Doc. Code - ISHU-LC&P-CON-RPT-0020 PROJECT DASHBOARD 020 - PERIOD M11.1 - FOR INTERNAL USE ONLY Date: 23/04/2020
Project Start Progress of Works (Earned Value) Certified Milestones Value (MCCs) Certified Milestones Value Paid (Drawdowns) Duration Details (Months) Project Completion Project Status
Contract: 10/6/2019 Planned: 23.75 % Planned: 47,877,291.00 $ Planned: 47,877,291.00 $ Project Duration: 27 Contract: 9/9/2021
Actual: 19.41 % Actual: 47,877,291.00 $ Actual: 33,297,925.50 $ Time Elapsed: 10.5 Delay on Completion: 0 Potential Delay
Final Design
Approval
30/10/2019
22 09/06/21 Hospital Building
Completed
Hospital 09-Jun-21
Building 33 15/05/21 Utilities N/W
M2
M2 09/06/21 Substantial Completion
Landscaping 20/5/2021
0.00
672,231.00
1,877,148.00
5,929,202.50
541,783.00
3,425,230.00
0.00
2,133,770.00
0.00
10,435,925.00
6,712,519.00
8,877,389.00
11,030,067.00
7,175,348.50
7,522,981.00
6,393,908.50
3,837,808.00
6,069,537.50
11,381,324.00
32,858,254.50
27,723,831.00
18,514,489.50
6,045,819.00
20,973,873.50
0.00
0.00
16,469,635.00
11 positions. Procedures are not being followed and rework
is often needed.
Planned The Contractor's schedule is extremely compressed with
Completed multiple critical or near critical paths, resources
22
Milestone Value requirements are extremely high. Delayed issue of IFC
drawings may worsen the situation.
0.00
97,461.00
1,046,580.00
953,368.50
5,158,437.00
5,189,748.00
412,335.00
1,721,435.00
487,305.00
129,948.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
procurement. Preventative measures taken by the loacal
government have considerably slowed down progress.
Milestones Completions Planned for following Period M11.2 Mil.4 5.1.a Order Confirmation acknowledged by manufacturer of Radiology & Imaging
125000000
(from 24/04/2020 to 09/05/2020) Mil.5 5.1.e Order Confirmation acknowledged by manufacturer of Cardiac Cath Lab
100000000
Mil.6 5.1.k Order Confirmation acknowledged by manufacturer of Intervention Radiology
75000000 19.41%
Mil.1 4.2.df Block F Substructures Mil.7 5.3.c Approval of Shop Drawings by Engineer for Radiotherapy Department + Cyclotron
50000000
Mil.2 4.3.j Nurses Hostel A Bulk Earthworks and Substructures Mil.8 4.2.b Block A Substructures
Mil.3 4.3.o Nurses Hostel B Bulk Earthworks and Substructures Mil.9 4.2.x Block B Substructures 25000000
Long Lead Procurement
Mil.4 4.4.a Recreation and Motel Bulk Earthworks Mil.10 4.2.ck Block E Substructures 0
43625
43655
43686
43717
43870
43899
44052
44083
44113
44236
44264
44295
44448
43747
43778
43808
43839
43930
43960
43991
44021
44144
44174
44205
44325
44356
44386
44417
Time
Mil.5 5.1.b Order Confirmation acknowledged by manufacturer of Nuclear Medicine 1 Lifts 29/11/2020
2 Transformers 15/01/2021
3 Generators 18/01/2021
Activities Carried out during Period M11.1 Activities Planned for following Period M11.2
5 WS Pumps 27/12/2020
(from 10/04/2020 to 23/04/2020) (from 24/04/2020 to 09/05/2020)
Reinforcement installation and form works for Hospital foundation Block A (rework due to Act.1 Ongoing Compaction, blinding concrete and waterproofing for hospital foundation for blocks E and F 6 Chiller 15/02/2021
Act.1
initial faulty concrete pour)
Act.2 Concrete pour at block A, rebar placements at Block B and E, concrete pour at Block B and E RFI MS SD 18 NCR IR 4 7 FAHU 15/02/2021
Act.2 Reinforcement installation and form works for Hospital foundation Block B Act.3 Appliances and furniture for the Engineer's site office to be completed TOT TOT TOT TOT 2 TOT 8 FCU 24/11/2020
Review/approval of revised Shop Drawings for Nurses hostel, Block C, D & F, method statements &
Act.3 Fabrication of Foundation's reinforcement and starter bars Act.4
risk assessments for other blocks. Prequalifactions of suppliers
271 2 177 11 90 9 Exhaust Fan 24/12/2020
Act.4 Applying water proofing primer and layer for Block Act.5 Lean concrete at Conference & Exhibition Center and Recreation & Motel NEW NEW NEW NEW NEW 10 CHW Pumps 15/01/2021
2 159 9 86
Act.5 Cleaning of temporary trench for drainage Act.6 Reviewing shopdrawings for 2nd Batching Plant 0 0 0 0 0 11 FF Pumps 19/12/2020
Act.6 Contruction Warehouse office Act.7 Procurement of materials for storm water drainage towards ZANA community 12 STP system 13/12/2020
Act.8 Shop drawings for storm water drainage outlets 13 Medical Equipments 14/01/2021
Act.9 Construction of water tank for office use, connected to borehole 14 FF&E 08/03/2021
Act.10 Excavation of Doctor's, Nurses and specialized training school buildings
Act.1 Installation of tower crane at Block B
7
13
29
Planned
Actual
Actual
331 367 438 486
26 26 44 44 29 29 24 24 34 34 100 37 88 244 168 32 21
12 12 12 6 14 0 0 0 69
Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21