2. Concept submission
Based on load calculation, and process demand, different alternative ideas could
be generated for treatment lead to propose two or three alternative systems,
and then a comparison between proposals to select the best solution, taking into
consideration the location circumstances.
The best suitable system is proposed based on the location circumstances.
3. Schematic submission
Extracting from the concept submission, schematic step to study the different
configurations can be used to implement of the concept, aim to have simple,
lower power consumption, lower installation cost good and balanced operation
for the system.
The schematic submission is already done.
4. Progress submissions
Could be three or four submissions needed, to reach the final acceptance, and
denote the submission (issued for construction).
In our case, we did not pass the concept submission, same also for schematic
submission, only what received an un marked copy of the design dated 30-4 -
2017 consisted of four sheets, it was discussed in a meeting held at17 -5- 2017,
without having any of, load calculations or equipment performance parameters,
based on that, we issued a general comments regarding the documents received.
5. Drawings
5.1 Ground floor
One sheet is general & three in larger scale
There are many AC units, range from400 cfm, to5000 cfm, these units are hanged
from ceiling, however that the metal frame are awarded to the contractor, some
of these unit having larger weight more than to be accepted from the contractor,
that will lead to issue variation, we need a confirmation that weighs of all units
are located in design are coordinated with issued design of steel work that in
contractor hand, and no variation what so ever issued from his side regarding
that item
The AC units up to 6000 CFM can be easily installed ceiling suspended.
Typical details needed for:-
a. Duct penetration from roof to indoor and how rain sealing will attain.
Will be provided by HVAC contractor in shop drawings.
b. How to support one of those heavy units in the steel structure.
Details will be provided by HVAC contractor in shop drawings.
f. Behavior of side discharge fans against wind direction change how can
isolate intakes and discharge outlets from being affected by wind direction
back pressure.
Wind direction will not effect on HVAC system.
g. Precautions against sand storm.
The sand filter with pre filter is provided in all AHUs. Also sand trap & filter is
provided in all louvers.
h. Air balance for the ground floor as one space.
The air balancing is done by providing volume control damper in main & branch duct.
In addition to this the each supply air diffuser/grill is with damper. The return air duct
is also provided with damper.
i. Do we have any measure for sound pressure level inside the floor?
In the air-condition area the sound level should be less than 40db.
6. BOQ
More details needed since that intention is to award the contract as
premeasured contract.
7. Conclusion
We cannot accept what included in the last submission as issued for construction
we have to receive load calculation and main equipment parameters as output
from schematic submission was not implemented to make full review on