COST VARIATION ITEM:-

Sl.No Variation/Item Dwg. No. Remarks

1) LT Room Size Increase TO accommodate panel and E-29


Dry transformer
2) LT room HVAC capacity increase. E-29

Splitting of Utility master Panel into sub panels Client confirmation


3) separate for Cooling Tower, Compressor, Chiller. E-06, E-15-1 required.

4) Splitting of Factory MCC Panel into sub panel sperate E-06, E-15-1 Client confirmation
for Air washer & Dock Levelors/Rolling shutters. required.

Overall revision of Utility Areas to accommodate LT


panels, DG Compressors, Evaporator , Cooling tower
Client confirmation
5) and chillers. (option including Making Utility RCC and required.
placing the Chillers and cooling towers on
Compressor and Evaporator room.

Others:-

Compressor Room size need to review and increase Compressor


1 Room size need
for feasible equipment positioning. to increase.

2
Evaporator Foundation (client scope) need to shift for
RO plant and pumps better positioning.

3
Outside area required for cooling tower and chillers
are more than planned area.

Utility area (LT, HT shed etc) exhaust fan provided in


transformer and DG area to avoid orientation in
4 Future expansion area however outdoor unit placed
in future expansion area to avoid positioning in front
side area.
answer cost up
recommended sizes

Present size - 5.75 X 5.75 m


recommended sizes Recommended size- 8.75 X 10.0 m

Evaporator foundation need to shift


by 1.2 m
Also pump room size need to increase
Present size - 5.75 X 5.75 m
Recommended size- 5.75 X 7.75 m
approx diemnsions

pls provide approx areas Present size - 6.0 X 8.3 m


requeirement Recommended size- 10.0 X 10.0 m

pls provide hand sketch