Professional Documents
Culture Documents
The extreme survey camp was conducted at two places Nandicross and Hegdehalli,
located about 30KM North of Bangalore. The survey work involved the investigation and design
of the following projects:-
New Tank project
Water supply and Sanitary Project
Highway Project
Old Tank Project/Restoration Tank Project
1. Levelling
2. Plane Table Surveying
3. Tacheometry
Levelling:-
Levelling is a method of surveying used for the determination of thedifference of elevations
of levels of various points on the surface of the earth. Levelling deals with distances in a vertical
plane.
Levelling is an important method of surveying used for many engineering works and
construction projects. It is required to determine the undulations of the earth’s surface for
topographic mapping. It is needed for the design of highways, railways, canals, sewers etc.
Levelling is essential for the layout of construction projects, for locating the excavation levels in
buildings, bridges, dams etc. the drainage characteristics of an area an be obtained by leveling.
The results of the leveling can be used to determine the catchment area, volume of the reservoir
and the area submerged by a reservoir. The results of leveling can also be used to determine the
volume of earth works for roads, railways and canals. Levelling is required in almost all engineering
works of importance in one from or the other. The most commonly used methods of leveling for the
survey work are described below.
Differential levelling:-
Differential levelling is the method of levelling which requires more than oncesetting of the
level instrument. The method is used when the two points, whose difference of elevation is
required, are situated quite apart or when their difference of elevation is large. Differential
levelling is also called as compound levelling. In this method, a number of settings of the
instrument are done one after the other, and the process is continued till last point is sighted.
Profile Levelling:-
Profile levelling is the process of levelling along a fixed line to determine the elevations of
the ground surface along that line. The fixed line is generally the Centre line of a highway,
railway, canal, sewer or any other such utility. The fixed line need not be a single straight line.
It may consist of different straight reaches connected by curves. Profile levelling is also known
as longitudinal sectioning.
The ground profile is the section of the ground obtained when a vertical plane cuts the
ground surface. The ground profile shows the elevation of the ground along that section. The
profile levelling is done to determine the undulations of the ground surface. The ground profiles
are used to study the relationships between the existing ground levels and the levels of
proposed routes. The gradient lines are drawn and the formation levels at various points are
determined and the amount of cutting and filling can be computed.
Field Procedure:-
Profile levelling is nothing but differential levelling done along a line. Profile levelling is
commenced from a bench mark and end at bench mark, as far as possible.
Let AB be the fixed line along which profile levelling is to be done. Let BM-1 and BM-2 be the
two bench marks. Intermediate points a, b, c etc. are first marked on the line AB at some
suitable interval, usually 20m. The positions of these intermediate points are located by
chaining along the line AB and nothing the distances from the starting station A. When the
ground surface doesn’t have much undulation, the intermediate points are fixed at a uniform
interval. However, if ground surface is irregular and there are abrupt changes in the ground
surface, the interval may be non-uniform. The interval is reduced in the reaches where there
are abrupt changes.
The instrument is setup on a firm ground at some suitable place (say) L1 so as to command a
large number of points on the line. A back sight is taken on BM1 to determine the height of
instrument at L1. The staff is then kept successfully at stations A, a, b, c and d and the
intermediate sights are taken to determine the levels of those points. It becomes necessary to
shift the instrument if the intermediate sight exceeds 100m or so, when further points become
invisible owing to large undulations in the ground.
Field notes of profile levelling are recorded in the standard level book. The height of
instrument method is used for the reduction of levels. Since the number of intermediate sights
is more, the height of instrument method is more convenient.
Cross Sectioning:-
Cross sections are run at right angles to fixed line along which the profile levelling is done.
These lines are taken on the both the sides of the fixed line obtain the lateral line of the ground
surface. They provide the data for estimating quantities of earthwork and other purposes.
The cross sections are numbered consecutively from the commencement of center line and
are set out at right angles to main line of section with the help of chain or tape, the cross-staff
or the optical square and the distances are measured on the left and right of the center peg.
The levels of each cross-section point are determined.
Block Levelling:-
This method is employed in the places where the ground profile over a certain area is
required. The area to be surveyed is divided into a number of squares of size varying from 2m to
20m, thus forming a grid or block. The level is setup in the middle of the area at a commanding
position. The height of the instrument is determined by taking a back sight on the bench mark
and then intermediate sights are taken on each of grid points.
From the elevations of grid points, the points on the various contours are located by
interpolation. Block levelling is essentially in places where a high degree of accuracy in terms of
the ground profile is required and where costly structures have to be constructed. This method
was used at the locations of waste weirs and cross-drainage works.
Contours:-
A contour is the line joining points of the same level on the earth surface or a contour is the
line of intersection of a level surface with the surface of the ground.
The difference of elevations between two successive contours is known as the contour
interval. For the survey works carried out in the camp, a contour interval of 1m has been used.
The indirect method of contouring has been used, wherein the elevations of some guide points
are determined in the field and the contours of a particularare interpolated from the elevations
of the guide points.
The storage capacity of a reservoir can be determined by the contour map. The contour line
Computation of volumes:-
The computation of volumes of various quantities from the measurements done in the field is
required in the design and planning of many engineering works. The volume earth work is
required for the selection of a suitable alignment for a road, a canal and a sewer. The volume
of earthwork is also required for preparation of the estimates and for the payment of materials.
The computation of the volume of water stored in a reservoir is required for its design, planning
and management. The direct consumption of the volume from the measurements of length,
width, and depth is not feasible for large engineering works. The computation of the volume is
done after computing the area of various cross sections. For the estimation of volume of water
in a reservoir, the contour map is used.
Capacity of a reservoir:-
The capacity of a reservoir is determined from a contour map. The volume is computed by
assuming that the reservoir is divided into a number of horizontal slices. For computation of the
volume, the whole area lying within the contour line and the upstream of the dam is
determined with a planimeter. The whole area is enclosed by successive contours are taken as
horizontal sections and the vertical interval between them as the constant distance for
computation of the volume by the trapezoidal rule.
If A1, A2, A3… are whole areas included by the contours and if ‘h’ is the contour interval,
then the volume of the reservoir is given as
V = h [A1+A2+A3+………+A(n-1) ]
The main feature of plan table surveying is that the plotting is done in the field where all the
stations and other features are in view of the surveyor, and a comparison between the plan and
Plane table surveying is a rough method of surveying. It is mainly used for small-scale and
medium scale mapping in open country where great accuracy is not required. It is also used for
plotting the topographical maps in field.
This method was used for capacity surveys, key plan of channel alignment, and alignment of
centerline of existing bund, key plan of highway alignment and for preparation of village map.
Tacheometry:-
Tacheometry is a branch of angular surveying in which the horizontal and vertical distances
of points are obtained by optical means as opposed to the ordinary slower process of
measurements by tape or chain. This method is very rapid and convenient. The primary object
of tacheometry is the preparation of contour maps or plans requiring both horizontal as well as
vertical both control. An ordinary transit theodolite fitted with stadia diaphragm is generally
used for tachometric survey. The horizontal distance between the instrument axis and the level
staff is determined using the distance equation.
D = Ks+C
Where
This method was employed for the capacity surveys; in the preparation of the contour map.
Irrigation may be defined as the process of supplying water to land by artificial means for the
purpose of cultivation. The basic objective of irrigation is to supplement the natural supply of
water to land so as to obtain an optimum yield from crops grown on the land.
In order to achieve this objective of irrigation, an irrigation system is required to be developed,
which involves planning, designing, construction, operation and maintenance of various irrigation
works viz. a source of water supply, a distribution system for carrying water from the source to the
agricultural land and its application on the land and various other works.
The engineering aspect of an irrigation project involves the development of a source of water for
irrigation and the arrangement for the conveyance of water from the source right up to the
agricultural fields. The development of the source of water constitutes the first phase of an
irrigation project. The water for irrigation may be derived from surface water sources such as
rivers, lakes, ponds, tanks etc., and it is known as Surface water. For obtaining water for irrigation
from rivers, two methods are commonly adopted. In one of the methods, a storage reservoir is
created by constructing a dam across the river and the water stored in the reservoir is used for
irrigation through a canal system. The second phase of an irrigation project comprises the
development of a system for the conveyance of water for irrigation.
Irrigation Tank is generally a small storage reservoir formed across a stream in a valley. Sometimes
these tanks could be having independent catchments, drawing their supplies from the runoff from
the catchment areas. These tanks fully depend on the rainfall in their catchments.
An irrigation tank essentially consists of the following:
An earthen bund across the valley creating storage
A surplus weir to dispose of flood discharge
Sluices to feed the channels
Channels from the sluices to feed the command area
The main barrier across the valley and stream bed, to store water in the tank, is usually an
earthen bund. For big tanks which are also called reservoirs, the height of the bund in the deep
course goes up to 10 to 15 meters.
Depending upon the method of construction, earth dams can be divided into two categories:
1. Rolled fill dam.
2. Hydraulic fill dam.
In the rolled fill dam, the embankment is constructed in successive, mechanically compacted
layers. The suitable materials are transported from the burrow pits to the construction site by
suitable earth moving machinery. It is then spread by bulldozers, and sprinkled to form layers of
limited thickness having proper water content.
In the case of hydraulic fill dam, the materials are excavated, transported, and placed by hydraulic
methods. Flumes are laid at a suitable falling gradient along the outer edge of the embankment.
The material, mixed with water at the borrow pits, is pumped and washed into these flumes
.
Rolled-fill earth dams can further be subdivided into following types:
Homogeneous embankment type.
Zoned embankment type.
Diaphragm embankment type.
2.5. SLUICES:
Like all earthen dams, tank bunds are generally provided with sluices or outlets for
discharging water from the tank for irrigation and other purposes. These sluices may be pipes or
rectangular openings passing near the base of the bund, carrying water into the downstream
channel below the bund.
In such a possible case, a vertical filter (are inclined upstream or downstream) is placed
along with horizontal filter, so as to intercept the seeping water effectively, as shown in figure.
Such an arrangement is termed as chimney drain. Sometimes a horizontal filter is combined and
placed along with a rock toe, as shown in figure.
The upstream of earth dam is protected against the erosive action of waves, by stone pitching or
by stone dumping as shown in the figure.
The thickness of the dumped rock should be about one meter, and should be placed over the gravel
filter of about 0.3-meter thickness. The filter prevents the washing of fines, from the dam into the
riprap. The provision of such a dumped riprap has been found to be most effective and has been
found to fail only in 5% cases.
The stone pitching, i.e. the handpicked riprap requires a lesser thickness and may prove more
economical if suitable rock is available only in limited quantity. However, when provided in smaller
thickness (i.e. single layer), it is more susceptible to damage and has been found to fall in about
30% cases.
Concrete slabs may also be laid over the upstream slope of the earth dam. Then such slabs are
constructed, they must be laid over a filter and weep holes should be provided so as to permit
escape of water, when the reservoir is drawn down. If the filter is not provided, the fines from the
embankment may get washed away from the joints, creating hollows beneath the slab and causing
the consequent cracking and failure of the slab under its own weight. Concrete slab protection has
been found to fail in about 36% cases mainly because of not providing filter below them.
The downstream slope of the earthen dam is protected against the erosive action of wave up to a
slightly above the water depth, in a similar manner as is explained above for upstream slope.
More over the downstream slope should be protected against erosive action of rain and its runoff
by providing horizontal berms at suitable intervals, say about 15 meter or so has to intercept the
rainwater and discharge it safely. Attempts should also be made so as to grow grass and plants at
the downstream slope, soon after their construction.
2.10.3 OBJECTIVE:
To estimate the quantity of earth work for a proposed construction of the earthen bund
similarly, as in case of all dam reservoir projects, tanks are provided with arrangements for spilling
away the excess water that may enter in to the tank, to avoid over–topping of the tank bund.
These escape arrangements may be in the form of a surplus escape weir or waste weir, provided in
the body or at one end of the tank bund. The weir is a masonry weir with its top level equal to the
Full tank level (F.T.P). When the tank is full up to its FTL and extra water comes in and discharges
Berms are narrow strip of earth provided on the downstream side of the embankment to see
to that the saturation line lies within the embankment. If the saturation line lies outside the
embankment, there is a chance of slipping of the dry side over the wet side.
2.11.1 Specifications:
The length of the proposed bund should be least.
There should be good foundation available.
A natural subsidiary is desirable at bund site for locating waste weir.
To meet the above specifications, the center line for the bund is fixed by means of at least two
flag posts (P and Q) on either side at elevation of 2m above the top level of bund.
2.11.5 OBJECTIVES:
To fix the capacity of tank bund
To fix the full tank level
To fix the MWL of tank
To fix the sill level of sluice
2.12. PROCEDURE:
Carry out fly levels from nearest TBM.
For a particular set up of the instrument, the required staff readings are made by tying a
colored material around the reading.
The center line of bund and that of waste weir is located on the plane table sheet.
Staff man moves with the staff in the direction indicated by the person at the dumpy level,
simultaneously the person at the plane table bisects the contour point.
The distance between dumpy level and the staff is calculated by method of tachometer
using the relation D=KS+C.
The distance obtained is converted to a scale of 1:1000 and plotted on the plane table.
The contour point should be located at closed intervals.
Block levels at waste weir.
2.12.2 PROCEDURE:
The reduced level of point ‘p’ is obtained by ferrying fly levels from temporary BM.
The bearing of the center line of the waste weir RP is taken with the help of prismatic
compass.
Levels are carried out at every 5m along RP and cross-sections are taken at every 5m or a
distance of 40-45m.
A neat sketch of the layout and the square block is formed and is indicated with clear
notations to identify the points for which the reduced level has to be determined.
2.13.1 OBJECTIVE:
To estimate the cost of channel and cross drainage works
Assuming the run-off co-efficient for the concerned catchment area to be 20% avg rainfall.
=2625000cumecs.
Assuming 4000cumecs of water per hectare as the duty of area that can be irrigated will be,
= 6.980m.
= 989.335 + 1
= 990.335m
Top width of Bund id taken as 3m. considering the stability of the dam, provide U/S slope as
2.5:1 & D/S slope as 2:1 for the bund with masonry core inside has assume hydraulic gradient as 4:1
for casting material and 3:1 for hearting material. A revetment of 50cm thick stone is provided on
upstream extending 30cm above the MWL with 10cm thick gravel backing.
Height of the core wall below the deepest point = 982.355 – 980.000
= 2.355m.
= 5-[ 2 x ¼ x 2.355 ]
= 3.82m Say 4m
Rectangular grip renches are provided (1.5m 1.5m) size along the bund length on D/S, and
longitudinal drains are provided on U/S, every 10m interval across the bund.
NATURE OF AREA OF
DUTY
CROP HECTARES
Sugar cane 150 800
Rice 200 1000
Wheat 100 1000
Vegetable 100 800
= 150/800
= (0.1875+0.20+0.10+0.125)/4
Since more water is required for Khariff period the discharge may be increased by 50%.
= 0.91875
= 0.92 cumec.
= Cd X A x √2gh
= [0.92/(0.66 x √2x9.81x1.5)]
A = 0.257m2.
A = (π/4) x d2
0.257 = (π/4) x d2
d = 0.57m = 0.6m
Sluice barrel:- The main vent way to b above for sluice barrel is about 60cm * 75 cm.
= 2 x 0.6 = 1.2m.
= 0.2m.
Cistern is rear of barrel, provide (2.5 x 4.85) m up to a depth of full supply level from foundation
level. The cistern functions as a discharge dissipater destroying for reducing the energy of incoming
water from tank to the channel dimensions.
Q = discharge m3/s
Q=A*V
A = Q/V
= 1.08 m3/s.
Assuming, the side slope of the channel as 1.5:1 for most economical trapezoidal section.
= d√n2+1
b + 2(1.5d) = 2d√1.52+1
b + 3d = 3.6d
b = 0.6d
m = d/2
m = area/wetted perimeter
d = 0.75m.
= 0.6*0.75m
b = 0.45m.Say 0.5m
C = Ryve’s co-efficient = 10
Rectangular weir :-
Q = 2/3*Cd*√2g *L*H3/2
Q = 61 cumec
Cd = 0.65
= 1m
It is proposed to make arrangement for storing water up to MWL for the non-monsoon period
A = 0.55 x (√H + √h )
= 988.335-982.355
= 5.98m
= 1m
= (5.98+1 /√2.25-1 )
Chainage Ground Top Depth Avg Side Side Area Sectional Volume
In ‘M’ Rl Bund of Depth Area Area Bd Area In ‘M3’
Level filling S1d2 S2d2 Bd+Sd2
0 990.335 990.335 0.000 - - - - - -
10 989.960 990.335 0.375 0.188 0.088 0.070 0.563 0.642 6.416
20 989.190 990.335 1.145 0.760 1.444 1.155 2.280 3.580 35.796
30 988.785 990.335 1.550 1.348 4.539 3.632 4.043 8.128 81.280
40 988.450 990.335 1.885 1.718 7.375 5.900 5.153 11.790 117.896
50 988.020 990.335 2.315 2.100 11.025 8.820 6.300 16.223 162.225
60 986.160 990.335 4.175 3.245 26.325 21.060 9.735 33.428 334.276
70 985.800 990.335 4.535 4.355 47.415 37.932 13.065 55.739 557.386
80 983.840 990.335 6.495 5.515 76.038 60.830 16.545 84.979 849.793
90 982.975 990.335 7.360 6.928 119.976 95.981 20.783 128.761 1287.606
100 982.655 990.335 7.680 7.520 141.376 113.101 22.560 149.798 1497.984
110 982.905 990.335 7.430 7.555 142.695 114.156 22.665 151.091 1510.906
120 982.955 990.335 7.380 7.405 137.085 109.668 22.215 145.592 1455.916
130 983.595 990.335 6.740 7.060 124.609 99.687 21.180 133.328 1333.281
140 982.355 990.335 7.980 7.360 135.424 108.339 22.080 143.962 1439.616
150 985.995 990.335 4.340 6.160 94.864 75.891 18.480 103.858 1038.576
160 986.480 990.335 3.855 4.098 41.974 33.579 12.293 50.069 500.689
170 987.160 990.335 3.175 3.515 30.888 24.710 10.545 38.344 383.443
180 987.685 990.335 2.650 2.913 21.207 16.965 8.738 27.823 278.235
190 988.975 990.335 1.360 2.005 10.050 8.040 6.015 15.060 150.601
201 990.335 990.335 0.000 0.680 1.156 0.925 2.040 3.080 30.804
The primary object of the minor irrigation tank is to store as well as provide water for the
irrigation purpose. New tank is constructed to give a perennial source of water for irrigation to
agricultural land area. This project involved for the construction of new tank in Hedgehalli.
Finally after the estimation for the project proposed and practically implemented it has to be
situated in terms of benefit and cost ratio. The benefit value coming out of the project should be
greater than the cost involved in the implementation of the project in all the forms including the
loss of land and forest area.
4.1. INTRODUCTION:
Public Health Engineering is a project carried out for the effective supply of water and proper
sanitation of water maintains. For the economic and efficient functioning of a water supply project
it is necessary to prepare a detailed plan, which incorporates the design of various components of
the project.
4.2 .OBJECTIVE:-
• To formulate and design a water supply schema at Nandi village considering the water is
available at the reservoir as a main source of supply.
• To ensure treated water supply at all times of the year at adequate pressure.
Besides promoting overall hygiene and public health, it ensures safety against fires by supplying
sufficient quantity to extinguish it. The existence of such a water supply scheme further helps in
attracting industries and thereby helping in industrialization and modernization of society,
consequently reducing unemployment and ensuring better living standards. Such schemes therefore
help in promoting wealth and welfare of the entire humanity as a whole.
• Sources of supply
• Intakes
• Reservoirs
• Valves
• Hydrants
The various types of water demands, which may have, can be broken down into the following
classes:
• Fire demand
• Climatic conditions
• Habits of population
• System of supply
• Loss of water
• Policy of meeting
Certain Physical, Chemical and Biological characterstics with maximum permissible limits as
follows
The design period chosen, should neither be so long as to throw unnecessary extra financial burden
on the present generation, nor should it be so short as to make the design insufficient for future
needs.
Population forecast:
Sl. No. YEAR POPULATION A.I.M G.I.M I.I.M
1 1951 1000 - - -
2 1961 1400 400 40 -
3 1971 2200 800 57.14 400
4 1981 2560 360 16.36 - 440
5 1991 3000 440 17.19 80
6 2001 3760 760 23.33 320
7 2011 4472 712 18.94 -48
X = 578.66 r = 26 Y = 62.4
Pn = po+nx
P2048= 4472+(3.7*578.66)
P2048= 6613.04
Pn = Po (1+r/100)n
P2048= 4472(1+(26/100))3.7
P2048=10516.5
Pn=po+nx +(n*(n+1)/2)
P2048= 4472+(3.7*578.66)+(3.7*(3.7+1)/2)
P2048 =6621.74
FLOATING POPULATION
• Number of daily pilgrims= 100
• Marriage’s=100
• Campus=100
= 40500 lpcd
= 1082418 l/d
= 1125418 l/d
= 1125418/103*24*60*60
= 1125.42 m3/day
= 0.0130 m3/sec
= 1.8*1125.42
= 2025.75 m3/d
= 0.0234 m3/sec
= 2025.75/(8*60*60)
Q = 0.070 m3/sec
Q=A*V
0.070 = (πd2/4)*0.9
CAPACITY OF PUMPS
BHP=QWH/75ŋ
H=HS+HF+HT
= 983.270-968.020+10
= 25.25 m
HF= flv2/2gd
= (0.04*1694*0.92)/ (2*9.81*0.32)
= 8.74 m
Where,
L = 1694 m
f = 0.04
HV= v2/2gd
= (0.92)/ (2*9.81*0.32)
= 0.130 m
TREATMENT UNIT:
1. SCREENS:
Assume velocity of flow through screens=0.1m/s
=0.01/.1=0.1M^2
L=A/H=0.1/0.3=0.34M
2. SEDIMENTATION TANK:
Assume sedimentation tank works for 8 hr /day
= 0.070M3/sec
= 0.070*5400 = 378M3
= 126 m2
B = 6.5m , L= 19.5m
Area = πd2/4
Dia, d = 25.33m = 26 m,
DP=2+0.5=2.5m
Assume L=2*B
Total area=v/d
= 0.070*60*60/0.1 = 2520m2
Area=L*B
2520 = 2B2
B= 25 m
L= 50 m
DP= 1.5m
= 252*0.3= 75.6 kg
Chlorine content in bleaching powder is 30%, it means 100 kg bleaching content of 30 kg chlorine
content
= 252 grams/day
Assume depth of 1 m,
=252/1=252 m2
252 = 2B2
B= 11.25 m,
L= 22.45 m
Q= 2025.75/(8*60*60)
= 0.070 m3/sec
A = πd2/4
V= 0.85*Ch*r0.66*S0.5
Ch=140
0.9= 0.85*140*0.080.66*S0.5
S= 1.604*10-3
S= 1 IN 623
Say S = 1 IN 650
CONCLUSION:
Public health engineering is a project carried out for the efficient supply of water and proper
utilization of water maintained zoological balance b/w living beings and environment.. Organized
community required service of water supply and sewage disposal in order ensure that availability of
sufficient quantity of good water. It becomes necessary to plan and built suitable water supply
scheme the provision of such a scheme shall ensure constant and reliable water supply to the
people as well as the disposal of sewage through sewage system.
They will make area disease free when more required thing for community, treatment for the
sewage is done to ensure that there will be proper disposal of sewage into nearby sea. If present
since in the nearby of the project side no seashore is there, disposal; of sewage done by sewage
drying bed.
Roadways
Railways
Waterways
Airways
Among these, transportation by road is the only mode which gives maximum service to
one and all. This mode also has maximum flexibility for travel with reference to route, direction,
time and speedof travel etc. through any mode of road vehicle. It is possible to provide door to
door service only by road transport. The other three modes of transportation have to depend on
roads for the service to and from their respective terminals, airports, harbors or stations. The road
network is needed not only to serve as a feeder system for other modes of transportation and to
Highway Engineering is a branch of engineering that deals with the development of a system of
roads, which can be used by vehicles and people, for the transportation of people and materials.
The road pavements area generally constructed on small embankments, slightly above the
generally ground level wherever possible, in order to avoid the difficult drainage and maintenance
problems. The term ‘road’ or ‘roadway’ has therefore been termed ‘Highway’ and the science and
technology dealing with road engineering is called ’Highway Engineering’.
In a nutshell, highway engineering deals with various phases like development, planning,
alignment, highway geometric design and location, highway traffic operations and its control,
materials, pavement design, constructing and maintenance, finance and administration of a road
system.
3.2.1Characteristics of roads:-
For short distance it saves time.
Speed of movement is directly related to the casualty.
It is the only means of transport that offers itself to the whole community alike.
Once the road is aligned and constructed, it is not easy to change the alignment due to
increase in cost of adjoining land and construction of costly structures by the roadside. Hence the
importance of careful considerations while finalizing the alignment of a new road need not be over
emphasized
1. Short – a straight alignment is the shortest alignment between two points, though there
may be several practical considerations which would cause deviations from the shortest
path.
2. Easy – the alignment should be such that it is easy to construct and maintain and operate
vehicles.
3. Safe – the alignment should be safe for construction and maintenance and traffic
operation with safe geometric features
4. Economical – the alignment would be economical only if the total cost including initial
cost, maintenance and vehicle operation cost is lowest.
The various factors which control the highway alignment in general may be listed as:
Obligatory points
Traffic
Geometric design
Economics
Other considerations
Stability
Drainage
Geometric standards of hill roads
Resisting length
3.5.2. Traffic:-
The alignment should suit the traffic requirements. Origin and destination study should be carried
out in area and the desire lines are drawn showing the trend of traffic flow. The new road should
be aligned keeping in view the desire lines, traffic flow patterns and future trends.
3.5.4. Economy:-
The alignment finalized based on above factors should also be economical. In working out the
economics, the initial cost and cost of maintenance and vehicle operation should be taken into
account. The initial cost of construction can be decreased if high embankment and deep cuttings
are avoided and alignment is chosen in manner to balance the cutting and filling.
The geometrics of highway should be designed to provide optimum efficiency in traffic operation
with maximum safety at reasonable cost.
Highway geometrics are greatly influenced by topography, locality, traffic characteristics and
requirements. The factors which control the geometric design requirement are speed, road users
and vehicular characteristics, design traffic, traffic capacity and benefit –cost consideration.
However, speed is the one factor which is important, governing most of the geometric design of
roads.
The geometric of the highway depends on several other factors, the most important of which are:
Design speed
Topography
Traffic factors
Design hourly volume and capacity
Environment and other factors
Horizontal alignment
Very often changes in the direction are necessitated in highway alignment due to obligatory points.
Various design factors to be considered in the horizontal alignment are design speed, radius of
circular curves, type and length of transition curves, super elevation and widening of pavement on
curves. The alignment should enable consistent, safe and smooth movement of vehicles operating
at design speed. It is hence necessary to avoid sharp curves which cannot be conveniently
negotiated by the vehicles at design speed. Improper design of horizontal alignment would
necessitate speed changes resulting in increased vehicle operation cost and high accident rates.
b. The important surface characteristics of the pavement are friction, unevenness, light reflection
characteristics and drainage of surface water
The width of roadway is the sum of the widths of carriageway and the shoulders.
Based on the IRC standards, the width of roadways for a Major District Road with single lane is
taken as 9.0m.
Super elevation
Extra widening of pavement
Horizontal transition curve
Flexible Pavements
Rigid pavements
Flexible pavements
These are the pavement which have negligible flexural strength and are rather flexible in their
structural action under the load. A typical flexible consists of four component
The pavement layers transmit the vertical or compressive stresses to the lower layers by grain to
grain transfer.
Selection of route.
Finalization of highway alignment and geometric design details
Collection of materials and testing of sub grade soil and other construction materials,
construction stages including quality control.
Map study
Reconnaissance survey
Preliminary survey
Location and final alignment
Detailed survey
Material survey
Design
Earth work
Pavement construction
Construction controls
Re –Alignment:-
As the olden roads were meant for slow traffic, they are found deficient in the
geometric design elements for the present day automobile traffic
Necessary of re- alignment
To improve the horizontal alignment design element.
Re construction of week and narrow bridges.
Construction of by pass to avoid the road running through a town or city
Key map
Index map
Preliminary survey plans
Detailed plan and Ls
Detailed Cs
Drawing of road intersection
The CBR value of the soil was considered to be an index which is related to its strength. The value
is highly dependent on the condition of the material at the time of testing. CBR value has been
correlated with the modulus of the sub grade reaction, modulus of resilience and plastic index.
CBR definition:-
It is a ratio of the load taken by the soil at 2.5mm or 5mm penetration by plunger of 50mm
diameter at the rate of 1.25mm per minutes to the load taken by the standard crushed stone at the
same penetration.
Apparatus:
Moulds with base plate
Collar
Spacer discs
Metal rammer
2.5kg 31cms fall
4.89kg 45cms fall
Adjustable stem with perforated plates and tripod
Annular weights of 2.5kg each
Loading machine with 500kg capacity, rate of deformation equal to 1.25mm per minute
50mm dia plunger
Dial gauge least count = 0.01mm
Sieves 19, 4.75mm sieve.
Measuring jar, filter paper and oven
Re-molded specimen; sieve the soil on a 19mm sieve. Take the soil that passes through the 19mm
sieve, allowance of larger materials is made by replacing it by an equal amount of material which
passes the 19mm sieve but it is restrained on the 4.75mm sieve.
Static Compaction:-
Volume of mould = cc
Weight of dry soil= *d gm
d=dry density by proctor test or sand replacement test
m=moisture content (field) or OMC
Weight of wet soil=
Amount of water
Procedure:
a) Mix the soil with water required
b) Fill it in the mould and tamp with a steel rod
c) Place a filter paper on top of the soil
d) Place the spacer disc
e) Compress it with a compression testing machine
f) Wait for 5minutes. The spacer disc should flush with the top of the mould
g) Before testing soak it for four days
h) [For existing roads, d and m are obtained by sand replacement method. For new roads d and
m are obtained by proctor density test.]
Dynamic Compaction:-
Find d and m by proctor test
Find the weight of the soil to be taken
Weight of soil = volume *dry density.
Add the amount of water
Amount of water = weight of soil
Penetration test:-
Place the surcharge weight in soil specimen.
Keep the mould in the machine
Apply kg seating load to ensure the plunger is fully in contact with the soil
The load and penetration dial gauges are set to zero
The load is applied such that the penetration of the plunger is 1.25mm per minute
Note down the value of load at 0.5,1.0,1.5,2.0,2.5,3.0,3.5,4.0,5.0,7.0,10,and 12.5mm
penetration
CBR CALCULATIONS :-
0 0 0 0
50 0.5 2 12.34
100 1.0 3 18.51
150 1.5 3 18.51
200 2.0 4 24.68
250 2.5 4 24.68
300 3.0 4 24.68
350 3.5 5 30.85
400 4.0 5 30.85
500 5.0 6 37.02
750 7.5 9 55.53
1000 10.0 12 74.04
1250 12.5 15 92.55
CBR CURVE
100
90
80
LOADS IN KG
70
60
50
40
30
20
10
0
0 2 4 6 8 10 12 14
PENETRARTION IN MM
= (0.0606060*1000)\9.81
= 6.17kg
6. CBR Calculations:
Load at 2.50mm penetration = 24.68kg
HIGHWAY DESIGN
Horizontal Curve
1. CAMBER PROVISION :
= 0.0875m = 87.5mm
R = [50]2 / [127(0.07+0.15)]
We = Wm + Wps
=[ (nl2)/(2R)] + [v / (9.5√R)]
= 0.955M
B = 7.96mt
4. TRANSITION CURVE:
(A) Centrifugal Acceleration (C):
C = (80) / (75+V)
Ls1 = (0.0215V3) / CR
= (0.07*7.96) e = 0.07
Ls2 = [E/2]*N
= 0.56*130 = 72.80mt
C) Ls3 = (2.7V2) / R
= (2.7*502) / 90 = 75mt
Chainage,x Offset,Y=x3/6RLs
10 0.025
20 0.197
30 0.667
40 1.580
50 3.086
60 5.333
70 8.469
75 10.420
CHA REDUC FORMA DEPT DEPT AVG AVG AREA AREA LE VOLUME VOLUME
INA ED TION H OF H OF DEPT DEPT OF OF NG OF OF
GE LEVEL LEVEL CUTT FILLI H OF H OF CUTTIN FILLIN TH CUTTING FILLING
ING NG CUTT FILLI G G
ING NG
0 992.090 984.600 7.490 - - - - - - -
10 991.520 984.412 7.108 7.299 126.265 10 1262.654
20 990.735 984.364 6.371 6.739 112.816 10 1128.159
30 990.325 984.246 6.079 6.225 101.001 10 1010.006
40 989.775 984.128 5.647 5.863 93.005 10 930.048
50 984.230 984.010 5.220 5.433 83.858 10 838.579
60 989.900 984.892 5.008 5.114 77.293 10 772.930
70 989.775 984.774 5.001 5.004 75.090 10 750.900
80 987.115 983.656 3.499 4.250 60.653 10 605.625
90 986.425 983.538 2.887 3.193 42.125 10 421.252
100 985.875 983.420 2.455 2.671 33.844 10 338.442
110 985.420 983.302 2.118 2.286 28.093 10 280.931
120 984.870 983.184 1.686 1.902 22.638 10 226.376
130 984.645 983.066 1.579 1.632 18.990 10 189.901
140 984.840 983.950 0.890 1.234 13.869 10 138.690
150 983.735 983.830 0.095 0.445 0.048 4.648 0.477 10 46.480 4.773
160 983.095 982.712 0.383 0.192 0.048 1.952 0.477 10 19.517 4.773
170 982.470 982.594 0.124 0.130 0.062 1312 0.624 10 13.118 6.238
180 982.965 982.540 0.425 0.151 0.062 1.528 0.624 10 15.277 6.238
190 982.630 982.440 0.190 0.308 3.170 10 31.696
200 982.090 982.362 0.272 0.095 0.136 0.959 1.378 10 13.785
210 981.730 982.286 0.556 0.414 4.311 10 43.114
220 981.330 982.209 0.879 0.717 7.690 10 76.898
230 980.750 982.132 1.382 1.130 12.583 10 125.830
240 979.730 982.055 2.325 1.853 21.970 10 219.705
250 979.470 981.978 2.508 2.416 30.004 10 300.045
260 979.080 981.901 2.821 2.664 33.745 10 337.446
270 978.805 981.824 3.019 2.920 37.726 10 377.264
280 978.180 981.747 3.567 3.293 43.774 10 437.738
CONCLUSION:
The transportation is increased day by day and for a good transportation it is required for
economical and safety purpose, as the project site was near the village. To arrive at the road
system and the different category of roads, this could provide maximum utility to connect the
villages nearby and also is therefore needed to serve as the feeder system for the nearby markets
and municipalities and to provide independent facility for road travel by well planned network of
roads throughout country. Thus keeping this into consideration, the highway project was done by
selecting the route to construct the highway as it was economical both in safety and cost.
1.1. INTRODUCTION
The storage irrigation that utilizes the water stored on upstream side of smaller earthen dam
called bund. Earthen bund which retains water is called tank. A large sized tank will be termed as
the reservoir. This may be formed by the materials such as masonry dams, concrete dams and
earthen dams where as the tank is formed by means of earthen bunds only.
The tanks are meant for storing water in it during the raining season due to the surface runoff of a
large amount of silt will be deposited in to the tanks hence it reduce the capacity of tank. This
reduce capacity of tank may be improved by removing the deposited silt from the tank
(restoration) or sometimes due to the bad maintenance the existing slope of the bund may get
deteriorated: for this the increasing the bund height should be done. So that the slope may
detained and hence increase in the storage capacity of reservoir.
The tank which is to be restored is situated 7 km from NH7 and 45 km from Brindavan college of
Engineering. The one end of the tank is touching the Hegdehalli village and other end to Nandicross
village. Due to the inadequate maintenance the top portion of the bund as eroded at several places
this requires a repair or increase in the existing height.
1.5.1. PROCEDURE:
The field work includes
• Fly leveling,
• Bund tracing,
PROCEDURE:
• Initially on the center line of the bund arrows are fixed at regular interval.
• By taking the TBM (temporary bench mark) located on the bore well the leveling is done to
find the RL of top of the bund.
• Longitudinal levels along the center line of the bund are taken at every 5m interval and
cross section is taken at the place of change the direction of the bund.
• Imported features such as location of any tree, stone, and sluices weir are noted.
• The cross section is taken on both side of the center line of the bund.
• Continue the procedure till the other end of the bund is reached.
• Last point should be located at the some convenient distance from the existing bund.
• The plotting of the existing build is also done parallel to fly leveling with the help of plane
table and alidade.
• Percolation
• Erosion by waves
If the free board is not enough, a breach may occur. To prevent this from happening, sufficient
free board is provided, wave breaks which are generally vertical stones fixed in the rip rap on the
upstream slope in a zigzag pattern, are also provided. This will help in breaking the waves as they
move riding along the slope.
1.8.4. Cut-off:
In order to ensure that the dam does not fail due to percolation through its body an impervious
cut-off, completely preventing seepage from upstream of the dam reaching the toe of the dam
along the foundations, is an absolute necessity. The latest technique is to form reinforced cement
concrete diaphragm wall, with its bottom ell keyed the bed rock and top well keyed to the hearting
zone.
It is desirable that banks are consolidated at optimum moisture content with power rollers to get
at least 98% Proctor’s density. Moisture content more than the optimum will mean low shear value
and less than optimum will increase pore pressure.
Procedure:
Taking the sill of the waste weir as benchmark, each contour is located by determining the
position of a series of points through which the contour passes.
The plane table is set up over a good commanding station where maximum points are
available and the place table is oriented.
The plane table and the leveling instruments are provided as near as possible to each other
so that the distance of the contour points be measured by the principle of tacheometry and
plotted on the plane table by the method of radiation.
The contours are plotted on the plane table and the capacity is determined by joining the
points of contours.
Procedure:
The instrument is setup at commanding position where maximum readings are available and
all the reduced level of the stations of the blocks are calculated. The contours of different
elevations are plotted by interpolation.
Volume = 4688.66m3
TOTAL VOLUME-4688.66m3
CONCLUSION:
The capacity of the existing tank bund had been reduced due to its age, also to all other features
such as change in the atmosphere condition and improper usage of the tank over a perennial
time. The projects were carried out calculation that the tank can be restored to it’s designed by
compacting soil to calculate height and making rise in the masonry work.
ABBREVIATIONS:
KG KILO GRAM
M METER
CM CENTIMETRE
KM KILOMETER
RL REDUCED LEVEL
HP HORSE POWER
SURVEYING:
1. Surveying-1&2 by B.C.Punmia
IRRIGATION:
WATER SUPPLY:
HIGHWAY: