Purpose
Use this procedure to open or Create Project.
Prerequisites
To open the project it should be created
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Via Transaction Code CJ20N
Procedure
Page 1 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
Page 2 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Purpose
Use this procedure to open Project and if anything want add we can add here.
Prerequisites
To open the project it should be created
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Via Transaction Code CJ20N
Procedure
2. Click on work list here last five project will displayed.
Page 3 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on the last created project the following screen will be displayed
Field Name R/O/ C User Action and Values Remarks
Start Date and R Give the Project Definition Enter
Finish date
Profit Center O Give The required project center NA
for the Project
Control Tab O Result Analysis Key Z9999
Page 4 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 5 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 6 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
You have changed the project.
Purpose
Use this procedure to Create the WBS BOM
Prerequisites
To the WBS BOM WBS element need to created.
Transaction Code
CS71
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CS71.
Page 7 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Via Menus Logistics or Acct> Project System > documents > document
management system > Environment > Bill of Material >WBS
BOM > Single Level
CJ20N
Via Transaction Code CS71
Procedure
Click on enter
Page 8 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
You have Created the WBS BOM.
Page 9 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
You have Created the WBS BOM.
Purpose
Use this procedure to Assign Material Component in project
Prerequisites
FG Material should be created
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
Builder
CJ20N
Procedure
Page 10 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on enter
Page 11 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Check the Requirement Date click on radio button and give the date if required manualy
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
You have Changed the Project.
Purpose
Use this procedure to Plan the dates in project
Prerequisites
NA
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Page 12 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Via Menus Logistics or Acct> Project System > Project > Project
Builder
CJ20N
Procedure
Page 13 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 14 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 15 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 16 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 17 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
You have Changed the Project.
Purpose
Use this procedure to Allocate the Project Budget.
Prerequisites
To allocation the project budget the material and activities should created.
Transaction Code
CJ30
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Financials >
Budgeting > Original Budget > Chage
Procedure
Page 18 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 19 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
and save
Page 20 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Document ---- is posted."
Result
You have post the project budget.
Purpose
Use this procedure to release the Project Budget.
Prerequisites
To release the project budget the allocated the project budget .
Transaction Code
CJ32
Page 21 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Financials >
Budgeting > Original Budget > Release
Procedure
Page 22 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 23 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
and save
Page 24 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Document ---- is posted."
Result
You have post the project budget.
Purpose
Use this procedure to Release the Project.
Prerequisites
NA
Transaction Code
CJ20N
Page 25 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Procedure
Page 26 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on save
Click on ‘Save’. The system displays the message, "Changes has been made."
Result
Page 27 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 28 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 29 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Purpose
Use this procedure to confirm the network activities of Project.
Prerequisites
NA
Transaction Code
CN25 for Individual and CN27 is collective
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CN25 and CN27
Procedure
Page 30 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Page 31 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on save
Page 32 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on Save
Click on ‘Save’. The system displays the message, "Changes has been made."
Page 33 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Purpose
Use this procedure to Techo the Project.
Prerequisites
Project Released
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Procedure
Page 34 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on set
Click on Save
Click on ‘Save’. The system displays the message, "Changes has been made."
Page 35 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Purpose
Use this procedure to close the Project.
Prerequisites
Project Teco
Transaction Code
CJ20N
Procedure Steps
Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Procedure
Page 36 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:
Click on ‘Save’. The system displays the message, "Changes has been made."
Page 37 of 37