Professional Documents
Culture Documents
Chapter 6
Generation with Limited Energy Supply
Generation with Limited Energy Supply
Economic operation requires that expenditures for fuel be
minimized over a period of time
condition #1: no limitation on fuel supply
economic dispatch using only the present conditions as the data
condition #2: energy resources available at a particular plant is
a limiting factor in operations
economic dispatch calculations must account for what has
happened before and what will happen in the future
examples include limited fuel supplies, fix cost fuels, take-or-
pay contracts, surplus fuels, etc.
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 2
Generation with Limited Energy Supply
Take-or-pay fuel supply contracts
consider a system with N classical thermal plants and one
turbine generator fueled under a take-or-pay agreement
the utility agrees to use a minimum amount of fuel over a
contracted time period in order to purchase at a bulk price
if the utility fails to use the minimum amount, it agrees to pay
the minimum charge for the minimum amount
while this unit’s cumulative fuel consumption is below the
minimum, the system is schedule to minimize the total cost,
subject to the constraint that the total fuel consumption for the
period for this unit is equal to a specified amount
once the min. fuel amount is used, the unit is scheduled normally
as a simplification, we will let the maximum fuel consumption is
equal to the minimum amount
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 3
Generation with Limited Energy Supply
Take-or-pay fuel supply contracts
consider an N + 1 unit system with operation over jmax time
intervals, and let:
P1
Pij = unit i power output at time j F1 1
PT
Fij = cost for unit i for interval j P2 T FT
F2 2
qTj = fuel input for unit T at time j
FTj = cost for unit T for interval j
PN
Pload j = total load at time j FN 3 Pload
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 4
Generation with Limited Energy Supply
Take-or-pay fuel supply contracts
ignoring for the moment the generator limits, the term
jmax
∑n F
j =1
j T j
j =1 i =1 j =1 i =1 j =1
the independent variables are the powers Pij and PTj
∂L dFi k ∂L dqT k
= 0 = nk − λk i = 1K N and = 0 = γ nk − λk
∂Pi k dPi k ∂PT k dPT k
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 5
Generation with Limited Energy Supply
Take-or-pay fuel supply start
j =1
ε ≤ ktolerance end
time False True
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 6
Generation with Limited Energy Supply
Example
find the optimal dispatch for a gas-fired steam plant
HT(PT) = 300 + 6.0PT + 0.0025PT2 [MBtu/h]
50 ≤ PT ≤ 400
Frate = 2.0 $/ccf (1 ccf = 103 ft3)
Hrate = 1100 Btu/ft3
the plant must burn 40×106 ft3 of gas
composite of remaining generation
FS(PS) = 120 + 5.1PS + 0.0012PS2 [$/h]
50 ≤ PS ≤ 500
load pattern
0h - 4h: 400 MW, 4h - 8h: 650 MW, 8h - 12h: 800 MW
12h - 16h: 500 MW, 16h - 20h: 200 MW, 20h - 24h: 300 MW
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 7
Generation with Limited Energy Supply
Example
ignoring the gas constraint, the optimum economic schedule is
period PS PT
1 350 50
2 500 150
3 500 300
4 450 50
5 150 50
6 250 50
operating cost of the composite unit for the 24h period: $ 52,128
total gas consumed: 21.8×106 ft3 (at a cost of $ 80k / 40×106 ft3)
total cost: $ 132,128
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 8
Generation with Limited Energy Supply
Example
consider now the gas constraint
using the gamma search method, the γ value ranges from 0.5 to
0.875 with a final value of 0.8742 $/ccf
the optimum economic schedule is
period PS PT
1 197.3 202.6
2 353.2 296.8
3 446.7 353.3
4 259.7 240.3
5 72.6 127.4
6 135.0 165.0
operating cost of the composite unit for the 24h period: $ 34,937
total gas consumed: 40×106 ft3 (at a cost of $ 80k)
total cost: $ 114,937
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 9
Generation with Limited Energy Supply
Composite generation production cost functions
composite production cost curves are a useful technique to
mix fuel-constrained and non-fuel-constrained generation
combines N non-constrained units into an equivalent generator
FS (PS ) = F1 (P1 ) + F2 (P2 ) + K + FN (PN )
PS = P1 + P2 + K + PN
dF1 dF2 dF
= =K= N = λ
dP1 dP2 dPN
if one of the units hits a limit, its output is held constant
a simple procedure for generating FS(PS) consists of adjusting
λ from λmin to λmax, where
dFi dFi
λ min
= min , i = 1K N & λ = max
max
, i = 1K N
dPi dPi
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 10
Generation with Limited Energy Supply
Curve finding start
fit curve to
λα +1 ≥ λmax points of (PS, FS)
False True
end
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 11
Generation with Limited Energy Supply
Example
consider the three generation
units with the following cost
functions
F1 (P1 ) = 561 + 7.92 P1 + 0.001562 P12
150 ≤ P1 ≤ 600
F2 (P2 ) = 434 + 10.99 P2 + 0.002716 P22
100 ≤ P2 ≤ 400
F3 (P3 ) = 117 + 11.955P3 + 0.00723P32
50 ≤ P3 ≤ 200
combine the units into an
equivalent composite
generating unit and find
the equivalent cost function
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 12
Generation with Limited Energy Supply
Lambda Steps for Composite Cost Curve Equivalent unit input / output curve
λ
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 14
Generation with Limited Energy Supply
Two gradient methods start
from arbitrary PS schedule
compute FS(PS) and dFS/dPS
a simple search approach
assume feasible schedule for
does not require an PS and PT for all j = 1,…,jmax
initial feasible schedule calculate γj for j = 1,…,jmax
does not require an
ε = ∑ [n j qT j ] − qtotal
jmax
ε >0
False True
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 15
Generation with Limited Energy Supply
Two gradient methods from a feasible schedule
start
compute FS(PS) and dFS/dPS
a relaxation technique
calculate
requires an initial jmax
assume feasible schedule such that
jmax
Ftotal = ∑ n j FS j
dFS
feasible schedule j =1
∑ n j qT j = qtotal
j =1
& nj
dPS
= λj
requires an initial
feasible fuel usage calculate γj for select j+ and j– such that γj +
j = 1,…,jmax is maximum for j = j+ and
schedule γj – is minimum for j = j–
approach insures calculate new values
of γj for j+ and j– adjust q in j+ and j–,
optimality qT j + = qT j + ∆qj/nj, j = j+
qT j– = qT j – ∆qj/nj, j = j–
adjust PT j+, PT j–
calculate
∆ Ftotal ≤ ε ∆Ftotal = ∆FS j + ∆FS j
j= j+ j= j−
False True
end
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 16
Generation with Limited Energy Supply
Example
find the optimal dispatch for a gas-fired steam plant
HT(PT) = 300 + 6.0PT + 0.0025PT2 [MBtu/h]
50 ≤ PT ≤ 400
Frate = 2.0 $/ccf (1 ccf = 103 ft3)
Hrate = 1100 Btu/ft3
the plant must burn 40×106 ft3 of gas
composite of remaining generation
FS(PS) = 120 + 5.1PS + 0.0012PS2 [$/h]
50 ≤ PS ≤ 500
load pattern
0h - 4h: 400 MW, 4h - 8h: 650 MW, 8h - 12h: 800 MW
12h - 16h: 500 MW, 16h - 20h: 200 MW, 20h - 24h: 300 MW
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 17
Generation with Limited Energy Supply
Example
initial dispatch
period PS PT qTj γj
1 350 50 2.205 1.0454
2 500 150 4.568 1.0267
3 500 300 8.455 0.9240
4 450 50 2.205 1.0877
5 150 50 2.205 0.9610
6 250 50 2.205 1.0032
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 18
Generation with Limited Energy Supply
Example
iteration #1
period PS PT qTj γj
1 350 50 2.205 1.0454
2 500 150 4.568 1.0267
3 500 300 8.455 0.9240
4 312.8 187.2 5.493 0.9279
5 150 50 2.205 0.9610
6 250 50 2.205 1.0032
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 19
Generation with Limited Energy Supply
Example
iteration #2
period PS PT qTj γj
1 242.1 157.9 4.762 0.9204
2 500 150 4.568 1.0267
3 500 300 8.455 0.9240
4 312.8 187.2 5.493 0.9279
5 150 50 2.205 0.9610
6 250 50 2.205 1.0032
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 20
Generation with Limited Energy Supply
Example
iteration #3
period PS PT qTj γj
1 242.1 157.9 4.762 0.9204
2 360.6 289.4 8.167 0.8811
3 500 300 8.455 0.9240
4 312.8 187.2 5.493 0.9279
5 150 50 2.205 0.9610
6 250 50 2.205 1.0032
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 21
Generation with Limited Energy Supply
Example
iteration #17
period PS PT qTj γj
1 199.1 200.9 5.841 0.8760
2 353.7 296.3 8.355 0.8746
3 446.0 354.0 9.954 0.8735
4 260.0 240.0 6.851 0.8745
5 71.6 128.4 4.042 0.8731
6 135.3 164.7 4.932 0.8745
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 22
Generation with Limited Energy Supply
Example
iteration #18
period PS PT qTj γj
1 197.4 202.6 5.884 0.8743
2 353.7 296.3 8.355 0.8746
3 446.0 354.0 9.954 0.8735
4 260.0 240.0 6.851 0.8745
5 71.6 128.4 4.042 0.8731
6 135.3 164.7 4.932 0.8745
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 23
Generation with Limited Energy Supply
Example
iteration #19
period PS PT qTj γj
1 197.4 202.6 5.884 0.8743
2 353.7 296.3 8.355 0.8746
3 446.0 354.0 9.954 0.8735
4 260.0 240.0 6.851 0.8745
5 72.4 127.6 4.022 0.8740
6 135.3 164.7 4.932 0.8745
© 2002, 2004 Florida State University EEL 6266 Power System Operation and Control 24