You are on page 1of 1

Energy and Power / Power Substation

Testing and Commissioning of


Current Transformer
By Edvard October, 19th 2012

Testing
Testing and
and Commissioning
Commissioning of of Current
Current Transformer
Transformer
(on
(on photo
photo two
two current
current transformers
transformers in
in MV
MV cubicle;
cubicle; by
by
alcatelmacedonia @ Flickr)
alcatelmacedonia @ Flickr)

Testing and Commissioning


Procedures //
1. Objective
2. Test Equipment Required
3. Test procedures

1. Mechanical Check and Visual


Inspection
2. Insulation Resistance Test
3. Polarity Test
4. Secondary/Loop Resistance Test
5. Burden Test (optional test)
6. Magnetization Curve Test (optional
test)
7. Turns Ratio Test (optional test)
8. Primary Injection Test
9. High Voltage Test
10. Commisioning Test
4. Applicable Standards
5. Live VIDEO CT Testing (6 Testings)

1. Objective

To confirm the physical condition and


electrical characteristics of current
transformer installed in the installation.
Ensure the CT is connected to system
properly in all respect (primary and
secondary).

2. Test Equipment Required

Required equipment for testing:

1. Insulation tester
2. Polarity tester
3. Digital low ohmmeter
4. Current source, multimeter
5. Variac, step-up transformer (0-2kv)
6. Primary current injection set

Go to Content ↑

3. Test Procedures

3.1. Mechanical Check and Visual Inspection

1. Verify nameplate ratings are in


accordance with the approved
drawings and specifications.
2. Inspect for physical damage/ defects
and mechanical condition.
3. Verify correct connection of
transformers with system
requirements.
4. Verify that adequate clearances exist
between primary and secondary
circuit wiring.
5. Verify tightness of accessible bolted
electrical connections by calibrated
torque-wrench method.
6. Verify that all required grounding and
shorting connection provided.
7. Verify all shorting blocks are in correct
position, either grounding or open as
required.
8. Verify single point grounding of
eachcore done properly. Grounding
point shall be nearer to the CT
location. However grounding shall be
at relay point in case of several CT
secondaries connected together like
differential protection.

Go to Content ↑

3.2. Insulation Resistance Test

The voltage shall be applied between:

1. Primary to secondary plus ground


(covered during switchgear test).
2. Secondary to primary plus ground.
3. Secondary core to core.

Test voltage limits mentioned in table


below. The ambient temperature shall be
noted down during test.

Table – Test Voltage Limits

Rated voltage Test voltage


100-1000V 1000V DC
AC/DC
>1000 to 5000V 5000V DC

Go to Content ↑

3.3. Polarity Test

Polarity test is to confirm the polarity


marking on the CT primary and secondary
and verify it is matching with drawing.
More ever it is giving an idea, how to
connect the secondaries to make the
protection (like directional, differential) and
metering function properly.

Isolate CT secondary from the load and


make circuit connection as shown in
Figure 1.

Close and open the battery switch


connected on the primary. Observe the
pointer is moving +ve direction, while
closing and –ve direction while opening
for correct polarity.

Figure
Figure 11 –– CT
CT Polarity
Polarity
Test
Test
Go to Content ↑

3.4. Secondary / Loop Resistance Test


(optional test)

Secondary resistance test is to verify the


CT secondary winding resistance with
specified one and no discontinuity in the
winding. This value can be used in other
calculations.

Loop resistance to ensure load is


connected properly and circuits not left
open. The circuit connection shall be made
as shown Figure 2 for secondary
resistance. Measure the dcresistance
value and record. The same shall be done
for all taps and cores. These values are
influenced by temperature, so ambient
temperature must be recorded during this
test. The circuit connection shall be made
as shown Figure 2 for loop resistance.

Measure the dc resistance including CT


and load, phase by phase and values can
be compared between them.

Limits:

The value must be with in specified on


nameplate after the effect of temperature
taken in to account. If not factory test
results shall be taken as reference.

Figure
Figure 22 –– CT
CT resistance
resistance // Loop
Loop Resistance
Resistance Test
Test

Notes:

Ohmmeter connection for CT


resistance excluding burden.
Ohmmeter connection for CT loop
resistance including burden.

Go to Content ↑

3.5 Burden Test (optional test)

Burden test is to ensure the connected


burden to CT is with in the rated burden,
identified on the nameplate.

Injected the rated secondary current of the


CT, from CT terminals towards load side
by isolating the CT secondary with all
connected load and observe the voltage
drop across the injection points. The
burden VA can be calculated as

Burden VA = Voltage drop x rated CT


sec. Current.

Limits:

The calculated burden should be less than


rates CT burden.

Note:

Ammeter selector switch should be at


respective phase during test.
High impedance relays shall be
shorted during the test.

Go to Content ↑

3.6. Magnetization Curve Test (optional test)

Magnetization Curve test is to confirm the


magnetisation characteristics of CT with
nameplate specification.

This test shall be conducted before ratio


test and after secondary resistance and
polarity test, since residual magnetism left
in the core due to DC test (polarity,
resistance), which leads additional error in
ratio test. The meters used for this test
shall be having true RMS measurement.

The circuit connection shall be made as


shown Figure 3. The primary should be
open during test.

Demagnetisation

Before start the test demagnetise the core


by Inject voltage on secondary terminals
and increase up to where considerable
increment in current with small voltage
increment. Now start decreasing the
voltage to zero, the rate at which
increased.

Magnetisation test

Now increase the voltage and monitor the


excitation current up to the CT reaching
near to saturation point. Record the
reading of voltage and current at several
points. Plot the curve and evaluate the Vk
and Img from the graph.

Limits:

Class X CT:
The obtained Vk should be greater than
specified one; mag current should be less
than specified one.

Protection class CT:


The secondary limiting voltage can be
calculated as follow:

Vslv = Is * ALF (Rct + (VA/Is*Is))

Where:
Is – rated secondary current
Rct – CT secondary resistance
VA – rated CT burden
ALF – Accuracy limit factor

The mag current (Img) drawn at Vslv can


be obtained from graph. The following
criteria should be satisfied.

Img < accuracy class * ALF * Is

Metering Class CT:


Accuracy can be ensured as follow:

Img at Vs (= 1.2 * VA / Is) should be less


than (accuracy class * Is)

And instrument security factor to be


verified.

Figure
Figure 33 –– Magnetisation
Magnetisation Test
Test
Go to Content ↑

3.7. Turns ratio Tests (optional test)

This test is to ensure the turn’s ratio of CT


at all taps. The circuit connection shall be
made as shown Figure 4. The primary
current of minimum of 25% rated primary
current to be injected on primary side of
CT with secondaries shorted and the
secondary current can be measured and
recorded for all cores.

Limits:

The obtained turn’s ratio should match with


rated nameplate ratio.

Go to Content ↑

3.8. Primary Injection Test

This test is to ensure the CT circuits are


properly connected with respected cores
and there is no mix up in the circuit (phase
identification).

The circuit connections shall be made as


shown in Figure 4. Single point grounding
shall be verified for CT circuits, before
starting this test. Inject 25% of rated
primary current between one phase and
earth with all connected burden. Measure
secondary current at all points of CT
circuits. It shall be done for other phases.

Core identification:

When one CT is having several cores


used for different purposes. The cores can
be identified during primary injection test
by shorting the one of the core at CT
terminal itself and check there isno current
only at relevant load. The same can be
verified for other cores.

Inject 25% of rated primary current


between phase to phase with all
connected burden. Measure secondary
current at all points of CT circuits. It shall
be done for other phases.

Limits:

Secondary current should only be


observed at respective phase and
neutral leads during Phase to earth
injection.
Secondary current should only be
observed at respective phases and no
current on neutral during Phase to
phase injection.

Figure
Figure 44 –– Primary
Primary injection
injection // Ratio
Ratio test
test
Go to Content ↑

3.9. High Voltage Test

This test is included with switchgear high


voltage.

Objective of HV test is to determine the


equipment is in propercondition to put in
service, after installation for which it was
designed and to give some basis for
predicting whether or not that a healthy
condition will remain or if deterioration is
underway which can result in abnormally
short life.

Test Instruments Required for HV Test

Calibrated AC hi-pot test set for switchgear


with leakage current indicator and overload
protection. Calibrated DC hi-pot test set for
cables with leakage current indicator and
overload protection.

Go to Content ↑

3.10. Commisioning Test

After commissioning, secondary current


measurement shall be carried out in CT
circuits. Phase angle check shall be done
for correct direction. Go to Content ↑

4. Applicable Standards

IEC 60044-1: Instrument transformers


– current transformer.
IEC 60694: common specifications for
HV switchgear.

Go to Content ↑

5. Live VIDEO CT Testing (6 Testings)

1. CT Tests – Ratio and Polarity

Cant see this video? Click here to watch it on Youtube.

2. CT Tests – Burden Secondary Side

Cant see this video? Click here to watch it on Youtube.

3. CT Tests – Excitation Curve

Cant see this video? Click here to watch it on Youtube.

4. CT Tests – Winding or Burden Resistance

Cant see this video? Click here to watch it on Youtube.

5. CT Tests – Voltage Withstand Test

Cant see this video? Click here to watch it on Youtube.

6. CT Tests – Polarity By Pulses

Cant see this video? Click here to watch it on Youtube.

Resource: Testing and Commissioning of


Electrical Equipment – Schneider Electric
Service Dpt.

Related EEP's content with sponsored


links

Premium Membership

Get access to premium HV/MV/LV


technical articles, electrical engineering
guides, research studies and much more! It
helps you to shape up your technical
skills in your everyday life as an electrical
engineer.

MORE INFORMATION

Edvard Csanyi

Electrical engineer,
programmer and
founder of EEP.
Highly specialized
for design of
LV/MV switchgears and LV high power
busbar trunking (<6300A) in power
substations, commercial buildings and
industry facilities. Professional in AutoCAD
programming.

12 Comments

Mohammad Kamruzzaman
JAN 01, 2020

Nice article. Very helpful


for me, thanks and wish
many more such articles.

Reply

JITHU RAJ
MAY 10, 2018

Very nice article.

Can anyone answer plz.


Why burden test is
mentioned to be optional?
and what is need of
shorting the high
impedance relay during
the test?

Reply

Shekhar
MAR 28, 2018

nice article

Reply

Himmat Gharat
AUG 14, 2017

I am JE of Nagbhir sub
station of 132/25 kv newly
electrified section and
testing started of current
transformer when test CT
ratio by injecting current in
primary bushing of old CT
which was 20 years old
CT installed in circuit,after
testing values not found
according to ratio,100
amps inject and found in
secondary terminal 3.9
amps please send me
solution.

Reply

Rajendar Rao Lade


JAN 01, 2018

First open links in jb


then measure ratio
,same repeat even after
links open directly
measure on secondary
across terminals ,if same
repeat primary terminals
have to be checked
properly (one should
earth another shouldn’t)
eventhough repeat …
have to replace

Reply

JEEVAN KUMAR
APR 20, 2015

I am a planning Engineer.
Recently I came in a
situation of our New
substation which is in
commissioning phase. I
was tasked to prepare a
detailed L7 schedule by
cubicles and activities. We
have a permanent grid
power source from an
existing substation. 2
incoming feeder from old
substation supply
permanent power to New
Substation.

I am wondering if there is
a sequence b/w various
steps mentioned above
and duration for each of
them, will help to plan a
detailed schedule and also
track them as well. Please
supports

Reply

AUSTINE CAESAR
APR 09, 2015

tHANKS FOr yoUR


VAluaBLE InfO OVer tTHE
yeARS MR. Edvard
Csanyi……

Reply

Abdul Ghaffar Soomro


JAN 29, 2015

Very helpful. Thanks Sir

Reply

Ankit051
AUG 24, 2013

sir i can’t download this


article because download
link is not available .plz
help me

Reply

Sunil De Silva
MAR 10, 2013

Yes, I am a Electrical
Engineer from SriLanka
and I have been reading
your valuable technical
Articles for more than one
year period and I have
learned a lot from them
and wish to add some
articles in the near future.
Thanks for your great
service.

Reply

Tarekdia
DEC 29, 2012

appreciate the article and


the vedios thanks very
much if you could include
the test formate please

Reply

Tanka
FEB 27, 2014

Can you provide me with


a test format or a
sample of test report
please.

Reply

Leave a Comment

Tell us what you're thinking... we care


about your opinion!

YOUR

REAL NAME *

EMAIL

ADDRESS *

I'm not a robot


reCAPTCHA
Privacy - Terms

SUBMIT COMMENT

© 2020 EEP - Electrical Engineering Portal. All

Rights Reserved | Privacy Policy | Terms of

Service

You might also like