Professional Documents
Culture Documents
Testing
Testing and
and Commissioning
Commissioning of of Current
Current Transformer
Transformer
(on
(on photo
photo two
two current
current transformers
transformers in
in MV
MV cubicle;
cubicle; by
by
alcatelmacedonia @ Flickr)
alcatelmacedonia @ Flickr)
1. Objective
1. Insulation tester
2. Polarity tester
3. Digital low ohmmeter
4. Current source, multimeter
5. Variac, step-up transformer (0-2kv)
6. Primary current injection set
Go to Content ↑
3. Test Procedures
Go to Content ↑
Go to Content ↑
Figure
Figure 11 –– CT
CT Polarity
Polarity
Test
Test
Go to Content ↑
Limits:
Figure
Figure 22 –– CT
CT resistance
resistance // Loop
Loop Resistance
Resistance Test
Test
Notes:
Go to Content ↑
Limits:
Note:
Go to Content ↑
Demagnetisation
Magnetisation test
Limits:
Class X CT:
The obtained Vk should be greater than
specified one; mag current should be less
than specified one.
Where:
Is – rated secondary current
Rct – CT secondary resistance
VA – rated CT burden
ALF – Accuracy limit factor
Figure
Figure 33 –– Magnetisation
Magnetisation Test
Test
Go to Content ↑
Limits:
Go to Content ↑
Core identification:
Limits:
Figure
Figure 44 –– Primary
Primary injection
injection // Ratio
Ratio test
test
Go to Content ↑
Go to Content ↑
4. Applicable Standards
Go to Content ↑
Premium Membership
MORE INFORMATION
Edvard Csanyi
Electrical engineer,
programmer and
founder of EEP.
Highly specialized
for design of
LV/MV switchgears and LV high power
busbar trunking (<6300A) in power
substations, commercial buildings and
industry facilities. Professional in AutoCAD
programming.
12 Comments
Mohammad Kamruzzaman
JAN 01, 2020
Reply
JITHU RAJ
MAY 10, 2018
Reply
Shekhar
MAR 28, 2018
nice article
Reply
Himmat Gharat
AUG 14, 2017
I am JE of Nagbhir sub
station of 132/25 kv newly
electrified section and
testing started of current
transformer when test CT
ratio by injecting current in
primary bushing of old CT
which was 20 years old
CT installed in circuit,after
testing values not found
according to ratio,100
amps inject and found in
secondary terminal 3.9
amps please send me
solution.
Reply
Reply
JEEVAN KUMAR
APR 20, 2015
I am a planning Engineer.
Recently I came in a
situation of our New
substation which is in
commissioning phase. I
was tasked to prepare a
detailed L7 schedule by
cubicles and activities. We
have a permanent grid
power source from an
existing substation. 2
incoming feeder from old
substation supply
permanent power to New
Substation.
I am wondering if there is
a sequence b/w various
steps mentioned above
and duration for each of
them, will help to plan a
detailed schedule and also
track them as well. Please
supports
Reply
AUSTINE CAESAR
APR 09, 2015
Reply
Reply
Ankit051
AUG 24, 2013
Reply
Sunil De Silva
MAR 10, 2013
Yes, I am a Electrical
Engineer from SriLanka
and I have been reading
your valuable technical
Articles for more than one
year period and I have
learned a lot from them
and wish to add some
articles in the near future.
Thanks for your great
service.
Reply
Tarekdia
DEC 29, 2012
Reply
Tanka
FEB 27, 2014
Reply
Leave a Comment
YOUR
REAL NAME *
ADDRESS *
SUBMIT COMMENT
Service