Professional Documents
Culture Documents
CAMPING
2080
PRESENTATION BY
GROUP-E
SURVEY IS THE FIRST STEP OF EVERY CIVIL
ENGINEERING DISCOVERIES
-JOHN BRADFIELD
• ASHWIN SHRESTHA
• MILAN GIRI
• KISHAN BHARDWAJ
TEAM
MEMBERS OF • BISWA PRAKASH PARASAR
GROUP -E
• ADARSHA SAPKOTA
• GAURAV GHIMIRE
INTRODUCTION TO SURVEY CAMPING
• Survey camping simply refers to the civil engineering training course for
2/3 weeks usually after completion of 4th semesters of bachelor of
technology that consist of 10-15 days working in field and 6/7 days of map
plotting manually or using different engineering software.
OBJECTIVES OF SURVEY CAMPING
BASIC OBJECTIVE
• To give students an opportunity to improve theoretical and practical knowledge in surveying under
actual field conditions
• To familiarize in handling different survey instruments and to be familiar with team work .
• Collection of data in systematic way and learn in time management in professional surveying period.
ADVANCED OBJECTIVE
• To conduct topographical survey and prepare topographical map of the area as per given technical
specifications.
• To conduct bridge and road site survey and prepare their respective reports .
Field works
TOPOGRAPHICAL SURVEY
6:30 AM to 7:30 AM: Theory Discussion class by Tula Ram Bhandari Sir
8:00 AM to 10:30 AM: Survey work
10:30 AM to 11:30 PM: Brunch
11:30 PM to 5:00 PM: Survey work
SATELLITE VIEW OF LOCATION AREA
PRINCIPLE OF SURVEYING:
• Working from whole to part
• Location of point by measurement from two points of reference
• Consistency of work
• Independent check
CLASSIFICATION OF SURVEYING
BASED ON INSTRUMENTS USED
Chain surveying Compass surveying Plane table surveying Theodolite surveying Photographic
surveying
BASED ON METHODS USED
• Triangulation surveying
• Traverse surveying
ERROR AND ACCURACY
IN SURVEY
Types of error:
q Mistakes(carelessness, inexperience)
q Accidental Errors(Compensating Errors)
q Systematic Errors(cumulative )
Sources of error:
q Instrumental Error
q Personal Error
q Natural Error
TOPOGRAPHICAL SURVEY
•Topographical surveying is the process of determining the
positions of existing features of the locality by means of
conventional signs on a topographical map.
•Topographic surveys are three-dimensional or 3D
TOPOGRAPHICAL SURVEY( i.e traversing and levelling). They provide the
SURVEY techniques of plane surveying and other special techniques to
establish horizontal and vertical control.( Traversing gives
the horizontal control and levelling gives vertical control.)
MAIN PRINCIPLE: •Objectives:
1)TRAVERSING • To prepare the topographic map
2) LEVELLING • To determine the positions of both horizontal and vertical
control on plan and elevation
3)DETAILING
•Description of the Area:
•The topographical survey was performed in IOE
PURWANCHAL CAMPUS . The major traverse runs
through the campus boundary , which covered 40% of the
total area of the campus. The minor traverse run within the
major traverse through the plot of the given map.
TRAVERSING
PART ONE
TRAVERSING
• Traverse is a series of connecting lines
whose length and bearing are known.
• It is also a method of control surveying
as we create control networks in the field.
• TRAVERSING consists of the measurement of :
PART ONE
Types of Traverse:
a) Open Traverse
b) Closed Traverse
The traverse in which angular measurements between traverse sides are made
with a theodolite, is known as theodolite traversing.
The straight line between two consecutive traverse stations is called a traverse
leg.
The angle at any station between two consecutive traverse legs is known as
traverse angle.
If the coordinates of the first station and the bearing of the first line are known, the
coordinates of all successive points can be computed as follows:
yB = yA + Lcosθ ;xB = xA + Lsinθ
METHODOLODY
• Measurement of Bearing
Reconnaissance:
Reconnaissance (Recce) means the preliminary inspection of the area before
commencing the actual detail survey, for the purpose of fixing the survey
stations and forming a general plan for the network of the chain lines.
While selecting the major and minor control points following points should be
considered:
• The adjacent stations should be clearly inter-visible and cover the whole area with least
number of stations as far as possible
• The stations should provide minimum level surface required to set up the tripod of the
instrument.
• The traverse line of sight should not be near the ground level to avoid the refraction.•
Measurement of Traverse (Length and Angle)
Traverse Length:
After completion of recce survey, Legs of the major traverse are measured
by Total station or EDM.
Leg ratio of 2:1 for major and 3:1 for minor was checked.
To attain the accuracy required of 1:5000 for major traverse length and
1:3000 for minor traverse length a two way measurement was done.
Fixing major and minor stations
After RECCE ,we can use SATELLITE VIEW for rough mind setup of
traverse stations so that it gives clear view of the area to be surveyed.
Major station=
Minor station=
NORTH
DISCREPANCY AND LINEAR MISCLOSURE:
In order to measure the lengths of the sides of the traverse, two ways measurement (forward and
backward) is done.
The difference in values obtained by forward and backward measurement is called discrepancy.
The reciprocal of the mean of the two measurements divided by the discrepancy is called
precision.
Both the discrepancy and the precision for each traverse leg should be within the given limits.
Mathematically,
Discrepancy = | Forward length - Backward length |
Linear precision =
MEASUREMENT OF HORIZONTAL ANGLES:
It was done in the following way-:
At face left temporary adjustment was done.
After setting zero to the first station the second station was sighted by unclamping the
upper screw.
For better accuracy and exact bisection horizontal angle was measured at the bottom of
the ranging rod .
Now again changing the face the horizontal angle was taken .
Now setting the reading to ninety at the first station again one set of horizontal angles
was taken.
For major traverse : more precision required so two set data was taken.
For minor traverse : Less precision is acceptable so one set of data was taken.
(NOTE: Difference between FL and FR angle shouldn't be greater than 20" or least count
of theodolite and mean of 2 set shouldn’t be greater than 1' )
LEVELLING
Part 2
LEVELLING
•Levelling is an art of determining relative altitudes of points on the surface of the earth or
beneath the surface of the earth.
•It is used to find the elevation of given points with respect to a given or assumed datum
and to establish points at a given elevation or at different elevations with respect to a given
or assumed datum.
METHODS OF LEVELLING
Direct Levelling: Indirect Levelling:
• Differential Levelling • Reciprocal Levelling
• Check Levelling
• Profile Levelling
• Cross-section Levelling
Temporary adjustments of Level:
• Selection of suitable position.
• Fixing level with tripod stand.
• Approximate levelling by legs of tripod stand.
• Perfect levelling by foot screws.
• Focusing the eye piece.
• Focusing the object glass.
• Take the staff readings.
Then the instrument was setup on the line near A or B and both staff readings (Top, Middle,
and Bottom) were taken.
Then computation was done in order to check whether the adjustment was within the
required accuracy or not.(i.e collimation error should be less than 1:10,000)
TWO PEG TEST DATA
Booking of reducing levels:
Among the two methods, Rise and fall method was used.
FLY LEVELLING
The fly levelling was carried out between TBM and C.P
1.
The RL of TBM was found by transferring the level from
known BM located at Mahedev chowk by the process of fly
levelling.
The R. L of the temporary benchmark was then
transferred to the control stations of the major and
minor traverse.
The closing error was found to be within the permissible
limits. The misclosure was adjusted in each leg of the
leveling path by using the following formula:
Permissible error = ±25√k mm (Where k is the total perimeter
in Km)
DAY-3
CALCULATIONS PART
YEHA SAMMA KISAN LE
CALCULATION FOR GALES TABLE:
ADJUSTMENT OF ANGULAR ERROR:
In a closed traverse, by geometry, the sum of the interior angles should be equal to (2N-4)*90˚.
If the angles are measured with the same degree of precision, the error in the sum of the
angles may be distributed equally among each angle of the traverse.
CALCULATION OF BEARING:
At first Bearing of one line was measured.
From bearing of one line , bearings of other lines were calculated as:
Bearing of forward line = bearing of previous line + included angle +/- 180 or –540
For anticlockwise traverse: Bearing of forward line = bearing of previous line + included angle
where included angle=interior angle.
For clockwise traverse: Bearing of forward line = bearing of previous line + included angle where
included angle = (360- interior angle)
COMPUTATION OF CONSECUCTIVE
CO-ORDINATES:
1)Direct method
points with the same elevations are found out by setting out the instrument at
a point and by hit and trial method of searching the points which gives the
same required staff reading.
Contours are located and directly plotted in field and are more tedious.
2)Indirect method
some suitable guide points are selected and
surveyed.
It is mainly done by :
1)square method 2) Tacheometric
method.
CONTOUR INTER POLATION
It is the process of spacing the contours between the plotted points .
It is done by :
1) By eye judgement
2) By arithmetic method
CONTOUR
CHARACTERISTICS
ü Two contour lines do not intersect: each other except
in the case of overhanging cliff.
ü Contour overlap or unit in a single line in case of
vertical cliff.
If the contour lines are parallel and distance apart
it shows that ground is gentle slope.
If contour line are spaced closer and non uniform then it
shows steep and undulated ground.
PART 3
PART TWO
Introduction
Bridges are the structures that are constructed with the purpose of connecting two places separated by
deep valleys or rivers and streams.
For places, where the ground is uneven and undulated and where the number of rivers is large,
bridges are the most economic, efficient and convenient way.
Bridges are usually a part of roads, making them shorter and hence economical.
Beam Bridge
(Narayani River, Chitwan) Truss Bridge (Ramdi)
Suspension Bridge
Tied Arch Bridge Cantilever Bridge
(Kushma)
(Bijulibajar, Kathmandu) (Budhigandaki River, Gorkha)
Objectives of bridge site survey
⮚ To select the possible bridge site and axis for the construction of bridge .
⮚ To collect the preliminary data i.e. normal water flow level, high flood level .
⮚ To carry out surveying for topographical mapping, longitudinal and cross sections at both
the upstream and downstream side of the river.
Site description
The bridge site survey was done
over Sardu River. But there was no
flow of water. There is plain
ground as well as sloping ground
places which surrounds the river.
The site is surrounded with sand
and stone boulders available in the
river. The width of river is not so
big but flood level covers slightly
bigger area. Watermarks on the
rock shows that the highest flood
level is quite high at sometimes.
Equipment & Accessories
Arrows
Total station Ranging Rods Pegs
Measuring Tape
Levelling Machine
& Staffs Prism Compass
The various methods performed during the bridge site
survey were:
Site selection
Topographic Survey
(Note: A triangle in which an angle of the triangle is less than 30 or greater than 120 is known as is ill
conditioned triangle.)
SATELLITE VIEW OF CONTROL STATIONS
NORTH
YEHA SAMMA BISWA LE
LEVELLING
Transferring R.L. from B.M. to control points:
•R.L. was transferred to the control station from the
B.M. by fly leveling by taking the back sight-reading
to the bench mark which should be within the given
accuracy.
• The R.L. was transferred to the opposite bank of
the river by reciprocal leveling.
Reciprocal Levelling
This method is applicable when taping
is obstructed but not the vision.
NORTH
COMMENTS AND CONCLUSION
Design of bridge depends upon the economy and duration.
The bridge axis should be designed such that the span length should be minimum and the location is
safe.
The bridge axis should not be smaller than the highest flood level of both bank of river.
The centerline and High flood level of river was taken during detailing.
PART 4
INTRODUCTION
A survey conducted for determining the route, grades of highway , road is known as road
alignment survey.
The most important point to be noted during road survey is selection of intersection point
and deflection angle .
Construction of road is considered as one of the most important aspect for the rapid
development of the nation.
DESCRIPTION OF LOCATION AREA
The ROAD alignment s survey was done over Sardu River but
there was no high flow of water. There is plain ground as well as
sloping ground places which surrounds the river. The site is
surrounded with sand and stone boulders available in the river.
Fixing of IP
Setting of Curve
IP4
IP3
DEFLECTION
ANGLE
IP1 IP2
IPo
Curve Setting:
A regular curved path followed by highway or railway alignment is curve.
It is introduced wherever it is necessary to change the direction of motion due to the nature
of terrain.
A curve may be circular, parabola or spiral and is always tangential to two straight
directions.
There may be different types of curves: Simple curve, Compound curve, Transition curve.
IP
While setting the road alignment, it should be kept in mind that the minimum IP points
should be taken as far as possible and deflection angles should be minimum as far as
possible.
THANK YOU
ANY QUERIES ??
YAHA SAMMA MILAN LE