Professional Documents
Culture Documents
Engineering)
Points to evaluate condition / capacities of Engg installations & their suitability for the existing
production plan.Following are the observations & suggestions :
Air balancing & air changes of Prep, RF & Autoconer adjusted to cater machine heat.
- There is no ahu control system installed /working condition. Adjustment is being
done manully based on complain from prdn deptt. In exisitng system it is very
difficult to ensure consistent deptt conditions and may influence production yield
alonwith quality variations.
- Condition of air washers nozzles / eleminators is needs improvement & plant
efficiency seems to be low. Nozzles need immediate repair /replacement.
- Ahu are not having rotary air filters, existing screen filters may be replaced for better
plant efficiency and clean air circulation.
- Ahus fan housing conditions is poor at some of the area need immediate replacement,
Air capacity / air changes observed to be on lower side.
- Its better to re-calculated ahus installed air capacity, max permissible deptt load &
expected deptt heat load by proposed spin plan and corrective action can be taken
accordingly
It is suggested :
- In JASML Savio Polar Winding area immediate alternative arrangement has to be
made to cater existing heat load which may lead fly genration and failure of
electronics and electrical components.
- Immediate action required to operate ahus as per installed capacity. Detailed action
plan to be made in consultaion of plant manufacturer / other competent vendor to
optimize and start the possible repair activities.
- It is recommended to have ahu revamping plan with electronic control system as per
the m/c layout & deptt heat load for the proposed spin plans. Expected investment can
be evaluated with expert agency providing services in this area.
- Nozzles to be replaced & It is recommended to replace screen filters by installing
rotary air filters with plush type filter media / filter seal.
iv) Engineering Workshop: To optimized restructring for effcient and prompt work
delivery.
v) Power Plant : Fuel to steam ratio to be calculated, helath of Boilers and turbine to be
checked, condensate recovery, auxiliary power cost analysis.
viii) STP & Waste Disposal: To review feasibility of food waste disposal and implement
proposals
x) Electrical system
- Existing electrical system in combination to Gas Power Plant & BDT 11 kV power is
capable to handle the existing power plan. But few area to be revamped to improve
the system reliability. Details as follows:
- 11kV metering box has observed high moisture, we have to connect panel heater
along with silica gel to prevent the same.
- existing transformer need silica change in breather with oil test (BDV, Flash point,
KOH & Water content) and filtration based on test report result.
- We have to schedule yearly magger of all 11KV and 0.4kV Incomer cables from
transformer and Gas Generators with records to avoid any possible breakdown and
change in insulation value due to aging.
- Condition of power factor correction panels is very unsafe. Recommend to use
automatic power factor panel with adequate capacitor in combination to harmonics
filters in phased manner to improve the reliability of electrical system.
- It is recommended to check all joints and put straight joint ferule low voltage heat
shrinkable kit during Eid holidays where ever required.
- No Metering has installed in the panels it is recommended to install metering at every
DB to monitor power consumption and control the losses if any.
Gas Generator : Waste Heat can be used for chilling or heating water. Overall genrator
efficiency can be be improved by minimizing heat losses.
- We are not adequately practicing for energy efficiency.It has been observed that
lighting is on at many outside area in day time also, which can be switched off by
training and education at shop floor level people. Lighting inside plant area also
remains on which may be kept off while not working. Expected saving per annum is
$3500.
- All motors rewind greater than five times can be replaced in phased manner with
energy efficiency motor for Ring frame and humidification area first. Expected pay
back 2 years.
- All the material transport fan can be optimized and suitable frequency drives can be
connected for saving purpose.
- Motor Load and suction of all waste collection system including fibre deposit plants
to be optimised for energy saving purpose.
- All Autoconer machine suction pressure can be optimise for different count.
Expected saving $5000 per annum.
- All Blow Room, Carding, Draw frame, Autoconer leakage can be regularly arrested
to save energy losses.
- RF Exhaust trench can be used for Elgi yarn conditioning machine water pre
heating. Possibilities to be optimized.
- All Power distribution board live wiring & component which are not in use to be
removed to avoid distribution losses.