Professional Documents
Culture Documents
1. INPUTS
1.1 Material Properties
Unit weight of concrete γConcrete 24
Concrete compressive strength (C30) 24
Tensile strength of steel
for dia <20 mm grade 300 300
for dia >= 20mm grade 420 420
Ec=.043g 1.5
c
sqrt(fc') 24768
Es = 200000
Allowable bearing capacity (Ultimate bearing cap.)= 990
Type of founding material Rock
1.2 Relevant Superstructure Data
1.2.1.Dimensions
Clear RDWY width = 7.32
Girder Depth= Left Side 0.9
Girder Depth= Right Side 0.9
Slab Depth= 0.22
Total depth of supersturcture (Bot.of Gird.toTop of curb)= Left Side 1.1548
Total depth of supersturcture (Bot.of Gird.toTop of curb)= Right Side 1.1548
Average depth = 1.1548
Road Way Elevation= 1884.191
Footing Elevation= 1873.532
Bearing Depth= Left Side 0.067
Bearing Depth= Right Side 0.067
No of Girders= 4
Center to Center dist.b/n girders = Left Side 2.6
Center to Center dist.b/n girders = Right Side 2.6
Out to out deck width= 10.32
Span Length(C/C of supports)= Left Side 12.6
Span Length(C/C of supports)= Right Side 12.6
# of lanes= 2
Height of Parapet= 0.6
Left Span+Right Span= 25.2
Skewness of support meaured from line normal to span in deg 0
Width of bearing = Left Side 0.6
Width of bearing = Right Side 0.6
1.2.2.Loads
2. PIER SECTION
B1
TOTAL PIER WIDTH
G
G
Dpc
Dpc
L2 L1 L2
Dc Dc
C
TOTAL PIER WIDTH
G
Dpc
Dpc
L2 L1 L2
Dc Dc
C
h
h1
h2
h2
W1 Dc W1 b1 b1
Df
Df
Df
Wf LF
2.1.Section Proportioning
2.1.1.Preliminary Sections
Insert parameters Length (pier cap) (m) Width (pier cap) (m)-B1 Depth (pier cap) (m)--(Dpc)
9.2 1.2 1.2
Diameter of column (Dc) Width (bracing col.) (m)-(a) Depth (bracing col.) (m)-(b)
1 0.6 0.6
C/C of Column (m)--© b1 (m) w1(m)
5 0.5 0.9
L1 L2 Lf
6.00 1.600 7.000
h h1 h2
8.7840 9.5840 7.5840
3. LOADS ON PIER
3.1 Dead Load
3.1.1 Substructure load
Items W1 (KN) W2 (KN) W3 (KN)
Unfactored Load 317.95 0 0.00
3.1.2 Superstructure load
DLET= 942.60 KN
DLIT= 669.92 KN
Un balanced moment= 0.00 KNm
3.2 Live Load
LLET= 234.36 KN
LLIT= 803.43 KN
Un balanced moment= 420.29 KNm
3.3 Braking force
According to the specifications, the braking force shall be taken as the greater of
25 % of the axle weight of the design truck or design tandem
OR
5 % of the design truck plus lane load or 5 % of the design tandem plus lane load
The braking force is placed in all design lanes which are considered to be loaded in accordance with S3.6.1.1.1
and which are carrying traffic headed in the same direction.These forces are assumed to act horizontally at a
distance of 6ft above the road way surface in either logitudinal direction to cause extreme force effects.
Br= 162.50 KN
Resultant Breaking force along axes of pier
Br Tpier (KN) Br Lpier (KN)
0 162.5
3.4 Wind load(w)
PD=PB*(VDZ/VB)^2 S 3.8.1.2.1-1
VDZ=2.5VO*(V10/VB)*LN(Z/ZO) for Z>10m and VDZ=VB for h<=10m S 3.8.1.1-1
Z 10000 mm
VO= 13.2 km/hr table 3.8.1.1-1
VB= 160 km/hr S 3.8.1.1
V10= 160 km/hr
ZO= 70 mm table 3.8.1.1-1
PB= 0.0024 Mpa table 3.8.1.2.1-1
VDZ= 160 km/hr
PD= 2.4 Kpa
3.4.1 Wind load on superstructure
Wind load transverse to the superstructure
FTsuper = Pwt*(Hwind)*[(Lback+Lahead)/2]
Where:
Pwt= transverse wind presure value=PB (Use table S3.8.1.2.2-1)
Hwind=the exposed superstructure height
Lback=left span length
Lahead=right span length
Wind load along axes of superstructure (longitudinal direction)
FLsuper = PwL*(Hwind)*(Lback+Lahead)/no of fixed pier
The transverse and longitudinal pressures should be applied simultaneously
Resultant wind load along axes of pier
The transverse and longitudinal superstructure wind forces,which are aligned relative to
the superstructure axis, are resolved in to components that are alined relative to the pier axis
Load perpendicular to the plane of the pier:
FLpier=FLsuper*cos(Ѳskew)+FTsuper*sin(Ѳskew)
Load in the plane of the pier (parallel to the line connecting the columns):
FTpier=FLsuper*sin(Ѳskew)+FTsuper*cos(Ѳskew)
** The vertical wind load is calculated by multiplying a 0.00096 Mpa vertical wind pressure by
out-to-out bridge deck width. It is applied to the windward qarter-point of the deck only
limit states that donot include wind on live load. Also the wind attack angle must be
zero degrees for the vertical wind load to apply
W vert= =0.00096*Wdeck
9.91 kn/m
It is assumed that the center of the bridge is the point of no translation for thermal effects. Furthermore it is assumed that the force
caused by the deformation of both end spans are absorbed by the abutements .therefore only the force caused by the deformation of half
of the middle span acts on the pier.
Deformation of the Girders
For concrete α=10.8*10-6 (m/m/OC)
L= 6.30m
Δtemp= 20 O
C
Δlength= 0.0013608m
Detrmination of force acting on the pier
Bearing Pad Thickness= 0.081m
Bearing pad Shear modulus= 0.66Mpa
Bearing pad area= L=0.4 and W=0.45 0.36m2
Height of pier= 9.58m
TU= 2.79KN
qmax=2*V/(3*(B/2-e))
qmin=0 V/(B-2ex)*(L-2ey)
m
m
m
m
m
m
m
m
m
degree
m
m
OTAL BRIDGE WIDTH)
AR BRIDGE WIDTH)
L1 L2
Dc
C
TAL PIER WIDTH
L1 L2
Dc
C
b1
LF
S 3.8.1.1
PB= basic wind pressure specified in table 3.8.1.2.1-1
height of the structure at which wind load is calculated
Stable 3.8.1.2.2-1
wind load along axes of pier
WLpier [KN] * longitiudinal force is not applicable if the bearing is expansion
0.00
13.27
26.53
35.38
39.80
39.80
S 3.8.1.2.3
is force is resolved
dicular to the end
o the front elevation
S4.7.4.1
S 4.7.4.4 SC 3.10.9.2
S 3.10.9.2 S 3.4.1
S4.7.4.4
S 4.7.4.4-1
KN
KN
KN
KN
193.82
108.09
S 3.11 S 3.11.3
S3.12
on the substructure
ations and number of S3.12.2
STable 3.12.2.1-1
0.71
STRENGTH IIIa SERVICE I EXTREME EVENT I
0.9 1.00
1 1.00
1.5 1.00
0 1.00
0 1.00
0 1.00
1.4 0.30
0 1.00
0.5 1.00
oads
STRENGTH IIIa SERVICE I
848.34 942.60
602.93 669.92
0.00 234.36
0.00 803.43
286.16 317.95
0.00 0.00
0.00 0.00
257.32 285.91
31.10 34.56
338.69 376.32
2364.54 3665.06
Loads
STRENGTH IIIa SERVICE I
55.72 11.94
25.43 5.45
17.47 3.74
5.53 1.18
0.00 6.93
0.00 162.50
1.39 2.79
105.54 194.54
My)
STRENGTH IIIa SERVICE I
752.45 161.24
32.88 7.05
84.57 18.12
0.00 83.57
0.00 0.00
857.91 571.94
1727.81 841.92
Mx)
STRENGTH IIIa SERVICE I
564.34 120.93
218.31 46.78
73.24 15.69
23.18 4.97
0.00 83.57
0.00 1959.59
0.00 0.00
0.00 105.07
11.74 23.48
890.80 2360.08
table represents
e-fourths of the base width .in rock foundations.
B= 2.80
L= 7.00
exmax=3*B/8 1.05
eymax=3*L/8 2.63
=(emax-e)/emax*100
Design margin (%)-ey condition
72.92 OK !!
66.97 OK !!
89.67 OK !!
85.65 OK !!
75.47 OK !!
0.80
30.00
Design margin (%) Condition
91.31 OK !!
89.40 OK !!
80.03 OK !!
72.26 OK !!
89.61 OK !!
2 Live Loads
a) Design Truck Load : HL-93
1.20m
The positioning is arrived at by first determining the number of design lanes, which is the integer par
Then the lane loading, which occupies 3000 millimeters of the lane, and the HL-93 truck loading, wh
wheel spacing and a 600 millimeter clearance to the edge of the lane, are positioned with in each lane
3.6m
P P
B
A
The unfactored girder reactions for lane load and truck load reactions do not include dynamic load all
Also, the reactions do not include the ten percent reduction permitted by the Specifications for interi
with a truck pair in conjunction with lane loading.
4300 4300
Rp1= 1.66 P
Rp2= 0.18 P
4300 4300
Rp1= 0.18 P
Rp2= 1.66 P
4300 4300
7500 75
Rp1= -0.06 P
Rp2= 0.45 P
4300 4300
7500
4300 4300
7500
Rp1= 0.45 P
Rp2= -0.06 P
4300 4300
Rp1= 1.74 P
4300
4300
Rp2= 1.74 P
Therfore the maximum axial load for maximum bending moment becomes;
Rpmax= 1.74 P
Moment about CLN of pier: MCL= 0.52 P
Summary of Loads
Design truck load
IM= 0.33
Pwheel= 159.56 KN
The value of the unfactored uniformly distributed load which represents the girder lane load reaction
This load is transversely distributed over 3000mm and is not subject to dynamic load allowance.
Wwheel= Rlane/3m*0.9
35.15 KN
The next step is to compute the reactions due to the above loads at each of the four bearing locations.
at the interior girder locations but continuous over the exterior girders.use the lever arm method to d
The computations for the reactions with only Lane B loaded are illustrated below as an example The
respective reaction:
R4_B= 117.18 KN
R3_B= 307.40 KN
R2_B= 0.00 KN
R1_B= 0.00 KN
The following table summerizes the remaining live load reactions at girders.
Brg.width
0.6
0.6
TRANSVERSE ARRANGEMENT
1.80m
TRANSVERSE ARRANGEMENT
N/mm uniformly distributed in the longitudinal direction.Transversely, the design lane load shall be
hall be assumed to be uniformly distributed over a 3000-mm width. The force effects from
mic load allowance.
sign lanes, which is the integer part of the ratio of the clear roadway width divided by 3600 millimeters per lane.
e, and the HL-93 truck loading, which has a 1800 millimeter wheel spacing and which has a 1800 millimeter
ne, are positioned with in each lane to maximize the force effects in each of the respective pier components
3.6m
P P P
B 3m
ns do not include dynamic load allowance and are given on a per lane basis (i.e., distribution factor = 1.0).
ted by the Specifications for interior pier reactions that result from longitudinally loading the superstructure
0 4300
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
Rp2 0.3
0 4300
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
Rp2 0.3
uniform load on all spans,and reaction at interior piers only, 90 percent of the effect of two design trucks
ck and the rear axle of the other truck, combined with 90 percent of the effect of the design lane load.
ken as 4300 mm.
4300 4300
0 7500
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
Rp2 0.3
4300 4300
7500 7500
4300 4300
7500 7500
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
Rp2 0.3
4300
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
4300 4300
4300 4300
C/C of Brg x=
Location of Reaction from the face of the pier
Rp2 0.3
C/C of Brg x=
Location of Reaction from the face of the pier
Rp1 0.3
Rp2 0.3
1.84 P
266.60 KN
0.52 P
75.78KN-m
load(KN)
sents the girder lane load reaction is computed next.
ct to dynamic load allowance.
each of the four bearing locations.This is generally carried out by assuming the deck is pinned (i.e., discontinuous)
ers.use the lever arm method to determine reactions at the girders due to the truck and lane loading.
ustrated below as an example The subscripts indicate the bearing location and the lane loaded to obtain the
R4_A= 0.00 KN
R3_A= 0.00 KN
R2_A= 401.72 KN
R1_A= 22.86 KN
e load
Lane B
Variable name Reaction (KN)
R1_B= 0.00 KN
R2_B= 0.00 KN
R3_B= 307.40 KN
R4_B= 117.18 KN
RANGEMENT
sely, the design lane load shall be
h. The force effects from
0.6
on of Reaction from the face of the pier
m
m
ercent of the effect of two design trucks
f the effect of the design lane load.
4300
0.6
on of Reaction from the face of the pier
m
m
0 4300
0 4300
0.6
on of Reaction from the face of the pier
m
m
0.6
on of Reaction from the face of the pier
m
0.6
on of Reaction from the face of the pier
m
0.6
on of Reaction from the face of the pier
m
m
0.85
on of Reaction from the face of the pier
m
m
assuming the deck is pinned (i.e., discontinuous)
s due to the truck and lane loading.
location and the lane loaded to obtain the
PRELIMINARY DIMENSION
L (pier cap) W (pier cap) D (pier cap) D (pier cap end)
9.20 1.20 1.20 1.20
Dia.of column W (bracing col.) D (bracing col.) D (footing) (m) Total depth of supersturcture
1.00 0.60 0.60 0.80 1.15
C/C of Column L1 L2 a
5.00 6.00 1.60 2.60
h h1 h2 No of column in a pier
8.78 9.58 7.58 2.00
SAP INPUT
Grid Data
X 0 2.1 7.10 9.20 0.00
Z 0 0.80 5.38 8.98
Section property
Member Width/dia. Depth
Pier Cap 1.20 1.20
Column 1.00
Bracing 0.60 0.60
Summary Of Unfactored Load On Axes Of Pier
Vertical Force (Z-Axis)
Item Type Force Location
VDLET Dead Load 471.3 0.7
VDLIT Dead Load 334.96 3.30
LLET Live Load 117.18 0.70
LLIT Live Load 401.72 3.30
Dead1 Dead Load 7.2 0.125
COLUMN
COLUMN 1 COLUMN 2
COMBINATION AXIAL M1 M2 AXIAL M1 M2
DESIGN LOAD 2292.18 1976.72 369.59 2381.60 1976.72 386.12
Assume a = 52.08 mm
As = Mu / ( Ø fy (d - a/2 ) ) 3,035 mm2
a= As*fy / ( 0.85 * fc' b ) = 52.08 mm
OK !!
Assume a = 18.45 mm
As = Mu / ( Ø fy (d - a/2 ) ) 1,076 mm2
a= As*fy / ( 0.85 * fc' b ) = 18.45 mm
OK !!
SPACING
0.125*fc' Smax (in) Smax 1 (in) Smax 2 (in) Spacing provided (mm)
0.435 9.116 247.313 12 231.551
Assume a = 23.44 mm
As = Mu / ( Ø fy (d - a/2 ) ) 683 mm2
a= As*fy / ( 0.85 * fc' b ) = 23.44 mm
OK !!
Assume a = 23.45 mm
As = Mu / ( Ø fy (d - a/2 ) ) 683 mm2
a= As*fy / ( 0.85 * fc' b ) = 23.44 mm
OK !!
Before the nominal shear resistance can be calculated all the variables used in the above equations need to be calculated.
Fv= b= bv [in] h [in] dv [in]
0.9 2 23.62 24 20.33
Now, Vn1 and Vn2 can be calculated:
Vn1 [Kn/m] Vn2 [Kn/m] Use Vn [Kn/m]
56.61 417.826 56.61
Since Vu < The Nominal Shear resistance,Transverse reinforcement is not required
SPACING
0.125*fc' Smax (in) Smax 1 (in) Smax 2 (in) Spacing provided (mm)
0.435 #DIV/0! 278.227 8 #DIV/0!
3.4.5 Check Minimum Temperature and Shirinkage reinforcement (S5.10.8)
Reinforcement for shrinkage and temperature stress is provided near the surfaces of the concrete exposed to daily temperature
changes and in structural mass concrete.Temperature and shrinkage reinforcement is added to ensure that the total reinforcement on
exposed surfaces is not lessthan that specified below.
For members less than 1.2m millimeters thick, the area of reinforcement in each direction shall not be spaced greater than
300mm and satisfy the lesser of As>=0.75Ag/fy or SumAb=0.0015Ag
Ag=mm2 fy=Mpa 0.75Ag/fy [mm2/mm] 0.0015Ag [mm2/mm] As [mm2/mm]
360000 420 642.857142857143 540 642.857142857143
The above steel must be distributed equally on both faces of the pier cap
Required Area of steel per face= 321.43 mm2
using dia= 12 mm
No of bars per face= 3
As provided= 339 mm2
Ok
mm Sequation5.7.3.6.2-2
N/mm2
mm
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
1200 60.00 1116
24
31.968
mm C/C 132 mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
S 5.7.3.4
neutral axis.
n Use n=
8.07 8.00
m the neuteral
As [mm2/mm] y [mm]
4.07150407905 877
mm Sequation5.7.3.6.2-2
N/mm2
mm
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
1200 50.00 1128
mm C/C 216 mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
S 5.7.3.4
neutral axis.
n Use n=
8.07 8.00
m the neuteral
As [mm2/mm] y [mm]
1.88495559215 958
(S5.8.3.3-1)
(S5.8.3.3-2)
(S5.8.3.3-3)
(S5.8.2.9)
endicular to the
(S5.8.3.4)
o increase the
crete strength
n S5.8.2.9 (in)
a distance d
calculated.
Vc(k) Vs
245.37 131.04
daily temperature
total reinforcement on
greater than
stributed along both face
de of the face is
0.33
mm2 7408.333333
ent is required
e main flexural steel.
to the lesser of 1.2 times S5.7.3.3.2
mm Sequation5.7.3.6.2-2
N/mm2
mm
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
600 50.00 528
mm C/C 120 mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
S 5.7.3.4
neutral axis.
n Use n=
8.07 8.00
m the neuteral
As [mm2/mm] y [mm]
1.57079632679 425
to the lesser of 1.2 times S5.7.3.3.2
mm Sequation5.7.3.6.2-2
N/mm2
mm
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
600 50.00 528
mm C/C 120 mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
S 5.7.3.4
neutral axis.
n Use n=
8.07 8.00
m the neuteral
As [mm2/mm] y [mm]
1.57079632679 425
(S5.8.3.3-1)
(S5.8.3.3-2)
(S5.8.3.3-3)
(S5.8.2.9)
endicular to the
(S5.8.3.4)
o increase the
crete strength
n S5.8.2.9 (in)
a distance d
calculated.
Vc(k) Vs
56.61 0
daily temperature
total reinforcement on
greater than
3.2 Dimensions
Center to center of column (C/C)= 5000 mm
Column diameter= 1000 mm
Footing pad top cover= 50 mm Stable 5.12.3-1
Footing pad bottom cover= 75 mm Stable 5.12.3-1
Back fill depth= 1000 mm
MOMENT
M1x M2x
1976.72 1976.72
MOMENT
M1y M2y
369.59 386.12
3594.503
M = 321.315985638017 KNM
Vwl = 610.00 KN
Assume a = 29.93 mm
As = Mu / ( Ø fy (d - a/2 ) ) 1,454 mm2
a= As*fy / ( 0.85 * fc' b ) = 29.93 mm
OK !!
Assume a = 118.72 mm
As = Mu / ( Ø fy (d - a/2 ) ) 5,766 mm2
a= As*fy / ( 0.85 * fc' b ) = 118.71 mm
OK !!
Assume a = 30.76 mm
As = Mu / ( Ø fy (d - a/2 ) ) 1,494 mm2
a= As*fy / ( 0.85 * fc' b ) = 30.76 mm
OK !!
Before the nominal shear resistance can be calculated all the variables used in the above equations need to be calculated.
Fv= b= bv [mm] h [mm] dvy [mm]
0.9 2 7 1 255.46
Now, Vn1 and Vn2 can be calculated:
Vn1 [Kn/m] Vn2 [Kn/m] Use Vn [Kn/m]
1454.24 10729.3724070673 1454.24
OK !!
ii ) For transverse face (Y-axis): (S5.8.3.3)
For one - way action, the shear resistance of the footing of slab will satisfy the requirements specified in S5.8.3
Vrx = fVn (S5.8.2.1-2)
Vws (KN) fc' [Mpa] fy a (mm) dsx (mm)
1180.00 24 300 30.76 715.00
Before the nominal shear resistance can be calculated all the variables used in the above equations need to be calculated.
Fv= b= bv [mm] h [mm] dvx [mm]
0.9 2 1000 800 699.62
Now, Vn1 and Vn2 can be calculated:
Vn1 [Kn/m] Vn2 [Kn/m] Use Vn [Kn/m]
568954.41 4197734.89864819 568954.41
OK !!
9.1.2 Determine Two - way punching shear capacity at the column : (S5.13.3.6.3)
I ) Nominal Shear force:
For two way action for section without transverse reinforcement, the nominal shear resistance,Vn in kips of the concrete
shall be taken as:
Vn= (0.063+0.126/bo)*fc'*bodv < =0.126fc'bodv (S5.13.3.6.3-1)
Where:
bo= ratio of long side to short side of the rectangular through which the concentrated
load or reaction force is transmitted
= (column equivalent length)/(column equivalent width)
(Notice,for circular column this ratio equals to one)
dv= average effective shear depth ( in )
= (dvx + dvy)/2
bo= perimetre of the critical section ( in ),the critical section is 0.5*d from the reaction area (S5.13.3.6.1)
II ) 7.3.4 Shear Capacity of the concrete:
Vr = 0.9*Vn
Design Shear force for punching 314.732493117475 k
OK !!
stable 3.5.1-1
S5.4.2.1
SC 5.4.2.1 Stable C5.4.2.1-1
S5.4.3
of the base area
ntial settlement.
t equal to the lesser of 1.2 times S5.7.3.3.2
mm Sequation 5.7.3.6.2-2
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
800 75 693
mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
[5.7.3.4]
[5.5.3]
mm Sequation 5.7.3.6.2-2
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
800 50 734
mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
t equal to the lesser of 1.2 times S5.7.3.3.2
mm Sequation 5.7.3.6.2-2
N/mm2
mm
D [ mm ] cover [ mm ] d [ mm ]
800 75 715
mm
0.85 S.5.7.3.3.1
24 N/mm2 S5.7.2.2
420 N/mm2 S5.7.3.3.1
urfaces of concrete
y temperature changes
s provided at the top of the
sed to satisfy
d perpendicular to the
in S5.8.3
d to be calculated.
Vc Vs
1454.24 0.00 S5.8.3.4.1
in S5.8.3
d to be calculated.
Vc Vs
568954.41 0.00 S5.8.3.4.1
ps of the concrete
action area (S5.13.3.6.1)
Vn (k) Vr (KN)
1020.91 918.8223764