1. PURPOSE
This document must be used during the testing of Gateway Panel before FAT.
2. INSTRUMENTS REQUIRED
3. REFERENCE DOCUMENTS
4. SYSTEM START-UP
Pre-Conditions
OK OK Checked
All MCB’s are off.
5. GENERAL CHECKS
Expected
Sl. No Description Result Remark
Result
Visual inspection
Labelling of panels As per GA Not done
(name & logo) drawing
Complete assembly of Some Surge Arrestor, OFC-
As per GA
components components RJ45 Converter and
drawing
missing Cisco Switch
As per GA OK Checked
Labelling of components
drawing
As per OK Checked
Ferruling of wires Circuit
diagram
1 OK Checked
Colour coding and cross As per
section of wires Circuit
diagram
Physical damage to Not OK Scratches on Left side
cubical if any of panel
All in good
condition
Paint
Panel Check
CI-8520:X1 with
CACB network
switch
CI-8520:X2 with
LDC network
switch
CI-8520:X1 with
CACB network
switch
CI-8520:X2 with
LDC network
switch
Expected
Sl. NO Description Result Remark
Result
1 Check Digital Inputs LED module
glows
220VDC-1 MCB X1:1 glows OK Tested
SUPERVISION
220VDC-2 MCB
SUPERVISION X1:2 glows OK Tested
230VAC MCB
SUPERVISION X1:3 glows OK Tested
24VDC MCB
SUPERVISION X1:4 glows OK Tested
SPARE_1
HARDWARE
WATCHDOG_2 OK X2:4 glows OK Tested
SURGE ARRESTER-1
OPERATED X2:5 glows OK Tested
SURGE ARRESTER-2
OPERATED X2:6 glows OK Tested
SPARE_2
SPARE_3
7 GF2006033604
Remote CI-8530 module