You are on page 1of 16

Rate Analysis

Block Work
Item Unit Quantity
A) Materials:
Ecogreen Block Nos 78.00
Ultra Tech Chemical Bags 25.00
Sub-Total of Material (M)
B) Labour:
Supervisor Day 0.50
Mason Day 1.00
Helper Day 1.00
Sub-Total of Labour (L)
Totalfor
Add (M+L)
Sundries &
C) Contingencies 1.00%
Add W.C & Electricity 1.00%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)

Block Ecogreen
Chemical Ultra tech Block Bond

Note:- Ecogreen Block & Utra Tech Block Bond Chemical Rate Taken From Online.
is
Rate Amount.
(Rs.) (Rs.)

52.00 4056.00
18.75 468.75
4524.75

800 400.00
600 600.00
300.00 300.00
1300.00
5824.75
174.74
116.50
873.71
6989.70
6989.70
69.90

From Online.
Rate Analysis
Internal Plaster Work
Item Unit Quantity
A) Materials:
Cement Bags 0.84
Sand Ton 0.17
Sub-Total of Material (M)
B) Labour:
Supervisor Day 0.50
Mason Day 0.50
Helper Day 1.50
Water Man Day 0.50
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries &
C) Contingencies 1.00%
Add W.C & Electricity 1.00%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)

Rate Analysis
External Plaster Work
Item Unit Quantity
A) Materials:
Cement Bags 1.58
Sand Ton 0.28
Sub-Total of Material (M)
B) Labour:
Supervisor Day 0.50
Mason Day 1.50
Helper Day 2.5
Water Man Day 0.50
Scaffolding Sft 100
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries &
C) Contingencies 1.00%
Add W.C & Electricity 1.00%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)
Note : Cement And Sand Rate Take From AsPer Hill Town Site.
sis
Work Rate Amount.
(Rs.) (Rs.)

305.00 256.20
480.00 81.60
337.80

800 400.00
900 450.00
300.00 450.00
250.00 125.00
1300.00
1637.80
49.13
32.76
245.67
1965.36
1965.36
19.65

sis
Work Rate Amount.
(Rs.) (Rs.)

305.00 481.90
480.00 133.92
615.82

800 400.00
900 1,350.00
300 750.00
250.00 125.00
2.5 250
2875.00
3490.82
104.72
69.82
523.62
4188.98
4188.98
41.89
Rate Analysis
Putty Work( 2 Coat )
Item Unit Quantity
A) Materials:
Birla Putty(5mm Thick) KG 5.00
Sub-Total of Material (M)
B) Labour:
Belder Day 0.50
Sub-Total of Labour (L)
Total
Add for(M+L)
Sundries &
C) Contingencies 1.00%
Add W.C & Electricity 1.00%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)

Note : Birla Putty Rate Take From Online Sources.


sis
Coat ) Rate Amount.
(Rs.) (Rs.)

20.00 100.00
100.00

600 300.00
300.00
400.00
12.00
8.00
60.00
480.00
480.00
4.80
Rate Analysis
Paint Work
Item Unit Quantity
A) Materials:
Prime Coat
Prime Paint one coat Litre 0.50
Weather Sheild Paint 2 coat Litre 2.00
Sub-Total of Material (M)
B) Labour:
Painter Day 1.00
Male Coolie Day 1.00
Sub-Total of Labour (L)
Totalfor
Add (M+L)
Sundries &
C) Contingencies 1.00%
Add W.CSand
Brushes & Electricity
Paper Putty 1.00%
Etc.
Add for Scaffolding Ladder 5.00%
Etc. 2.50%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)

Rate Analysis
Paint Work
Item Unit Quantity
A) Materials:
Asian Brand
Primer Litre 0.50
Plastic Emulsion Paint Litre 1.25
Sub-Total of Material (M)
B) Labour:
Painter Day 1.00
Male Coolie Day 1.00
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries &
C) Contingencies
Brushes Sand Paper Putty 1.00%
Etc.
Add for Scaffolding Ladder 5.00%
Etc. 2.50%
Add W.C & Electricity 1.00%
Add for OH & C.P 15.00%
Total Amt.
Cost Per 100 Sqf (Rs.)
Cost Per 1 Sqf (Rs.)
Note : Weather Sheild PaintAnd Asian Brand Rate Take From Online Sources & Colour Distributor
sis
k Rate Amount.
(Rs.) (Rs.)

80.00 40.00
110.00 220.00
260.00

750 750.00
750.00 750.00
1500.00
1760.00
52.80
35.20
88.00
44.00
264.00
2244.00
2244.00
22.44

sis
k Rate Amount.
(Rs.) (Rs.)

80.00 40.00
237.50 296.88
336.88

750 750.00
750 750.00
1500.00
1836.88
55.11
91.84
45.92
36.74
225.00
2291.48
2291.48
22.91
ne Sources & Colour Distributor
Rate Analysis
1. Vitrified Work Rate Amount.
Item Unit Quantity (Rs.) (Rs.)
A) Materials:
Tile (600 mm X 600 mm) +
5% Wastage
Black cement for slurry Sft 100 30.00 3000.00
over base @ 3.3 Kgs/Sqm Bags 0.613 305.00 186.97
J.K White Cement K.G 0.5 17.00 8.50
Sand Ton 1.15 480.00 552.00
Cement Bags 3.8 305.00 1159.00
Sub-Total of Material (M) 4906.47
B) Labour:
Tile mason Day 0.5 800.00 400.00
Coolie (M) Day 0.5 300.00 150.00
Sub-Total of Labour (L) 550.00
Total (M+L) of Tiles
Add Carriage 5456.47
C) cement etc. for pointing
Add Mortar 0.50% 27.28
in White/colour
Add for sundirescement
i/e Tool 0.50% 27.28
& Plants & Contingencies 1.00% 54.56
Add W.C & Electricity 1.00% 54.56
Add for OH & C.P 15.00% 818.47
Cost 100 Sqf 6438.63
Cost Per Sqf 64.39

2. Marble Mosaic
Rate Amount.
Item Unit Quantity (Rs.) (Rs.)
A) Materials:
Marble Mosaicfor slurry
Black cement Sft 100 150.00 15000.00
over base @ 3.3 Kgs/Sqm Bags 0.613 305.00 186.97
Sand Ton 0.77 480.00 368.64
Cement Bags 2.5 305.00 762.50
Sub-Total of Material (M) 16318.11

B) Labour:
Tile mason Day 0.75 800.00 600.00
Coolie (M) Day 0.75 300.00 225.00
Sub-Total of Labour (L) 825.00
Total (M+L) of Tiles
Add Carriage 17143.11
C) cement etc. for pointing
Add Mortar 0.50% 85.72
in
AddWhite/colour
for sundirescement
i/e Tool 0.50% 85.72
& Plants & Contingencies 1.00% 171.43
Add W.C & Electricity 1.00% 171.43
Add for OH & C.P 15.00% 2571.47
Cost 100 Sqf 20228.86
Cost Per Sqf 202.29

3. Kota stone flooring

Rate Amount.
Item Unit Quantity (Rs.) (Rs.)
A) Materials:
Kota
BlackStone
cement for slurry Sft 100 45.00 4500.00
over base @ 3.3 Kgs/Sqm Bags 0.613 305.00 186.97
Sand Ton 0.78 860.00 666.50
Cement Bags 2.5 305.00 762.50
Sub-Total of Material (M) 6115.97

B) Labour:
Tile mason Day 0.75 800.00 600.00
Coolie (M) Day 0.75 300.00 225.00
Sub-Total of Labour (L) 825.00
Total (M+L) of Tiles
Add Carriage 6940.97
C) cement etc. for pointing
Add Mortar 0.50% 34.70
in White/colour
Add for sundirescement
i/e Tool 0.50% 34.70
& Plants & Contingencies 1.00% 69.41
Add W.C & Electricity 1.00% 69.41
Add for OH & C.P 15.00% 1041.14
Cost 100 Sqf 8190.34
Cost Per Sqf 81.90

4. Italian Marble
Rate Amount.
Item Unit Quantity (Rs.) (Rs.)
A) Materials:
Italian Marblefor slurry
Black cement Sft 100 230.00 23000.00
over base @ 3.3 Kgs/Sqm Bags 0.613 305.00 186.97
Sand Ton 1.15 480.00 552.00
Cement Bags 3.8 305.00 1159.00
Sub-Total of Material (M) 24897.97

B) Labour:
Tile mason Day 1 800.00 800.00
Coolie (M) Day 1 300.00 300.00
Sub-Total of Labour (L) 1100.00
Total (M+L) of Tiles
Add Carriage 25997.97
C) cement etc. for pointing
Add Mortar 0.50% 129.99
in
AddWhite/colour
for sundirescement
i/e Tool 0.50% 129.99
& Plants & Contingencies 1.00% 259.98
Add W.C & Electricity 1.00% 259.98
Add for OH & C.P 15.00% 3899.69
Cost 100 Sqf 30677.60
Cost Per Sqf 306.78

Note : All Type Of Tiling Rate Take From Online Sources & Colour Distributor

You might also like