You are on page 1of 12

Applied Energy 208 (2017) 1150–1161

Contents lists available at ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Cost comparison of printed circuit heat exchanger to low cost periodic flow T
regenerator for use as recuperator in a s-CO2 Brayton cycle

Jacob F. Hinzea, , Gregory F. Nellisb, Mark H. Andersonc
a
University of Wisconsin – Madison, 1500 Engineering Drive, 1335 Engineering Research Building, Madison, WI, USA
b
University of Wisconsin – Madison, 1500 Engineering Drive, 1303 Engineering Research Building, Madison, WI, USA
c
University of Wisconsin – Madison, 1500 Engineering Drive, 737 Engineering Research Building, Madison, WI, USA

H I G H L I G H T S

• AThecostregenerator
comparison between periodic regenerators and conventional heat exchangers is conducted.
• The cycle model model is integrated with a supercritical CO Brayton cycle model.
2

• A high order costisestimate


used to optimize the design of the regenerator.
• The LCoE shows is improvedof byregenerator and recuperator is conducted.
• switching to periodic flow regenerators.

A R T I C L E I N F O A B S T R A C T

Keywords: Supercritical Carbon Dioxide (sCO2) power cycles have the potential to deliver high efficiency at low cost.
Supercritical CO2 However, in order for an sCO2 cycle to reach high efficiency, highly effective recuperators are needed. These
Brayton recuperative heat exchangers must transfer heat at a rate that is substantially larger than the heat transfer to the
Regenerator cycle itself and can therefore represent a significant portion of the power block costs. Regenerators are proposed
Recuperator
as a cost saving alternative to high cost printed circuit recuperators for this application. A regenerator is an
indirect heat exchanger which periodically stores and releases heat to the working fluid. The simple design of a
regenerator can be made more inexpensively compared to current options.
The objective of this paper is a detailed evaluation of regenerators as a competing technology for recuperators
within an sCO2 Brayton cycle. The level of the analysis presented here is sufficient to identify issues with the
regenerator system in order to direct future work and also to clarify the potential advantage of pursuing this
technology. A reduced order model of a regenerator is implemented into a cycle model of an sCO2 Brayton cycle.
An economic analysis investigates the cost savings that is possible by switching from recuperative heat ex-
changers to switched-bed regenerators. The cost of the regenerators was estimated using the amount of material
required if the pressure vessel is sized using ASME Boiler Pressure Vessel Code (BPVC) requirements. The cost of
the associated valves is found to be substantial for the regenerator system and is estimated in collaboration with
an industrial valve supplier. The result of this analysis suggests that a 21.2% reduction in the contribution to the
Levelized Cost of Electricity (LCoE) from the power block can be realized by switching to a regenerator-based
system.

1. Introduction efficiency at elevated turbine inlet temperature. Supercritical and su-


perheated steam cycles operate at higher efficiencies than the sCO2 -
Supercritical carbon dioxide (sCO2) power cycles are closed Brayton cycle at low temperatures; however, once the turbine inlet temperature
cycles operating with CO2 as the working fluid. The main advantage to is above 550 °C the sCO2 cycle becomes the most efficient alternative.
an sCO2 cycle is the increase in thermal efficiency over a typical There is an ongoing push in the power industry to operate at these high
Rankine cycle, as shown in Fig. 1. temperatures in order to realize the associated higher efficiency. Ad-
It is clear from Fig. 1 that the sCO2 cycle provides the highest ditionally, an sCO2 turbine with an equal work output to a steam


Corresponding author.
E-mail address: jfhinze@wisc.edu (J.F. Hinze).

http://dx.doi.org/10.1016/j.apenergy.2017.09.037
Received 15 May 2017; Received in revised form 30 August 2017; Accepted 9 September 2017
Available online 21 September 2017
0306-2619/ © 2017 Elsevier Ltd. All rights reserved.
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

Nomenclature LCoE Levelized Cost of Electricity


NTU Number of Transfer Units
As surface area of packed bed ṁ mass flow rate
BPVC Boiler & Pressure Vessel Code mb mass of packed bed
Ċ capacity rate mc carryover mass
cb specific heat capacity of packed bed ṁ c carryover mass flow rate
Cm matrix capacity ratio P0 switching period
̇
Cmin minimum capacity rate PCHE Printed Circuit Heat Exchanger
cp,avg averages specific heat capacity PH high pressure in regenerator
CtHB Cold to Hot Blow PL low pressure in regenerator
D diameter of regenerator RCBC Recompression Brayton cycle
DFM Design For Manufacture SCBC Supercritical carbon dioxide Brayton cycle
ev void volume fraction sCO2 Supercritical carbon dioxide
FCC Fluidized Catalytic Cracker T(x) temperature of CO2 at position x
hcC heat transfer coefficient on cold side of regenerator UA conductance
hcH heat transfer coefficient on hot side of regenerator ρ density
HtCB Hot to Cold Blow

turbine will be approximately 1/10th of the size [2], resulting in lower for this analysis [4].
capital costs. There are potential benefits associated with dry cooling No matter the cycle configuration, a large amount of recuperation is
sCO2 systems as well, which becomes important in hot, dry climates required in order for the sCO2 cycle to be competitive from a perfor-
where CSP applications might be sited [3]. Because of these advantages mance point of view. Indeed, a key reason for the high performance
there has been renewed interest in sCO2 cycles. exhibited by the sCO2 cycle is that it combines the advantages of low
The performance and cost of an sCO2 cycle can vary depending on back-work ratio due to the high density fluid entering the compressor
the configuration of the cycle. A Simple Closed Brayton Cycle (SCBC) with the potential for aggressive recuperation due to the high turbine
operates with only a compressor (1), turbine (2), primary heat ex- exit temperatures. The current best option for sCO2 recuperators is the
changer (3), precooling heat exchanger (4), and recuperator (5) as Printed Circuit Heat Exchanger (PCHE) [5]. PCHEs are made by etching
shown in Fig. 2(a). The efficiency of the simple cycle is limited because flow patterns in many plates, stacking the plates, diffusion bonding the
the temperature pinch point in the unbalanced recuperator limits the block together, and welding on headers. A PCHE is able to create very
amount of internal heat transfer. When carbon dioxide is near its cri- small flow channels and achieve high effectiveness. Traditional heat
tical point, the specific heat capacity of the fluid increases dramatically exchanger types such as shell and tube or plate heat exchangers either
causing a local mismatch in the capacitance rates of the high and low have poor heat transfer, excessive costs, or are not able to withstand the
pressure flows. The Recompression Closed Brayton cycle (RCBC) adds a required pressure [6]. The cost of the PCHE required by an sCO2 cycle
second compressor (7) and recuperator (6) to balance the capacitance can be up to 24% of the total power block costs [7]. Also, the mono-
rates as shown in Fig. 2 (b). lithic block that results from a PCHE design does a poor job of handling
The recompressor takes warm fluid leaving the low pressure side of thermal stresses which can be significant if the block is going through
the low temperature recuperator and compresses it to high pressure rapid thermal cycling [8]. Finally, the small channel size means it can
before returning it to the cycle after the low temperature recuperator. be difficult to clean or maintain a PCHE. Significant work has been done
The recompressor reduces the limitation associated with the pinch to design PCHEs that have the optimal performance for sCO2 cycles
point in the recuperator, allowing more heat recovery and therefore a [9,10]. Additionally, several organizations are working on testing
higher thermal efficiency. Since the RCBC can achieve higher efficiency PCHEs under prototypic conditions [11–13]. This work is advancing the
than the SCBC for the same size recuperator, the RCBC cycle was used state of the art of PCHE technology, but also pointing out potential

60 Fig. 1. Cycle efficiency as a function of the turbine inlet temperature


for various working fluids, .
adapted from [1]

50
Cycle Efficiency (%)

40

30
Helium Brayton cycle
Supercritical CO2 cycle
Supercritical steam cycle
Superheated steam cycle
20

10
350 450 550 650 750 850 950
Turbine Inlet Temperature (°C)

1151
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

Fig. 2. (a) Simple Closed Brayton Cycle (SCBC) and (b) Recompression
Closed Brayton Cycle (RCBC).

barriers to its eventual adoption. One subtle issue with PCHEs is that result, the materials issues associated with the pressure vessel and
the effectiveness that can be achieved is limited to a number less than valves are relatively new. Further, the impact of the regenerator oper-
100% (even at high conductance) due to the unavoidable cross-flow ating characteristics (e.g., carry over, switching time, and pressure/flow
that must be present in the header region [14]. fluctuations) on a power cycle have not been thoroughly studied pre-
A periodic flow regenerator provides a possible alternative to the viously. Regenerators have been used in the power industry but usually
PCHE that could be constructed at lower cost, with a more conventional for preheating air for burners or air Brayton cycles [18]. These devices
construction, and without any limit on the effectiveness that can be operate at low pressure differential, usually under 6 bar which means a
achieved. A regenerator can use low cost materials even at high oper- rotary regenerator can be used [19]. The high pressure differential as-
ating temperatures and provides a design that is easy to clean. There is sociated with the high and low pressure sides of a sCO2 cycle (170 bar)
no cross-flow region necessary in a regenerative system. The re- preclude the use of a rotary regenerator. Instead the bed examined in
generator is a packed bed of stainless steel spheres surrounded by a this work must be located in pressure vessels and the flow is directed
pressure vessel. The bed is first exposed to hot fluid during the Hot to using a series of valves.
Cold Blow (HtCB) where the bed stores energy. Next, the energy is The high temperature and high pressure regenerator examined in
removed from the bed during the Cold to Hot Blow (CtHB). By oper- this paper has not been used previously within a Brayton power cycle
ating two beds out of phase with each other a quasi-steady flow can be and therefore it must be carefully considered in order to understand
achieved, as observed by the balance of the system. Regenerators are whether the potential advantages outweigh its disadvantages. This
currently used extensively for cryogenic applications in regenerative paper presents a detailed evaluation of regenerators as a competing
cryocoolers in order to recover heat from the helium working fluid. technology for recuperators within an sCO2 Brayton cycle. The level of
These systems can operate using either oscillatory flow driven by a the analysis presented here is sufficient to identify the key issues with
piston (as in a Stirling or pulse-tube type cycle) or by switching valves the regenerator system in order to direct future work and also to clarify
(as in a Gifford-McMahon cycle) [15–17]. Although the temperature the potential advantage of pursuing this technology. A reduced order
range is very different (cryogenic vs. high temperature), these cryo- model of a regenerator is integrated with a cycle model of an sCO2
genic regenerative systems are in many ways similar to the sCO2 re- Brayton to allow design and optimization. An economic analysis in-
generators being considered here. The systems operate in the super- vestigates the cost savings that is possible by switching from re-
critical range and experience relatively large pressure swings. A key cuperative heat exchangers to switched-bed regenerators. The result of
challenge associated with cryogenic regenerators is the identification of this analysis suggests that a 21.2% reduction in the contribution to the
materials that retain high heat capacity even at low temperatures. The Levelized Cost of Electricity (LCoE) from the power block can be rea-
regenerator in a high temperature system does not suffer from this lized by switching to a regenerator-based system.
degradation in heat capacity. However, the scale of a regenerator for
use in an sCO2 cycle is many orders of magnitude larger than what is
used in the cryogenic industry and the pressures are much larger. As a

1152
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

2. Regenerator operation bed will reach a quasi-steady state. Since each regenerator bed can only
have hot fluid or cold fluid passing through it at any instant of time, at
A regenerator has been proposed as a replacement to the re- least two regenerator beds operating out of phase with each other are
cuperator in order to accomplish the internal heat transfer that is re- needed if the regenerator is to provide continuous flow to the rest of the
quired by the cycle to achieve high efficiency. A regenerator operates cycle.
by alternatively passing a hot fluid and then a cold fluid over a matrix Since there is no need to have common boundary between the high
that has both large surface area and high heat capacity. The four steps pressure and low pressure streams in a regenerator, the construction of
involved in a simple, switched bed regenerator process are shown in the device is much simpler than a recuperator. A regenerator consists of
Fig. 3. During the HtCB process, hot fluid from the turbine is passed a vessel that is packed with a matrix material (for example, stainless
over the cold bed and the thermal energy associated with the resulting steel balls) with headers welded on and connected to a manifold of
heat transfer is stored in the bed. Since the fluid returning from the valves. Since there is no complicated fabrication process required, there
turbine is at low pressure and the fluid from the compressor is at high is a potential for significant cost savings. Additionally, since the sphere
pressure, the interstitial volume within the bed must be pressurized size in the bed can be made very small, the specific surface area (i.e.,
after the HtCB process by opening only the valve linking the bed to the the surface area per unit volume) of a regenerator can be much higher
compressor outlet. During the subsequent CtHB process, cold fluid from than the specific surface area of a recuperator. More surface area allows
the compressor is passed over the bed in the opposite direction as the the regenerator to have a higher conductance and therefore higher ef-
HtCB process. During this process, heat is transferred from the bed to fectiveness, which results in a higher cycle efficiency. The headers in a
the fluid so that the fluid exits at an elevated temperature. In order to recuperator provide a significant challenge to their design. Due to the
return the system to its original state, the carbon dioxide trapped in the overlaid plate geometry that is used for PCHE recuperators there is
bed volume must be reduced to a low pressure through a blowdown inevitably some section of the header that provides a cross flow ar-
process that occurs by opening only the valve connecting the bed to the rangement even if the bulk of the device operates in counter flow. The
precooler and compressor inlet. If this cycle is repeated many times, the crossflow region can cause a reduction in effectiveness that is

Fig. 3. The four steps involved in a switched bed


regenerator operation.

1153
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

significant at the performance levels that are appropriate for an sCO2 that the bed can hold much more energy than the fluid can impart, and
cycle. A regenerator does not have this issue and can be operated in true therefore the temperature of the matrix will change very little with time
counter flow fashion, which results in higher theoretical effectiveness. during each cycle. In the extreme case where the matric capacity ratio
However, the regenerator does suffer from carry over losses related to approaches infinite, the regenerator will behave in exactly the same
the blow down and pressurization process and the associated valves are way as a recuperator because, as in a recuperator, the bed (wall) tem-
complicated and expensive. Therefore, this paper provides a thorough perature will not change with time. As the matrix capacity ratio is re-
comparison of these two options in the context of the sCO2 cycle. duced, the effectiveness of the regenerator also decreases because the
temperature of the bed changes more dramatically during each cycle as
3. Regenerator design it absorbs and releases energy. After the HtCB, the temperature at the
hot end of the regenerator will be approximately equal to the tem-
Regenerators have found use in both power and HVAC applications perature of the hot fluid entering from the turbine. During the CtHB,
primarily using low pressure air as the working fluid in an energy re- cold fluid will start flowing through the bed in the opposite direction.
covery application. Previous work has been done to create an numeri- At the beginning of the CtHB, the exit temperature will be very close to
cally validated model of a regenerator for regenerators operating with the temperature of the hot fluid. However, as the process continues the
gas flows [20]. In the sCO2 cycle, there is a significant unbalance in the temperature will decrease since the temperature of the bed is being
regenerator where one of the fluid stream is operating nearer to the reduced by the cold fluid passing over it. The temperature of the fluid at
pseudocritical point. This is similar to the conditions that might be the hot end of the regenerator is shown in Fig. 4 for a typical operating
encountered in cryogenic regenerators for the same reason. In [21] an condition.
effectiveness-NTU-Cm method is presented for regenerators in cryogenic Since the temperature is not constant at the exit of the regenerator
cooling systems that remains analytic and therefore computationally in the way that it is for a recuperator, a different method is needed to
efficient but allows the consideration of the regenerator unbalance. This calculate effectiveness. However, the effectiveness must equivalently
design method is very similar to the effectiveness-NTU method that is represent the impact of the performance of the device on the overall
used for heat exchangers, but adds an additional parameter, the matrix cycle efficiency. The mass-averaged enthalpy of the fluid at the hot end
capacity ratio defined by Eq. (1.1). is used to define the effectiveness so that the performance of the tran-
sient system can be used directly in the steady state cycle model.
mb cb
Cm = The Number of Transfer Units (NTU) also factors heavily into the
̇
P0 Cmin (1.1)
effectiveness of the regenerator. Much like a recuperator, a higher NTU
where mb is the mass of the matrix material, cb is the specific heat ca- will result in higher effectiveness. The NTU is a function of the
pacity of the matrix material, P0 is the flow time (the time associated minimum capacitance rate and the conductance, defined by Eq. (1.3).
with the HTCB and CTHB processes), and Cmin ̇ is the minimum capa-
1
citance rate of the fluid passing through the bed. The capacitance rate UA = 1 1
of each stream is defined by Eq. (1.2). hcH As
+ hcC As (1.3)

Ċ = cp,avg ṁ (1.2) where hcH is the average heat transfer coefficient during the HtCB, hcC
is the same quantity for the CtHB, and As is the surface area that is
where cp,avg is the average specific heat capacity of the fluid passing exposed to the fluid. NTU is defined according to Eq. (1.4).
through the regenerator and ṁ is the mass flow rate of the fluid. The
matrix capacity ratio is a dimensionless parameter that is important in UA
NTU =
the design of the regenerator. A high matrix capacity ratio indicates ̇
Cmin (1.4)

Fig. 4. Temperature as a function of time of the fluid


streams into and out of regenerator at the hot and cold ends
during a complete cycle.

1154
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

It is easier (i.e., less costly) to obtain a large NTU in a regenerator as processes using a correlation for flow in a packed bed [22] and debits
compared to a recuperator because the specific surface area of a bed of the pressure ratio experienced by the turbine accordingly.
spheres is much higher than the specific surface area associated with a The effectiveness-NTU-Cm model expects that the dimensions of the
PCHE and the interstitial passages are quite small, leading to high heat regenerator are inputs and the performance of the device is an output.
transfer coefficients. The typical balanced regenerator model described However during the design process, it is desirable to specify the effec-
by [20] must be corrected to reflect the unbalanced nature of the re- tiveness and pressure drop associated with the regenerator and have the
generator operating in an sCO2 cycle that occurs because the capaci- model determine the required dimensions. To accomplish this, the
tance rate of the flow during the HtCB is different than the flow during Engineering Equation Solver (EES) software is used [23]. Fluid prop-
the CtHB. The correction calculates the capacitance ratio and uses it to erties are obtained through the internal property database in EES which
correct the NTU and Cm for the unbalanced flow situation. The model uses [24]. The user specifies the effectiveness, sphere size, switching
takes the corrected NTU and Cm and determines the effectiveness [21]. period, and pressure drop, and the model iteratively solves for the
The carryover mass is an unavoidable loss that is associated with the diameter, length, and carryover mass for a regenerator meeting the
operation of a regenerator that is not present when using a recuperator. desired operating parameters.
The carryover mass refers to the high pressure fluid that remains in the
regenerator when it is switched from the CtHB to the HtCB process. 3.1. Numerical validation
Since the pressure difference is large between the CtHB and HtCB, the
specific volume of the fluid held up in the regenerator differs greatly. In order to verify that the relatively simple, corrected effectiveness-
As a result, the amount of mass that enters the regenerator at high NTU-Cm model provides correct results, a more sophisticated but also
pressure and then returns to the compressor during the blowdown more computationally intensive model [25] was created based on the
process in Fig. 3 without going through the turbine can be significant. numerical one-dimensional regenerator equations using the method
This carryover mass is not captured in the corrected effectiveness-NTU- outlined in [26]. This model is provided with the dimensions of the
Cm model and corresponds to a direct reduction to the cycle efficiency regenerator, the temperature and mass flow rate of the fluid entering
since the compression work associated with that mass is not recovered the regenerator at each side, and average heat transfer coefficient for
in the turbine. The carryover mass is estimated according to: each blow of the regenerator. The model uses matrix decomposition to
calculate the temperature of the fluid as a function of time and space
x=L πD 2
mc = ∫x=0 4
(1−e v )[ρ (T (x ),PH )−ρ (T (x ),PL)] dx
(1.5) during a quasi-steady cycle with successive substitution to account for
the temperature and pressure dependent properties. The numerical
where D is the inner diameter of the regenerator vessel, ev is the void model predicts a parasitic heat transfer rate (which is related to the
volume fraction of the packed bed (ev = 0.37 for a randomly packed ineffectiveness) that is approximately 5% smaller than the value pre-
bed of spheres), and ρ(T(x),PH) and ρ(T(x),PL) are the densities of the dicted by the corrected effectiveness-NTU-Cm model for the low tem-
fluid at location x in at the time that the CtHB and HtCB flow processes perature regenerator, and 2.5% smaller for the high temperature re-
are complete, respectively. The carryover loss is estimated assuming generator under a typical operating condition. The numerical model
that the temperature of the fluid varies linearly from the hot inlet shows adequate agreement with the modified effectiveness-NTU-Cm
temperature to the cold inlet temperature. Since two regenerator beds model and therefore provides confidence in the results it predicts; the
are operating back-to-back, the mass of fluid associated with the car- modified effectiveness-NTU-Cm model appears to be slightly con-
ryover is returned to the compressor twice during every switching servative relative to the actual performance.
period. This carryover mass is quantified as a mass flow rate according
to Eq. (1.6) and treated as a leakage in the system that reduces the 4. ASME BPVC design
efficiency.
2mc In order to accurately determine the cost of the regenerator, the
ṁ c = outer shell must be sized correctly using ASME Boiler and Pressure
P0 (1.6)
Vessel Code (BPVC) [27]. Modeling and simulation of the regenerator
The model also calculates the pressure drop during both flow lead to an optimal design with an internally insulated pressure vessel.

Fig. 5. Concept drawing of insulated regenerator


THERMAL
OUTER SHELL pressure vessel.
STANDOFF

HIGH TEMP
INLET

LOW TEMP
INLET

INSULATION
PACKED BED

1155
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

The insulation reduced the temperature of the outer wall, allowing a entire shell remains below 375 °C and also experiences minimal thermal
less expensive material to be used. The insulation also limits the tem- cycling. This design was analyzed and the results are shown in Fig. 6, at
perature transients and associated thermal stresses caused by the per- the conclusion of the HtCB process. The outer pipe size was chosen
iodic flow through the bed. This concept is illustrated in Fig. 5. assuming the same insulation in the gap that is used on the inner sur-
This insulated regenerator design is similar to a Fluidized Catalytic face of the pressure vessel and natural convection on the outer surface.
Cracker (FCC) which is an internally insulated pressure vessel that also The heat lost to the cooling of the outer pipe is insignificant compared
contains a packed bed. Type 91 was chosen for its low cost, high to the heat transfer occurring within the pipe. The stress due to the
strength, and proven corrosion resistance to CO2 at temperature less thermal strain is small (about 5 MPa at the maximum) and due to the
than 375 °C [27]. high conductivity and high heat capacity of the wall and the insulation,
The insulation for the pressure vessel needs to be carefully designed the wall temperature does not change significantly over the cycle.
to avoid damage to the turbo-machinery due to material loss or loss in Since the effect of temperature on stress cycling has been eliminated
efficiency. The insulation needs to withstand the high pressure and high in the larger diameter portion of the pressure vessel using the thermal
temperature sCO2 environment without dusting. Any dust will in- standoff design, Chapter 5 of BPVC Section VIII Division 2 can be em-
evitably find its way to the seals in the turbo-machinery and cause them ployed to determine the wall thickness needed for the required pres-
to fail. The insulation must have low conductance and low porosity to sure-based stress cycling. Chapter 5 defines a limit on the number of
the working fluid. If the insulation is too conductive then the pressure cycles for a given stress amplitude. The stress amplitude in the BPVC
vessel needed to contain it will get larger, increasing costs. Any porosity must be estimated using a model of the entire pressure vessel simulated
causes in increase in carryover which reduces the efficiency of the throughout the entire stress cycle. This model takes into account stress
cycle. A castable type insulation sealed with thin sheets of stainless steel from pressure, structural loading, and thermal sources. A full finite
has been chosen for the insulation. The insulation is strong enough to element analysis is impractical for this high level study where the goal
withstand the pressure, while the thin sheet of stainless steel effectively is to obtain a reasonable estimate of the cost of a regenerator; the model
encapsulates the insulation, preventing any dust from entering the must be able to rapidly iterate on the regenerator size. Instead, analy-
stream and eliminating any potential problem with carryover. tical methods are used to determine a pressure vessel size that will
ANSYS was used to create a 2-D, axisymmetric thermal model of the approximately pass the BPVC. The analytical solution does not include
regenerator shell and insulation in order to determine the temperatures thermal stresses in the stress amplitude; these thermal stresses have an
that will be experienced by the shell. The sizing of the wall of the re- insignificant variation over each cycle. The stress amplitude due to the
generator is described in the following section. The temperature-de- pressure variation will have a maximum value at the point where the
pendent material properties of the insulation and wall were programed largest absolute stress exists; this value can be determined using stress
into ANSYS along with the bed temperature and heat transfer coeffi- equations for a cylindrical pressure vessel experiencing internal pres-
cient obtained from the numerical model. The outside of the re- sure. Chapter 5 of the BPVC provides a lookup table for the allowable
generator was allowed to convect to an ambient temperature of 32 °C, stress amplitude as a function of the number of cycles that the vessel
with the heat transfer coefficient calculated assuming natural convec- must withstand. The lookup table was programed into the design model
tion [26]. Radiation from the wall was not considered but would only along with the stress amplitude calculations in order to automate the
act to further reduce the wall temperature. The inlet and outlet nozzles process of selecting the vessel dimensions. The stress amplitude was
of the regenerator were included in the model and are assumed to have found using cylindrical shell stress equations [28]. The diameter of the
the same temperature as the bed at the nearest point. The heat transfer pressure vessel was determined by the regenerator model, taking into
coefficient in the nozzles is calculated assuming forced convection in a account the additional thickness needed for the insulation. The number
pipe [26]. The entire model was initialized at a constant temperature of cycles in the life of the system is calculated using the lifetime of the
and successive substitution was used to solve for the steady state tem- power plant (30 years), the daily number of hours of operation (10 h),
perature of the bed under quasi-steady state conditions. and the switching time (45 s); these conditions are consistent with the
A thermal standoff was added on the inlet and exit which allows the objectives of the Department of Energy APOLLO project. For these
shell of the regenerator to stay cool at the entrance and exit of the conditions there will be 10 million cycles during the lifetime of the
regenerator. The standoff consists of two pipes where the inner pipe regenerator. To account for startup and other pressure cycling events,
carries the flow and the outer pipe is the pressure boundary. The an- the total number of cycles is increased by 20 percent to 10 million
nular gap between outer pipe and the inner pipe is filled with insula- cycles for the design basis. Using this total number of cycles, the al-
tion. The outer pipe can be cooled so that its temperature is below lowable stress amplitude can be determined using the lookup table
375 °C at the location where it is joined to the shell. In this way, the provided by the BPVC Chapter 5. In order to check the results of the

High Low Fig. 6. Temperature (°C) distribution in wall and


insulation of regenerator with a thermal standoff,
Temperature Temperature results are shown at the end of the HtCB process
Inlet Inlet where the temperatures are highest.

Bed Packing

Thermal
Standoī
InsulaƟon
Pressure
Vessel Shell

1156
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

analytical model used to predict the pressure stress in the design model, published by Ho et al. [7]. The costs for the machinery are based on
a 2-D axisymmetric ANSYS model was created [29]. The analytical scaling equations available from the various sources that are indicated
method was found to be within 5% of the ANSYS model. In addition, in the paper. For a recompression cycle, the regenerator costs are es-
the penetrations in the regenerator shell were designed according to timated to be 244$/kWe which is 24% of the total cost of the power
BPVC rules. block. The cost of recuperators for a 10 MWe cycle was calculated using
In conclusion, an appropriate pressure vessel that meets the BPVC each of these sources and the results are shown in Table 3.
uses a design that employs a thermal standoff at the hot end of the This comparison shows that the cost numbers provided by CompRex
vessel and refractory insulation on its inner surface in order to eliminate for the recuperators are similar to previously presented information.
thermal transients in the outer wall of the vessel and reduce the wall There is likely to be a discontinuity in the cost curves for recuperators
temperature, respectively. The vessel wall is then sized to reduce the when it becomes necessary to shift from a standard 316 stainless steel to
stress amplitude associated with the pressure load to below the allow- high nickel content alloys at higher temperatures. It is possible that
able limit given the anticipated number of cycles. The pressure vessel regenerators do not experience this discontinuity due to the potential
dimensions for a 10 MWe power plant are listed in Table 1. for cooling the pressure vessel wall and the fact that the bed itself does
not experience any load. This suggests that the advantage associated
5. Heat exchanger costs with the use of regenerators over recuperators becomes more pro-
nounced as the cycle temperatures continue to increase.
Since the main objective of this paper is to assess the potential for
cost savings of using a regenerator in place of a recuperator, it is im-
portant to have an accurate cost model of the regenerators as well as 6. Regenerator optimization
their associated hardware (e.g., valves) and also of the recuperators that
they are replacing. The main cost associated with the regenerator bed is The goal for designing the regenerator is to have the largest possible
expected to be associated with the materials themselves as the manu- reduction in LCoE related to the replacement of the recuperators with
facturing involved is not complicated. There are three materials needed regenerators. The primary reduction in LCoE is associated with the
for the regenerators: Type 91 steel for the shell, 304SS for the packed reduced capital cost. However, carryover has a dramatic and negative
bed, and the refractory insulation. The wall material was chosen for its effect on the performance of a cycle that uses a regenerator. Therefore,
low cost and good strength at the expected wall temperature 375 °C. it is important to reduce the carryover loss as much as possible. The
Other high alloy stainless steel or nickel alloys could be used, however largest reduction in the carryover mass can be achieved by using the
this would drastically increase the cost even if the insulation could be high pressure fluid in one regenerator to partially fill the low pressure
eliminated. The material for the packed bed was chosen with the desire regenerator rather than allowing this mass to drain directly back to the
of getting the highest possible efficiency. The optimization of the bed compressor. If a linking valve is introduced that allows the two re-
material is outlined in Section 6. The appropriate insulation is less generators to exchange mass with each other before opening the valves
clear; therefore, the most expensive of the current insulation options to the compressor then some of the high pressure fluid that would have
was chosen for costing. The mass of each of these materials is calculated returned directly to the compressor during the blowdown process will
using the dimensions returned by the effectiveness-NTU-Cm model in- instead partially fill the regenerator. This fluid would otherwise be
tegrated with the BPVC calculations, as discussed in the previous two obtained from the compressor during the pressurization process. Once
sections. The cost of material is calculated using cost information from the pressure has equalized between the two regenerators, the valves are
Design for Manufacture (DFM): Concurrent Costing, which is a com- opened and normal operation is resumed. Adding one linking valve and
puter program that provides costing information based on the part operating the system in this fashion reduces the carryover mass by
being created and the operations needed for its manufacture [30]. The approximately a factor of 2 and, depending on the operating condition,
costs are listed in Table 2 with a 10 percent increase to account for increases the thermal efficiency of the cycle by as much as 3 percent.
uncertainties in costs. This valve operation is illustrated in Fig. 7.
There are three major operations needed for the manufacture of the Fig. 7 shows the additional equilibration process where all valves to
regenerator: forming the outer tube and end caps, casting the insulation each regenerator must be closed except for the added linking valve;
inside of the shell, and welding the shell together. The cost of these with only two beds there will be nowhere for the high pressure fluid
operations is estimated using DFM [30]. These processes together with exiting the compressor to go during this period of time. To eliminate
the material costs together were integrated with the cost model for the this issue, the regenerator is broken into at least four beds so that
regenerator. In order to establish some confidence in these calculations, continuous flow can be maintained. This means that while one pair of
a quote from a manufacturer for the shell of the regenerator was ob- beds are pressurizing/depressurizing the other beds are still operating
tained and found to be within 15% of the cost predicted by the model. normally. The additional beds also provide some secondary benefits
In addition to the cost for regenerators, the cost of the recuperators including more efficient operation under part load conditions and mi-
also must be understood in order to accurately determine the cost tigation of fluctuations of pressure and mass flow rate that would
savings that is possible. A manufacturer of PCHE heat exchangers, otherwise be experienced by the turbomachines. If all of the beds had to
CompRex, is a partner on the project and was able to provide a cost be used under part load conditions then the regenerators would be
correlation for the recuperators as a function of their conductance much larger than is needed to obtain high effectiveness. The extra bed
which was used to estimate the cost of the recuperators avoided by volume results in larger carryover relative to the mass flow through the
using a regenerator. For low conductance recuperators, the cost nor- system and reduces the thermal efficiency. By breaking the regenerators
malized by conductance is higher but as conductance increases the
normalized costs are reduced. The average cost is around 2,500 $/(kW/ Table 1
K). At the 2016 sCO2 symposium, SuperCritical Technologies presented Regenerator dimensions for 10 MW power plant.
a general cost relationship for various parts of the sCO2 power block
Dimension Low temp regenerator High temp regenerator
[31]. The cost of the recuperators was reported there to be 2,500 $/
(kW/K) which is similar to the costs provided by CompRex in the range Length 1.25 m (4.1 ft) 1.00 m (3.3 ft)
of UA required for a 10 MWe power plant (500–800 kW/K). The Diameter 1.19 m (3.9 ft) 1.31 m (4.3 ft)
Total frontal area 1.11 m2 (11.9 ft2) 1.35 m2 (14.5 ft2)
agreement between the two sources provided some confidence in the
Regenerator volume 1.39 m3 (49.1 ft3) 1.35 m3 (47.7 ft3)
estimated cost of the recuperators. Wall thickness 53.2 mm (2.09 in.) 57.9 mm (2.28 in.)
The other source of cost information for recuperators is a paper

1157
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

Table 2 The bed packing material can also have a significant effect on car-
Cost of materials in regenerator system from [30]. ryover. Since any volume in the bed that is not taken up in the packing
will result in more carryover, it is desirable to store as much energy as
Material Cost ($/kg)
possible in the smallest space. This suggests that the bed material
304 1.43 should have a large volumetric heat capacity. All materials show a re-
Type 91 3.79 latively constant volumetric heat capacity, with variations on the order
Insulation 3.08
of 10%. Stainless steel is one of the materials on the high end of vo-
lumetric heat capacity that can also withstand a high temperature high
Table 3
pressure CO2 environment. Additionally, stainless steel is low cost
Cost comparison of recuperators for a 10 MW power cycle from various compared to the other options such as refractory or metal foams.
sources. The effectiveness and pressure drop of the recuperators must be
simultaneously optimized. There are two requirements for obtaining a
Source Cost (k$)
high effectiveness regenerator: the first is to have a Cm ratio and the
CompRex 3,125 second is to have a high NTU. Eq. (1.1) shows that to keep the same Cm
SuperCritical Technologies [31] 3,368 for a given minimum capacitance rate, the mass of the bed must be
Ho et al. [7] 2,440 increased if the switching time is increased. Therefore, the switching
time should be kept as short as possible to keep the bed as small as
possible. The optimization of LCoE tends to push the regenerator to-
into more beds, unneeded regenerators can be taken offline and the
wards a relatively high NTU, moderate Cm operating design in order to
cycle can always operate with nearly an optimally sized regenerator.
keep the bed small. The NTU is based on the conductance (UA) of the
The disadvantage of this approach is that more relatively expensive
bed which can be increased by making the size of the spheres used for
valves are required to implement this option.

Fig. 7. Bypass valve operation to reduce carryover.

1158
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

the matrix smaller. This increases the UA both by increasing the specific valves, depending on the configuration, varied between $500,000 and
surface area of the bed and also by increasing the heat transfer coeffi- $1,500,000 for the entire system. The configuration with the lowest
cient due to the reduction in the hydraulic diameter of the passages. LCoE was the low pressure drop option, because the higher efficiency of
The disadvantage of this approach is that the pressure drop also in- the larger valves made up for their cost.
creases with a smaller hydraulic diameter. A smaller pressure drop re-
quires beds with short length and large diameter which increases the
8. Cost comparison
thickness required for the shell and therefore its cost. A larger pressure
drop results in a reduction in thermal efficiency. The optimal effec-
In order for regenerators to replace recuperators, they must to
tiveness is a balance between high heat recovery at high effectiveness,
provide an advantage in one or more of the following categories: cost,
with low carryover and low cost at low effectiveness.
maintenance, reliability, or lifetime so that the replacement of re-
The models described here allow a comprehensive optimization of
cuperators with regenerators creates a reduction in the LCoE. The LCoE
the system that includes the tradeoffs discussed. The optimal pressure
takes into account all of the capital costs associated with the power
drop for each regenerator is approximately 220 kPa. The optimal value
block and spreads them out evenly to the electricity produced by the
for effectiveness for the high temperature regenerator is 98.7% whereas
cycle using the method outlined in [32]. The LCoE calculations for this
the optimal value for the low temperature regenerator is only 96.0%.
analysis were done for a power plant with a 20 MWt heat input. To
The reason for this difference is related to the carryover contributions
make the results more general, only the contribution to LCoE from the
associated with each unit. In the low temperature regenerator the
power block (not the heat source or fuel) was considered in this ana-
density variation with pressure is much higher and, as a result, about
lysis. The constant heat input takes into account the difference in
75% of the total carryover loss in the cycle occurs in the low tem-
thermal efficiencies associated with using regenerators compared to
perature regenerator. By lowering the effectiveness slightly, the carry-
recuperators. A high efficiency results in more power generation and
over is reduced and the thermal efficiency of the cycle actually in-
thus more energy to spread the capital costs over. The costs for the
creases.
power block and recuperators were obtained from [7] and the re-
Several limits were placed on the values of the parameter space
generator system cost was estimated using the techniques and cost es-
explored during the optimization described in this section. The
timates discussed in this paper. The system was assumed to be an RCBC
switching time could not be made arbitrarily small since the valves
operating with a 720 °C turbine inlet temperature at pressures of
need a finite time to respond. The valve response time was estimated to
25 MPa and 8 MPa. The recuperators were specified to have a effec-
be 3 s to fully open and close and therefore the smallest allowable flow
tiveness of 94%, which has been reported to be the maximum practical
period was set to be much larger than this value, 45 s. The size of the
value due to the crossflow nature in the headers [14]. The effectiveness
spheres in the packed bed were limited to 3 mm or higher.
of the low temperature regenerator is set to 96.0% while the high
temperature regenerator is set to 98.7% effectiveness; these higher
7. Valve selection
values are possible because a regenerator can be operated in a true
counter flow configuration. The thermal efficiency of the optimized
From a cost standpoint it was found that the valves used to control
cycle, the LCoE, and the cost of the recuperator or regenerator plus
the flow of the high temperature and high pressure carbon dioxide were
valves, are summarized in Table 4.
almost as important as the regenerator beds themselves. Not only is the
The cycle operating with a regenerator shows a modest increase in
temperature of the fluid in the valves very high (560 °C for a 720 °C
cycle efficiency while maintaining a substantial reduction in LCoE due
turbine) but the temperature experienced by the valve fluctuates during
to the lower cost for the regenerator system. It is important to also know
each cycle causing thermal cycling. Fig. 4 shows an example of the
the sensitivity to costs of the regenerators and valves as they contain the
temperature variation that the valve will experience every 45 s as the
most uncertainty in this analysis. Fig. 8 shows contours of constant
cycle is running for a typical cycle. Large temperature changes cause
reduction in LCoE as a function of a cost multiplier for the regenerator
thermal stresses in the valve body which can result in leakage or pre-
and valve costs.
mature breakage of the valves. Ideally a valve would last for the life-
Even with a 50% increase to the costs of the regenerators and valves
cycle of the power plant (30 years) but that may not be feasible in such
there is still a 12.8% decrease in the LCoE for the regenerator system as
a hostile environment. The minimum valve life that is acceptable is one
compared to the recuperator cycle. This analysis shows that re-
year, which is how often most plants shut down for maintenance. The
generators have the potential to reduce the costs of the sCO2 power
valves also need to be able to open and close quickly so that re-
cycle under a wide range of cost conditions.
generators can operate correctly. Finally, the valve pressure drop must
meet performance targets.
Information on commercially available valves has been gathered in 9. Conclusions
collaboration with the project partner FlowServe in order to compare
the capital and maintenance costs for each type of valve. A table of The sCO2 power cycle has the potential to provide electricity at
valve operating conditions was provided to FlowServe, who analyzed much greater efficiency than current Rankine cycle technologies due to
three types of valve for this application; open/close globe valve, three its ability to operate at much high temperatures. However the high
way valve, and rotary valve. The three way valve and rotary valve degree of recuperation necessary for high efficiency means that the
options resulted in a high cost and more complexity for this application printed circuit heat exchangers currently being considered for this ap-
leaving the open/close globe valve as the best choice. The valves were plication are a large portion of the cost of the power block [7]. This
sized to have the lowest possible cost for the operating conditions. paper describes a thorough and realistic estimate of the potential for
Valves located in positions that do not experience high temperature are
designed with lower cost alloys. Several scenarios were considered Table 4
Efficiency, recuperator costs, and LCoE for a recuperator and regenerator operating at
which corresponded to both high and low values for both pressure drop
identical conditions.
(30 kPa and 90 kPa) and flow rate so that the cost penalty associated
with these options could be considered. As expected, the costs were Thermal LCoE Recuperator/regenerator
lower for a high pressure drop option but the efficiency of the system efficiency ($/kWh) + valves cost (k$)
was also reduced. It was determined that the efficiency gained by using
Recuperators 51.76% 0.01957 4177
the lower pressure drop valves was more important than the capital cost Regenerators 52.27% 0.01542 1897
savings associated with the valve in terms of the LCoE. The cost of the

1159
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

1.5 Fig. 8. Percentage reduction in LCoE of regenerators as compared to


recuperators as a function of a cost multipliers for valves and re-
13.5 generators.
1.4
15
Valve Cost Multiplier

1.3
16.5
1.2
18

1.1
19.5

1.0
21

0.9 22.5
24

0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5


Regenerator Cost Multiplier

cost savings that is associated with replacing the recuperators with its use would not infringe privately owned rights. Reference herein to
regenerators. Regenerators provide a slightly higher thermal efficiency any specific commercial product, process, or service by trade name,
due to the higher effectiveness that is possible with a pure counter flow trademark, manufacturer, or otherwise does not necessarily constitute
configuration. The cost of regenerators was estimated by optimally or imply its endorsement, recommendation, or favoring by the United
designing these components and then combining the amount of mate- States Government or any agency thereof. The views and opinions of
rial with an estimate of the material and manufacturing costs. The re- authors expressed herein do not necessarily state or reflect those of the
generator shell was sized such that it could approximately meet the United States Government or any agency thereof.
ASME BPVC. The cost of the valves required by a regenerator system
was obtained in partnership with a well-established industrial valve References
manufacturer and the cost of the recuperators that are replaced by the
regenerators was estimated using several sources, including a partner- [1] Driscoll MJ. Supercritical CO2 Plant Cost Assessment. Cambridge; 2004.
ship with a well-established manufacturer of PCHEs. The result of this [2] Persichilli M, Kacludis A, Zdankiewicz E, Held T. Supercritical CO2 power cycle
developments and commercialization: why sCO2 can displace steam. Power-Gen
analysis suggests that switching from recuperators to regenerators can India Cent Asia 2012:1–15.
result in a modest improvement in thermal efficiency and a 50% re- [3] Conboy TM, Carlson MD, Rochau GE. Dry-cooled supercritical CO2 power for ad-
duction in capital cost of the heat transfer equipment. These effects vanced nuclear reactors. J Eng Gas Turbines Power 2014;137:12901. http://dx.doi.
org/10.1115/1.4028080.
result in a 21.2% reduction in the contribution to LCoE from the power [4] Dyreby JJ. Modeling the Supercritical Carbon Dioxide Brayton Cycle with
block. The current drawbacks to widespread adoption of regenerators is Recompression; 2014.
the lack of testing. Recuperators, even the relatively new PCHEs have [5] Pierres R Le, Southall D, Osborne S. Impact of Mechanical Design Issues on Printed
Circuit Heat Exchangers. In: Proc. sCO2 Power Cycle Symp. 2011, Boulder: 2011.
had significant testing, whereas regenerators operating at these condi- [6] Musgrove GO, Pierres R Le, Nash J. Tutorial: heat exchangers for supercritical CO2
tions have not been thoroughly studied. The sCO2 cycle creates a need power cycle applications; 2014.
for lower cost regenerators because of the high temperatures and high [7] Ho CK, Carlson M, Garg P, Kumar P. Cost and performance tradeoffs of alternative
solar-driven S-CO2 Brayton cycle configurations. Proc. ASME 2015 Power Energy
pressures that are not present in a more conventional Rankine cycle.
Convers. Conf. 2015. p. 1–10.
While regenerators are much further down the technology readiness [8] Urquiza E, Lee K, Peterson PF, Greif R. Multiscale transient thermal, hydraulic, and
scale, they have the potential to disrupt the sCO2 heat exchanger mechanical analysis methodology of a printed circuit heat exchanger using an ef-
market. fective porous media approach. J Therm Sci Eng Appl 2013;5:1–8. http://dx.doi.
org/10.1115/1.4024712.
[9] Carlson MD, Bell C, Schalansky C, Fleming DF, Rochau G. The Selection, Evaluation
Acknowledgments and Rating of Compact Heat Exchangers (SEARCH) Software Suite - Code
Capabilities and Experimental Comparison. In: 5th Int. Symp. - Supercrit. CO2
Power Cycles, San Antonio; 2016, p. 1–13.
Special thanks to Evan Reznicek from Colorado School of Mines for [10] Jentz IW. Modeling, performance testing, and ASME BPVC Certification of a s-CO2
his help with modeling the regenerator, Rich Gradle from FlowServe for Marbond Channel Heat Exchanger. University of Wisconsin-Madison; 2016.
[11] Carlson MD, Kruizenga AK, Schalamsky C, Fleming DF. Sandia Progress on ad-
his work with sizing and designing the valves, and Zhijun Jia from vanced heat exchangers for SCO2 Brayton Cycles. In: 4th Int. Symp. - Supercrit. CO2
Comprex for obtaining cost estimates for the PCHE recuperators. Power Cycles; 2014, p. 1–10.
[12] Kruizenga A, Anderson M, Fatima R, Corradini M, Towne A, Ranjan D. Heat transfer
of supercritical carbon dioxide in printed circuit heat exchanger geometries. J
Funding Therm Sci Eng Appl 2011;3:31002. http://dx.doi.org/10.1115/1.4004252.
[13] Tsuzuki N, Utamura M, Ngo TL. Nusselt number correlations for a microchannel
heat exchanger hot water supplier with S-shaped fins. Appl Therm Eng
This material is based upon work supported by the U.S. Department 2009;29:3299–308. http://dx.doi.org/10.1016/j.applthermaleng.2009.05.004.
of Energy under Award Number DE-EE0007120. [14] Nikitin K, Kato Y, Ngo L. Printed circuit heat exchanger thermal – hydraulic per-
This report was prepared as an account of work sponsored by an formance in supercritical CO2 experimental loop. Int J Refrig 2006;29:807–14.
http://dx.doi.org/10.1016/j.ijrefrig.2005.11.005.
agency of the United States Government. Neither the United States [15] Gheith R, Aloui F, Ben Nasrallah S. Determination of adequate regenerator for a
Government nor any agency thereof, nor any of their employees, makes Gamma-type Stirling engine. Appl Energy 2015;139:272–80. http://dx.doi.org/10.
any warranty, express or implied, or assumes any legal liability or re- 1016/j.apenergy.2014.11.011.
[16] Hu JY, Luo EC, Dai W, Zhang LM. Parameter sensitivity analysis of duplex Stirling
sponsibility for the accuracy, completeness, or usefulness of any in-
coolers. Appl Energy 2017;190:1039–46. http://dx.doi.org/10.1016/j.apenergy.
formation, apparatus, product, or process disclosed, or represents that

1160
J.F. Hinze et al. Applied Energy 208 (2017) 1150–1161

2017.01.022. Phys Chem 1996;25.


[17] Gifford WE. The Gifford-McMahon Cycle. Adv. Cryog. Eng., Boston, MA: Springer [25] MathWorks. Matlab2015a; 2015.
US; 1966, p. 152–9. doi:10.1007/978-1-4757-0522-5_16. [26] Nellis G, Klein SA. Heat Transfer. New York: Cambridge University Press; 2009.
[18] El-Wakil MM. Powerplant Technology. 1st ed. New York: McGraw-Hill; 2013. [27] Engineers AS of M. Section VIII Rules for Construction of Pressure Vessels. In:
[19] Korakianitis T, Wilson DG. Models for predicting the performance of Brayton-Cycle American Society of Mechanical Engineers B and PVC, editor. ASME Boil. Press.
engines, vol. 2 Aircr. Engine; Mar. Microturbines Small Turbomach. ASME; 1992, p. Vessel Code, New York; 2007.
V002T02A020. doi:10.1115/92-GT-361. [28] Beer FP, Johnston ERJ, DeWolf JT, Mazurek DF. Mechanics of Materials. 6th ed.
[20] Dragutinovic GD, Baclic BS. Operation of Counterflow Regenerators. Boston: New York: McGraw Hill; 2012.
Computational Mechanics Publications; 1998. [29] ANSYS Academic Research, Release 16.1 n.d.
[21] Barron R, Nellis G. Cryogenic Heat Transfer. 2nd ed. Taylor and Francis; 2016. [30] Boothroyd Dewhurst Inc. DFMA 2016.
[22] Kays WM, London AL. Compact Heat Exchangers. 3rd ed. New York: McGraw Hill; [31] Wright SA, Davidson CS, Scammell WO. Thermo - economic analysis of four sCO2
1984. waste heat recovery power systems. In: 5th Int. sCO2 Symp., n.d., p. 1–16.
[23] F-Chart. EES Engineering Equation Solver; 2015. [32] Short W, Packey DJ, Holt T. A manual for the economic evaluation of energy effi-
[24] Span R, Wagner W. A new equation of state for carbon dioxide covering the fluid ciency and renewable energy technologies; 1995.
region from the triple-point temperature to 1100 K at pressures up to 800 MPa. J

1161

You might also like