Title: END TO END PROCESS

My SAP: Transaction Documentation


TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

1. Create or Open The Project CJ20N

Purpose
Use this procedure to open or Create Project.

Prerequisites
 To open the project it should be created

Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Via Transaction Code CJ20N

Procedure

1. Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter
WBS Element O NA NA
Network O NA NA

Page 1 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on Enter the following will be displayed

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result

Page 2 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

You have changed the project.

2. Change or Open The Project CJ20N

Purpose
Use this procedure to open Project and if anything want add we can add here.

Prerequisites
 To open the project it should be created

Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N
Via Transaction Code CJ20N

Procedure
2. Click on work list here last five project will displayed.

Page 3 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on the last created project the following screen will be displayed
Field Name R/O/ C User Action and Values Remarks
Start Date and R Give the Project Definition Enter
Finish date
Profit Center O Give The required project center NA
for the Project
Control Tab O Result Analysis Key Z9999

Page 4 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Check the Network assignment Tab

Page 5 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Create WBS element for the Project click on

Field Name R/O/ C User Action and Values Remarks


Level R Give the Level of the WBS
element Enter
WBS Element R EEPL-010000111-10-01 NA
Description R Description of the WBSE It will created with WBSE
description
Planning, Acct, O Click on Check box
billing Element

Page 6 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result
You have changed the project.

3. Create the WBS BOM CS71

Purpose
Use this procedure to Create the WBS BOM
Prerequisites
 To the WBS BOM WBS element need to created.

Transaction Code
CS71

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CS71.

Page 7 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Via Menus Logistics or Acct> Project System > documents > document
management system > Environment > Bill of Material >WBS
BOM > Single Level
CJ20N
Via Transaction Code CS71

Procedure

Field Name R/O/ C User Action and Values Remarks


WBS Element R EEPL-010000111-10-01 NA
Material R P2-RAKSCR-FS-316-0010-0405 NA
Plant R 1002 NA
BOM Usage R 1 NA

Click on enter

Page 8 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result
You have Created the WBS BOM.

Page 9 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result
You have Created the WBS BOM.

4. Assign The FG Martial component in Project C20N

Purpose
Use this procedure to Assign Material Component in project
Prerequisites
 FG Material should be created

Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.

Via Menus Logistics or Acct> Project System > Project > Project
Builder
CJ20N

Via Transaction Code CJ20N

Procedure

Field Name R/O/ C User Action and Values Remarks


Project Definition R EEPL-010000111 NA
Material R P2-RAKSCR-FS-316-0010-0405 NA
Required Quantity R 1 NA
Item Category R L NA

Page 10 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on enter

Page 11 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Check the Requirement Date click on radio button and give the date if required manualy

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result
You have Changed the Project.

5. Change the Activities date Planning C20N

Purpose
Use this procedure to Plan the dates in project
Prerequisites
NA
Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.

Page 12 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Via Menus Logistics or Acct> Project System > Project > Project
Builder
CJ20N

Via Transaction Code CJ20N

Procedure

Field Name R/O/ C User Action and Values Remarks


Project Definition R EEPL-010000111 NA

Click on dates tab

Page 13 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Give the Dates and enter or use the

Page 14 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

The following screen is displayed

By using the connecter

Page 15 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Network Cost Calculation In Project Builder:.

Page 16 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Cost Activity Adding.

Page 17 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result
You have Changed the Project.

6. Budget Allocation For the Project CJ30

Purpose
Use this procedure to Allocate the Project Budget.

Prerequisites
 To allocation the project budget the material and activities should created.

Transaction Code
CJ30

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Financials >
Budgeting > Original Budget > Chage

Via Transaction Code CJ30

Procedure

Page 18 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

3. Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter
WBS Element O NA NA
Currency O NA NA

Click on Enter the following will be displayed

Page 19 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Give the Plan Value or more and click on

and save

Page 20 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Document ---- is posted."

 You have completed this transaction.

Result
You have post the project budget.

7. Budget Release For the Project CJ32

Purpose
Use this procedure to release the Project Budget.

Prerequisites
 To release the project budget the allocated the project budget .

Transaction Code
CJ32

Page 21 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Financials >
Budgeting > Original Budget > Release

Via Transaction Code CJ32

Procedure

Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter
WBS Element O NA NA
Currency O NA NA

Click on Enter the following will be displayed

Page 22 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Page 23 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Give the Current budget click on

and save

Page 24 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Document ---- is posted."

 You have completed this transaction.

Result
You have post the project budget.

8. Release the Project CJ20N

Purpose
Use this procedure to Release the Project.

Prerequisites
 NA

Transaction Code
CJ20N

Page 25 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N

Via Transaction Code CJ20N

Procedure

Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter

Click on Enter the following will be displayed

Page 26 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on save

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.

Result

Page 27 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

You have changed the project.

Project Report Act/ Plan/com/ total S_ALR_8701342

Page 28 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Budget Report S_ALR_87013557

Page 29 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

9. Confirm Network activities CJ25

Purpose
Use this procedure to confirm the network activities of Project.

Prerequisites
 NA

Transaction Code
CN25 for Individual and CN27 is collective

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CN25 and CN27

Procedure

Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Network R Give the Network Enter
Activity R Activity Number

Page 30 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Page 31 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on save

Page 32 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on Enter the following will be displayed

Click on Save
Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.


Result

Page 33 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

You have changed the Network.

10.Teco (Technically Completion) Project CJ20N

Purpose
Use this procedure to Techo the Project.

Prerequisites
 Project Released

Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N

Via Transaction Code CJ20N

Procedure

Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter

Click on Enter the following will be displayed

Page 34 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on set

Click on Save
Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.


Result

Page 35 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

You have changed the project.

11.Close Project CJ20N

Purpose
Use this procedure to close the Project.

Prerequisites
 Project Teco

Transaction Code
CJ20N

Procedure Steps

 Start the transaction using the Menu Path or Transaction code: CJ20N.
Via Menus Logistics or Acct> Project System > Project > Project
builder
CJ20N

Via Transaction Code CJ20N

Procedure

Enter the required data.

Field Name R/O/ C User Action and Values Remarks


Project Definition R Give the Project Definition Enter

Click on Enter the following will be displayed

Page 36 of 37
Title: END TO END PROCESS
My SAP: Transaction Documentation
TEST BIRLA CELLULOSE RACK SCREENS
PROJECT:

Click on ‘Save’. The system displays the message, "Changes has been made."

 You have completed this transaction.


Result

You have changed the project.

Page 37 of 37