Professional Documents
Culture Documents
D-00-Instructions For Erection - EN - Compressed
D-00-Instructions For Erection - EN - Compressed
D – GENERAL
INSTRUCTIONS FOR
ERECTION, NO-
LOAD TESTS AND
COMMISSIONING
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
1.0 - GENERAL
INFORMATION
FOR ERECTION
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Attention!
The purpose of the manuals is to provide operators and specialised
personnel with instructions for the correct assembly and
commissioning of the machines/equipment and any necessary
information to safely carry out the various activities required.
Personnel must not perform any activities or procedures on their own initiative if these are
outside of their area of responsibility and/or could create hazardous situations for people or
things.
This document must be kept for the entire life of the plant; a new copy can be requested if it
gets lost or damaged.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
So the operator's attention is immediately drawn to certain topics or aspects, the following
symbols with their corresponding meaning are used:
Attention!
Anyone dealing with the plant installation and commissioning must carefully read and
observe the information identified by the symbols, obviously in addition to all the safety
standards applied nationally, locally and within the company.
All personnel, regardless of their rank and position, must cooperate with their managers to
identify any potentially hazardous conditions and prevent or eliminate any damages to
people or things.
Attention
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The Contractor or its representatives shall identify and select the PPE (Personal Protection
Equipment) category according to the company risk assessment provisions and the
guidelines contained in this manual.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
In addition to the safety regulations in force in the user country and any in-plant safety
regulations concerning operation, maintenance and erection, the following general
instructions must be observed:
Attention!
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Workers must use the PPE specified in the safety signs and manuals
provided by SMS Group S.p.A.
Only use the specified tools and equipment, and ensure they are
kept in good condition.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Personnel
The plant as supplied is in conformity with what is the current state of technology, is
operationally dependable and safe.
Any activities to be carried out on the machines/plant must be undertaken exclusively by
qualified personnel and/or individuals who have been properly and specifically trained.
Any errors arising from lack of proper knowledge of the plant/machine may:
Protection Equipment
In compliance with the current safety regulations, the machine/plant is fitted with fixed or
removable devices and guards (collective protection equipment) that minimise risks for
anyone operating near the machine/plant as far possible using current technology, keeping
the operating conditions in mind.
Attention
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Attention!
Emergency switches should be inspected for functional ability at
regular intervals.
Do not store any material near the emergency stop buttons as this
might make it difficult to access them.
Lighting
Attention!
Local light must ensure good visibility in every area without creating
dangerous reflections and make it possible for control panels to be
read clearly, as well as to identify the emergency buttons.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Attention!
Avoid accumulating dangerous quantities of oil and grease
No smoking or using open flames.
Report any deterioration in the equipment that may cause
overheating and in electrical systems to prevent sparks.
In the event of fire, cut off the power supply and put out the fire using
powder or CO2 extinguishers.
The user must have availability of fire-fighting equipment near the
plant/machine, especially an appropriate number of portable powder
or CO2 extinguishers that can put out the start of a fire due to the
oils used.
Do not use water under any circumstances.
Do not leave any oil, grease or potentially flammable liquid residues
in the vicinity of welding or cutting operations.
Assembly, repair and testing activities on machines/plant can only
be performed by qualified operators who have undergone
appropriate training;
Attention
In unexpected circumstances, please reach the nearest emergency
button and press it.
Place an “Out of order” sign on the general switchboard and remove
the keys from the various selectors to stop them from being
accidentally activated.
Before restoring the line or individual machine operation, please
check that:
- the emergency condition no longer exists;
- the area that generated the hazardous condition is
undamaged and in good working order.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Attention
Do not disable or modify the safety devices, or apply them in a different way
than intended.
After an emergency stop, the operator can re-set and re-start the machine only after having
identified the nature of the fault and resolved it, if necessary with the assistance of a
maintenance person. In any case, make sure that no-one is present in a dangerous area
before re-starting the machine. If that is the case, have them move outside of such
hazardous area before restarting the machine.
Attention
In the event of flooding, do not touch the machines that constitute the
equipment - power them off and remove the water from the area first.
Do not use open flames and do not smoke in areas that are at high
risk of fire.
Do not use saw dust or cotton waste due to the fire hazard they
create.
Note
In the event of an injury, go to the main switch, activate it and call the
corporate emergency team immediately.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
This chapter contains a list of the main residual risks associated with installing and
commissioning the equipment.
Residual risk / Dangerous area Exposed individual Activities and operating measures to eliminate the risk
Individuals who have not received appropriate training are not allowed to use the plant.
TRANSPORTATION
INSTALLATION: X Before using the plant, operators must be trained and educated, including by reading
Various risks associated with the
USE: X and understanding the content of the instructions for use.
equipment operation by ADJUSTMENT: X
unauthorised (and lacking MAINTENANCE: X
DISPOSAL: Safety signs:
specific training) personnel.
“No entry to unauthorised personnel”
“No access for pedestrians“
Only use appropriately rated lifting equipment.
Securing the loads and using cranes or overhead cranes must be done by skilled,
qualified personnel.
Handling personnel must follow the lifting procedures instructed by the employer or
site manager, in collaboration with the SMS Group supervisor. Procedures must
consider any equipment operating while exposed to winds and identify the wind top
TRANSPORTATION: X
INSTALLATION: X speed above which the lifting equipment should not be used in its various
USE: X configurations.
Risk of drop ADJUSTMENT: X
MAINTENANCE: X
DISPOSAL: Implement procedures to prevent mutual interference.
Observe the guidelines included in the Instructions for Use and the technical drawings,
and use the lifting points identified on the machine, if available.
Safety signs:
“No entry to unauthorised personnel”
“No access for pedestrians“
“ Danger Overhead loads“
Doors to electrical switchboards must be kept locked during normal operation and keys
must be handed to the electrician.
It is prohibited to
- perform works on live equipment.
TRANSPORTATION: - touch machines if not authorised to do so.
INSTALLATION: X
USE: :X
- remove guards and safety covers before switching off the power supply.
Risk of electrocution as a result ADJUSTMENT: X
of accidental contact with live MAINTENANCE: X It is mandatory to
elements. DISPOSAL :X
- turn off the circuit power supply switches before carrying out any works
- ensure there is proper earthing connection before starting works.
- keep well insulated from ground, with dry hands and feet or using a platform and
insulating gloves.
Works on supply cables before switches or on switches must be done after cutting off
power supply upstream.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Residual risk / Dangerous area Exposed individual Activities and operating measures to eliminate the risk
Use personal protection equipment.
Operators must be educated and trained to use the equipment and be aware of the
attachment points on the machine.
When possible, use equipment for works at height (ladders, platforms, etc.) ensuring
Fall as a result of carrying out this is done correctly.
TRANSPORTATION:
activities by climbing onto INSTALLATION: X
equipment on the line. USE: :X If this is not possible, use safety harnessing.
ADJUSTMENT: X
MAINTENANCE: X
Risk of fall during during DISPOSAL: Operators using a harness must have attended a special training course.
installation works at height.
Safety signs:
“No entry to unauthorised personnel”
“Risk of fall”
“Safety belts must be used”
“Safety boots must be worn”
Beware of protrusions.
TRANSPORTATION:
INSTALLATION: X Safety signs:
Tripping hazard from protrusions USE: :X
ADJUSTMENT: X Suitable lighting
on the floor
MAINTENANCE: X Yellow/black tape indicating permanent hazard
DISPOSAL :X “Safety boots must be worn”
Before starting activities on hot components, the operator must check that these are
TRANSPORTATION: not too hot.
INSTALLATION: X Prevent any possible contact (with machinery, rolled products, hot liquid splashes and
Contact with very hot parts. USE: :X
ADJUSTMENT: X radiant heat) using special protection equipment (protective gloves and goggles).
MAINTENANCE: X
DISPOSAL :X Safety signs:
“Safety goggles and gloves must be worn”
TRANSPORTATION:
Risks deriving from the machine INSTALLATION: X
or line being unexpectedly USE: :X
restarted ADJUSTMENT: X Inform personnel on the circuit breakers location.
MAINTENANCE: X
DISPOSAL :X
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Do not smoke
TRANSPORTATION: X Report any deterioration in the equipment that may cause overheating and in electrical
INSTALLATION: X systems to prevent sparks.
USE: :X
Risk of fire ADJUSTMENT: X
MAINTENANCE: X Do not leave any oil, grease or potentially flammable liquid residues in the vicinity of
DISPOSAL: welding or cutting operations.
Safety signs:
“Fire, naked flames and smoking are prohibited
“Do not extinguish fires with water“
Safety covers and devices must not be removed by users. Indeed, users must ensure
they are enabled and in proper working order.
Removal is only allowed for maintenance purposes, after the machine/plant has been
made safe according to the procedures described in this document.
Various risks (primarily of impact TRANSPORTATION:
INSTALLATION: X Some moving parts cannot be protected during the line installation. Prepare and fit
and crushing against moving
USE: :X removable barriers until the line assembly is completed.
parts of the equipment) arising ADJUSTMENT: X
from unauthorised tampering MAINTENANCE: X
DISPOSAL: Before starting any operation, ensure no-one is in the vicinity of the machine to be
with safety devices.
operated.
Safety signs:
“No entry to unauthorised personnel”
“No access for pedestrians“
Operators who are exposed to risks associated with high noise levels must be
provided with hearing protection equipment (ear muffs or ear plugs). These must be
TRANSPORTATION: personal and tailored for the individual operator and their working conditions.
INSTALLATION: X
Risk deriving from noise emitted USE: :X
ADJUSTMENT: X Training and information on how to use noise control PPE
by work activities
MAINTENANCE: X
DISPOSAL: Safety signs:
“Ear muffs must be worn”
Use of PPE. Operators must be provided with special safety masks or breathing
apparatus to protect breathing airways.
TRANSPORTATION:
INSTALLATION: X Training and information on how to use PPE
Risks to breathing airways due USE: :X
to dust and gas emissions. ADJUSTMENT: X
MAINTENANCE: X Safety signs:
DISPOSAL: “Masks must be worn”
“Breathing apparatus must be worn”
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The purpose of safety signs is to reduce residual risks and enhance safety for people
working on the plant. These signs comprise:
• Prohibitive signs
• Warning signs
• Mandatory signs
• Rescue signs
• Informative signs
• Signs identifying permanent hazard areas
• Signs for protection of specific work areas
It is necessary to post these signs during and after assembly in job and hazard areas
throughout the plant.
All persons employed will be informed on the significance of all safety signs prior to
commencement of their activities, and in subsequent periods at adequate intervals, but at
least once a year.
The responsibility for posting such signs shall rest with the plant user.
Caution!
Machine manufacturer shall not be liable in case of non compliance
with above safety instructions.
Signs around the plant must be kept in good condition and replaced
in case of damage/loss.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Prohibitive signs
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning signs
j) Warning: k) Warning:
danger of danger of
crushing laser beam
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Mandatory signs
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Rescue signs
* This arrow of direction shall be used only in connection with another rescue sign for
first-aid-kids.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Information signs
Identification of permanent hazard areas for instance such places which involve the risk of
hitting, crushing, tumbling, stumbling of persons or dropping of loads.
Steps, floor hatches etc.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Board indicating cut out and reconnection requirements for drives during repair or non.
production shifts.
1. _________________________________ 1. _________________________________
2. _________________________________ 2. _________________________________
3. _________________________________ 3. _________________________________
4. _________________________________ 4. _________________________________
5. _________________________________ 5. _________________________________
6. _________________________________ 6. _________________________________
7. _________________________________ 7. _________________________________
8. _________________________________ 8. _________________________________
9. _________________________________ 9. _________________________________
Material: AlMg3F23
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning Plate:
Fixed by 3 chain links on every barrier chain, additionally screwed or hooked on walls
and equipment.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Anyone involved in installing machines, equipment, parts and components must wear
appropriate safety equipment. Below please find general information on how to use and
select the PPE.
Note
Clothing must not have any loose parts that may increase the risk
of entanglement in moving parts. Avoid wearing necklaces,
bracelets and anything else that may cause the same type of
hazard.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
In any case, personnel must receive instructions from the safety officer and must be given
the safety data sheet for each product to be used; PPE and prescribed measures and
instructions must also be adopted.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Note
Assembly and commissioning personnel must have the
instruction manuals for installation, along with any other
documentation annexed. If further and more detailed
information is needed, please contact the Site Manager SMS
Group S.p.A. Supervisor.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Responsibility of Employees
The employees are obliged to take care of their own safety and health as well as of those
of other persons and to cooperate with the supervisors of the contractor to prevent
dangers of accidents. They are also obliged to use the prescribed safety outfit.
Workers must use safe working practices and procedures, reporting any practices and
situations that jeopardise safety.
Attention
All operators must be appropriately trained on how to assemble,
adjust and service all equipment components. The training must be
based on the manuals supplied by SMS Group.
Do not leave any work objects or tools in areas where there is a risk
of flying fragments or collision with moving parts.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Note
Please refer to the specifications under the previous chapter
Mobile Gear
Only authorized drivers are permitted to operate the mobile gear. This also relates to the
staff of the subcontractors.
Cranes
Observe the applicable safety instructions and accident prevention rules for cranes.
Possible causes of accidents in conjunction with cranes and hoisting appliances are as
follows:
• Human failure of crane operator, attacher or other persons involved in the hoisting
procedure; inattentiveness, boredom, readiness for risks, inobservance of applicable
guidelines or faults may be the cause of a failure.
• Insufficient attachments - in regard to bad weather conditions such as strong wind.
• Inappropriate load receiving means, unsuitable or damaged sling means.
• Improper use and mal operation of hoisting appliances.
• Tools or devices dropping from the crane due to detachment by crane movement.
• Possible contact with current-conducting collector wires or obstruction by restricted
space.
• These sources of dangers are to be recognized and secured. Moreover, other sources
of danger have to be considered which may arise in the respective working area.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Angle grinder
Grinders must be used observing the instructions relating to grinding items and tools. In
addition, comply with all instructions relating to the following components that can be fitted
to grinding machines, including portable electrical and pneumatic grinding devices.
• Grinding tools and disks can only be used after fitting the protective devices.
• Grinding components can only be clamped to grinders or cutter grinders, never to
circular saw shafts.
• Grinding components can only be clamped by experienced staff. Do not use faulty
items.
• Do not exceed the maximum permissible peripheral speed for the grinding
components. Details regarding the max. permissible rotational speed contained in the
label attached to the grinding component must match those printed on the machine
identification plate. Do not use any grinding components that do not carry a label.
• It is imperative that eye protections are worn when performing grinding jobs.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Transport, Slinging
• Only such transport facilities will be used which are suitable for the intended purpose
and which are in unobjectionable state and condition (chains, ropes, suspension
gears).
• All rigging or hang-on aids provided should definitely be used (eyebolts, lugs).
• Moving or loose parts on equipment should be reliably secured for transport.
• Communication with the crane operator by one person only.
Utilities
To avoid any personal injuries, please observe the following rules when assembling and
starting hydraulic and pneumatic systems:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Attention!
Performing maintenance and repair works on operating and
pressurised piping systems is prohibited, as elements might break
and result in personal injuries that can be fatal.
Notes:
Certain accumulators such as those of the balancing system will
have to be kept under pressure in spite of pressure system relief.
• The position and condition of seals and packings is to be particularly checked during
and after any work on equipment units.
• Retightening of pipe screw joints and flange connections as well as any other sealing
measure shall be allowed to be carried out only with the pipeline system in
unpressurized state.
• Mechanical, welding or soldering work is not allowed to be carried out on hydraulic
accumulators.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Mobile working platforms and/or step ladders with a platform must be used for any work to
be performed approx. 2 m above floor level.
In any case, use is only allowed to authorised personnel who has been suitably trained.
Personnel must also comply with current applicable regulations / internal rules specified
by the contractor.
Attention
Works at height carry a risk of fall
If works are to be performed at the top of the machines making up
the plant, appropriate means of access must be used.
Unauthorised personnel who has not been specifically trained is
prohibited from using any means of access to height or any
tools/equipment that are unsuitable for this purpose
Note
Wherever possible, the operator must use equipment for works at
height such as lifting platforms or rolling scaffolds. When this is not
technically possible, use portable ladders and/or safety harnessing.
Attention
If maintenance works are carried out at such a height that plant
components can be reached from the ground or from an elevated
deck that can be easily accessed (walkways or platforms),
operators must:
• Wear the personal protection equipment provided.
• for each of the components concerned, always have the
necessary equipment to hand (keys, screwdrivers, etc.). Smaller
tools must be carried by the person using a bag fastened to the
waist with a special belt.
In any case, works performed on walkways or platforms must not
expose operators to the risk of falling down. If that is not possible
(e.g. when greasing particular points in the equipment), safety
harnessing must be used.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Dangerous Matters
Dangerous matters must be stored and used in line with safety regulations.
Containers and packaging containing dangerous substances must be clearly labelled and
be strong enough for the chemical and physical properties and hazardous profile of the
substance. Containers normally containing foodstuffs or beverages are never allowed to
be used!
Common examples of hazardous substances are:
• lye solutions
• acids
• degreasing agents and solvents
• bitumen, tear, pitch
• PUR painting and insulation materials
Containers with toxic/harmful wastes and/or hazardous substances must be labelled and
marked as per standards so the contents can be clearly identified.
Fire Protection
Suitable fire extinguishers are made available at site for fire protection.
Pay special attention to the fire protection regulations when welding and abrasive cutting
work is done.
Gas bottles and inflammable materials are to be stored appropriately and checked
regularly to prevent fires.
Observe „No Smoking“ signs and do not use any matches or other open flame near
inflammable materials.
Special requirements of the customer for fire protection are to be adhered to strictly.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
The plant consists of several components and machines that are already partly
assembled at SMS Group S.p.A., while other parts must be assembled on site for reasons
related to transport, handling and assembly.
All the equipment components shall be delivered in appropriate packaging that protects
goods during transportation and storage while awaiting for assembly.
Below please find some general information on transportation and installation.
Users should be aware that any machined and unpainted surfaces on parts of the
machines that make up the plant have been wrapped by SMS Group S.p.A. with a
protective film.
Attention
Risk of load tipping over or falling.
Do not stand under suspended loads during loading and unloading
activities.
Unauthorised personnel is prohibited from entering the work area,
Notes!
Before handling the packaging or parts of the equipment/machine,
clear transit routes from any obstacles so means of transport can
move safely, and keep away any individuals who are not involved
in handling operations.
Lifting, moving, handling, etc. must be done by qualified, trained
personnel who has been provided with appropriate equipment.
Always ensure that personnel tasked with handling is perfectly
aware of any safety regulations to be implemented when
transporting equipment components.
When attaching and lifting the load, establish where the centre of
gravity is using the information specified on the packaging and in
any annexed documents, manuals included. If such documentation
is not available, please contact the site manager or SMS Group
supervisor.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
handled.
This equipment, as well as lifting hooks, chains and ropes, must
clearly indicate their maximum permissible load.
Such limit must be strictly observed.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Below are some examples illustrating how to lift and handle the crates
There are various types of packaging:
Lifting and transportation must be done using a forklift truck, gripping the
component/machine using the specially marked lifting points.
.
Make sure the lifting forks do not touch any component or mechanical part, if on the lower
side.
- Packaging in wooden crate
Generally used for sea shipping, this consists of a reinforced wooden base that can
withstand the machine or equipment component weight, with strong wooden walls
attached to it. The component/machine, or parts of it, are also covered by a waterproof
plastic film (barrier shroud) that protects them from oxidation (optional). The crate is then
closed off by a lid having the same shape/structure as the walls. For suspended
transportation, place the lifting ropes on the symbols printed on the crate (where
applicable).
Some examples:
Lift with a hook (1).
Lift and transport the crate using a forklift truck (2), paying attention to the location of the
crate’s centre of gravity.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Attention
The centre of gravity is not necessarily located at the centre of the
packaging
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Load Capacity in kg
Single Strand Double Strand
Rope with inclination angle
Rated
Diameter
from 0° to 45° from 45° to 60°
45°
mm 60°
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Load Capacity in kg
Single Strand
Rope with inclination angle
Rated
Diameter
directly from 0° to 45° from 45° to 60°
45°
mm 45° 60°
60°
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Load Capacity in kg
Single Strand Double Strand
Rope with inclination angle
Fibre material
Rated
Diameter directly braided from 0° to from 45° to 60°
45°
mm 45°
45° 60°
60°
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Load Capacity in kg
Single Strand Double Strand
Fibre material
mm 45° 60°
45°
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Due for laying aside; chemical fibre ropes and natural fibre ropes
Fibre ropes (in general) are to be taken out of use upon discovery of the following types of
damage or defects:
• Fracture of a strand.
• Mechanical damage, heavy wear or slackening.
• Damage caused by aggressive matter.
• Slackening of splices.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
45°
mm 60° 45° 60°
If several strands are used for slinging, only two of them are allowed to be taken as
carrying means.
This does not apply in case it is sure that the load is uniformly distributed also onto
additional strands.
Should the load distribution not be uniform, the admissible load of the individual strands
must not be exceeded.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
45° 60°
mm
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Storage, Slinging
Attention
Risk of load tipping over or falling.
Do not stand under suspended loads during loading and unloading
activities.
Unauthorised personnel is prohibited from entering the work area
Do not apply undue pressure on the packaging during handling, as
packaging must be kept in the position shown by the printed
symbols at all times.
Avoid any sharp movements and do not stand near the handling
area.
Notes!
On delivery, the client must carefully inspect the packaging
conditions and make sure there are no damages.
Before unloading the plant/machine components, make sure that all
anchoring systems have been removed.
The plant/machine must be placed on the installation spot with
accuracy, adhering to reference axes and height/level parallelism
specifications.
Handling (i.e. transfers within the production site) must take place
using appropriate lifting equipment having suitable capacity.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
....max kg
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Irrespective of the packing medium used, distinction will made between two basic types of
packing for shipment.
Figure 17 : Figure 18 :
Figure 19 : Figure 20 :
After unpacking, the contents of each package will be checked for completeness and
potential damage with reference to applicable shipping documents.
The conditions and contents of the cases to be confirmed by an appropriate certificate
(see Chapter 1.15.2, Appendix).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Perform this operation only if the packaging is stable on the resting surface and following
the procedures listed below:
Warning!
The centre of gravity is not necessarily located at the centre of the
packaging
Notes!
While opening the package, check the contents against the
packing-list.
1) Carefully read all information on the packaging concerning type of material, weight,
special handling requirements, lifting equipment attachment points. If further and more
detailed information is needed, please contact the Site Manager SMS Group S.p.A.
Supervisor.
2) When opening the packaging, remember to proceed carefully in order not to damage
the content. Also beware of protruding nails or screws as these can damage things and
injure people.
3) Carefully extract the plant/machine accessories from the crate.
4) Inspect the contents to ensure they are totally free from any restraint to the crate before
removing them.
5) The crates may also contain bags, ties or small crates that may be secured to prevent
any movements; it is advisable to remove all secondary packagings first.
6) Anchoring items such as nails, bolts or threaded rods must be removed using
appropriate tools, bearing in mind that there could be hazards resulting from energy
stored by gravitational load. If further and more detailed information is needed, please
contact the Site Manager SMS Group S.p.A. Supervisor.
Notes!
Check if parts or accessories of the plant/machine that are
essential for installation, connections, etc. (for example bolts,
brackets, electrical components) have been removed. Inform the
manufacturer if any details are found to be missing.
Ensure that:
- there are no damages due to incorrect storage;
- rotating part are free to rotate and there are no impediments
such as rust, dirt or other;
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
If it is necessary to store the components for extended periods of time, adopt the
precautions described below as they ensure the components maintain their original
characteristics. Place all the components in a dry, covered area.
Open the packages containing machined components and place these components on
wooden pallets and cover them with a tarpaulin.
Inspect machined surfaces monthly, checking if they are adequately protected. If the
protections are damaged, replace them with a similar one.
On a monthly basis, turn the motors and gearboxes shafts manually and check the
protections on the uncovered ends.
On a quarterly basis, inspect the paint condition on metalwork components.
On a monthly basis, check crates containing electrical and electronic components to
ensure the silica gel is still present/effective.
Do not place other items on top of the packages.
Plastic and rubber parts should be protected from the action of sun and light with a
waterproof cover.
Gearboxes should be topped up with protective oil as specified by the manufacturer.
Motor and gearbox shafts must be rotated manually at least once a week.
Warning!
Do not apply undue pressure on the packaging during handling, as
packaging must be kept in the position shown by the printed
symbols at all times.
Avoid any sharp movements and do not stand near the handling
area.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Components/machinery must be assembled by trained personnel
under the supervision of a qualified technician. Qualified technician
means an individual who, in their profession, has acquired
experience and knowledge and is fully aware of requirements
regarding accident prevention and operating conditions.
Operators performing these tasks must wear safety boots, gloves,
helmet and clothing.
Welding works on components/machinery require express
authorisation. During these activities, operators must use
appropriate PPE such as goggles or face shields, suitable
footwear, aprons, etc.
If handling loads, please refer to the safety rules under par. 1.2.
Make sure the foundation tie-rods nuts are tightened properly, as
failure to do so may cause dangerous vibrations or instability during
operation.
Notes!
Follow the assembly drawings during assembly as they provide the
correct dimensions.
Assembly tolerances are specified in the assembly drawings or in
the following chapters of this manual.
Tightening torques are provided in this manual.
Clean the mechanical component parts that were greasing for
transportation.
Fit guards in place, if they are not delivered already installed and
checked upon final testing in the workshop at SMS Group S.p.A.
Once assembled, check that all components are undamaged and
match whatever was agreed or specified in this Document under
every aspect.
If any parts are damaged, it is the buyer’s responsibility to inform
SMS Group S.p.A. immediately in writing to receive clarification on
the best course of action. Should there be any damaged parts, due
to any reason whatsoever, the installer shall not commission the
machine until such damaged part is repaired.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Buildings, Foundations:
• Roofing of bays completed.
• Sidewall panelling closed as far as practicable.
• Foundations complete and in broom-clean state.
• Anchor and other holes clean, i.e. free from dirt or other impurities.
• Embedded parts fitted in accordance with applicable drawings.
• Electric rooms complete and fitted with doors and windows.
• Floor finishes in electric rooms and cellars will be provided on completed erection and
after placing the grouts for main equipment.
Warning!
Check if masonry works have provided for all the necessary
infrastructures to prevent the danger of falls from height, such as
parapets, walkways, stairs, covers, allowing free movement to
means and operating personnel.
Place all the required safety signs; these can only be removed after
completion of all the various installation activities.
Bay Cranes:
• Bay cranes will be made available in ready-to-operate condition, including qualified
crane drivers.
• Suitable mobile cranes will be needed for the erection of equipment with single weights
above the load capacity of the bay cranes.
• Suitable mobile cranes, chain falls and rope winches are needed for work outside
crane reach areas.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Miscellaneous:
• Access ways to erection site provided with hard facing.
• Bay lighting complete.
• Adequate lighting provided in utility cellars.
• Sump pumps installed where necessary to keep ducts and cellar spaces free from rain
water.
• Ready-to-operate extraction points for site power, compressed air and water supply in
adequate volumes.
• Adequate space for unpacking, cleaning and preassembling of equipment components
and interim storage thereof, if any.
• Check that utility lines for use at the site (power, compressed air and water, etc.) have
been installed in compliance with current laws
• Availability of qualified erection personnel in adequate number.
• Availability of erection tools and consumables.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Pay attention to the equipment design. While performing surveys, it
is possible that operators may work near holes in the ground or at
height. Please also refer to the provisions contained in this manual
regarding works at height.
Strictly adhere to the safety regulations contained in this manual.
Required points are shown on sketches of axis plan and erection measuring reports.
The locations of axis and elevation points will be laid down in a drawing by purchaser.
Any other axes and elevation points necessary for foundation checks and machine
erection will be determined during field erection (Figure 26 - Figure 28).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Legend: 1) Grout
2) Epoxy Resin with Quartz Sand
3) Concrete
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 26: Setting of Centrelines using Piano Wire and Plumb Bob
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 28: Setting of auxiliary Axis using Piano Wire and Plumb Bob
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Pay attention to the equipment design. While performing surveys, it
is possible that operators may work near holes in the ground or at
height. Please also refer to the provisions contained in this manual
regarding works at height.
Strictly adhere to the safety regulations contained in this manual.
Surveys for individual machine foundations will be made with reference to the foundation
drawings to fix:
• their position by main longitudinal and transversal axis
• the spacing between anchor holes
• the elevations of the foundation top surfaces as poured.
It should be observed in this conjunction that the machine grout thicknesses as given in
the foundation drawings will be complied with. This check will be effected by means of a
levelling instrument (figure 29).
It is recommendable to assort the foundation bolts provided in each case with reference to
the anchor drawings and to keep them handy close to the respective place of use. The
orientation of T-head anchors is marked in the bolt heads.
Construction of Batterboards
Batterboards will be constructed from steel angles or channels in the form of vertical
columns with crossbeams welded on top and diagonal braces (figure 32).
Longitudinal or transversal axis points are to be fixed by transposition to the batterboard
transoms, using an adjustable device on the transoms and/or crossbeams or notches in
the latter (figure 33 and 34).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Longitudinal and transversal axes will be identified by a steel wire of abt. 0,5 mm diameter
(dia.) which is loaded on both ends and which is taken from the above defined fixed
points.
Precision bobs to shall be used for all plumb bob measuring operations.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
CORRUGATED PIPE
Legend: 1) Measuring Rod
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Pay attention to the equipment design. While performing surveys, it
is possible that operators may work near holes in the ground or at
height. Please also refer to the provisions contained in this manual
regarding works at height.
Strictly adhere to the safety regulations contained in this manual.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Attention!
Pay attention to the equipment design. While performing surveys, it
is possible that operators may work near holes in the ground or at
height. Please also refer to the provisions contained in this manual
regarding works at height.
Strictly adhere to the safety regulations contained in this manual.
Fig. 38
The machines are positioned and aligned in the foundations by resting the baseplate on
levelling shims (figure 38).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
e distances of the plates from the holes of the anchor bolts are represented in figure 3.
Fig. 40
The plate must not protrude from the bottom part of the machine.
Fasten the plate to the foundations with rheoplastic concrete at a level of 8 - 10 mm lower
than the bottom part of the machine.
The plate must be levelled with a levelness tolerance of 0.1 mm for a length of 100 mm.
• Attend the curing of the concrete.
• Rest the machine, complete with anchor bolts, on the shims.
• Carry out the final levelling by using various shims of 1, 3 or 5 mm (figure 44).
• Fasten the shims with spot welding.
Fig. 41
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Fig. 42
• Fill the holes of the anchor bolts up to a height of about 80% with rheoplastic concrete
(figure 42).
• Attend the curing of the concrete.
• Tighten the anchor bolts.
• Re-check the positioning and the levelling of the machines.
• Carry out the final grouting with rheoplastic concrete, Emaco 5.5 or similar.
• Re-check the tightening torque of the anchor bolts after the curing of the concrete.
Where T-head bolts are used, check to see that these have been fitted into the foundation
anchor holes prior to setting up any of the machine or equipment units.
Install machines on prepared bases or levelling screws and adjust to specified elevation
while simultaneously taking surveys by means of level.
On this, the machine or equipment unit concerned will be levelled/aligned to defined
longitudinal and transversal axes during which operation the anchor bolts will be tightened
down to adjust the unit to specified level and elevation. (It may be necessary to detach the
machine or equipment unit and place additional shims. This operation can be omitted by
means of levelling screws.)
Machines or equipment units anchored by means of stone bolts will be pre-levelled/pre-
aligned to their defined level and axes. Stone bolt holes will be filled with initial grouts to
three quarters of their height. The machine or equipment unit concerned will be finish-
levelled/finish-aligned after the grout has cured.
Examples
Levelling/alignment of bedplates, bases, roller tables etc. (figure 43).
Measurement of couplings (figure 44 and figure 45).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Legend: 1) Misalignment
Figure 45:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
If using hazardous materials, refer to the contents of the material
safety data sheet.
Before placing undergrouts for individual machine or equipment units or before bringing in
initial grouts for stonebolts, a written request will be sent to the competent contract partner
for grout release.
All anchor holes will be so sealed flush with the foundation top edge before placing the
final undergrout of equipment units secured by means of T-head bolts that penetration of
undergrout material into the anchor holes will be prevented.
Foundation areas mark in the construction drawings will not be grouted until after
installation and/or erection of the corresponding equipment units when these have been
aligned/levelled and their foundation bolts have been firmly tightened down. The quality of
the undergrout material used must at least be equal to that of the foundation concrete. It is
recommended instead of concrete or mortar to use a special undergrout mass which is
both shrink-free and also faster curing.
Where undergrout areas are not distinctly identified, the basic rule applies that all
horizontal faces under machine frames will be grouted.
All concrete surfaces will be thoroughly cleaned and wetted prior to placing the undergrout
to ensure a good bond between foundation concrete and grout material.
All anchor bolts will have to be retightened and checked for tight fit after the undergrout
has cured.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 46:
1) Machine part
2) Shims
3) Formwork
4) Foundation
5) Grout
6) Funnel
Figure 47:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 48:
• Formwork
Tightly secure and seal.
• Mixing
Is ready for use, requiring only the addition of water. 7 - 9 l of water are required for 50
kg of grout.
• Grouting
Pour from one side or corner only without interruption.
• Note
Open areas are to be protected against premature water evaporation.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Using portable mobile cutting equipment or machinery: please refer
to the contents of this manual under par. 1.1.5.
The materials listed below are required for the erection, running and maintenance of the
plant devices and equipment.
1.9.7 Sundries
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
1.1 Upright drilling machine
Morse taper 3, 100 – 1000 rpm with motor for direct-
on-line starting and 5 m long connecting cable,
complete with plug.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
1.6 Compressor
Mobile screw type compressor 4.00 m3/min. referred
to 7 bar, max. operating pressure 8 bar.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
2.1 Dummy level / Transit
Precision 0.1 mm, including stand.
2.4 Theodolite
Including stand.
2.9 Straightedge
Lengths = 5, 4, 3, 2, 1.5, 1 and 0.5 m.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
2.11 Surface plate
200 x 300 mm, size 4, class 1
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
2.20 Plumb bob
Complete with cord.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
3.1 Hand drilling machines
N.B. All pneumatic machine tools should be supplied with suitable hoses and fittings.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
4.1 Electric multi-speed hand operated drilling
machines
Drilling capacity for steel up to 32 mm.
N.B.. All electric units should supplied with connecting cable and plug.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
5.1 Eyebolt
DIN 580
5.2 Crowbar
Dia. 20 mm, length = 500 and 1000 mm.
5.7 Pincers
Length = 250 mm.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
5.10 Chain pipe tong
2 – 12”.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
5.18 Set of milled files
Lengths = 150, 250 and 350 mm
Cuts 1, 2 and 3.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
5.29 Set of single-ended open jaw wrenches
Sizes from 30 to 90 mm.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
5.42 Set of taps, 2-part
Threads from G 1/8 to G 2.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
6.1 Mechanic’s work-pipe bench
Vise up to 3” and parallel vise with 150 mm jaw width
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
6.10 Pipe die stock
For ISO 228 threads 1/8", 1/4", 3/8", 1/2", 3/4", 1", 1
1/4", 1 1/2", 1 3/4", 2", 2 1/4", 2 1/2", 2 3/4", 3", 3
1/2", 4".
Including ratchet and dies.
6.16 Backsquare
300 x 175 mm
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
1.9.7 Sundries
Item Description
7.1 Aluminium assembly ladder
Lengths = 4 and 6 m
7.5 Flashlights
Complete with cells and bulbs (spare bulbs and cells
must be available)
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
7.8 Scaffold planks
Length = approx. 4 m
7.9 Pails
Plastic, capacity = approx. 10 / 11 litres
7.11 Bottle
Graduated polyethylene collecting bottle
Capacity = 200 ml and 850 ml
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
7.18 Minimess box
N.B. Spares and wearing parts in adequate number must be available at site for all
machines and devices.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
8.1 Hydraulic jacks
Hand pump
100 t, stroke = 250 mm
50 t, stroke = 200 mm
20 t, stroke = 150 mm
20 t, stroke = 50 mm
20 t, stroke = 400 mm
10 t, stroke = 150 mm
10 t, stroke = 50 mm
5 t, stroke = 20 mm
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
9.1 Wire rope, with loops
Dia. 8 x 1.5 m, 10 x 1.5 m, 12 x 1.5 m, 14 x 1.5 m,
16 x 1.5 m, 12 x 4.0 m, 12 x 6 m, 12 x 8 m, 16 x 4 m,
16 x 6 m, 16 x 8 m, 20 x 8 m, 20 x 10 m, 36 x 8 m,
36 x 10 m, 36 x 12 m, 42 x 8 m, 42 x 10 m, 24 x 6 m,
24 x 8 m, 24 x 10 m, 24 x 12 m.
9.2 Hemp rope
Endless, dia. 20, 30 and 40.
9.4 Shackles
DIN 82101
1, 2, 4, 6, 8, 10 and 12 t
9.5 S-hooks
0.2, 0.5, 1, 2 and 5 t
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
10.1 Cutting torch kit
Complete with handle, cutting tips size 3 – 8,
pressure gauges and hoses.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
11.1 Hand shield
Complete with light and dark panes.
Protection class 13.
11.2 Fixed shield
Complete with light and dark panes.
Protection class 13.
11.3 Protective gloves
Leather with long cuffs.
11.8 Lighters
For welding and cutting torch.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Item Description
11.9 Bottle cart
For 2 bottles, load capacity of 500 kg, sturdy tubular
structure, high stability, wheels arranged on ball
bearings, dia. of 400, solid rubber-tired.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Gas Welding
Gas welding rods, diameter:
2.0 mm
2.5 mm
3.0 mm
4.0 mm
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Arc Welding
Stick electrodes, diameter:
2.50 mm
3.25 mm
4.00 mm
5.00 mm
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Sundries
Oils and greases (for assembly of machinery and equipment)
Acetylene
Oxygen
Argon or helium
Sealing tape
Loctite
Liquid surface sealing compound
Filter elements for flushing according to SMS GROUP circuit diagrams.
Shim Plates
Material: St 37 or similar.
Shims must be plane-parallel and deburred on all sides.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Welders must use the specific PPE for this activity.
Welders must not carry out unrequired jobs that may jeopardise
their safety or that of other people.
Steel piping is normally obtainable on the market in lengths of ca. 6 metres and must
follow the contour of walls and machines during erection work. Pipe connections are
therefore inevitable.
A distinction is made between:
• welded and thus fixed connections and
• pipe couplings that can be separated
A piping network has to be manufactured and installed diligently since the reliability of a
media supply system depends upon the quality of the design of the network. It is therefore
important that the work on the pipeline system be executed in the necessary quality.
The basis for the manufacture and installation of piping are the plant schematic and the
piping drawings.
In some cases the piping is measured and manufactured on the site after the plant
components have been erected.
The following must be observed in particular:
• split-up into prefabrication and fabrication on the site,
• installation of straight, direct, clearly arranged and flow-favourable lines,
• cleanness during work,
• proper fastening of the piping system,
• tension-free installation.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Prefabrication
In the case of prefabrication the piping is manufactured in a workshop and delivered to the
site for installation.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Fabrication on site
In the case of manufacture on the site the piping is manufactured in accordance with the
progress of erection.
Figure 49: Saw off pipe at right angles and deburr it but do not use a pipe cutter. Use a
sawing machine if possible. Slightly deburr pipe ends on inside and outside.
Clean.
Cleanness in work
During the installation work it must be ensured without fail that dirt does not penetrate into
the piping system. Piping and components must be delivered to the place of installation in
a properly closed state.
During the progress of the installation work the connections of the pipes and components
must remain closed. Only when they are actually connected, may the caps be removed.
Prior to being fitted the connections and their surfaces must be checked for cleanness. It
is not sufficient to rely solely upon the flushing of the system that may take place after the
installation work.
Tension-free fitting
It is very important that the lines be laid tension-free. If lines can only be installed under
tension, they must be aligned or re-fabricated.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
A distinction must be made between the “pipe/pipe coupling” and the “pipe
coupling/component” connection (valves, base plates, control blocks, pumps).
Figure 50: Screw connection, metal-metal sealing, holding function using thread, use in
low-pressure range (e.g. on water lines)
In the fitting of ferrule pipe couplings a ferrule (bite ring) is pulled onto the
pipe); it fulfills at this point the “holding” and “sealing” functions. The
function “sealing” is also metal-metal. The holding function of a ferrule
toward the pipe coupling is ensured with the aid of the union (cap) nut.
Ferrule couplings have to be serviced as they would otherwise tend to leak
due to their metal-metal sealing and to the “settling” that results therefrom.
Due to the surface brittleness it is however only possible to tighten within
certain limits.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
The ferrule should be pulled onto the pipe with particular care, as the
ferrule would slip from the pipe under load if it did not cut sufficiently far into
the pipe.
During fitting it should also be ensured that the pipe ends are cut off at right
angles and cleanly deburred.
The fitting instructions of the coupling maker must be observed.
In the fitting of welding-nipple pipe couplings a welding cone is welded on to the pipe (butt
welding).
The sealing between the welding cone and the coupling is elastic. The holding function
between the cone and the coupling is fulfilled by the union nut.
The fitting instructions of the coupling maker must be observed.
• Figure 52: Welding-nipple coupling with cone, elastic sealing, holding function by
weld seam.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
With sealing-edge coupling bodies a sealing edge that seals metal-metal on the
components is machined onto the screwed plug. The precondition is that the screw-on
surface is at right angles to the thread and does not display any cross scoring. The
pulsation usual in the hydraulic equipment may lead to material hardening occurring
that necessitates the retightening of the couplings.
Normally the threads are however glued in with sealing material, e.g. with Loctite. The
sealing function is then in the thread.
The fitting instructions of the coupling makers and of the sealing-material maker must
be observed.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
• SAE flanges
• Many components in hydraulics have screw-on surfaces for so-called SAE flanges
from DN 40. A distinction is made between
◊ one-part SAE flanges and
◊ multi-part SAE flanges
Figure 57: SAE flange, one-part with O-ring, holding function by bolts
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 58: SAE flange, multi-part, elastic sealing, holding function by bolts
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Fitting of compensators
Compensators serve in piping systems as elastic pipe connections to compensate strains,
stresses, shifts and movements that are caused by temperature fluctuations, foundation
settling, changing loads or vibrations. They are also used to dampen body sonic transfer
and impacts as well as to compensate fitting inaccuracies.
The compensators used in hydrosystems are made of steel or rubber/artificial rubber in
various qualities that is affixed to a rugged carcass of synthetic fibre or steel wire,
depending upon the pressure.
For attachment to the piping system pipe couplings are used from DN 40 upwards steel
flanges in St 37.2 or, if necessary, in other materials (figure 60 and 61).
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
(1) Outerlayer
(2) Inner layer
(3) Flange with profile collar
(4) Flange with full profile
Compensators as elastic pipe connections must be installed in such a way that visual
monitoring is possible. The rubber parts must not be coated (painting). No insulation
material may be applied.
Compensators should be installed in such a way that if possible they are loaded when
pressed together. Stretching in the operating state must be avoided. Torsion is
inadmissible.
Between two fixed points a max. of only one elastic pipe connection must be used.
Rubber compensators should be protected against radiation and heat and if necessary
covered or equipped with a protective sleeve.
If electric currents are led through across the piping (e.g. grounding for welding
transformers), the compensator must be sufficiently well bridged. If there is no such
bridge, the compensator may act as an electric resistor and be destroyed.
An eddy current that leads to an increase in the noise level may be caused in the
compensators as a result of the special shape of the latter. A guide pipe must then be
installed.
The fitting instructions of the compensator maker must be observed.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 64: Clamp stack, e.g. for two pipes arranged one above the other
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
The piping system is usually secured to the machine structure or to the foundation walls.
A separate substructure must often be created for the piping (figure 65).
The distance between two clamps depends upon the pipe outer diameter.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
1.11.2 Bending
For pipe bending radii, minimum dimensions for angled pipes and determination of pipe
lengths with consideration to various bending angles and bending radii also see NS 144.
1.11.3 Welding
Single V α b 2–5
over 2 butt weld
t
s=t c To 2
to 20 c
b
α 60°
Bult-type joint
b 2–5
Single – U β
butt weld r c To 2
over 20 t s=t
c r 4
b
β 10°
Steep- b 6 – 10
flanked β
Single – J b 2–5
c
butt weld β
all b s=t c To 2
Comer joint
t
β 30° - 40°
t
Fillet weld
all s=t
t
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Note:
Welding work should only be carried out by qualified specialists in
possession of welder‘s qualification certificates to EN 287
Part 1. The provisions stipulated in ISO 5817 apply in regard to
welding quality assurance.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 66:
Note:
Root welding for oxygen, lubrication oil and hydraulic oil shall be always
performed by TIG welding with the pipe plugged and filled of inert gas.
• Socket welding
Figure 67:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Note:
SMS GROUP does not apply to socket welding!
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Warning!
Works or pressure tests on hydraulic and pneumatic equipment
must be carried out by experienced, qualified operators only.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Operating procedure concerning pickling, flushing, pressure test and quality control
operations on hydraulic, oil and grease lubricating circuits.
1.12.5 Pickling
1.12.6 Passivation
1.12.7 Drying
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
For hydraulic and lubricating oil piping standard media for the pressure test is the water. If
SMS Group decideds not to perform the in-line pickling of the piping, the pressure test will
be performed with oil. In this case, at the end of the pressure test, the piping will be flused
as provided by paragraph 1.11.8.
1.12.5 Pickling
Pickling removes all oxide that may be inside piping elements.
The most common fluids for this purpose are:
citric acid,
sulphuric acid,
chloric acid,
orthophosphoric acid
Fluids:
Citric acid 30 kg / m³ water
Inhibitor, RODINE 1 kg / m³ water
Ammonia 25%, to 3.5 pH
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Pickling operation must be maintained until the concentration of the iron solution becomes
stabilised, indicating that no oxide is present.
For all purposes and reasons, the minimum duration for a pickling operation is 4 hours.
1.12.6 Passivation
The passivation operation creates an anti oxidation protective coating on iron surfaces.
To the fluid used for the pickling procedure and still within the circuit, 0.5% (5 kg / m³) of
nitric acid and ammonia is to be added, so that the pH value of the solution reaches a
reading of 9.2
This solution is kept circulating at a temperature of 60° C for 1 hour, after which sodium
nitrite art a ratio of 5 kg per m³ of solution is added thereto.
This part of the process will last for about 4 h.
When finished, empty the solution into appropriate containers.
1.12.7 Drying
Once the circuit is completely emptied, pipeline is dried using nitrogen jets at a pressure
of 10 to 15 bar; exhaust valves are to be opened alternatively so as to concentrate the gas
flow in the various parts of the circuit.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Annexes hereto:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
ISO / DIS PARTICLES ACFTD MIL STD 1246 NAS 1638 SAE
4406 10 µ / cm³ mg / l A (1967) (1964) (1963)
CETOP
RP 70 H
26 / 23 140,000 1,000 -- -- --
25 / 23 85,000 -- 1,000 -- --
23 / 20 14,000 100 700 -- --
21 / 18 4,500 -- -- 12 --
20 / 18 2,400 -- 500 -- --
20 / 17 2,300 -- -- 11 --
20 / 16 1,400 10 -- -- --
19 / 16 1,200 -- -- 10 --
18 / 15 580 -- -- 9 6
17 / 14 280 -- 300 8 5
16 / 13 140 1 -- 7 4
15 / 12 70 -- -- 6 3
14 / 12 40 -- 200 -- --
14 / 11 35 -- -- 5 2
13 / 10 14 0.1 -- 4 1
12 / 9 9 -- -- 3 0
18 / 8 5 -- -- 2 --
10 / 8 3 -- 100 -- --
10 / 7 2.3 -- -- 1 --
10 / 6 1.4 0.01 -- -- --
9/6 1.2 -- -- 0 --
08 / 5 0.6 -- -- 00 --
7/5 0.3 -- 50 -- --
6/3 0.14 0.001 -- -- --
5/2 0.04 -- 25 -- --
2/8 0.01 -- 10 -- --
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
kW / ND 0.5 m/s 1 m/s 1.5 m/s 2 m/s 3 m/s 4 m/s 5 m/s 7 m/s 8 m/s 10 m/s
8 1.5 3 4.5 6 9 12 1.5 21 24 30
10 2.3 4.6 7 9.2 14 18.4 23.2 32.4 36.8 46.4
12 3.4 6.8 10.2 13.6 20.4 27.2 34 47.6 54.4 68
15 5.3 10.6 16.9 21.2 31.8 42.4 53 74.2 74.8 106
16 6 12 16 24 36 48 60 84 96 120
20 9.5 19 28.5 38 57 76 95 133 152 190
25 15 30 45 60 90 120 150 210 240 300
32 24 48 73 96 144 192 240 336 384 490
40 36 76 114 152 226 304 380 532 608 760
50 60 120 180 240 360 480 600 840 960 1,20
65 100 200 300 400 600 800 1,00 1,400 1,600 2,000
80 150 300 450 600 900 1,200 1,500 2,100 2,400 3,000
100 240 480 720 960 1,440 1,920 2,400 3,360 3,840 4,600
125 370 740 1,110 1,480 2,220 2,960 3,700 4,180 5,920 7,400
150 540 1,080 1,620 2,160 3,240 4,320 5,400 7,560 8,640 10,600
175 750 1,500 2,250 3,000 4,500 6,000 7,500 10,500 12,000 15,000
200 950 1,900 2,850 3,800 5,700 7,600 9,500 13,300 15,200 19,000
225 1,200 2,400 3,600 4,800 7,200 9,600 12,000 16,800 19,200 24,000
250 1,470 2,940 4,420 5,880 8,820 11,760 14,700 20,580 23,520 29,400
300 2,120 4,240 6,360 8,480 12,720 16,960 21,200 29,680 33,920 42,400
350 2,890 5,780 8,670 11,560 17,340 23,120 26,900 40,460 46,240 57,800
400 3,800 7,600 11,400 15,200 22,800 30,400 38,000 53,200 60,800 76,000
450 4,760 9,520 14,280 19,040 26,560 38,080 47,600 66,640 76,160 95,200
500 5,900 11,800 17,700 23,600 35,400 47,200 59,900 82,600 94,400 116000
550 7,125 14,250 21,375 28,500 42,750 57,000 71,250 99,750 114000 142500
600 8,450 16,900 25,350 33,800 50,700 67,600 84,500 118300 135200 169000
700 11,550 23,100 34,650 46,200 69,300 92,400 115500 161700 184800 231000
800 15,750 31,500 47,250 63,000 94,500 126000 157500 220500 252000 315000
900 19,100 38,200 57,300 76,400 114600 152800 191000 267400 305600 382000
1,000 23,500 47,000 70,500 94,000 141000 188000 235000 329000 376000 470000
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Saybolt Universal
Seconds (SSU) ISO-VG CentiStoke CentiPoise*
31 2 1.0 0.876
35 3 2.5 2.19
40 5 4.2 3.68
45 5/7 5.9 5.17
50 7 7.5 6.57
55 7/10 8.8 7.71
60 10 10.5 9.20
70 10/15 13.2 11.56
80 15 15.7 13.75
90 22 18.2 15.94
100 22 20.6 18.05
150 32 32.0 28.03
200 46 43.2 37.84
300 68 65.0 56.94
400 68/100 86.0 75.34
500 100 108 94.61
750 150 162 141.91
1000 220 216 189.22
1500 320 323 282.95
2000 460 431 377.56
3000 680 648 567.65
4000 1000 862 755.11
* Centipoise are given for oil of 0.876 specific gravity. Relationship: centistokes X specific
gravity = centipoise
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
APPENDIX A / to P.PRD.2.ST.001
WELDED JOINTS
Unless otherwise specified in the relevant plans, project specification, a first class
execution of all welded joints implicates the following:
1.1 Foreword
All pipe edges that are to be welded must be machine or flame cut and then duly
chamfered at a 37° 30’ angle, as per ANSI B. 16.25 and /or UNI 11001.
For pipes featuring the same outer diameter but different wall thickness, the inside
edge of the thicker pipe must be chamfered at a cylindrical / tapered angle of 15°,
whilst the shoulder surface must be perpendicular to pipes axis so as to obtain a
perfect correspondence of the inner diameters.
Thickness Distance
° 6 mm thick, or less: 2 mm
° 7 to 22 mm: 2.5 mm
° 23 mm and over: 3 mm
All parts to be welded must be perfectly aligned with each other (admissible
alignment deviation not to exceed 20% of pipe’s wall thickness; in any case 1.5 mm,
max.), and temporarily fastened with suitable holding elements (e.g. cross bars).
All pipe edges must be thoroughly inspected for no defects prior to welding.
Eventual defects must be removed and remedied (hammered, grinding, etc.), and
where a repair is not possible, a piece of the pipe must be cut off.
Pipes should be properly and externally coupled using manual or hydraulic devices.
If pipes are somewhat of an oval shape, they must be rounded off by means of
hydraulic jacks, or similar devices, whenever possible.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Seamed pipes must be welded with seams located diametrically opposite to each
other.
Welding build up must be ground off after first welding pass, so as to have a
perfectly smooth and even pipe surface.
Any cutting operation required on existing piping that convey flammable fluids or
oxygen must be executed using manual, electric or pneumatic pipe cutting devices
equipped with water cooling.
Welds must be performed using the electric arc process with lined electrodes.
Inert gas welding may be used only on oxygen, hydraulic or lubricating piping.
Weld testing and selection of sampling probes shall be according to UNI 5132
and/or AWS - ASTM A 233 58T.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Only welders who have successfully sustained a weld qualifying test for the related
types of welding conditions may be employed.
All qualifying tests shall be in accordance to UNI 4633 and 4634 and / or ASME
Code, Sec. IX.
All welders must have a qualifying license, bearing the qualification rating and their
identification number.
The Contractor reserves the right to ascertain welders’ qualification via appropriate,
direct tests.
Each welder must punch in, or mark with indelible paint, his / her identification code
besides each weld.
Weather conditions
No welding operation may be performed when the existing and prevalent weather
conditions in that particular area may have an influence on the welding results.
With strong wind, rain or snow, or sand storms, all areas subjected to welding operations
must be properly and adequately protected.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
With ambient temperatures in the welding area below 5° C, all the surface around this
area must be covered with a thermal plaid to avoid a too abrupt cooling effect.
When a welding procedure has been interrupted or the part is being submitted to a
second passage, all slag, scrap, etc., must be duly removed (hammering, brushing),
so as to have a perfect joining root and a continuous weld bead.
In case natural grooves or slag material are present in subsequent welding passes,
all these imperfections must be ground off, providing a perfect joining root.
All welds must be incorporated into the base metal, and bead thickness must not be
less than pipe wall thickness; welding add on must not exceed 1 + 1.5 mm.
Before a heat treatment process, or pre heating of weldings on joints or specials, all
openings, save one, must be duly covered to avoid draughts inside the pipe.
No welding that has not received at least two weld passes may be interrupted (e.g.
at the end of the day).
When welding a pipe with an horizontal axis, there may be two different situations:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
a) pipe is rotated so that the weld is executed in the upper position, preferably in a
continuous manner with no interruptions, until the joint is perfectly finished.
b) weld must be started from the lowest point, proceeding towards the top until the
upper pipe generating line is reached; weld is therefore achieved in two stages.
When a pipe with vertical axis is to be welded and the weld is on an horizontal
plane, the welder must execute each single bead going around the pipe (if possible),
in order to achieve a continuous, uninterrupted welding.
When the welder goes from one bead to another, careful attention must be paid to
the above descriptions.
1.5 Pre-heating
When pipe or fitting thickness exceeds 19 mm, all pieces must be pre heated at
200° C before the first welding pass is made.
Pre heating must be repeated whenever welding operation has been interrupted or
before applying subsequent weld layers.
A 300 mm wide band from the joint’s centreline must be heated to above stated
temperature.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
The part submitted to heat treatment must be at least 8 times the width of the
welding beam, referred to joint’s centreline.
Generally, stress relieving temperatures are in the 600 to 650° C range, with an
approximate temperature rising gradient of 150° C + 200° C per hour.
Material must be maintained at the stress relieving temperature for 1 hour, at least,
per inch, or fraction thereof, of thickness. Minimum stress relieving time is 1 hour.
Temperature decrease gradient must not exceed 250° C per hour. This is achieved
by covering the heat treated parts with appropriate, non-flammable insulating plaids.
Recording diagram of the heat treatment process must detail the references of the
pertinent joints and must be handed over to the contractor‘s Site Manager.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
All welded parts must be sight checked to verify a proper execution, the continuous
state of the welding bead, absence of slag or cracks. Unless otherwise specified in
the drawings, quality level D as per standard DIN EN ISO 5817:2006-10 shall be
considered.
Unless otherwise specified, the hereafter non destructive tests and pressure tests shall be
performed on pipes conveying different fluids, with the percentages shown in the following
table. The non destructive tests here after reported can be substituted with similar
procedures for the internal quality verification. For this purpose the authorization of SMS
Group is required.
X- Rays in compliance to SME norms, Code Sec. V, latest edition and standard ISO
17636.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
When weld defects are above admissible values, they must be appropriately
repaired or completely remade. The edges must be adequately prepared and
welded by the same welder. Thereafter new x rays will be taken.
If the percentage of defective joints with respect to the joints verified is greater than
20%, the Contractor may request a verification of all joints (100 %), and no payment
shall be due by said.
The selection of the joints that are to be verified must be made in such a manner as
to maintain an adequate supervision of all involved welding personnel.
All x rays must be appropriately numbered; their position must be recorded in the
relevant register or marked on the plans or sketches, with reference to the welding
executed and checked.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
APPENDIX B to P.PRD.2.ST.001
TRIALS / TESTS
1.1 Foreword
It is presumed that the various line or system components are delivered at the site already
hydraulically tested by each supplier.
Hydraulic testing may not be used for those instances where the sustaining elements are
not adequate to support a pipeline filled with water, or when the test water may leave
damaging traces to the lines or systems once the fluid that they convey is injected into
them.
Temporary supporting elements, designed to sustain the greater weight, are allowed only
on steam conveying lines when these must be subjected to a hydraulic test.
Said supports shall be removed once the test is successfully completed.
A preliminary pneumatic test, at a max. pressure of 2.5 kg / cm², may be used on single,
non assembled tracts to ascertain if there are any leaks. All welded joints must be left
bare (unlined, non insulated, etc.) to enable proper verification during the testing
operations.
During testing, all expansion compensating devices must be properly blocked to avoid
excessive stresses produced by the testing procedure.
Special equipment or secondary line tracts that operate at a lower pressure rating than
that of the main line, must be disconnected and isolated before the tests are carried out.
When these tests are performed, appropriate exhaust valves must be provided at the
highest points of the lines or systems involved, so as to eliminate all air pockets when they
are filled.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Upon successful completion of the tests, said exhaust valves will be maintained on piping
that conveys water or other liquids; if piping conveys gas, all exhaust valves must be
removed.
Hydraulic test is normally executed using normal tap water (clear, soft and clean).
All connected equipment must be thoroughly checked before the test is begun.
Dial fittings, usually located at the lowest point on the system, must be equipped with taps
in case they require replacement.
Once the test pressure is reached, the pump must be disconnected from the line,
followed with 1 hour waiting period.
If the pressure does not decrease during this period, it must be maintained for the
period prescribed in the relevant technical specification, and never less than 24 h.
If, during said waiting period, there is a pressure reduction on the dials, testing
operation must be repeated twice; thereafter the line may be considered not testable
until the cause of the leak is not established.
If, during the test and due to great thermal variations, the line’s inner pressure
exceeds the maximum rating detailed in the relevant technical specification, the line
pressure must be partially released until the initial testing values are achieved.
Upon successful completion of all testing procedures, the lines must be completely
emptied and dried (compressed air), unless they are to convey water, in which case
they may be kept filled.
Generally pneumatic tests are carried out using compressed air or nitrogen.
It is also possible to use the same gas that the line is to convey, as long as no hazardous
situation for the personnel involved is created thereby.
Special precautions must be taken to avoid a pressure increase of the fluid caused by
increases in temperature.
To this end, it is advisable to install safety valves, set at 1.25 of the rated test pressure
value.
It is also strongly recommended that the same situation be created as when the line is
filled with the fluid it is designed to convey.
Before the test can be safely carried out, all connected equipment must be thoroughly
checked to verify that all connections have been correctly made.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Pressure within the line or system must be applied gradually until half of the test value is
reached; afterwards, the pressure is increased in steps of 1/10th of the test pressure, up
to the required pressure value.
Test pressure is 1.2 the commissioning pressure on tanks, compressors or special valves,
or 90% of the yield stress value of the line or system components.
The line or system must be tested for ≈ 24 h, or for a sufficient period to verify whether
there are any leaks.
At the end of the pneumatic test, all traces of soap around welding beads must be
removed (wash away with water), to ensure proper lining adherence.
Not applicable.
Testing schedule must be agreed upon between the Project Manager, the Subcontractor
and other parties who are active in the area where the tests are to be executed.
The dates and the methods of the tests shall be communicated, in writing, by the Project
Manager to the Subcontractor and to all other parties concerned, who must acknowledge
receipt thereof, in writing.
A layout plan of the areas involved in the tests shall be given to the Subcontractor and to
the other parties concerned.
When the lines under testing are filled, all personnel present in the adjacent areas must
leave and all pending works on the line must be interrupted for the whole duration of the
test.
Appropriate warning signs, at a distance of 25 m from each other and in any case at each
sectioning point, must be posted.
Said signs shall be posted only when pneumatic tests with air, nitrogen, oxygen, etc., or
high pressure hydraulic tests are being carried out.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Specially authorised personnel shall patrol the areas where the lines are being tested, for
the whole duration of the test, so as to prevent any unauthorised person from approaching
these potentially hazardous areas.
Due account must be made for those systems maintained operative that could be
damaged by the tests or that could constitute a potentially hazardous situation.
Nevertheless, the Project Manager may, before commencing any testing operation:
a) ascertain that all parties involved have been duly informed on the date and timing
of the tests;
b) verify the status of the line or system and its correspondence to the plans;
c & d) verify that all safety measures, warning signs included, have been duly
implemented;
e) check that all unauthorised personnel have been removed from the area
involved, as well as the presence of the supervisory staff;
f) verify that all equipment has been duly and properly secured and that all
connections have been correctly made.
Once the Project Manager has ascertained the application of above and has verified that
the testing operations can be commenced, the appropriate order to begin the tests will be
issued.
All lines shall be filled, as previously specified, and the inspection of the parts being tested
will begin after 1 hour has passed from the completed filling operation.
Parts are verified for leaks. Eventual repairs or replacements are executed as specified at
4.2.1 herein. Thereafter, the lines are tested again, as detailed above.
In any case and if any leaks are found, the Subcontractor cannot repair, carry out non
destructive tests or repeat the tests without prior approval from the Project Manager.
At the end of a successful test, i.e. after lines/systems have been fully tested and no
deformations and/or no leaks have occurred, the Project Manager shall declare that the
test is satisfactorily completed.
All testing equipment and warning signs will then be removed, and the supervisory
personnel shall be released from its duties and all works in the areas involve will
recommence.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
It is due to specific erection sequences that some of the machines and components have
to be assembled before being placed on top of their foundations.
All faces machined for assembly are to be carefully cleaned from anticorrosion coatings
applied. Moreover, such faces are to be checked for damage that may have been caused
during transport. Damage or defects, if any, are to be eliminated with the aid of suitable
tools, such as files, scrapers, emery paper etc. prior to assembly.
Assembly as well as matching of machines and components will be effected in due
compliance with applicable drawings.
After preassembly, all machined faces are to be protected against corrosion by applying a
film of oil or grease thereto.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Particular attention is invited to the notes and instructions given in various drawings for
field erection.
These activities are the responsibility of the erection contractor in charge of erecting
corresponding plant components.
Required tools, appliances and consumables are not included in the SMS GROUP extent
of supplies.
Example:
• Field-welded
Figure 68:
• Field-attached
• Field-drilled
• Adapted during field erection
• Exact dimension determined and adapted during field erection
• Bolted joints secured with LOCTITE
• Faces sealed with sealing compound etc.
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Mobile Crane
Tractor-Flatbed
Trailer Units
Trucks
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
1.15 Appendix
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Part Part Quantity SMS GROUP Complaints Report Field Erection No.
missing damaged
Instructions:
Outdoors Repackaging
Dry room
Remarks:
XXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Aligning
The couplings compensate for positional variations of the shaft ends to be connected up to the
data refer to page 152.
When aligning, keep the radial and angular misalignment of the shaft ends as small as
possible because hereby the service life of the flexible is increased under otherwise the same
operating conditions.
Alignment is to be carried out in two axial planes vertical to each other. This is possible by
means of a ruler (radial misalignment) and feeler gauge (angular misalignment) according to
the figure.
By using a dial gauge, the alignment precision can be increased.
Ruler
Feeler gauge
Figure 69:
Caution!
Check the tightening torque of the screws after re-establishing the
connection
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Figure 70:
Coupling Type Axial misalignment Angular misalignment Radial misalignment Tightening torques
∆ Ka ∆ Kw ∆ Kr TA
Caution!
Angular and radial misalignments may occur at the same time.
The sum of both misalignments must not exceed the max.
permissible value of the angular or radial misalignment.
(Kw + Kr)existing ≤ ∆ Kw X Sn o ∆ Kr X Sn
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Loads on screws
These instructions provide the possibility of rapidly determining the dimensions of the screws
with a property class of 8.8. The following factors are used to convert the pretensioning forces
and the tightening torques when the property of the screws differs from 8.8.
Materials: 5.8 = 0,47 10.9 = 1,41 12.9 = 1,69 A2-70 = 0,71.
These instructions do not apply to screws with a fine thread.
The admissible axial operating loads FA indicated in the following table consider the
fatigue of a bolted joint. If these operating loads are exceeded, the fatigue failure cannot
be assured.
The operating loads indicated in the following table refer only to the axial loads and the force
applied to the axis of the screws with an ISO metric thread at an admissible temperature that
ranges from -50°C to +300°C. The calculation assume s a fatigue of 40 N/mm2 for screws
<M20 and 33 N/mm2 for screws ≥M20. The control of the tightening of the screws that use the
torques indicated in the table and the pretightening forces is an important precondition for the
life duration of the bolted joints. The fine threads have other admissible tightening torques,
operating and pretightening forces. A highly resistant plane washer is to be installed to avoid
excessive pressures on the joint of the bodies (UNI 5719 – DIN 6916). The property classes of
10.9 and 12.9 should be used only in exceptional cases. The parts that require a controlled
pretightening must have this value indicated in the assembly drawing.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
ERECTION TOLERANCES
Here below you shall find a general tolerance guide for specific machine groups. It covers major
machine groups indicating the important tolerances that need to be monitored carefully.
During the erection of the machines it is necessary that strict records of the erection figures are kept
and they must be compared and judged for acceptability. It is also advisable that the customer makes
the checks independently of the erectors to ensure that figures are recorded correctly.
To assist the user in understanding the tolerance list, we define the meaning of the terms used.
• Coordinates - Used to express measurement to the axis lines in both directions of the floor
plane.
• Coaxial - The tolerated axis must lie within a cylinder having a diameter equal to the
given tolerance.
• Symmetrical - The central line of two axis must lie between two parallel lines symmetric to
the reference axis whose distance is equal to the given tolerance.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Horizontal Stand
Note: Elevation of the baseplate has to checked with the elevation of the rails of the stand changing
device. This distance should have a tolerance of 0.5 mm.
B. Gear box
C. Motor
Vertical stand
A. Column
• Elevation ± 1 mm
• Vertical ± 0,2 mm / meter Referred to the stand sliding surface
• Baseplate axis position ± 2 mm
• Baseplate pass line axis ± 1 mm
position
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
• Elevation ± 1 mm
• Horizontal ± 0.5 mm / meter
• Rails distance 0 -2 mm
• Symmetrical to the stand ± 0,5 mm
axis
A. Shear baseplate
Note:
For coupling assembly and alignment of gearbox and shear shafts see sheet 25.
C. Motor
Note:
For coupling assembly and alignment of gearbox and motor shafts see sheet 25.
D. Openable channel
• Elevation ± 1 mm
• Position ± 1 mm
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Shear CVP50
A. Shear baseplate
• Elevation ± 1 mm
• Horizontal ± 0.5 mm / meter
• Baseplate axis position ± 5 mm
• Baseplate pass line axis ± 1 mm
position
B. Openable channel
• Elevation ± 1 mm
• Position ± 1 mm
A. Pinch roll
• Elevation ± 1 mm
• Horizontal ± 1 mm / meter
• Baseplate axis position ± 5 mm
• Baseplate pass line axis ± 1 mm
position
A. Rails
• Elevation ± 0,5 mm
• Horizontal ± 0.5 mm / meter
• Rails distance 0 -2 mm
Note: Elevation of the rails has to be checked with the elevation of the baseplate of the
horizontal stand or the elevation of the rails of the vertical stand . This distance should have a
tolerance of ± 0.5 mm.
Note: The hydraulic cylinders and supports must be positioned and aligned with the respective
stand changing car. This changing car should be set in the changing position which should be
aligned with the stand baseplate.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Roller tables
A. Rolls
• Elevation ± 1 mm
• Horizontal roll to roll ± 0,5 mm
• Coordinates ± 1 mm
Chain transfer
A. Driven shafts
• Elevation ± 1 mm
• Coaxial 0.05 mm
• Coordinates ± 1 mm
Note: For coupling assembly and alignment of gearbox and motor shafts see sheet 25.
B. Lifting shafts
• Elevation ± 1 mm
• Coordinates ± 1 mm
A. Driven shafts
• Elevation ± 1 mm
• Coordinates ± 2 mm
• Coaxial 0.05 mm
• Parallel 0.05 mm
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Main Frames
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Main Frames
Main Frames
Main Frames
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
05. Pusher (elevator entry, furnace entry, rejected billet at furnace exit)
Main Frames
Main Frames
Main Frames
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Main Frame
Main Frame
Main Frame
Main Frame
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
FURNACE
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
Main Frames
GENERAL NOTES:
• Before starting any assembly activity check the references regarding the plant main axis
referred to the warehouse columns; check also the general plant 0.00 reference level and
the raw level for the machines placing that should be always lower (minimum 50 mm) than
the machine placing final level.
• Verify the depth of the not feed-through corrugate pipes.
• Concerning the piping before install always the central units.
• Preset the supports for the bigger pipes and fix them with great care.
• Before install always the pipes with the larger diameter.
• Verify and coordinate the assembly with the electrical wireways passages in order to avoid
interferences.
• Pay attention to the tolerances indicated for the installation of the plates fixed into the
cement for the vertical stands and check with care the alignment.
• Align the couplings of all the drive groups following the tolerances required and then
execute the grouting final cast.
• Cast the final grouting only after the final alignment of all the machines.
• We suggest to use the jack-screw for the precision levelling of some kinds of machines
(for example the finishing block).
• Standard assembly sequence: stand - gearbox - motor
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
2.0 - SINGLE/COLD
FUNCTION TESTS
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
2.2.23 Separator: Cup Assembly, Run-off Diameter, Temperature, Safety Device ..................... 36
2.2.24 Oil Pressure at the Consumers ........................................................................................ 37
2.2.25 Water-Inlet Alarm Device ................................................................................................. 38
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
Preparation activities should only be assigned to personnel who
has been duly trained by the contractor.
Check the motors correct direction of rotation very carefully,
keeping well away from moving parts (as guards still only partly
installed). As soon as the necessary inspections are completed,
install all the guards.
• All machine components, especially skidways, rails, rollers, rolls and piston rods are to be
carefully cleaned from remaining preservatives and other contaminations.
• All electrical functions inclusive of interlockings are to be tested by the responsible electrical
equipment supplier.
• All auxiliary media are available in a function-tested state.
• All erection work has been checked for unobjectionable completion as
for instance:
◊ tight fit of all screw joints (especially on universal joint shafts, couplings and other
rotating parts)
◊ tight fit of all pipe fastenings
◊ tight fit of all anchor bolts
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Warning!
To perform all these checks, observe all the operating instructions
contained in this document and the preconditions for executing the
tests.
• In case of drives with two rotational senses care will be taken to ensure that the correct
sense of rotation is allocated to the control element (for instance starting button).
When maxi- or main drives (for instance stand/reel drives) are concerned , the sense of
rotation has to be ensured by the electrical specialist including compliance of these drives
with special rules and safety instructions.
If, for technical or other reasons, the electrical drive cannot be uncoupled from the working
unit (pump, gear unit, rolls ....), the check for a proper rotational sense is to be carried out
only in inching mode, or by starting and instantaneous switch-off.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
So the following items are checked for instance as far as proximity limit switches are
concerned:
• correct attachment of limit switch
• passage of switch flag
• working clearance of switch flag
• presence of inadmissible impairment of the magnetic field
• switching or rather moving positions for which purpose the relevant switch points have to be
approached, if possible, and the response behavior of the switch-off device to be checked.
In case of conspicuous limit switches the function can be checked by means of a light-
emitting diode at the limit switch. Is the function not conspicuous, the proper function can be
tested in the terminal box locally or at the light-emitting diode of the centralized PLC. If this
is not possible either, the electrical specialist can check this function by making
measurements or on the display of the plant control pulpit. During testing, special care will
be taken to ensure conflict- and collision-free functioning of the transducers and sensors
with regard to their attachments.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The reference values are contained in the technical data or rather equipment arrangement
drawing.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The pass line will be checked by use of a theodolite. The check will be made with reference to
the measuring points for the longitudinal and transversa axes as well as to the level marks as
determined during the design, mechanical manufacture, construction of foundations and field-
assembly. How these measurements are to be carried out in practice is described in detail in
this Erection Manual.
Visual check of roll gap
Checks to be made:
• Distance between the rolls
The roll gap will be measured through measurements of the work roll positions by means of a
position transducer at the mill stand in connection with the electrical control. In case of mill
stands without roll gap control, these measurements will take place by means of a feeler
gauge directly in the roll gap. The demanded roll gap dimension will be input at the electrical
control system.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The vertical adjustability of the top or rather bottom roll will be checked for which purpose the
respective rolls will be moved into the upper or rather bottom end position by means of the
hydraulic or mechanical vertical adjusting systems. The other end position in each case is not
allowed to be reached while the traversing stroke of the vertical adjusting system is being
performed as otherwise the top roll will contact the bottom roll and could damage same.
In case of hydraulic vertical adjusting systems, the vertical shifting stroke is checked by means
of an elector-hydraulic position control, i.e. through position measurements by position
transducer at the mill stand.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
2.2.7 Adjustment of Mechanical Equipment such as Rest Bar, Mill Guides etc.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Both the mechanical and the hydraulic systems of the stand clamping device will be visually
checked.
Checks to be made:
• Opening and closing of the stand clamping mechanism.
The first step is to open the stand clamping device by pressurization. It will be checked if the
clamping device is fully opened and thus allows the stand housing to be shifted or rather
removed. Then, the clamping device is disconnected from the hydraulic pressure and relieved.
If existing, the other connection is then pressurized for closing the clamping device. There is to
be checked whether the clamping faces of the housing and the stand clamping device have
closed. This check can additionally be made by use of a feeler gauge. Even the thinnest feeler
gauge is not allowed to be inserted between the closed clamping faces.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
When operating the grease pump, check some grease points for escape of
grease.
In case of automatic, electrically driven grease systems the electrical control system is
switched on and the automatic operation switched off for checks. Thereafter, the first half of
the greasing cycle is initiated manually.
Checks to be made:
• Pump pressure on pump pressure gauge;
• Grease distributors (visual check) for escape of grease in the connected grease points.
However, in each half greasing cycle only half of the grease points connected to a grease
distributor is greased as a function of system design.
• The limit pressure switches by disconnecting the grease pump when the set absolute
operating limit pressure is attained at the main line end or the required differential pressure
between the two main lines at the line end.
• Immediately after automatic switch-off of the grease pump through the limit pressure switch,
the system operating pressure can be read on the pressure gauge at the main line end.
After a pause of at least half an hour, the second half of the greasing cycle is started
manually. Same as in the first half of the greasing cycle, Items 1 to 4 will again be checked,
but this time for the other main line.
In grease facilities in the progressive system the check of Items 3 and 4 and of the second
half of the greasing cycle is omitted.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Check of technical data and set values of the hydraulic cylinders will be done visually.
Checks to be made:
• Cylinder stroke by approaching the two cylinder end positions by means of the switched-on
hydraulic control. In both end positions the extension length of the piston rod is measured
by use of a measuring ruler. The difference between the values results in the cylinder
stroke. Due to the machine design it is not possible to move all hydraulic cylinders into their
stroke end positions. In these cases it is not necessary to check the cylinder stroke.
• Stroke speed. It is calculated from the time for one cylinder stroke and the length of the
cylinder stroke. The time needed to perform a cylinder stroke is measured by means of a
stop watch.
• End position damping will be checked visually. The reduction of the stroke speed in the
cylinder end positions is distinctly recognizable with correct setting of the damping.
The reference values are indicated in the technical data or rather equipment arrangement
drawing.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Checking of technical data and set values of the pneumatic cylinders is visual.
Checks to be made:
• Cylinder stroke by approaching both cylinder end positions by means of the switched-on
pneumatic control. In both end positions the extension length of the piston rod will be
measured by use of a measuring ruler. The difference between the values produces the
cylinder stroke. Due to the machine design it is not possible to move all pneumatic cylinders
into their stroke end positions. In these cases, the cylinder stroke need not be checked.
• Stroke speed. It is calculated from the time for one cylinder stroke and the length of the
cylinder stroke. The time needed to perform a cylinder stroke is measured using a stop
watch.
• End position damping will be checked visually. The reduction of the stroke speed in the
cylinder end positions is distinctly recognizable with correct setting of the damping.
The reference values are indicated in the technical data or rather product arrangement
drawing.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
2.2.13 Check of Pressure Limiting Valves for Compliance with Preset Pressure
Visual check of the opening pressure set on the pressure limiting valve
(safety valve).
Checks to be made:
• At which oil pressure in the hydraulic system or rather in the lube-oil recirculation system
the pressure limiting valve opens. The pressure reference value is stated in the technical
data or rather system diagram.
• A deviating pressure set value might be determined and set during trial operation and later
during commissioning in order to adapt the opening pressure to the operating conditions of
the hydraulic system or rather the lube-oil recirculation system.
• It is reasonable to check the opening pressure on an appropriate test stand. If there is none
this test can also be carried out by a short-time increase of the system operating pressure.
For checking the opening pressure at the pressure limiting valve, a pressure measuring
instrument featuring an appropriate measuring range is connected to the corresponding test-
point connection by means of a hose with Test-point coupling.
Then, the pump of the hydraulic system or rather the lube-oil recirculation system is switched
on through the electrical control system. On this, the set system operating pressure can be
read on the pressure measuring instrument and recorded.
To assess the set opening pressure of the pressure limiting valve, the previously read and
recorded system operating pressure = pump pressure is slowly and cautiously increased by
raising the operating pressure setting for the pump until the pressure limiting valve opens.
In so doing care has to be taken to ensure that the max. admissible operating pressure of all
incorporated hydraulic devices and pipelines will not be exceeded to avoid damage to the
hydraulic system.
The opening of the pressure limiting valve is audibly distinguished by flowing noises since
opening is accompanied by heavy noise emission. Moreover, valve opening is recognized by
the fact that the pressure indicated by the pressure meter does not increase any further
despite rising of the operating pressure setting for the pump.
Now, the pressure setting of the pressure limiting valve on the pressure meter can be read and
recorded.
Prior to disconnecting the hydraulic system or rather the lube-oil recirculation system, the
system operating pressure has to be reset to the normal operating pressure assessed at the
commencement of the measurements.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The operating pressure reference value is indicated in the technical data or rather system
diagram.
A deviating pressure set value might be determined and set during trial operation and later
during commissioning in order to adapt the operating pressure to the operating conditions of
the hydraulic system.
For checking the operating pressure in the hydraulic system a pressure measuring instrument
featuring an appropriate measuring range is first connected to the corresponding test-point
connection by means of a hose with test-point coupling.
Then, the hydraulic system pump is connected with the electrical control system. On this, the
set operating pressure = pump pressure will be read on the pressure measuring instrument
and recorded.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
For this purpose the relevant switch points have to be approached, if possible, and the
response behavior of the switch-off device to be checked. In case of conspicuous switches the
function can be checked by means of a light-emitting diode at the switch. If the function is not
conspicuous, the proper function can be tested in the terminal box locally or at the light-
emitting diode of the centralized PLC. If this is not possible either, the electrical specialist can
check this function by making measurements or on the display of the plant control pulpit.
During testing, special care will be taken to ensure conflict- and collision-free functioning of the
transducers and sensors with regard their attachments.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
For the purpose of checking the differential pressure, the respective system with the
associated pump is switched on via the electrical control system. On response or changeover
of the electrical differential pressure switch (pilot lamp) or if and when the indicator is within the
“red range” in case of mechanical clog-up indication, it will be necessary to clean or change
the filter. If duplex filters are used, change-over to the other filter cartridge can be made.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
For the purpose of checking the water flow, the cooling water system and the hydraulic system
with its associated pumps have to be connected via the electrical control system.
When the hydraulic system has reached its operating temperature, the cooling water feed to
the oil cooler will be opened via the electrical control system either automatically or manually.
For water flow checking, the temperature will then be measured outside at the cooling water
lines by use of a contact thermometer or even by hand.
If and when the temperature of the cooling water return line is distinctly higher than the
temperature of the cooling water feed line, water flow is ensured.
If the operating temperature in the hydraulic system has not been attained, a screw joint in the
cooling water return line of the oil cooler can be somewhat slackened cautiously as an
alternative to check the water flow. If cooling water escapes under pressure, water flow is
ensured.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
To check the nitrogen pre-fill pressure the first step is to close the oil-pressure-side shutoff
valve at the safety shutoff block whereupon the oil pressure relief valve will be opened at the
safety shutoff block. Now, the accumulator oil side is discharged by the leak oil line in the tank.
On this, the accumulator fill and test device on top at the nitrogen connection of the
accumulator is connected. Now, the pre-fill pressure can be read at the pressure meter of the
fill and test device and compared with the reference value in the technical data or rather the
system diagram. If necessary, the pressure can also be corrected using the fill and test device
by refilling or discharging nitrogen.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Visual and/or electromechanical function checks of the solenoid valves and/or the proportional
valves and servo valves.
Checks to be made:
• Way valves: the alternating stroke movements of the respective hydraulic cylinder.
Proportional valves and/or servo valves: the stroke speed and/or the position control of the
respective cylinder.
It is convenient, however, to check the hydraulic valves on a suitable test stand. If no such
stand is available, the hydraulic valves can be checked in installed state, too.
For checking the way valves, the hydraulic system is cut on with its pump via the electrical
control. Then the way valve to be checked is actuated manually under special observance of
the safety instructions via the electrical control and monitored to test the alternating stroke
movement of the associated hydraulic cylinder.
If the function of a valve is not selectable separately, appropriate aids are to be used for
triggering, as a substitute even hand operation of the valve.
The hydraulic system is cut on with its pump via the electrical control likewise for checking the
proportional valves and servo valves.
As regards those valves that control the cylinder stroke speed, cylinder strokes are manually
performed via the electrical control under special observance of the safety instructions. For
checking, the stroke speed of the hydraulic cylinder is monitored by means of a stopwatch.
The stroke speed is calculated from the time needed for one cylinder stroke and the length of
the latter.
In case of valves which cause a position control, the position actual value is measured, when
the position control has been cut on, by use of suitable electronic and/or visual measuring
facilities, and is for checking compared with the demanded set point and/or nominal value.
The stroke speed or the position set point is indicated in the Technical Data, in the Equipment
Arrangement Drawing and/or in the Plant Layout and may also depend on the selected
production program.
During trial operation and later during start-up, yet possibly deviating valve setting values have
been and/or will be fixed and set in order to tune the valves to the operating conditions of the
hydraulic system.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
To this end, the relevant switching points are, if possible, to be approached and the response
of the cut-off equipment to be tested. As regards observable switches, the function can be
checked by means of the LED on the switch. Should the function not be observable, the
proper function can be tested in the terminal box locally or at the LED of the centralized PLC. If
this fails to be possible as well, then the person in charge of the electrics may check that
function by way of measurement or on the display of the plant control. Particular attention
should be paid to conflict- and collision-free function of the transducer and sensor attachment.
In case of pressure switches for example, the following features are checked:
• the correct fixture of the pressure switch
• the switching-pressure presetting
• the tightness against the escape of media
• the pressure switching points
A check is made as to the oil pressure in the hydraulic system at which the pressure switch will
be operative. The pressure set point is stated in the Technical Data and/or in the Plant Layout.
During trial operation and later during start-up, a yet possibly deviating pressure setting value
will be fixed and set in order to tune the pressure switching points to the operating conditions
of the hydraulic system.
It is convenient to check the pressure switches on a suitable test stand. If no such stand is
available, the check can also take place through short-time boosting of the operating pressure
of the system.
For checking the pressure switching points at the pressure switch, a pressure measuring
device with a suitable measuring range is connected by means of a hose with test-point
coupling to the corresponding test-point connection.
Following this, the pump of the hydraulic system is cut on with the electrical control.
Thereafter, the set operating pressure of the system may be read at the pressure measuring
device and recorded.
So as to establish the set pressure switching points of the pressure switch, the previously read
and recorded system operating pressure = pump pressure is slowly and carefully increased by
way of raising the operating-pressure setting for the pump until the pressure switch has
become operative.
When doing so, it is to be observed that the admissible maximum operating pressure of all
installed hydraulic devices and pipelines will not be exceeded to avoid damage to the hydraulic
system.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Now the switching-pressure setting of the pressure switch can be read and recorded at the
pressure measuring device.
The operating pressure of the system has, prior to cutting-off of the hydraulic system, to be
reset to the regular operating pressure determinate at commencement of the measurements.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
During trial operation and later during start-up, a yet possibly deviating pressure setting value
will be fixed and set in order to tune the operating pressure to the operating conditions of the
machines (consumers).
Measurements of the operating pressure in the lube-oil recirculation system are effected by
the firmly integrated operating pressure measuring system of the lube-oil recirculation system.
For checking, the lube-oil recirculation system with its pump is switched on through the
electrical control system whereupon the system operating pressure can be read on the
pressure-measuring device, and recorded.
If there is no such firmly integrated pressure measuring device available at the lube-oil
recirculation system, a pressure measuring device with a suitable measuring range is, for
checking of the operating pressure in the lube-oil recirculation system, connected to the
corresponding test-point connection by means of a hose with test-point coupling and the
operating pressure read thereon.
• The operating temperature of the lube-oil recirculation system.
• The temperature set point is stated in the Technical Data and/or in the Plant Layout. For
checking the operating temperature of the lubricating-oil circulation system, the system with
its pump is cut on via the electrical control and the temperature measured at the outside of
the oil-tank wall after lapse of several hours of oil circulation by use of a contact-type
thermometer. Should the lubricating-oil circulation system avail of a firmly installed
temperature measuring device, the operating temperature can also be read there.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
During trial operation and later during start-up, a yet possibly deviating pressure setting value
will be fixed and set in order to tune the operating pressure of the pressure tank to the
operating conditions of the machines (consumers).
Measurements of the operating pressure in the pressure tank of the lube-oil recirculation
system are effected by the firmly integrated operating pressure measuring system at the
pressure tank.
For checking, the lube-oil recirculation system with its pump is switched on through the
electrical control system whereupon the operating pressure in the pressure tank can be read
on the pressure-measuring device, and recorded.
If there is no such firmly integrated pressure measuring device available at the pressure tank,
a pressure measuring device with a suitable measuring range is, for checking of the operating
pressure in the pressure tank, connected to the corresponding test-point connection by means
of a hose with test-point coupling, and the operating pressure in the pressure tank read
thereon.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
To check the cup assembly, the hood of the drum is opened and the correct installation as
well as the visual condition of the cup assembly are inspected in accordance with the
Operating and Maintenance Instruction. Following this, the hood must be reclosed carefully.
For checking the balancing, the separator is cut on via the electrical control and examined
as to vibrations. Should abnormal vibrations or noises occur, the machine is to be cut off at
once,
• The temperature of the oil feed as well as the temperature between flow-heater and
separator drum.
The heating and the oil feed to the flow-heater are cut on to check the temperature of the oil
feed. The separator drum has to be switched on previously.
For checking the temperature of the oil feed, the temperature is then measured at the
outside of the oil feed pipe to the separator, either by use of a contact-type thermometer.
Should a firmly installed temperature measuring device be available at the flow-heater, the
temperature of the oil feed to the separator can also be read there. The reference value of
the separating temperature is about 90° C - 100° C. Attention: risk of burning!
For checking the brake, the separator is cut on via the electrical control and cut off as soon
as the operating speed has been achieved. The brake is applied immediately upon cutting-
off of the separator. When the brake is operating properly, the run-out time of the drum will
be intensely shortened, thus passing the critical speed of the drum faster.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The pressure set point is indicated in the Technical Data and/or in the Plant Layout.
During trial operation and later during start-up, a yet possibly deviating pressure set point will
be fixed and set in order to tune the operating pressure to the operating conditions of the
machine (consumers).
Measurements of the operating pressure at the machine (consumers) are effected by the
firmly integrated pressure measuring system at the machine (consumers).
For checking, the lube-oil recirculation system with its pump is switched on through the
electrical control system whereupon the operating pressure at the machine (consumers) can
be read on the pressure-measuring device, and recorded.
If there is no such firmly integrated pressure measuring device available at the machine
(consumers), a pressure measuring device with a suitable measuring range is, for checking of
the operating pressure at the machine (consumers), connected to the corresponding test-point
connection by means of a hose with test-point coupling, and the operating pressure read
thereon.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Visual check of the electrical switching elements of the water-inlet alarm device.
Checks to be made:
• The mechanical function and, if necessary in this connection, the electrical function of the
electrical switching elements as stated with due consideration to the technical data,
contained the set values and possibly indicated in the equipment arrangement drawing.
To this end, the relevant switching points are, if possible, to be approached and the response
of the cut-off equipment to be tested. As regards observable switches, the function can be
checked by means of the LED on the switch. Should the function not be observable, the
proper function can be tested in the terminal box locally or at the LED of the centralized PLC. If
this fails to be possible as well, then the person in charge of the electrics may check that
function by way of measurement or on the display of the plant control. Particular attention
should be paid to conflict- and collision-free function of the transducer and sensor attachment.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
The pressure set point is indicated in the Technical Data and/or in the Plant Layout.
During trial operation and later during start-up, a yet possibly deviating pressure setting value
will be fixed and set in order to tune the operating pressure to the operating conditions of the
pneumatic system.
For checking the operating pressure in the pneumatic system, a pressure measuring device
with a suitable measuring range is connected by means of a hose with test-point coupling to
the corresponding test-point connection.
Following this, the pneumatic system with its compressor is cut on via the electrical control.
Thereafter, the operating pressure of the system may be read at the pressure measuring
device and recorded.
Since the compact unit avails of a firmly installed pressure measuring device, the operating
pressure can also be read there.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
For this purpose, the oil-filled and vented hydraulic-oil lines are pressurized with operating
pressure through switch-on of the pump. Weld seams, screw joints and connections to pumps,
hydraulic cylinders and control elements are especially critical locations.
Unright locations can be recognized by a sizzling noise. To this end, the compressed-air lines
are pressurized. Weld seams, screw joints and connections to pneumatic cylinders and control
elements are especially critical locations.
To this end, the water-filled and vented water lines are pressurized through switch-on of the
pump. Weld seams, screw joints and connections to nozzles and control elements are
especially critical locations.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
To this end, the grease-filled and vented grease lines are pressurized through switch-on of the
pump. Screw joints and connections to grease metering blocks and control elements are
especially critical locations.
Also see the test features: Grease Systems, Control and Function.
To this end, the oil-filled and vented oil-lubricating lines are pressurized through switch-on of the pump.
Weld seams, screw joints and connections to control elements are especially critical locations.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXX
Enclosures:
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
3.0 - GENERAL
INSTRUCTION FOR
COLD
COMMISSIONING &
NO-LOAD TESTS
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Warning!
In compliance with current safety regulations, only personnel
involved in assembly or erection works is admitted to the site
before the commencement of no-load (cold) tests. The safety
instructions in Volumes A, B, C, D, E, as well as all applicable local
safety and accident prevention rules must be strictly observed
when executing any works.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Lubrication
The first step is to start up all central lubrication systems and to make sure that all manually
served lube points have been adequately fed with lubricant.
Interlocking Conditions
Before cutting in any of the motors, all interlocking conditions against lube oil starvation and
potential damage to or destruction of any of the machines must be effective.
Cutting-in of Motors
After cutting in, all of the drive motors should be allowed to operate in their lower speed
range for a certain time and only then be gradually accelerated to maximum operating
speed.
− Trained personnel only have been assigned to their job areas throughout the mill
− Roll grooves have been set in strict conformity with the applicable roll pass design
− All mill guides have been correctly adjusted
− Tools such as hammers, crowbars, wrenches, ratchets, transport facilities, hand
torches etc. are available in sufficient quantities
− Tongs for transporting test pieces as well as hook chains, ring chains and ropes are
available in adequate quantities
− All rolls have been cleaned from preservation agents and grease
− All auxiliary drives and all main drives have been correctly adjusted
− Spare parts, especially rolls and mill guides, are available in sufficient number
− Centralized lubrication and hydraulic systems are at operating temperature
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Checks:
Prior to commencement of any of the no-load tests, checks must be made to confirm
unobjectionable completion of erection and maintenance work, for instance:
• Have all switching elements (limit switches, rotary cam switches, light barriers, level
switches etc.) been set such that they will act in the positions as required to thereby
interlock or release other functions?
• Have all bolted joints on flanges, pipe attachments, especially universal shafts,
couplings and other moving elements and anchoring been duly tightened down?
• Have machine components, especially skid ways, rails, rollers and rolls as well as
piston rods been carefully cleaned from preservation agent residues and impurities?
• Have all lube points been checked to see that lubricant has been provided in adequate
amount? If not so, regreasing has to be effected in accordance with applicable
Lubricating Instructions.
• Pillow block bearings are to be opened up and filled with the appropriate amount of
grease.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Oil Changes:
Oil contained in splash-lubricated gearboxes will be changed in accordance with
manufacturers' maintenance instructions, see Components Manual C.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Warning!
Operations described are left to authorised qualified personnel.
- Check electric system conduits for compliance with cable and terminal plans
- Fill hydraulic fluid into tank making sure that the specified level will not be exceeded
- Open tank shutoff valve and evacuate air from suction line
- Fill each pump with hydraulic oil externally through leak oil connection
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- Check to see that interconnecting pipelines have been connected in compliance with
the applicable control diagram
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- Start recirculation pump, possibly evacuate air from such special units as filters,
cooler, heating system
- Cooler checks
• Water feed and water drain flow
• Thermostatic control function
- Evacuate air from interconnecting pipelines to special equipment units and filters
- Flush pipeline systems while watching filter clog up indicators and possibly change
filters
- Check quality
• Pollution, amount of fine-grained impurities
• Neutralization value
• Water content
• Chemical properties where deemed necessary
- Set pressure controllers and pressure relief valves on main pumps, incl. pressure test
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Preconditions:
Warning!
Operations described are left to authorised qualified personnel.
- Release mechanical equipment, make sure all hydraulic drives are in their safe end
positions
- All shut-off cocks on the upstream side of single functions or functional groups have
been closed
- Check to see that interconnecting pipelines have been connected in compliance with
applicable Control Diagram
- Check electric wiring for compliance with applicable cable and terminal plans
- Measure and test incoming electric control signals received by solenoid valve
(power, voltage)
- Test switching functions of all solenoid valves for any single function or functional
group
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- Start up control oil station and remove air from control oil line
Note: Hydraulic accumulator in control oil supply system remains shut off.
Note: Repeat actuation will facilitate air evacuation from pilot control
lines.
When valves are operated through emergency hand actuator, care will
be taken to ensure that no electric actuation can take place.
- Remove air from pipelines and cylinders in the places provided for this purpose
(Minimess couplings)
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- Test movements, especially movements into end positions (stroke etc.). It is a general
rule that the entire system will be checked for leaks at all time during work
performance.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Preconditions:
Warning!
Operations described are left to authorised qualified personnel.
- Check pipeline system for compliance with applicable Control Diagrams while
eliminating leaks at the same time.
- Fill oilers
- Set pressure
- Set operating speed and simultaneously test switching functions of solenoid valves
via emergency hand actuator after electric plugs have been pulled.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- All moving elements (pumps, pump drives, level switches) must be freely rotatable
and in a clean state (contaminations due to assembly and/or erection work must have
been removed)
- All limit switches, level switches etc. will be set in accordance with the special
instructions as applicable, and function-tested
- Before first starting a drive motor, same should be rotated by hand (if possible) to
make sure that freedom of movement is provided on the mechanical side
- Drive sense of rotation will then be checked by momentary jogging (observe the
instructions furnished by the manufacturers of individual units!)
- All oil tanks and filter elements are to be inspected for clean state and/or to be
cleaned where necessary prior to filling
- All fitted regulators have been checked for proper installation and setting
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- Check to see that all connections to consumers have been properly established
- Open discharge-side shutoff valves on pumps while opening slide valve in the bypass
line and closing slide valve upstream the oil cooler in the main line
- Start pumps
- Cooler checks
• Water feed and discharge system
• Thermostatic control
- Filter checks
• Clog up indicator
• Changeover unit
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Warning!
Operations described are left to authorised qualified personnel.
Cold Tests
- manual operation of machinery into final end position (single movements)
- supply units for grease and oil lubricants, coolant and hydraulic function correctly along
with internal interlocking systems.
- electrical drive units are properly adjusted before being coupled to motors
No-Load Test
- All movements connected with electrical drive units have been tested and properly
adjusted.
- Fault indication system, signals etc. have been fully tested.
- Entire manual and automatic modes have been tested and operated several times
without any fault occurring.
- Local control systems have been tested e.g. during roll change.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- On and off switching systems for all media systems including coolant have been tested
and function correctly.
- Cranes, personnel, repair tools and transport are in readiness.
- Safety measures have been taken as required.
Ghost rolling (simulation of the automatic process in the reversing mill area without
material) is intended as an aid in the commissioning phase as well as for testing new pass
schedules. The presence of material is simulated by activation of photoelectric cells. The
ghost rolling process can only be initiated when there is no material in the breakdown mill.
The conditions and interlocking conditions correspond to those for the "normal" automatic
mode.
After the No-Load Tests / Area Cold Tests have been executed, the Preconditions
for operation of individual units are given as follows:
Preheating Furnace
- The temperature of the furnace must be constant.
- The removal transport device must be ready for operation.
Descaler
- The descaler must have the correct water pressure as well as a controlled spraying
pattern.
- Upper spraying header positioned in accordance with the rolling schedule.
- Adjustable side guides and side spray headers set to the width of the bloom being
rolled.
Sideguard Manipulators
- Set movable side guards to groove center with clearance corresponding to pass
schedule
- Set tilting devices to starting position depending on profile requirements
- Take account of setting stroke depending on rolling direction.
Breakdown Stand BD
- The stand must be calibrated beforehand.
- All guides are allocated to program and set accordingly.
- The correct roll gap is set in accordance with pass schedule.
- The cooling water system is switched on.
- Complete set of reserve rolls with guides ready for use on roll-changing device.
- All media supply units are ready for operation.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Hot Saw
- Cropping saw is in starting position
- Media supply is ready for operation.
- Scrap guide is in the correct position for removal of scrap.
Roll cooling
The roll cooling system is not switched on until the tip of the bloom has left the stand. This
prevents the tip of the bloom from becoming too cold and makes it easier to grip the rolling
material.
Centering Devices
- The centering guides must be in the correct starting position for the material being
rolled.
- Before beginning two-high rolling operations, calibrations should be carried out for the
barrel length.
- The collision protection system is activated.
- The coolant supply system must be switched on.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
- The entire automatic process has been tested, along with the units in front of and
behind the tandem mill
- The coolant sprays are set at the correct angle
- The guides between the stands are correctly set
- The roll-changing equipment is ready for operation
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
Remark: machine working with high stresses caused by the centrifugal force of
rotating parts; routine non destructive tests by ultrasonic or magnetic-particle
methods are required to ensure that all rotating parts are in good order (see
Equipment and Maintenance Manual concerning VCC machine).
Containment rolls:
- idle cycle simulation
- check whether screws and bolts are tightened (at every product change)
Spider:
- idle cycle simulation
- check whether screws and bolts are tightened (at every product change)
Rotating table:
- idle cycle simulation
Coil car:
- idle cycle simulation
Billet conveyor:
- chain rotation test
- simulation with a coil to check limit stops positioning
For
- technical data of each unit
- functional description
- setting data
- interlocking conditions
- special requirements by first commissioning
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXX
General Instruction for Cold Commissioning & No- JOB ITEM XXXXX
Load Tests
D - General Instructions for Erection, No-Load CHAPTER SHEET REV.
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXXX
4.0 - ENCLOSURES
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXXX
4.0 Enclosures
4.1 List of Standards ................................................................................................................. 3
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX
CONTRACT N°
ONLY FOR REFERENCE XXXXXXX
Standards Description
XXXXX Property of SMS GROUP S.p.A; copy and disclosure of this document are prohibited XXXXX