You are on page 1of 1

1.

11 Quantity Surveying as a reference when the actual works


eventually commence. The location of the
The quantity survey for road works offset pegs needs to be carefully recorded.
should be carried out after the road
alignment has been selected and the Estimating Quantities
appropriate road design standard has When a final choice of the exact position 1
been approved. This task should be done of the road alignment has been made, the
by the engineer and technician with next step is to carry out a full estimate

P L A N N I N G A N D P R E PA R AT I O N O F W O R K S
the setting out team and based on the of the quantities of work. The estimated
data assembled in the road alignment work quantities form the basis of the cost
drawings. Once the initial volumes have analysis and determine future inputs of
been estimated, it may be necessary to labour, materials, tools and equipment.
re-adjust the road alignment in order to
reduce the volumes of work. Based on the information recorded in the
road alignment drawings, it is possible
If the works consist of improving an to carry out a complete estimate of the
existing road on which no changes are construction quantities.
envisaged to the road alignment, there
should be sufficient data in the road Here again, it may be necessary to re-
condition forms. adjust the road alignment in order to
find the best location and optimal road
Recording Information levels. When building a new road, the
Once the road alignment (horizontal, main task when carrying out a quantity
vertical and cross sections) has been set, survey is to estimate the exact volumes
all measurements should be carried out of earthworks. The road alignment
at regular intervals and marked with pegs will determine the amount of cut and
and recorded in a Works Quantity Form. fill required. Based on the information
It is useful to draw up the cross section collected during the field surveys and
at regular intervals along the road in a the quantity estimates, it is possible to
notebook clearly describing the dimensions prepare the Bill of Quantities.
BUILDING RURAL ROADS

and chainage. By drawing these cross-


sections to scale, it is then easier to The work quantities will vary along
calculate the cross-sections of cut and fills. the road alignment, depending on the
terrain features. In order to calculate the
Solid offset pegs should be established volumes of work with a reasonable degree
during this exercise to mark the alignment of accuracy, the road is therefore split into
in the field, which can then be used shorter segments with uniform geometric
features to simplify the calculations.

The estimates of t he volumes of


earthworks are based on the cross-
sections drawn up at regular intervals
along the road alignment during the field
0 4 9

You might also like