Maruyasu Design Changes (Tri)
4) Splitting of Factory MCC Panel into sub panel sperate E-06, E-15-1 Client confirmation
for Air washer & Dock Levelors/Rolling shutters. required.
Others:-
2
Evaporator Foundation (client scope) need to shift for
RO plant and pumps better positioning.
3
Outside area required for cooling tower and chillers
are more than planned area.