You are on page 1of 2

Office of Electric Transmission and Distribution

Superconductivity
P ar tner ships with Industr y
tnerships
Plugging America Into the Future of Power

Project Fact Sheet


This project involves field-testing of a long-length WHAT ARE THE PROJECT ACCOMPLISHMENTS TO DATE?
HTS cable under real environmental stresses and real ULTERA was created as a partnership between U.S.
electrical loads. The cable system will form an impor- cable manufacturer Southwire and nkt cables of
Columbus HTS Power Cable

tant electrical link in a utility substation in Columbus, Germany, formed to continue the development and
Ohio, replacing conventional cables with limited eventual commercialization of HTS cables.
current-carrying capacity.
WHAT ARE ITS PRIMARY APPLICATIONS?
HTS power cables are used for electricity transmission
and distribution. The Columbus cable is a distribution
cable, conducting electricity within a local grid.
WHAT ARE THE BENEFITS TO UTILITIES?
HTS cable, carrying three to five times more power
than conventional cable, can meet increasing power
demands in urban areas via retrofit applications,
eliminating the need to acquire new rights-of-way.
The new cable design incorporated in this project has
the potential to further reduce space requirements by
running all three phases of a power line through a single
cable. Power transmission in underground HTS cables A five meter section of triaxial cable being inserted into the
can substitute for overhead transmission lines when cryostat for laboratory testing.
environmental and other concerns prohibit overhead
installation. Exceptionally low losses made possible by The 200 meter cable project was awarded in late 2002.
HTS cable will enhance overall system efficiency, ULTERA will share the cost of the project with the
increase flexibility, and reduce electricity costs. U.S. Department of Energy. Project scientists, along
with Oak Ridge National Laboratory (ORNL), have
WHAT IS THE MARKET POTENTIAL? already performed extensive research on a new “tri-
As energy demands increase and environmental axial” cable design, and one and five-meter cables have
concerns heighten, underground HTS cable will been fabricated and tested. Research involving cable
provide the necessary alternative to meet power supply terminations, a challenging issue with a tri-axial cable,
needs. The development of commercially viable HTS and bend-testing of the cables continues.
transmission cable will allow U.S. industry to capture
The demonstration cable is expected to begin opera-
a large portion of the growing national market. In
tion in a utility substation by early 2006, and will serve
addition, international markets are estimated to be 10
a large section of the city of Columbus, Ohio, includ-
times larger than the U.S. market, and growing more
ing both residential and industrial customers. The
rapidly.
cable is being designed to operate at 13.2 kV and carry
Superconducting cables have the potential to create an up to 3,000 amps. Half of the length of the cable will
efficient “electricity superhighway,” much like the be run above ground, while the other half will be run
advent of fiber optic cable has aided the development through conduit below grade to simulate a common
of the “information superhighway.” cable application.

WHAT IS THE STATUS OF THE PROJECT?


The project was awarded in 2002. ULTERA and ORNL have undertaken extensive testing on the triaxial cable
design, using a 5-meter prototype for termination design and testing. A 100-foot HTS cable developed in an
earlier Southwire/DOE partnership continues to supply reliable power to three Southwire manufacturing plants.

http://electricity.doe.gov Phone: 202 \ 586-1411

Office of Electric Transmission and Distribution, TD-1


U.S. Department of Energy – 1000 Independence Avenue, SW – Washington, DC 20585.
Goal:
Complete the development,
installation, and testing of a 200 The
cable
meter, 3-phase high-temperature
requires a cooling
superconducting (HTS) power system to refrigerate
cable at a substation in Colum- the HTS conductors to a
bus, Ohio. The project will temperature at which resis-
demonstrate how a triaxial HTS tance is minimized, about 321
cable may be used in the future to degrees Fahrenheit below zero.
replace existing oil-filled under- To further reduce costs and alternating
The result of an earlier public-private partnership, current (AC) losses in the 3-phase power
ground copper cables and greatly
Southwire’s HTS cables have delivered 1,250 A to
increase the capacity of a power a manufacturing plant for over 25,000 hours.
line, Southwire has been investigating the
link. “tri-axial” design for a power cable. In this
The project builds on an earlier, very scheme, rather than having three indepen-
successful partnership between Southwire dent HTS cables comprising the three
Team: and DOE in which three 100-foot long phases, a single cable is constructed with
ULTERA (team leader) cables were constructed and installed above three electrically insulated layers of supercon-
American Electric Power ground in Carrollton, Georgia. These cables ductor built around the same axis.
(host utility) exceeded design goals by over 100 percent, Southwire believes the new design will reduce
and began delivering power to three the cooling load of the system, and having
Oak Ridge National Laboratory Southwire manufacturing plants on February concentric phases will also lead to reduced
(supporting technology and 18, 2000. That system has been in continu- electro-magnetic fields. In addition, the new
research) ous operation and has run unsupervised at design will require only about half of the
100 percent load for over 25,000 hours. superconducting materials required by the
Integrations Concepts
Recent analysis of the system showed no earlier design and will take up less space,
Enterprises (power controls) since a single cable will perform the job of
significant degradation in the conductivity of
the HTS wire over that time. In addition to what previously required three separate
Period of incorporating a new design, the new project cables.
Performance: will carry about twice the current of the
4/2002-7/2006 earlier pilot project.
HOW DOES IT WORK?
Cumulative Project Conventional conductors of copper or
Funding: aluminum are replaced by HTS wire,
Private $4.32 million (50%) enabling the cable to carry greater amounts Graphical depiction of the triaxial cable design.
DOE $4.32 million (50%) of current with fewer losses due to resistance.
Total: $8.65 million Like its predecessor, the cable will be a
ALIGNMENT WITH ADMINISTRATION “cryogenic dielectric” cable design in which a
PRIORITIES: central former is wrapped with three HTS
What is it? National Energy Policy: “ …expand the layers of tape and electrical insulation. The
A power cable is designed to carry Department’s research and development on entire assembly is then insulated and jacketed
large amounts of electrical current transmission reliability and superconductivity” to protect it from thermal and physical
over short or long distances. National Transmission Grid Study: “ … damage. The cable is cooled by passing
accelerate development and demonstration liquid nitrogen through the hollow central
former along the length of the cable, which is
Information of its technologies, including high-tempera-
ture superconductivity… then returned through gaps in an outer layer
Contact: of the cable assembly.
Secretary of Energy: “… focuses R&D
David Lindsay, ULTERA
dollars on long-term, potentially high- The cable is expected to lose only
(770) 832-4916 payoff activities that require Federal about a half of a percent of the
david_lindsay@southwire.com involvement to be both successful and power it transmits, com-
Jonathan Demko, ORNL achieve public benefit.” pared to the 5–8 percent
(865) 574-1469 Energy Information Administration: “Of lost by traditional
[advanced power delivery] technologies, power cables.
demkoja@ornl.gov
superconductivity holds the most promise
for yielding significant efficiency gains.”

REVISION DATE: 5/28/04 SUPERCONDUCTIVITY PROGRAM FOR ELECTRIC SYSTEMS

You might also like