You are on page 1of 28

Application of Tack Coat

Considered Qunatity : 300 m2


Assumptions:
1 Clean road surface before apply tack coat by manually.
2 Apply Tack Coat Just before Asphalt Concrete layer @ 0.5 Lts /m 2 Average

No. of No.of
Ref No. Labour Costs Rate (Rs) Amount (Rs)
Men Hours
Skilled labor 2 8.0 262.50 4,200.00
Unskilled labor 2 8.0 187.50 3,000.00
2.5% Of Plant cost for Tools 180.00
1 Sub-total for Labour 7,380.00

No. of No.of
Ref No. Equipment Costs Rate (Rs) Amount (Rs)
Units Hours
2 Bowser 1 6 1,360.00 8,160.00
Sub-total for Plant 8,160.00

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Emulsion ( CSS-1) L 150.0 60.00 9,000.00
3 Sub-total for Materials 9,000.00

4 Total Basic Costs : (1)+(2)+(3) 24,540.00


5 Profit & Overhead (4) × 28.0% 6,871.20
6 Total Cost (4)+(5) 31,411.20
7 Unit Rate (6)/Q Rs/ m2 104.70

Rs/m2 104.70
Unit Rate for Application of Tack Coat
US$/m2 0.70

Prepared by Checked by Approved by


Name
Designation
Signature
Date
Cleaning and Sand Sealing

100 m long x 3.0 m


Considerd Quantity : 300 m2
wide road
Assumptions :
1 sand Thickness is 8 mm
2 Considered additional 5% of materials for wastage during handling

No. of
Ref No. Labour Costs No.of Hours Rate (Rs) Amount (Rs)
Men
Skilled labor 2 8.0 262.50 4,200.00
Unskilled labor 5 8.0 187.50 7,500.00
2.5% Of Plant cost for Tools 292.50
1 Sub-total for Labour 11,992.50

No. of
Ref No. Equipment Cost No.of Hours Rate (Rs) Amount (Rs)
Units
5 ton truck 1 2 1,360.00 2,720.00
Roller (mannual) 1 12 500.00 6,000.00
2 Sub-total for Plant 8,720.00
Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Sand m3 2 6,713.78 13,427.56
MC 30 Cut back mt 300 98.00 29,400.00
3 Sub-total for Materials 42,827.56

4 Total Basic Costs : (1)+(2)+(3) 63,540.06


5 Profit & Overhead (4)× 28.0% 17,791.22
6 Total Cost (4)+(5) 81,331.28
7 Unit Rate (6)/Q Rs/ 1 m2 271.10

Rs/m2 271.10
Unit Rate for Cleaning and Sand Sealing
US$/m2 1.80

Prepared by Checked by Approved by


Name
Designation
Signature
Date
Construction of 200 mm thick Gravel Road
Considered area : 20m long, 2.5m wide, 200mm thick road section 50 m2
Assumptions :
1 Fill materials to be transported average 10 km
2 Material rate includes Supply, Loading, Transport cost up to stock pile and transport cost up to
work locations
3 Allowed 35% for compaction & 5% for wastage during double handling of materials

No. of No.of
Ref No. Labour Costs Rate (Rs) Amount (Rs)
Men Hours
Skilled labor 2 8.0 262.50 4,200.00
Unskilled labor 4 12.0 187.50 9,000.00
1 Sub-total for Labour 13,200.00

No. of No.of
Ref No. Equipment Cost Rate (Rs) Amount (Rs)
Units Hours
8000L water bowser 1 8 1,360.00 10,880.00
Dozer (forming Stock Piles
1 2 4,500.00 9,000.00
& initial Spreading)
Loader (1.7m3 capacity) 1 8 4,000.00 32,000.00
Grader (65 HP) 1 8 3,500.00 28,000.00
3 Cube tipper 1 4 1,450.00 5,800.00
10t roller 1 8 2,600.00 20,800.00

2.5 % for Tools Of plant cost 2,662.00

2 Sub-total for Plant 109,142.00

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Gravel m3 14.5 3,300.00 47,850.00
3 Sub-total for Materials 47,850.00

4 Total Basic Costs : (1)+(2)+(3) 170,192.00


5 Overheads & Profit (4) × 28.0% 47,653.76
6 Total Cost (4)+(5) 217,845.76
7 Unit Rate for 1 m2 (6)/Q Rs/m2 4,356.92

Rs/1 m2 4,356.92
Unit Rate for Construction of 200 mm thick Gravel Road
US$/ 1 m 2
28.94

Prepared by Checked by Approved by


Name
Designation
Signature
Date
Forming Shoulders (If imported materials used, appliable rate from BOQ is considered for material cost)

Considered Quantity : 3 m3 (loose volume)


1.85 m3 (compacted volume)
Assumptions:
1 Filling Thickness is 250 mm
2 If imported materials are used, the applicable rate in the Schedule of Contract Works is used.
3 Considered additional 5% of materials for wastage during handling
4 Considered additional 35% of materials for compaction
5 Considered quantity is loose volume

Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Unskilled labor 4 3.0 187.50 2,250.00
Add for Small tools
56.25
2.5% of Labour
2 Sub-total for Labour 2,306.25

Ref
Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.
JCB 1 2.0 2,720.00 5,440.00
Rammer - 60kg 1 2.0 1,100.00 2,200.00
8000L water bowser 1 1.0 1,360.00 1,360.00
Dump Truck 1 1.0 1,530.00 1,530.00
3 Sub-total for Plant 10,530.00

4 Total Basic Costs : (1)+(2)+(3) 12,836.3


5 Profit & Overheads (4) × 28% 3,594.16
6 Total Cost (4) + (5) 16,430.46
7 Unit Rate (6)/Q Rate for 1 m3 Rs/m3 8,881.33
Rate for 1 Cube Rs/Cube 25,134.16

Rs/1 m3 8,881.33
Unit Rate for Forming Shoulders (excluding cost of material)
US$/ 1m3 58.99

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Forming Settlement Joint in 100 mm Concrete Road Surface

Considered Quantity :
Considered 10 Joints In 4 m wide road 40 m

Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Skilled labor 1 2.0 262.50 525.00
Unskilled labor 2 2.0 187.50 750.00
Add for Small tools 2.5%
31.88
of Labour
1 Sub-total for Labour 1,306.88

Ref
Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.

2 Sub-total for Plant 0.00

Ref
Material Costs Qty Unit Rate (Rs) Amount (Rs)
No.
Styro foam boards 1mx1m
(25 mm thick) 1 Nos 544.00 544.00
Backer Rod 25 mm
diameter 40 m 68.00 2,720.00
X cellular PS800 Primer 0.35 L 7,000.00 2,450.00
Sealing compound 16 L 3,650.00 58,400.00

Add 5% of material cost for


loading unloading &
transport to warehouse and
to structure locations 3,205.70
3 Sub-total for Material 67,319.70

4 Total Basic Costs : (1)+(2)+(3) 68,626.58


5 Overheads & Profit (4)× 28.0% 19,215.44
6 Total Cost (4)+(5) 87,842.02
7 Unit Rate (6)/Q Rate for 1 m Rs/1 m 2,196.05

Unit Rate for Forming Settlement Joint in 100 mm Concrete Rs/1 m 2,196.05
Road Surface US$/ 1m 14.59

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Construction of M10 Rubble Masonry Retaining Walls without scaffolding
Considered Quantity : 01 cube
2.83 m³
Assumptions
01 Average Height up to 5 m
02 Weep Holes, Filter materials, Transverse & Vertical joint, Geo textile Measured separately
03 Material rate includes transport cost up to work location
04 Rate includes cost for forming vertical transverse surface.

Ref Amount
Labour Costs No. of Men No.of Hours Rate (Rs)
No. (Rs)
Skilled labor Mason 2 5.0 262.50 2,625.00
Unskilled labor 4 6.0 187.50 4,500.00
Unskilled labor (for Curing) 1 2.0 187.50 375.00
Small tools 2.5% of Labour 187.50
01 Sub-total for Labour 7,687.50

Ref Amount
Equipment Cost No. of Units No.of Hours Rate (Rs)
No. (Rs)
Mortar Mixer (Diesel) 1 5.0 1,200.00 6,000.00
Water Bowser including pump and
1 2.0 1,500.00 3,000.00
storage tank
JCB 1 3.0 2,720.00 8,160.00
02 Sub-total for Plant 17,160.00

Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
6'' ~ 9" Rubble Cube 1.1 8,250.00 9,075.00
Sand Cube 0.4 19,000.00 7,600.00
Cement (50 kg ) Bags bag 7 1,000.00 7,000.00
Curing Materials Item Sum 300.00
03 Sub-total for Materials 23,975.00

04) Total Basic Costs : (1)+(2)+(3) 48,822.5


05) Profit & Overheads : (4) × 28.0% 13,670.30
06) Total Cost : (4)+(5) 62,492.80
Unit Rate : (6)/QRate Rs for 1 Cube Rs/Cube 62,492.80
Rate Rs for 1 m 3
Rs/m3 22,082.26

Unit Rate for Construction of M10 Rubble Masonry Retaining Walls without Rs/1 m3 22,082.26
scaffolding US$/1 m3 146.67

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Construction of M10 Rubble Masonary Retaining Walls with scafolding
Considered Quantity 01 cube
2.83 m³
Assumptions
01 Average Height up to 5 m;
02 Weep Holes, Filter materials, Transverse & Verticle joint, Geo textile Measured separately
03 Material rate includes transport cost up to work location
04 Rate includes cost for forming vertical transverse surface.

Ref Amount
Labour Costs No. of Men No.of Hours Rate (Rs)
No. (Rs)
Skilled labor Mason 2 5.0 262.50 2,625.00
Unskilled labor 4 6.0 187.50 4,500.00
Unskilled labor( for curing) 1 2.0 187.50 375.00
Labour for erecting & dismantaling
scafolds
Unskilled labor 3 3.0 187.50 1,687.50
Small tools 2.5% of Labour 229.69
Scafolding 5% of Labour 459.38
01 Sub-total for Labour 9,876.57

Ref Amount
Equipment Cost No. of Units No.of Hours Rate (Rs)
No. (Rs)
Mortar Mixer (Diesel) 1 5.0 1,200.00 6,000.00
Water Bowser including pump and
1 2.0 1,500.00 3,000.00
storage tank
JCB 1 3.0 2,720.00 8,160.00
02 Sub-total for Plant 17,160.00

Ref
Material Costs Unit Qty Rate (Rs)Amount (Rs)
No.
6'' ~ 9" Rubble Cube 1.1 8,250.00 9,075.00
Sand Cube 0.4 19,000.00 7,600.00
Cement (50 kg ) Bags bag 7 1,000.00 7,000.00
Curing Materials Item Sum 300.00
03 Sub-total for Materials 23,975.00

04) Total Basic Costs : (1)+(2)+(3) 51,011.57


05) Profit & Overheads : (4) × 28.0% 14,283.24
06) Total Cost : (4)+(5) 65,294.81
07) Unit Rate : (6)/QRate Rs for 1 Cube Rs/Cube 65,294.81
Rate Rs for 1 m3 Rs/m3 23,072.37

Unit Rate for Construction of M10 Rubble Masonary Retaining Walls with Rs/m3 23,072.37
scafolding US$/ m3 153.24

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Grade 20 Concrete Rubble Retaining Wall

Considered Quantity : 10m long, 1.5m high, 1.3m thick retaining wall
Total volume : 19.50 m3
Grade 20 concrete volume 14.63 m3
Rubble volume : 4.88 m3

Assumptions :
1 Pouring to be done in step by Step with alternative rubble pack
2 75% C20 Concrete & 25 % Rubble by Volume

Materials for Grade 20 Design Mix for


Unit Quantity Rate Amount (Rs)
Concrete 14.63 m3 1 m3
Course Aggregate 0.625 m3 9.14 2756.18 25,191.49
Quarry Dust 0.301 m3 4.40 2756.18 12,127.19
River Sand 0.282 m3 4.13 6713.78 27,727.91
Cement 300 Kg 4,390.00 20.00 87,800.00
Admixtures 2.4 Kg 35.11 571.00 20,047.81
Water 150 L 2,195.00 1.00 2,195.00
Materials Cost sub total for 14.63 m3 175,089.40

Materials Cost for 4.88 m3


m3 4.88 2915.19 14,226.13
Rubble

Plant for Mixing 14.63 m3 Nr of PlantNr of Hrs Rate Amount (Rs)


Batching (Plant Ref Unit Rate) Annex -3 m3
Loader (1.7m3 capacity) 1 2 4,000.00 8,000.00
Plant Cost for mixing sub total for 14.63 m3 8,000.00

Labour for Mixing 14.63 m3 Nr of MenNr of Hrs Rate Amount (Rs)


Skilled Labour 1 2 262.50 525.00
Unskilled Labour 3 2 187.50 1,125.00
Labour Cost for mixing sub total for 14.63 m3 1,650.00

Plant for Transport 14.63 m3 Nr of Pl Nr of Hrs Rate Amount (Rs)


Transit Mixer 2 6 2,850.00 34,200.00
Plant Cost for Transport sub total for 14.63 m 34,200.00

Plant for Transport 4.88 m3 Rubble Nr of PlNr of Hrs Rate Amount (Rs)
Dump Truck (5 tonne) 1 2 2,300.00 4,600.00
Loader (1.7m3 capacity) 1 1 4,000.00 4,000.00
Plant Cost for Transport sub total for 4.88 m3 Rubble 8,600.00

Labour for Placing 14.63 m3 Gr 20 Con &Nr of MenNr of Hrs Rate Amount (Rs)
4.88 m3 Rubble
Skilled Labour 6 8 262.50 12,600.00
Unskilled Labour 12 8 187.50 18,000.00
Labour Cost for Placing 14.63 m3 Gr 20 Con & 4.88 m3 Rubble sub total 30,600.00

Plant for placing 14.63 m3 Gr 20 Con & Nr of PlantNr of Hrs Rate Amount (Rs)
4.88 m3 Rubble
Concreter Vibrator 1 8 1,900.00 15,200.00
Excavator 1 8 4,500.00 36,000.00
50 KVA Generator 1 8 884.00 7,072.00
Plant Cost for placing sub total for 14.63 m3 & 4.88 Rubble 58,272.00

Nr of MenNr of Hrs Rate Amount (Rs)


Labour for curing 19.5 m3 Retaining Wall
Unskilled Labour 2 8 187.50 3,000.00
Labour Cost for Curing sub total for 14.63 m3 3,000.00

Plant for curing 19.5 m3 Retaining Wall Nr of PlantNr of Hrs Rate Amount (Rs)

8000 lt Water Bowser 1 8 1,360.00 10,880.00


Plant Cost for Curing sub total for 14.63 m3 10,880.00

Total Cost For 19.50 m3 Retaining Wall for Mixing Transporting placing &
Curing 344,517.53 Rs
Add 28% profit & O H 96,464.91 Rs
Total cost for 19.50 m3 440,982.44 Rs
Unit Rate for 1 m3 Rs/ m3 22,614.48 Rs
Rs/Cube 63,998.98 Rs

Rs/ m3 22,614.48
Unit Rate for Grade 20 Concrete Rubble Retaining Wall
US$/ m3 150.20

Prepared by Checked by Approved by


Name
Designation
Signature
Date
Supplying & Fixing Styrofoam Boards for Transverse & Vertical Joints

Considered Quantity : 4.5 m2

No.of
Ref No. Labour Costs No. of Men Rate (Rs) Amount (Rs)
Hours
Skilled labor 1 1.0 262.50 262.50
Unskilled labor 1 1.0 187.50 187.50
Add for Scaffolding& Small
11.25
tools 2.5% of Labour
1 Sub-total for Labour 461.25

No.of
Ref No. Equipment Cost No. of Units Rate (Rs) Amount (Rs)
Hours

2 Sub-total for Plant 0.00

Ref No. Material Costs Qty Unit Rate (Rs) Amount (Rs)
Styrofoam boards 1mx1m (25
mm thick) 5 Nos 544.00 2,720.00
Backer Rod 25 mm diameter 8m 68.00 544.00
X celular PS800 Primer 0.07 L 7,000.00 490.00
Sealing compound 3.2 L 3,650.00 11,680.00

Add 10% of material cost for


loading unloading & transport to
warehouse and to structure
locations 1,543.40
3 Sub-total for Material 16,977.40

4 Total Basic Costs : (1)+(2)+(3) 17,438.65


5 Overheads & Profit (4)× 28.0% 4,882.82
6 Total Cost (4)+(5) 22,321.47
7 Unit Rate for 1 m2 (6)/Q Rs/m2 4,960.33

Unit Rate for Supplying & Fixing Styrofoam Boards for Rs/1 m2 4,960.33
Transverse & Vertical Joints US$/1 m2 32.95

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Forming of Weep Holes with 110mm dia PVC Type 1000 Pipes
Considered Quantity :
Retaining wall thickness - 2.0 m
No. of weep holes - 4
Total length of weep hoes - 8 m

No. of
Ref No. Labour Costs No. of Men Rate (Rs) Amount (Rs)
Hours
Unskilled labor 1 0.5 187.50 93.75

Add for Small tools 2.5% of Labour 2.34

1 Sub-total for Labour 96.09

No.of
Ref No. Equipment Cost No. of Units Rate (Rs) Amount (Rs)
Hours

2 Sub-total for Plant 0.00

Ref No. Material Costs Qty Unit Rate (Rs) Amount (Rs)

1 110mm dia type 1000 PVC Pipes add


5% for waste 8.4 m 1,450.00 12,180.00

Add 5% of material cost for loading


2 unloading & transport to warehouse
and to structure
locations( Scaffolding& Materials) 609.00
3 Sub-total for Materials 12,789.00

4 Total Basic Costs : (1)+(2)+(3) 12,885.09000


5 Profit & Overheads (4)× 28% 3,607.83
6 Total Cost (4)+(5) 16,492.92
7 Unit Rate (6)/Q Rs/m 2,061.62

Unit rate for Forming of Weep Holes with 110mm dia PVC Type 1000 Rs/m 2,061.62
Pipes US$/ m 13.69

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Grade 20 Concrete

Considered Quantity : 14.63 m3


Assumptions :
a Dry sand Density 1,680.00 kg/m3

b Coarse aggregate density 1,620.00 kg/m3


c Quarry dust density 1,730.00 kg/m3
d Average transport distance 6.00 km
e Volume of a concrete mixture truck 8.00 m3

Labour for batching of concrete


Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Skilled labor 1.00 2.00 262.50 525.00
Unskilled labor 3.00 2.00 187.50 1,125.00
Add for Small tools 2.5%
41.25
of Labour
1.00 Mixing Sub-total for Labour 1,691.25

Labour for placing of concrete


Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Skilled labor 6.00 8.00 262.50 12,600.00
Unskilled labor 12.00 8.00 187.50 18,000.00
Add for Small tools 2.5%
765.00
of Labour
2.00 Placing Sub-total for Labour 31,365.00

Equipment for batching of concrete


Ref
Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.
Loader (1.7m3 capacity) 1.00 2.00 4,000.00 8,000.00

3.00 Sub-total for Plant 8,000.00

Materials for batching of concrete


Ref
Material Costs Qty Unit Rate (Rs) Amount (Rs)
No.
Cement 4,390.00 Kg 20.00 87,800.00
Sand 4.13 m3 6,713.78 27,727.91
3/4 " Metal 9.14 m3 2,756.18 25,191.49
Quarry dust 4.40 m3 2,756.18 12,127.19
Admixures 35.10 Kg 571.00 20,042.10
Water 2,195.00 L 1.00 2,195.00
4.00 Sub-total for Material 175,083.69

Plant & Equipment for transport of concrete


Ref
Transport Costs No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.

Concrete mixture truck 2.00 6.00 2,850.00 34,200.00

5.00 Sub-total for Plant 34,200.00

6.00 Total Basic costs (1)+(2)+(3)+(4)+(5) 250,339.94


7.00 Overheads & Profit (4)× 0.28 70,095.18
8.00 Total Cost (6)+(7) 320,435.12
9.00 Unit Rate (8)/Q Rs/ 1m3 21,902.61
Rs/ 1 Cube 61,984.39

Rs/ 1 m3 21,902.61
Unit Rate for Grade 20 Concrete
US$/ 1 m3 145.47

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Grade 20 Concrete

Considered Quantity : 14.63 m3


Assumptions :
a Dry sand Density 1,680.00 kg/m3

b Coarse aggregate density 1,620.00 kg/m3


c Quarry dust density 1,730.00 kg/m3
d Average transport distance 6.00 km
e Volume of a concrete mixture truck 8.00 m3

Labour for batching of concrete

Ref No. Labour Costs No. of Men No.of Hours Rate (Rs)

Skilled labor 4.00 2.00 262.50


Unskilled labor 3.00 2.00 187.50
Add for Small tools
2.5% of Labour
1.00 Mixing Sub-total for Labour

Labour for placing of concrete

Ref No. Labour Costs No. of Men No.of Hours Rate (Rs)

Skilled labor 6.00 8.00 262.50


Unskilled labor 12.00 8.00 187.50
Add for Small tools
2.5% of Labour
2.00 Placing Sub-total for Labour

Equipment for batching of concrete

Ref No. Equipment Cost No. of Units No.of Hours Rate (Rs)

Loader (1.7m3 capacity) 1.00 4.00 4,000.00

3.00 Sub-total for Plant

Materials for batching of concrete

Ref No. Material Costs Qty Unit Rate (Rs)

Cement 4,390.00 Kg 20.00


Sand 4.13 m3 6,713.78
3/4 " Metal 9.14 m3 2,756.18
Quarry dust 4.40 m3 2,756.18
Admixures 35.10 Kg 571.00
Water 2,195.00 L 1.00
4.00 Sub-total for Material

Plant & Equipment for transport of concrete

Ref No. Transport Costs No. of Units No.of Hours Rate (Rs)

Concrete mixture truck 2.00 6.00 2,850.00

5.00 Sub-total for Plant

6.00 Total Basic costs (1)+(2)+(3)+(4)+(5)


7.00 Overheads & Profit (4)× 0.28
8.00 Total Cost (6)+(7)
9.00 Unit Rate (8)/Q Rs/ 1m3
Rs/ 1 Cube

Rs/ 1 m3
Unit Rate for Grade 20 Concrete
US$/ 1 m3

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Calculation of Rate for Grade 20 Concrete for Structures under Provisiona
Assumptions
1.00 Based on Mix Design SRP/G 20/CR -34
2.00 Estimated volume of Wall ( 10 m Long xxxxxxxxxx wide ,1.3 m High)
Gr 20 Concrete Volume

Materials for Gr
Design Mix for 1 m3 Unit
20 Con 14.63 m3

Course Aggregate 0.63 m3


Quarry Dust 0.30 m3
River Sand 0.28 m3
Cament 300.00 Kg
Admixtures 2.40 Kg
Amount (Rs)
Water 150.00 L
2,100.00 Materials Cost sub total for 14.63 m3
1,125.00

80.63

3,305.63 Plant for Mixing 14.63 m3 Nr of Plant


Batching (Plant Ref Unit Rate) Annex -3 m3
Loader 1.00
Amount (Rs)
Plant Cost for mixing sub total for 14.63 m3
12,600.00
18,000.00 Labour for Mixing 14.63 m3 Nr of Men
765.00
Chinese Skilled Labour 1.00
Skilled Labour 3.00
Unskilled Labour 3.00
Labour Cost for mixing sub total for 14.63 m3
Amount (Rs)

16,000.00 Plant for Transport 14.63 m3 Nr of Plant


7,200.00
23,200.00 Transit Mixer 2.00
Plant Cost for Transport sub total for 14.63 m

Amount (Rs)
Labour for Placeing 14.63 m3 Nr of Men
87,800.00 Chinese Skilled Labour 1.00
27,727.91 Skilled Labour 2.00
25,191.49 Unskilled Labour 12.00
12,127.19 Labour Cost for mixing sub total for 14.63 m3
20,042.10
2,195.00 Plant for Placeing 14.63 m3 Nr of Plant
175,083.69 Concreter Vibrater 1.00
Excavator 1.00
50 KVA Genarator 1.00
Amount (Rs)
Plant Cost for Placeing sub total for 14.63 m3
34,200.00

34,200.00 Labour for cureing 14.63 m3 Nr of Men


Chinese Skilled Labour 1.00
235,789.32 Unskilled Labour 3.00
66,021.01 Labour Cost for Cureing sub total for 14.63 m3
301,810.33
20,629.55
58,381.63 Plant for Cureing 14.63 m3 Nr of Plant
8000 lt Water Bowser 1.00
20,629.55 Plant Cost for Cureing sub total for 14.63 m3
158.69

Approved By

Total Cost For 14.63 m3 for Mixing Transporting Placeing & Cureing

Design Fee
Structures under Provisional Sum Works

xxx wide ,1.3 m High)


14.63 m3

Quantity Rate Amount (Rs)

9.14 3,072.00 28,078.08


4.40 2,756.00 12,126.40
4.13 6,714.00 27,728.82
4,389.00 20.40 89,535.60
35.11 571.00 20,047.81

2,194.50 1.00 2,194.50


179,711.21

Nr of Hrs Rate Amount (Rs)


14.63 2,312.00 33,824.56
2.00 4,000.00 8,000.00

41,824.56

Nr of Hrs Rate Amount (Rs)

2.00 1,200.00 2,400.00


2.00 283.00 1,698.00
2.00 212.00 1,272.00
5,370.00

Nr of Hrs Rate Amount (Rs)

6.00 2,856.00 34,272.00


34,272.00

Nr of Hrs Rate Amount (Rs)


4.00 1,200.00 4,800.00
4.00 283.00 2,264.00
4.00 212.00 10,176.00

Nr of Hrs Rate Amount (Rs)


4.00 1,900.00 7,600.00
4.00 4,500.00 18,000.00
4.00 884.00 3,536.00

Nr of Hrs Rate Amount (Rs)


21.00 1,200.00 25,200.00
21.00 212.00 13,356.00

Nr of Hrs Rate Amount (Rs)


21.00 1,360.00 28,560.00

nsporting Placeing & Cureing 261,177.77


Grade 40 Concrete

Considered Quantity : 14.63 m3


Assumptions :
a Dry sand Density 1,680.00 kg/m3
b Coarse aggregate density 1,620.00 kg/m3
c Quarry dust density 1,730.00 kg/m3
d Average transport distance 6 km
e Volume of a concrete mixture truck 8 m3

Labour for batching of concrete


Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Skilled labor 1 2.0 262.50 525.00
Unskilled labor 3 2.0 187.50 1,125.00
Add for Small tools 2.5%
41.25
of Labour
1 Mixing Sub-total for Labour 1,691.25

Labour for placing of concrete


Ref
Labour Costs No. of Men No.of Hours Rate (Rs) Amount (Rs)
No.
Skilled labor 6 8.0 262.50 12,600.00
Unskilled labor 12 8.0 187.50 18,000.00
Add for Small tools 2.5%
765.00
of Labour
2 Placing Sub-total for Labour 31,365.00

Equipment for batching of concrete


Ref
Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.
Loader (1.7m3 capacity) 1 2.0 4,000.00 8,000.00
3 Sub-total for Plant 8,000.00

Materials for batching of concrete


Ref
Material Costs Qty Unit Rate (Rs) Amount (Rs)
No.
Cement 5,560.00 Kg 20.00 111,200.00
Sand 3.99 m3 6,713.78 26,787.98
3/4 " Metal 9.25 m3 2,756.18 25,494.67
Quarry dust 4.24 m3 2,756.18 11,686.20
Admixure 37.31 Kg 571.00 21,304.01
Water 2,340.00 L 1.00 2,340.00
4 Sub-total for Material 198,812.86

Plant & Equipment for transport of concrete


Ref
Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
No.
Concrete mixture truck 2 6.0 2,850.00 34,200.00
5 Sub-total for Plant 34,200.00

6 Total Basic Costs : (1)+(2)+(3)+(4)+(5) 274,069.11


7 Overheads & Profit (6)× 28.0% 76,739.35
8 Total Cost (6)+(7) 350,808.46
9 Unit Rate (8)/Q Rs/ 1 m3 23,978.71
Rs/ 1 Cube 67,859.75

Rs/ 1 m3 23,978.71
Unit rate for Grade 40 Concrete
US$/ 1m 3
159.26

Prepared by Recommended By Approved By


Name
Designation
Signature
Date
Construction of 40mm thick Asphalt Road Surface
50m2
Considered Quantity : 20m long, 2.5m wide, 40mm thick road
section
Assumptions :
1 Material rate includes loading, Supply, transport and unloading to work location
2 Considered additional 5% of materials for wastage during handling
3 Rates for Tack Coat & sand sealing of ABC layer considered separately

No. of No.of
Ref No. Labour Costs Rate (Rs) Amount (Rs)
Men Hours
Skilled labor 2 6.0 262.50 3,150.00
Unskilled labor 6 6.0 187.50 6,750.00

2.5% of Plant cost for Tools 247.50

1 Sub-total for Labour 10,147.50

No. of No.of
Ref No. Equipment Cost Rate (Rs) Amount (Rs)
Units Hours
Bowser 1 3 1,360.00 4,080.00
Asphalt Paver 1 5 10,200.00 51,000.00
3 cube tipper 2 4 1,450.00 11,600.00
Pneumatic Roller 1 5 7,500.00 37,500.00
2 Sub-total for Plant 104,180.00

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)

Asphalt Concrete Mt 5.2 10,500.00 54,600.00


3 Sub-total for Materials 54,600.00

4 Total Basic Costs : (1)+(2)+(3) 168,927.50


5 Profit & Overhead (4) × 28.0% 47,299.70
6 Total Cost (4)+(5) 216,227.20
7 Unit Rate (6)/Q 4,324.54

Rs/ 1 m2 4,324.54
Unit Rate for Construction of 40mm thick Asphalt Road Surface
US$/ 1 m2 28.72

Prepared by Checked by Approved by


Name
Designation
Signature
Date
Random Rubble Masonry in cement mortar 1:5 in Superstructure

Considered Quantity : 1 Cube

Ref
Labour Costs Unit No.of Days Rate (Rs) Amount (Rs)
No.
Skilled labor Labour Day 3 2,200.00 6,600.00
Unskilled labor Labour Day 4 1,600.00 6,400.00

Add for Small tools &


390.00
Scafolding 3% of Labour

1 Sub-total for Labour 13,390.00

Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
6" - 9" Rubble Cu 1.3 8,250.00 10,725.00
Cement Bag 5 990.00 4,950.00
Sand Cu 0.3 19,000.00 5,700.00
Water Gal 100 1.00 100.00
Sub-total for Materials 21,475.00

3 Total Basic Costs : (1)+(2) 34,865.0


4 Profit & Overheads (3) × 27% 9,762.20
5 Total Cost (3) + (4) 44,627.20
Unit Rate Rate for 1 Cube Rs/Cube 44,627.20
Rate for 1 m3 Rs/m3 15,769.33
15,770.00

Unit Rate for Random Rubble Masonry in cement mortar 1:5


Rs/m3 15,770.00
in Superstructure

1
Mixing & Placing of Grade C30 Concrete

Considerd Quantity : 1 Cube

Assumptions:
1 Considered additional 5% of materials for wastage during handling

Labour for mixing of concrete

Ref No. Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)

Skilled labour 1 0.34 2,200.00 748.00


Unskilled labour 1 2 1,600.00 3,200.00
1 Sub-total for Labour 3,948.00

Equipment for mixing of concrete

Ref No. Equipment Cost No. of Units No.of Days Rate (Rs) Amount (Rs)

Concrete Mixer 1 0.34 9,600.00 3,264.00


2 Sub-total for Plant 3,264.00

Materials for mixing of concrete

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)

Cement Bag 31 990.00 30,690.00


Sand Cube 0.44 19,000.00 8,360.00
3/4 " Metal Cube 0.96 8,000.00 7,680.00
Water Gal 200 1.00 200.00
3 Sub-total for Materials 46,930.00

4 Total Basic Costs Rs/Cube 54,142.00


5 Add 5% of Wastage 2,707.10
6 Total Basic Costs for Grade C 30 Concrete Mixing Rs/Cube 56,849.10

Labour for Placing & Curing of concrete


Ref No. Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
Skilled labour 1 0.5 2,200.00 1,100.00
Unskilled labour 1 1.5 1,600.00 2,400.00
7 Sub-total for Labour 3,500.00

Equipment for placing & Curing of concrete


Ref No. Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
Concrete Vibrator 1 2.72 520.00 1,414.40

8 Sub-total for Plant 1,414.40

2
Materials for Placing & Curing of concrete
Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Water Gal 100 1.00 100.00
9 Sub-total for Materials 100.00

10 Concrete C 30 mixing Rate for 1 Cube 56,849.10

11 Total Basic Costs : (7)+(8)+(9) +(10) 61,863.50


12 Profit & Overhead (11)× 27.0% 16,703.15
13 Total Cost (11)+(12) 78,566.65
14 Unit Rate (14)/Q Rs/ Cube 78,566.65
Rs/ m3 27,762.07
27,763.00

Unit Rate for Mixing & Placing of Grade C30 Concrete Rs/m3 27,763.00

3
225 mm thick Brick wall in cement sand 1:5 in Superstructure

Considered Qunatity : 1 Square


Assumptions:
3 Considered additional 5% of materials for wastage during handling

Ref No. Labour Costs No. of Units No.of Days Rate (Rs) Amount (Rs)

Skilled labour 1 2.25 2,200.00 4,950.00


Unskilled labour 1 3.75 1,600.00 6,000.00
Add for Small tools & Scafolding 3%
328.50
of Labour
1 Sub-total for Labour 11,278.50

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)

Bricks No 1090 10.00 10,900.00


Allow 5% of Wastage 545.00
Cement Bag 3 990.00 2,970.00
Sand Cu 0.2 19,000.00 3,800.00
Water Gal 115 1.00 115.00
3 Sub-total for Materials 18,330.00

4 Total Basic Costs : (1)+(2)+(3) 29,608.50


5 Profit & Overhead (4) × 27.0% 7,994.30
6 Total Cost (4)+(5) 37,602.80
7 Unit Rate (6)/Q Rs/sq 37,602.80
Rs/m2 4,046.06
4,047.00

Unit Rate for 225 mm thick Brick Wall Rs/m3 4,047.00

4
Clearing site and grubbing up all small trees not exceeding 500mm girth and including
bushes, scrubs, undergrowth hedges etc

Considered Quantity : 1 Square

Ref
Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
No.
Unskilled labour 1 0.75 1,600.00 1,200.00
2.5% of Plant cost for
30.00
Tools
1 Sub-total for Labour 1,230.00

4 Total Basic Costs : (1)+(2)+(3) 1,230.00


5 Profit & Overhead (4) × 28.0% 344.40
6 Total Cost (4)+(5) 1,574.40
7 Unit Rate (6)/Q Rs/sq 1,574.40
Rs/m2 169.41
170.00

Unit Rate for Clearing site and grubbing up all small trees not
exceeding 500mm girth and including bushes, scrubs, undergrowth Rs/m2 170.00
hedges etc.

5
Removing top soil to a Depth not Exceeding 150 mm

Considered Quantity : 10 Square

Ref
Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
No.
Unskilled labour 1 10.00 1,600.00 16,000.00
2.5% of Plant cost for
400.00
Tools
1 Sub-total for Labour 16,400.00

2 Total Basic Costs : 16,400.00


3 Profit & Overhead (2) × 28.0% 4,592.00
4 Total Cost (2)+(3) 20,992.00
5 Unit Rate (4)/Q Rs/sq 2,099.20
Rs/m2 225.87
226.00

Unit Rate for Removing top soil to a Depth not Exceeding 150 mm Rs/m2 226.00

You might also like