. 4
M. Disinfection Nos. 1 and 2

14. Obias J. A. Installation of Soil, Waste, Nos. 7, 8, 9, 10, 11, 12 and 13


Drain and Vent Pipe
N. As Built Drawings Nos. 1 and

15. Rosales P. B. Water Pipes, Fittings and Nos. 1, 2, 3, and 4


Connections

16. Salvino G. B. Water Pipes, Fittings and Nos. 5, 6, 7 and 8


Connections

17. Tagle D. C. Fire Standpipe System


D. Valves and Hose Bibs Nos. 1, 2, 3, 4, 5, and 6

18. Tonio H. E. Fixtures, Equipments and Nos. 1, 2, 3, 4, and 5


Fastenings

19. Unlayao N. F. Pipe Hangers, Inserts and Nos. 1, 2, 3, 4 and 5


supports
L. Defective Works No. 1 and 2

20. Ventolero R. G. Plates and Flashing Nos. 1, 2, and 3


H. Protection and Cleaning Nos. 1, 2, and 3

21. Villanueva R. I. Inspection, Warranty Test No. 1


and Disinfection
J. Drainage System Test Nos. 1, 2, and 3
-End-