Professional Documents
Culture Documents
Licensee
Licensed to SAIPEM (SPCM) on 11 Sep 2002
Conditions of use
This is a licensed electronic copy of a document where copyright is owned or managed by
Standards Australia International. Your licence is a single user licence and the document may not
be stored, transferred or otherwise distributed on a network. You may also make one paper copy
of this document if required.
Web Check-up
AS 2885.1—1997/Amdt 1/2001-04-19
STANDARDS AUSTRALIA
Amendment No. 1
to
AS 2885.1—1997
Pipelines—Gas and liquid petroleum
Part 1: Design and construction
REVISED TEXT
The 1997 edition of AS 2885.1 is amended as follows; the amendments should be inserted in the appropriate
places.
SUMMARY: This Amendment applies to the, Preface, Table 2.4.4(B), Table 2.5.1 and Table 4.3.9.5,
Clauses 1.0 (New), 1.1, 1.10.3, 1.10.29, 1.10.50 (New), 2.1, 2.2.2, 2.4.3, 2.4.4, 2.8, 3.0 (New), 3.2, 4.1, 4.1(A)
(New), 4.2.5.1, 4.2.5.2, 4.2.5.4(a)(ii), 4.2.5.4(b)(iii), 4.2.6.5 (New), 4,3.4.1(a), 4.3.5, 4.3.6.2, 4.3.6.3(b),
4.3.6.5, 4.3.7, 4.3.8.7, 4.3.9, 4.3.9.1, 4.3.0.2, 4.3.9.3, 4.3.9.4, 4.3.9.5, 4.3.9.6, 4.4.1, 4.4.4.1 and 4.4.4.2 and
Figures 1.1(A) & 1.1(B), 4.1(A) (New), 4.3.7 and 4.3.8.7(B)(b), and Section 5, and Appendices A and F.
(d) Operations and maintenance shall provide for continued monitoring and safe
operation of the pipeline.
(e) Where changes occur in or to a pipeline, which alter the design assumptions or affect
the original integrity, appropriate steps shall be taken to assess the changes, to ensure
continued safe operation of the pipeline.
Where the Standards do not provide detailed requirements appropriate to a specific item,
the fundamental principles set out above and the principles and guidelines set out in the
Standards are the basis on which an engineering assessment is to be made. Specific
requirements in the Standards do not replace the need for appropriate experience and
engineering judgment.
the pipeline on the side of the valve remote from the pipeline. The limit may be a flange, a
weld or a point defined by dimensions.’
system that have different MAOP shall be designed to prevent the MAOP of each section
from being exceeded.
Where isolation is used to separate sections with a different MAOP, the minimum
requirement for separation by isolation is two isolation components, two valves or one
valve and a blind. A method of venting the space between the two isolation components
shall be provided.
Where pressure control is used to separate sections with a different MAOP, the minimum
requirement for isolation by pressure control is a pressure control system complying with
the requirements of Clause 4.2.6.4.
Where hydraulic gradient is used to control the pressure, the pipeline control system shall
ensure that the MAOPs of the sections are not exceeded.’
NOTES:
1 Stable liquids have no significant vapour phase at atmospheric pressure, e.g. distillate or processed crude (not
wellhead products).
2 Lean natural gas consists almost entirely of methane. For the purpose of this classification it may contain up to 5%
ethane. However, it shall contain less than 1% total of higher hydrocarbons.
3 Other gases and liquids include all other fluids such as, but not restricted to, wellhead products, LPG, HVPL, rich
natural gas, multiphase fluids and CO2.
4.3.7.2 Fracture control plan The fracture control plan shall define—
(a) the stresses and pipe temperatures for which arrest of fracture is to be achieved;
(b) the design fracture arrest length (which may be expressed as the total number of pipe
lengths or the number of pipe lengths each side of the point of initiation, and which
may have a default value of two); and
(c) the methods of providing for crack arrest.
The stress, temperature and fracture arrest length parameters need not be uniform over the
whole pipeline and may differ for each location class or for each relevant fracture mode.
AMDT The fracture control plan shall be approved. Any measures determined as necessary to limit
No. 1
APR.
fast fracture propagation shall be implemented and monitored in accordance with
2001 AS 2885.3.
The sequence of decision making required, to develop and implement a fracture control
plan to ensure arrest of fast fracture, shall be in accordance with Figure 4.3.7.2.
NOTE:The following two fast fracture modes are known to occur in pipelines:
(a) A brittle fracture in which the fracture propagates in the predominantly cleavage mode at or
below the transition temperature of the pipe steel. The appearance of the fracture surface is
crystalline.
(b) A tearing fracture (commonly called ductile fracture) in which the fracture propagates in the
shear mode above the transition temperature. The appearance of the fracture surface is
fibrous.
Licensed to SAIPEM (SPCM) on 11 Sep 2002. Single user licence only. Storage, distribution or use on network prohibited.
AMDT
No. 1
APR.
2001
Licensed to SAIPEM (SPCM) on 11 Sep 2002. Single user licence only. Storage, distribution or use on network prohibited.
NOTE: 40% SMYS is a conservative approximation of the threshold stress for tearing fracture, which is more
accurately given by 30% of the flow stress. A higher value than 40% SMYS, based upon actual data, may be
used where approved.
NOTE: S F = a factor that takes into account the statistical distribution of the Charpy toughness in
an actual pipe order. A value of 0.75 may be used as a default value in order to ensure that 50%
of pipes in an order meet the predicted arrest requirement. For grade X80, a unique value shall be
established. Other values of S F may be used, where approved, when the statistical distribution of
toughness, or the design arrest length, is different.
Pipeline assemblies are elements of a pipeline assembled from pipe complying with a
nominated Standard and pressure-rated components complying with a nominated Standard
or of an established design and used within the manufacturer’s pressure temperature rating.
Pipeline assemblies shall be designed, fabricated, inspected and tested in accordance with
Clause 4.3, unless otherwise approved.
A clearance adequate for elastic strain during pressure testing and operation shall be
maintained between the bore of a concrete anchor and the pipeline.
4.3.11.4 Forces on an above-ground pipeline The stresses from forces on the above-
ground pipeline shall not exceed those specified in Clause 4.3.6.
4.3.11.5 Attachment of anchors, supports, and clamps An anchor, support, or clamp shall
be attached to a pipeline in such a way as will prevent excessive local stress concentration
in the pipe wall. The combined stress shall not be greater than that specified in
Clause 4.3.6.
Where a pipeline is designed to operate at a hoop stress of less than 50% SMYS, a support
or an anchor may be welded directly to the pipe.
Where a pipeline is designed to operate at a hoop stress of greater than 50% SMYS, a
support and a clamp shall completely encircle the pipe. Where it is necessary to provide
positive attachment, the pipe may be welded only to an encircling member, and the support
or clamp shall be attached to the encircling member and not to the pipe. The weld between
the encircling member and the pipe shall be continuous.
4.3.11.6 Restraint due to soil friction The adequacy of anchorage by soil friction shall be
determined and, where necessary, additional anchorage shall be provided.
4.3.11.7 Anchorage at a connection The interconnection of pipelines shall have the
strength and flexibility to cater for possible movement, or each pipeline shall be provided
with anchors sufficient to develop the forces necessary to limit the movement.
Where a branch connection is made to an existing pipeline and consolidated backfill is
removed, firm foundations shall be provided for both the branch and the pipeline. The
stresses shall not exceed those determined in accordance with Clause 4.3.6.
NOTE: Lateral forces at a branch connection may greatly increase the stresses in the branch
connection, unless the backfill is thoroughly consolidated or provision is made to resist the force.
__________________________________________________________________________
__________________________________________________________________________
AMDT Page 43 Clause 4.4.1
No. 1
APR. Delete existing clause and replace with the following:
2001
4.4.1 General Stations are facilities that allow for the control, measurement, storage or
pressure maintenance of pipeline fluids. Stations covered by this Clause 4.4 include
compressor and pump stations, storage facilities, pressure regulation and metering facilities.
Other facilities that involve frequent operational activity or public access may also be
designated stations for the purpose of this Standard. Pipeline assemblies (see Clause 4.3.9)
are not considered as stations in this Standard. They may, however, be located within the
physical boundaries of a station.
Stations shall be protected from damage caused by the environment and from external
interference.
Stations shall comply with regulatory requirements for the safety of personnel and the
public.
The limits of the station shall be defined.
__________________________________________________________________________
Licensed to SAIPEM (SPCM) on 11 Sep 2002. Single user licence only. Storage, distribution or use on network prohibited.
__________________________________________________________________________
AMDT Page 45 Figure 4.3.8.7(B)
No. 1
APR. Delete existing figure and replace with the following:
2001
Licensed to SAIPEM (SPCM) on 11 Sep 2002. Single user licence only. Storage, distribution or use on network prohibited.
NOTES:
1 Dimensions A, B and C shall be not less than those determined by the external interference design and
Clause 4.3.6.
2 Where separation by burial is a selected physical measure, dimension A shall not be less than 1200 mm
and dimension B shall comply with Table 4.2.5.3.
3 Where separation by barrier is a selected physical measure, dimension C and dimension D shall not be less
than 300 mm without approval by the authority responsible for the road, and the operating authority.
4 Dimension A should be established in consultation with the authority responsible for the road, but shall
not be less than 1000 mm.
5.1 BASIS OF SECTION Measures shall be taken to mitigate corrosion and other
destructive processes, such as environment-related cracking, which could affect the
integrity of the pipeline. When determining necessary measures, consideration shall be
given to the potential for both internal and external corrosion and degradation. Implicit
within, and central to, a corrosion mitigation strategy is the design of corrosion and
condition monitoring programs, to provide assurance that the measures implemented are
successfully achieving their objectives.
Any changes to the operation of the pipeline, which could result in a change in the potential
for corrosion, shall be reviewed and their impact assessed. Appropriate changes to the
mitigation program shall be implemented.
Corrosion protection measures shall be approved.
TABLE 5.4.2
APPLICABLE METHODS FOR MITIGATING CORROSION
Coating X X X
CP/stray current X X
drainage
X = applicability
NOTES:
1 Cathodic protection would normally only be used in conjunction with an appropriate
coating system. However, in specific circumstances, such as temporary lines and gathering
lines, cathodic protection may be applied to uncoated pipelines.
2 Where the pipeline is externally coated, cathodic protection would normally be applied.
3 The addition of an allowance for the effect of corrosion does not mitigate corrosion, but is a
valid method for providing for its effect during the design life of the pipeline.
5.4.3 Corrosion allowance Where it is considered that corrosion mitigation methods will
not minimize corrosion sufficiently to ensure the integrity of the pipeline over its design
life, a corrosion allowance may be used. Corrosion allowance is an increase in the wall
thickness of the pipe by an approved amount in excess of that required, to withstand
internal pressure, external loads and other defined requirements.
Corrosion allowance may be used as all or part of the corrosion mitigation measures for
both internal and external corrosion. Where internal corrosion is expected, corrosion
allowance should be used in conjunction with other active corrosion mitigation methods to
provide additional protection against unexpected corrosion rates or failure of the other
methods.
A corrosion allowance may be appropriate for above-ground pipelines, particularly where
the conditions are conducive to minimal or general external surface corrosion, and in
particular where external coating systems may be difficult or impractical to maintain and
the risk of pitting corrosion is high. An external corrosion allowance would be unusual on
buried pipelines, except in conjunction with other corrosion mitigation methods, unless it
can be shown that the external corrosion is uniform and generalized.
A corrosion allowance shall be approved.
5.5 CORROSION MONITORING The performance of corrosion mitigation systems
AMDT
No. 1 shall be monitored using systems that can measure the adequacy of corrosion mitigation
APR. measures. Where corrosion is detected or anticipated, systems capable of determining the
2001
corrosion rate or loss of wall thickness shall be employed. Corrosion-monitoring programs
for the pipeline shall be maintained for the life of the pipeline.
The frequency of monitoring shall be appropriate to the expected corrosion rate. Monitoring
systems may include physical inspection, removable coupons, proprietary instrumentation,
and internal inspection devices and equipment.
Corrosion monitoring methods shall be approved.
lining used for the purpose of preventing corrosion shall be continuous across welds and
repairs to the pipeline.
NOTES:
1 Linings prevent corrosion while they are physically intact. As it is difficult to ensure this in
service, it is normal practice to supplement the lining with inhibitor addition. No inhibitor is
considered necessary if the lining is installed solely to reduce friction.
2 Lining selection should take account of any intended pigging program for the pipeline, to
prevent mechanical damage to the lining.
5.6.3 Corrosion inhibitors and biocides Selection of corrosion inhibitors or biocides to
be added to the process stream shall be based on the effectiveness of the chemical under the
operating conditions of the pipeline. Effectiveness of the chemicals shall be determined in
laboratory tests or by previous experience. Such tests shall take into account the levels of
turbulence in the system. Chemicals added to the fluid in this way shall be—
(a) chemically and physically compatible with the pipeline components and linings, with
any other chemicals added to the pipeline and with the downstream facilities; and
(b) injected at sufficient concentrations and intervals to achieve the desired purpose.
shall include times when there are extreme adverse effects of the stray current on the
pipeline. For example, in an urban area, the morning and evening transit peaks should be
included.
NOTES:
1 Provision should be made to enable earthing systems to be decoupled during measurements
2 Where possible, the potential should be measured by the use of cyclic on/off techniques, and
the instantaneous-off or polarization potential of the pipe should be compared with the
−850 mV criterion.
3 For guidance on the measurement of instantaneous off-potential, refer to AS/NZS 2832.1.
5.7.7 Electrical earthing Where potentially hazardous potential rises could occur with
respect to the neighbouring earth, the pipeline shall be electrically earthed or otherwise
protected by a suitable means. Such potential rises could occur by virtue of parallelisms
with high voltage a.c. powerlines or proximity to power earthing systems.
5.9.1 Pipeline lining The purpose of the lining (e.g. short-term corrosion protection,
long-term corrosion protection and friction reduction) shall be specified and documented
and the materials used shall achieve the specified purpose. The need to apply lining to
welds and site repairs is dependent on the purpose of the lining and shall be clearly
specified in the project documentation.
The suitability of the material for the service and environmental conditions of the pipeline
and of the application method shall have been demonstrated by tests, investigations or
experience.
Procedures for application of the lining shall be developed, so that the desired physical and
chemical qualities are obtained and the application thereafter is in strict accordance with the
procedures. Surface preparation, application and testing of the coating shall be subject to an
approved quality control program.
Where a two-component catalyzed epoxy lining is specified, the methods of application and
inspection and the criteria of acceptance should comply with API RP 5L2.
5.9.2 Joint and repair lining Materials used for the lining of joints and repairs to the
lining shall be compatible with the original lining. The suitability of the material and the
application methods for the service conditions and the environment shall have been
demonstrated by tests, investigations or experience.
Procedures for application of the repair material shall be developed and shall be subject to
an approved quality control program.
__________________________________________________________________________
AMDT Page 66 Clause 6.18
No. 1
APR. Add the following 2 items:
2001
(i) The fracture control parameters, if not uniform over the length of the pipeline.
(j) The location and type of protection measures.
AMDT Page 71 Appendix A
No. 1
APR. 1 Delete the following:
2001
AS/NZS 3931(Int) Risk analysis of technological systems—Application guide
AS/NZS 4360 Risk management
2 Add the following:
AS/NZS 2648 Underground marking tape
AS/NZS 2648.1 Part 1: Non-detachable tape
AS 4799 Installation of utility services and pipelines within railway boundaries
API RP 1102 Recommended practice for liquid petroleum pipelines crossing
railroads and highways
(c) Eiber R J, Bubenik T J and Maxey W A, Fracture Control Technology for Natural
Gas Pipelines, American Gas Association NG18, Report No. 208, December 1993.
This Standard does not require development of a fracture control plan for initiation.
Two modes of propagating fracture have been recognized in pipelines. These are brittle
fracture and tearing fracture. Tearing fracture is commonly referred to as ductile fracture.
F2.4.4 Temperature The inherent fracture toughness of pipe steels shows a marked
change over a transition temperature range. The change is from brittle fracture below the
transition range to ductile fracture (tearing) above the transition range. The change is
usually characterized by the fracture appearance transition temperature (FATT), measured
as the temperature at which 85% of the surface appearance of a propagating fracture is
shear.
The local temperature of pipeline steel is dependent on the climate (for a submerged
pipeline this is the temperature of the water), the location relative to the surface of the
ground and the contents of the pipeline, which may be modified by thermodynamic effects.
Except where stress is lower than the threshold stress for brittle fracture, a pipeline should
be pressure tested and operated at a temperature above the fracture appearance transition
temperature. The Lodmat diagram shown in Figure F2.4.4 may be used to predict areas in
Australia where low temperatures are probable, and indicates the lowest mean ambient air
temperatures local to the surface. Temperatures below ground do not vary to the same
extent as the temperatures of the air above ground, and tend to be relatively constant over a
diurnal period and seldom reach the low temperatures experienced at the surface.
F2.4.5 Limitations on testing Meaningful tests for fracture appearance and energy
absorption become more difficult as the diameter decreases and the wall thickness reduces.
This Standard requires that fracture appearance testing be conducted using the dropweight
tear test method set out in AS 1330. AS 1330 states that the dropweight tear test is intended
for the line pipe, or strip or plate intended for line pipe, having an outside diameter of not
less than 300 mm and that difficulty may be experienced in applying the test to material of
less than 5 mm thickness. AS 1330 excludes testing of weld metal.
This Standard permits the testing of pipe materials for fracture properties to be carried out
on strip, plate or finished pipe. With modern pipe steels, the effect of pipe forming on
fracture properties is usually very small.
F2.5 Calculation of Charpy energy requirements for the arrest of ductile tearing
AMDT
No. 1 fracture The Charpy energy requirements of the fracture control plan for the arrest of
APR. ductile tearing fracture should be determined by an appropriate method taking into account
2001
the pipeline design, especially the MAOP, SMYS, diameter, the conveyed fluid, the backfill
conditions, and the required arrest length. Suitable methods for most pipeline designs are
given in the references listed in Paragraph F1 (see also Clause 4.3.7.3).