Professional Documents
Culture Documents
Masonry
12 12 0.888 102 48 47 44 66 100 100 100 58 42 20
10.5 0.888 142 87 75 98 100 63 63 63 77 65 60
9 0.888 125 134 153 187 125 95 95 95 162 186 200
7.5 0.888 68 140 146 156 205 259 259 259 174 181 150
6 0.888 194 119 76 109 98 89 89 89 103 67 109
10 12 0.616 29 58 58 58 47 32 32 32 32 32 32
10.5 0.616 24 123 123 123 54 29 29 29 29 29 29
9 0.616 77 89 80 79 128 176 176 176 181 184 184
7.5 0.616 70 29 34 34 70 72 72 72 81 91 91
6 0.616 41 228 228 228 149 76 76 76 76 76 76
Struct'l.
12 12 0.888 926 428 421 392 596 889 889 889 517 377 182
10.5 0.888 1262 778 666 871 898 563 563 563 689 582 535
9 0.888 1113 1194 1360 1660 1109 850 850 850 1439 1653 1783
7.5 0.888 608 1243 1299 1386 1822 2310 2310 2310 1553 1611 1332
6 0.888 1728 1057 680 969 875 796 796 796 917 596 967
10 12 0.616 202 411 411 411 331 224 224 224 224 224 224
10.5 0.616 173 869 869 869 383 202 202 202 202 202 202
9 0.616 544 628 565 559 906 1247 1247 1247 1284 1302 1302
7.5 0.616 498 203 244 244 496 513 513 513 577 642 642
6 0.616 291 1618 1618 1618 1059 536 536 536 536 536 536
22ND 24TH 26TH 28TH 30TH R.DECK
32ND qty
23RD 25TH 27TH 29TH 31ST MR
230 22,055.16
510 42,791.81
2,196 157,934.12
1,700 101,885.25
210 10,068.66
10 10 5 5 228 17,272.37
14 14 18 14 474 31,419.80
48 204 44 32 1,650 93,748.05
334 42 192 90 1,934 91,570.07
44 34 36 18 766 29,014.55
112 104 102 98 94 52 52 1,852 107,408.59
100 94 94 98 174 56 56 1,920 97,433.28
86 186 70 78 76 43 43 3,102 134,927.69
100 90 164 226 264 53 53 3,215 116,535.71
150 144 124 148 172 86 86 2,600 75,394.80
30 30 30 30 30 20 20 920 42,548.16
60 60 60 60 60 30 30 1,140 46,132.38
212 344 140 140 266 70 82 2,819 97,779.83
250 298 298 302 204 56 56 2,254 65,151.87
30 30 30 15 30 102 678 15,678.07
0.00
63 363 9,399.16
14 14 310.72
80 80 80 80 80 22 17 739 13,667.81 2,654,411.53
28 3 331 4,897.48
190 190 190 190 190 100 30 2,550 48,317.40
30 30 30 30 30 20 20 830 13,760.99
10 1,190 16,911.09
30 30 30 30 30 20 20 834 9,876.65
220 2,084.28 1,515,975.78
156 156 156 156 156 90 90 6,549 69,786.14
292 392 360 204 188 94 129 8,506 79,309.94
1318 1010 736 696 696 348 340 17,051 136,271.59
1068 1458 1468 1580 1652 826 680 24,008 159,893.28
1160 1168 1276 1082 788 390 490 15,097 80,436.82 525,697.78
388 388 388 388 388 219 220 7,767 57,413.66 454,329.88
350 350 350 350 350 210 170 9,712 62,817.22 980,027.65
2256 2256 2256 2224 2192 1090 940 31,977 177,280.49
1112 1112 1112 980 848 530 860 15,361 70,967.82
928 928 928 1186 1020 560 1370 23,228 85,850.69 980,027.65
47 47 47 47 47 27 28 1974 21034.944
88 118 108 61 57 28 39 2562 23888.088
397 304 222 210 210 105 102 5138 41062.896
322 439 442 476 498 249 205 7235 48185.1 158407.41
350 352 384 326 237 118 148 4549 24237.072 158408.1
20 20 20 20 20 12 12 851 9,068.26
38 51 47 27 25 12 17 1110 10,349.64
172 132 96 91 91 46 44 2229 17,814.17
140 191 192 207 216 108 89 3140 20,912.40
152 153 167 142 103 51 64 1974 10,517.47 68,661.94
32 32 32 32 32 18 18 638 4,716.10
29 29 29 29 29 17 14 797 5,155.00
184 184 184 181 179 89 77 2608 14,458.75
91 91 91 80 69 43 70 1251 5,779.62
76 76 76 97 83 46 112 1896 7,007.62 37,117.08
105,779.02
874,248.64
182 182 182 182 182 105 105 7626 81262.656
340 456 419 237 219 109 150 9900 92307.6
1534 1176 857 810 810 405 396 19849 158633.208
1243 1697 1709 1839 1923 962 792 27949 186140.34
1350 1360 1485 1260 917 454 570 17573 93628.944 611972.748
224 224 224 224 224 126 127 4483 33138.336
202 202 202 202 202 121 98 5604 36246.672
1302 1302 1302 1284 1265 629 543 18458 102331.152
642 642 642 566 490 306 496 8869 40974.78
536 536 536 685 589 323 791 13416 49585.536 262276.476
874249.224
2,654,412.12
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Schedule
Ø L kg/m FDN 2ND 3RD 4TH 5TH 6TH 7TH 8TH 9TH 1OTH 12TH 14TH 16TH 18TH 20TH 22ND 24TH 26TH 28TH
GRD 11TH 13TH 15TH 17TH 19TH 21ST 23RD 25TH 27TH 29TH
36mmØ 12 7.991 230 22,055.16 0.00
Gr. 60 10.5 7.991 510 42,791.81 0.00
9 7.991 120 8,630.28 0.00 360 360 360 420 276
7.5 7.991 516 30,925.17 404 24,212.73 420 404 292 180
Prepared by : Noted by :
20 12 12 2950.232 31437.7
25 12 17 3944.496 36778.5
91 46 44 5530.696 44201.3
216 108 89 5497.64 36614.3
103 51 64 4046.592 21560.2 170592.0
32 18 18 1709.84 12639.1
29 17 14 2543.36 16450.5
179 89 77 3971.824 22019.8
69 43 70 1865.46 8618.4
83 46 112 3793.96 14022.5 73750.3
TOTAL WEIGHT
QTY/Priority
PRIORITY GRADE DELIVERED STATUS BALANCE SUPPLIER
Ordered
(IN KGS.)
1st Priority GRADE 60 74,299.47 Complete 70,351.87 Pagasa
2nd Priority GRADE 60 82,105.44 Complete 82,105.44 Pagasa
3rd Priority GRADE 60 83,612.41 Incomplete 87,589.60 3,977.19 Pagasa
4th Priority GRADE 60 93,892.39 Complete 93,892.39 0.00 Pagasa
5th Priority GRADE 60 106,083.38 Complete 106,083.38 0.00 Pagasa
6th Priority GRADE 60 113,282.60 Complete 113,282.60 0.00 Pagasa
7th Priority GRADE 40 108,530.26 Complete 108,530.26 0.00 Pagasa
8th Priority GRADE 40 95,358.23 Incomplete 113,240.33 17,882.10 Capitol
9th Priority GRADE 40 88,850.08 Incomplete 113,039.20 24,189.12 Capitol
10th Priority GRADE 60 112,735.78 Complete 112,735.78 0.00 Pagasa
11th Priority GRADE 60 107,943.40 Complete 107,943.40 0.00 Pagasa
12th Priority GRADE 40 111,724.97 Incomplete 111,727.63 2.66 Pagasa
13th Priority GRADE 60 103,894.56 Incomplete 106,206.95 2,312.39 Pagasa
14th Priority GRADE 40 38,811.70 complete 38,811.70 0.00 Pagasa
15th Priority GRADE 40 30,982.64 Incomplete 32,923.04 1,940.40 Capitol
16th Priority GRADE 40 43,113.84 Complete 36,295.64 0.00 Pagasa
17th Priority GRADE 40 36,017.52 Complete 36,017.52 0.00 Capitol
18th Priority GRADE 40 23,906.65 Incomplete 30,734.09 6,827.44 Pagasa
19th Priority GRADE 60 49,275.35 Complete 49,275.35 0.00 Pagasa
20th Priority GRADE 60 209,918.03 Incomplete 212,245.12 2,327.09 Pagasa
21st Priority GRADE 60 238,193.09 Incomplete 249,781.25 11,588.16 Pagasa
22nd Priority GRADE 60 20,852.46 Complete 20,852.46 0.00 Pagasa
23rd Priority GRADE 40 17,802.18 Incomplete 30,991.64 13,189.46 Pagasa
24th Priority GRADE 60 148,437.55 Incomplete 153,355.85 4,918.30 Pagasa
25th Priority GRADE 40 32,894.40 Incomplete 134,664.68 101,770.28 Pagasa
26th Priority GRADE 60 8,193.29 Complete 8,193.29 0.00 Pagasa
27th Priority GRADE 60 42,758.84 Incomplete 88,890.87 46,132.04 Pagasa
28th Priority GRADE 40 42,802.45 Incomplete 98,883.71 56,081.26 Capitol
29th Priority GRADE 40 62,506.76 Incomplete 101,695.54 39,188.77 Capitol
30th Priority GRADE 40 0.00 Incomplete 17,245.54 17,245.54
TOTAL 2,223,470.48 2,667,586.10 349,572.19
GMQ DELIVERED:
GRADE 40 : 991,599.59
GRADE 60 : 1,662,811.24
2,654,410.83
GRADE 40 : 495,799.33
GRADE 60 :
495,799.33
GRADE 40 : 509,001.18
GRADE 60 : 1,662,785.58
2,171,786.76
GRADE 40 : 356,517.68
GRADE 60 :
356,517.68
GRADE 40 : 376,783.99
GRADE 60 : 1,595,478.02
1,972,262.01
FDN/GRD
Ø L kg/m Wt. in Kgs.
(in pcs)
36mmØ 12 7.991 230 22,055.16
Gr. 60 10.5 7.991 510 42,791.81
9 7.991 120 8,630.28
7.5 7.991 516 30,925.17
6 7.991 0.00
32mmØ 12 6.313 188 14,242.13
Gr. 60 10.5 6.313 190 12,594.44
9 6.313 61 3,465.84
7.5 6.313 348 16,476.93
6 6.313 0.00
28mmØ 12 4.833 0.00
Gr. 60 10.5 4.833 176 8,931.38
9 4.833 160 6,959.52
7.5 4.833 64 2,319.84
6 4.833 150 4,349.70
25mmØ 12 3.854 80 3,699.84
Gr. 60 10.5 3.854 160 6,474.72
9 3.854 190 6,590.34
7.5 3.854 0.00
6 3.854 0.00
20mmØ 12 2.466 0.00
Gr. 60 10.5 2.466 300 7,767.90
9 2.466 0.00
7.5 2.466 0.00
6 2.466 300 4,438.80
16mmØ 12 1.579 200 3,789.60
Gr. 60 10.5 1.579 400 6,631.80
9 1.579 300 4,263.30
7.5 1.579 150 1,776.38
6 1.579 220 2,084.28
12mmØ 12 0.888 239 2,546.78
Gr. 60 10.5 0.888 327 3,048.95
9 0.888 288 2,301.70
7.5 0.888 157 1,045.62
6 0.888 447 2,381.62
0.00
Struct'l.
12mmØ 12 0.888 926 9,867.46
Gr. 40 10.5 0.888 1262 11,766.89
9 0.888 1113 8,895.10
7.5 0.888 608 4,049.28
6 0.888 1728 9,206.78
10mmØ 12 0.616 202 1,493.18
Gr. 40 10.5 0.616 173 1,118.96
9 0.616 544 3,015.94
7.5 0.616 498 2,300.76
6 0.616 291 1,075.54
Grade 60 232,583.81
Grade 40 52,789.88
285,373.69
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule ( 1st BATCH) 1st Priority
(To be Delivered @ Kakarong Staging Area)
FDN/GRD Total KGS
Ø L kg/m Wt. in Kgs. DELIVERIES DATE WEIGHT
(in pcs) Delivered
36mmØ 12 7.991 77 7,383.68 77 7,383.68 10-Oct 20,363.94 20,363.94
Gr. 60 10.5 7.991 88 7,383.68 88 7,383.68 10-Sep 18,634.37 38,998.31
9 7.991 84 6,041.20 84 6,041.20 10-Sep 8,776.67 47,774.97
7.5 7.991 88 5,274.06 88 5,274.06 10-Sep 6,006.52 53,781.49
6 7.991 0.00 3,977.19 57,758.68
32mmØ 12 6.313 41 3,106.00 41 3,106.00 14-Sep 9,157.10 66,915.78
Gr. 60 10.5 6.313 0.00 7,383.68 74,299.47
9 6.313 82 4,658.99 82 4,658.99 14-Sep
7.5 6.313 0.00 70 3,977.19 22-Sep x 9.0m
6 6.313 0.00
28mmØ 12 4.833 0.00
Gr. 60 10.5 4.833 0.00
9 4.833 0.00
7.5 4.833 0.00 74,299.47 complete
6 4.833 0.00
25mmØ 12 3.854 42 1,942.42 42 1,942.42 27-Sep
Gr. 60 10.5 3.854 72 2,913.62 72 2,913.62 27-Sep
9 3.854 124 4,301.06 124 4,301.06 27-Sep
7.5 3.854 35 1,011.68 35 1,011.68 14-Sep
6 3.854 0.00
20mmØ 12 2.466 0.00
Gr. 60 10.5 2.466 150 3,883.95 150 3,883.95 11-Sep
9 2.466 0.00
7.5 2.466 0.00
6 2.466 150 2,219.40 148 2,189.81 11-Sep
16mmØ 12 1.579 142 2,690.62 142 2,690.62 19-Sep
Gr. 60 10.5 1.579 200 3,315.90 200 3,315.90 19-Sep
9 1.579 200 2,842.20 200 2,842.20 11-Sep
7.5 1.579 132 1,563.21 132 1,563.21 11-Sep
6 1.579 200 1,894.80 200 1,894.80 11-Sep
12mmØ 12 0.888 300 3,196.80 300 3,196.80 11-Sep
Gr. 60 10.5 0.888 200 1,864.80 200 1,864.80 11-Sep
9 0.888 150 1,198.80 150 1,198.80 11-Sep
7.5 0.888 250 1,665.00 250 1,665.00 10-Sep
6 0.888 0.00
0.00
Struct'l.
12mmØ 12 0.888 0.00
Gr. 40 10.5 0.888 0.00
9 0.888 0.00
7.5 0.888 0.00
6 0.888 0.00
10mmØ 12 0.616 0.00
Gr. 40 10.5 0.616 0.00
9 0.616 0.00
7.5 0.616 0.00
6 0.616 0.00
Grade 60 70,351.87
Grade 40 0.00
70,351.87
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule ( 1st BATCH) 2nd Priority
(To be Delivered @ Kakarong Staging Area)
Grade 60 82,105.44
Grade 40 0.00
82,105.44
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule ( 1st BATCH) 3rd Priority
(To be Delivered @ Kakarong Staging Area)
Grade 60 87,589.60
Grade 40 0.00
87,589.60
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule ( 2nd BATCH) 4th Priority
Grade 60 93,892.39
Grade 40 0.00
93,892.39
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (5th Priority)
(To be delivered @ Kakarong Staging Area)
4TH/5TH (in
Ø L kg/m pcs) Wt. in Kgs. DELIVERIES DATE WEIGHT
Grade 60 106,083.38
Grade 40 0.00
106,083.38
Total KGS
Delivered
44,320.43
50,776.14
65,137.20
66,298.70
71,511.79
73,156.15
100,095.29
106,083.38
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (6th Priority)
(To be delivered @ Kakarong Staging Area)
6TH/7TH (in
Ø L kg/m Wt. in Kgs. DELIVERIES DATE WEIGHT
pcs)
36mmØ 12 7.991 0.00 8,589.57
Gr. 60 10.5 7.991 0.00 20,084.11
9 7.991 360 25,890.84 360 25,890.84 DEC.17 & JAN.3 5,660.64
7.5 7.991 0.00 8,348.82
6 7.991 0.00 18,314.01
32mmØ 12 6.313 0.00 29,943.79
Gr. 60 10.5 6.313 50 3,314.33 50 3,314.33 Dec15&20 6,165.62
9 6.313 264 14,999.69 264 14,999.69 Dec15&20 11,811.84
7.5 6.313 44 2,083.29 44 2,083.29 17-Dec 4,364.20
6 6.313 52 1,969.66 52 1,969.66 17-Dec
28mmØ 12 4.833 130 7,539.48 130 7,539.48 DEC. 10 AND JAN. 17
Gr. 60 10.5 4.833 86 4,364.20 86 4,364.20 JAN. 20
9 4.833 350 15,223.95 350 15,223.95 Dec 3&5, jan6
7.5 4.833 160 5,799.60 160 5,799.60 JAN.6
6 4.833 160 4,639.68 160 4,639.68 JAN.5
25mmØ 12 3.854 130 6,012.24 130 6,012.24 JAN.6
Gr. 60 10.5 3.854 20 809.34 20 809.34 10-Dec
9 3.854 40 1,387.44 40 1,387.44 8-Dec
7.5 3.854 58 1,676.49 58 1,676.49 22-Nov
6 3.854 78 1,803.67 78 1,803.67 8-Dec 113,282.60
20mmØ 12 2.466 0.00
Gr. 60 10.5 2.466 0.00
9 2.466 0.00
7.5 2.466 30 554.85 30 554.85 JAN.5
6 2.466 0.00
16mmØ 12 1.579 0.00
Gr. 60 10.5 1.579 0.00
9 1.579 342 4,860.16 342 4,860.16 Dec 3&5
7.5 1.579 82 971.09 82 971.09 JAN.5
6 1.579 0.00
12mmØ 12 0.888 102 1,086.91 102 1,086.91 22-Nov
Gr. 60 10.5 0.888 225 2,097.90 225 2,097.90 22-Nov
9 0.888 309 2,469.53 309 2,469.53 8-Dec
7.5 0.888 359 2,390.94 359 2,390.94 22-Nov
6 0.888 251 1,337.33 251 1,337.33 22-Nov
0.00
Struct'l.
12mmØ 12 0.888 0.00
Gr. 40 10.5 0.888 0.00 113,282.60
9 0.888 0.00
7.5 0.888 0.00
6 0.888 0.00
10mmØ 12 0.616 0.00
Gr. 40 10.5 0.616 0.00
9 0.616 0.00
7.5 0.616 0.00
6 0.616 0.00
Grade 60 113,282.60
Grade 40 0.00
113,282.60
Total KGS
Delivered
8,589.57
28,673.68
34,334.32
42,683.14
60,997.16
90,940.94
97,106.56
108,918.40
113,282.60
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (7th Priority)
(To be delivered @ Kakarong Staging Area)
Ø L kg/m FDN 3RD (in Wt. in Kgs. DELIVERIES DATE WEIGHT Total KGS
pcs) Delivered
36mmØ 12 7.991 0.00 19,852.13 19,852.13
Gr. 60 10.5 7.991 0.00 19,020.96 38,873.09
9 7.991 0.00 27,166.14 66,039.23
7.5 7.991 0.00 14,428.22 80,467.45
6 7.991 0.00 6,497.57 86,965.02
32mmØ 12 6.313 0.00 4,531.30 91,496.32
Gr. 60 10.5 6.313 0.00 17,033.94 108,530.26
9 6.313 0.00
7.5 6.313 0.00
6 6.313 0.00
28mmØ 12 4.833 0.00
Gr. 60 10.5 4.833 0.00
9 4.833 0.00
7.5 4.833 0.00
6 4.833 0.00
25mmØ 12 3.854 0.00 108,530.26
Gr. 60 10.5 3.854 0.00
9 3.854 0.00
7.5 3.854 0.00
6 3.854 0.00
20mmØ 12 2.466 0.00
Gr. 60 10.5 2.466 0.00
9 2.466 0.00
7.5 2.466 0.00
6 2.466 0.00
16mmØ 12 1.579 0.00
Gr. 60 10.5 1.579 0.00
9 1.579 0.00
7.5 1.579 0.00
6 1.579 0.00
12mmØ 12 0.888 0.00
Gr. 60 10.5 0.888 0.00
9 0.888 0.00
7.5 0.888 0.00
6 0.888 0.00
0.00
Struct'l.
12mmØ 12 0.888 1354 14,428.22 1354 14,428.22 Nov16&Dec8
Gr. 40 10.5 0.888 2040 19,020.96 2040 19,020.96 Nov 11&17
9 0.888 2484 19,852.13 2484 19,852.13 Nov 4,9,11&15
7.5 0.888 1851 12,327.66 1851 12,327.66 Nov 15&17
6 0.888 2785 14,838.48 2785 14,838.48 Nov 15,17&23
10mmØ 12 0.616 613 4,531.30 613 4,531.30 5-Dec
Gr. 40 10.5 0.616 1042 6,739.66 1042 6,739.66 JAN. 30
9 0.616 1172 6,497.57 1172 6,497.57 3-Dec
7.5 0.616 701 3,238.62 701 3,238.62 JAN. 30
6 0.616 1909 7,055.66 1909 7,055.66 JAN. 30
Grade 60 0.00
Grade 40 108,530.26
108,530.26
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (8th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 113,240.33
113,240.33
Total KGS
Delivered
57,462.76
71,677.57
77,909.03
86,694.90
95,358.23
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (9th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 113,039.20
113,039.20
Total KGS
Delivered
30,379.27
59,825.80
88,850.08
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (10th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 112,735.78
Grade 40 0.00
112,735.78
Total KGS
Delivered
14,672.96
16,473.02
37,739.71
80,507.39
84,207.23
90,427.46
100,652.70
112,735.78
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (11th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 107,943.40
Grade 40 0.00
107,943.40
WEIGHT Total KGS
Delivered
38,464.31 38,464.31
25,451.01 63,915.32
10,544.86 74,460.17
10,248.75 84,708.92
4,452.78 89,161.70
1,387.44 90,549.14
4,640.06 95,189.20
12,754.20 107,943.40
107,943.40
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule (12th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 111,727.63
111,727.63
WEIGHT Total KGS
Delivered
22,790.78 22,790.78
25,142.04 47,932.82
8,482.18 56,415.00
10,498.82 66,913.82
44,811.14 111,724.97
111,724.97
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (13th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 106,206.95
Grade 40 0.00
106,206.95
Total KGS
Delivered
19,218.02
70,561.85
83,603.75
95,428.37
98,912.88
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (10mm)14th Priority
(To be delivered @ Kakarong Staging Area)
Supplier : Pagasa Steel Works, Inc
Grade 60 0.00
Grade 40 38,811.70
38,811.70
WEIGHT Total KGS
Delivered
6,397.78 6,397.78
22,974.34 29,372.11
9,439.58 38,811.70
0.00 38,811.70
0.00 38,811.70
38,811.70
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 ( 10mm)15th Priority
(To be delivered @ Kakarong Staging Area)
Supplier : Capitol Steel Corporation
Grade 60 0.00
Grade 40 32,923.04
32,923.04
WEIGHT Total KGS
Delivered
25,774.06 25,774.06
5,208.59 30,982.64
0.00
0.00
0.00
30,982.64
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 ( 10mm)16th Priority
(To be delivered @ Kakarong Staging Area)
Date of Delivery ; March 23, 2012
43,113.84
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 ( 10mm)17th Priority
(To be delivered @ Kakarong Staging Area)
Date of Delivery : March 23, 2012
Grade 60 0.00
Grade 40 36,017.52
36,017.52
Total KGS
Delivered
36,017.52
36,017.52
36,017.52
36,017.52
36,017.52
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 ( 10mm)18th Priority
(To be delivered @ Kakarong Staging Area)
Date of Delivery : April 4, 2012
Grade 60 0.00
Grade 40 30,734.09
30,734.09
Total KGS
Delivered
2,310.00
21,351.79
23,906.65
23,906.65
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (19th Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : March 20, 2012
Grade 60 49,275.35
Grade 40 0.00
49,275.35
Total KGS
Delivered
20,437.82
44,650.55
49,275.35
49,275.35
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (20th Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : April 27, 2012
Ø L kg/m (in pcs) Wt. in Kgs. DELIVERIES DATE WEIGHT Total KGS Delivered
Grade 60 212,245.12
Grade 40 0.00
212,245.12
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (21st Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : May 21, 2012
Grade 60 249,781.25
Grade 40 0.00
249,781.25
WEIGHT Total KGS
Delivered
238,193.09
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (22nd Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : June 6, 2012
Grade 60 20,852.46
Grade 40 0.00
20,852.46
Total KGS
Delivered
6,141.85
20,852.46
20,852.46
20,852.46
20,852.46
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (23rd Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : June 21, 2012
Grade 60 0.00
Grade 40 30,991.64
30,991.64
Total KGS
Delivered
17,802.18
17,802.18
17,802.18
17,802.18
17,802.18
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (24th Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : June 23, 2012
Grade 60 153,355.85
Grade 40 0.00
153,355.85
Total KGS
Delivered
48,185.73
54,459.43
73,815.60
75,539.05
82,823.11
90,478.58
94,931.36
104,007.53
129,318.49
131,894.19
139,506.17
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (25th Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : July 21, 2012
Grade 60 0.00
Grade 40 134,664.68
134,664.68
Total KGS
Delivered
13,704.77
32,894.40
32,894.40
32,894.40
32,894.40
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (26th Priority)
(To be delivered @ Kakarong Staging Area)
Date of Delivery : August 2, 2012
Grade 60 8,193.29
Grade 40 0.00
8,193.29
Total KGS
Delivered
8,193.29
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 60 (27th Priority) revised
(To be delivered @ Kakarong Staging Area)
Date of Delivery : August 2, 2012
Grade 60 88,890.87
Grade 40 0.00
88,890.87
Total KGS
Delivered
9,975.31
35,712.32
42,758.84
42,758.84
42,758.84
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Not Yet Deliver and delivered 10mm Grade 40 which converted by 12m
(To be delivered @ Kakarong Staging Area)
Wt. in
Ø L kg/m (in pcs) Convert by 12m (pcs) Remarks
Kgs.
10mmØ 12 0.616 0 0.00 0
Gr. 40 10.5 0.616 886 5,730.65 775
9 0.616 3250 18,018.00 2437.5
7.5 0.616 837 3,866.94 523
6 0.616 2980 11,014.08 1490
Wt. in
Ø L kg/m (in pcs) Convert by 6m (pcs)
Kgs.
12mmØ 12 0.888 130 1,385.28 260
Gr. 60 10.5 0.888 146 1,361.30 256
9 0.888 158 1,262.74 237
7.5 0.888 598 3,982.68 748
6 0.888 206 1,097.57 206
Remarks
Delivered(20th)
delivered(13th) AS 12MM X 10.5
Delivered(20th)
Not yet delivered(13th)
delivered(13th)
1209
Ø L kg/m
SUPPLIER
12mmØ 12 0.888
Gr. 40 10.5 0.888
9 0.888
7.5 0.888
6 0.888
10mmØ 12 0.616
Gr. 40 10.5 0.616
9 0.616
7.5 0.616
6 0.616
6th PRIORITY 10th PRIORITY 11th PRIORITY
360 360
420
50 36 22
264 170 56
44 70 216
52 64 76
130 128 126
86 102 106
350 388 106
160 148 420
160 172 112
130 80 30
20 80 80
40 151 148
58 56 126
78 35 30
30 30 30
130 190
60 30
342 30
82 32 30
7th PRIORITY 8th PRIORITY 9th PRIORITY 10th PRIORITY 11th PRIORITY
PAGASA CAPITOL CAPITOL
1354 813 1485
2040 1537 1461
2484 3230 2101
1851 2685 4132
2785 1649 1671
613 822 555
1042 1738 585
1172 1124 2153
701 488 1009
1909 3236 1595
PRIORITY( SUPPLIER: PAGASA ONLY (GRADE60))
12th PRIORITY 13th PRIORITY 14th PRIORITY 15th PRIORITY 16th PRIORITY 17th PRIORITY 18th PRIORITY
420
22
56
96
76
126
106
310
120
112
30
80
204
54
30
359
190
30
30
230
146
158
598
206
PRIORITY(GRADE 40)
12th PRIORITY 13th PRIORITY 14th PRIORITY 15th PRIORITY 16th PRIORITY 17th PRIORITY 18th PRIORITY
1778
1126
1824
4620
1592
448 640 506 544 544 449
404 728 527 491 491 395
2494 2959 2684 3132 3098 2250
1026 1422 1318 1500 1319 1337
1072 1731 1300 1300 1502 1680
19th PRIORITY 20th PRIORITY 21st PRIORITY 22nd PRIORITY
404
25
72 46
248 296
338 568
202 114
366 318
318 288
720 342
564 354
444 418
30 90 96
80 230 200
204 548 596
54 334 692
30 90 124
3
63 68
14 17
230 28
31 61
190 570 596
30 90 125
21
30 90 104
804
15
26
86
292
68
216 198
204 286
176 162
534 370
308 344
30
60 120
140 418
302 316
15 132
443
190
30
30
515
539
912
1458
653
25th PRIORITY
729
10752
5657
3347
3492
TOTAL
172
510
1200
2968
0
228
464
1512
2230
652
1852
1920
3102
5815
2600
856
1160
2719
2135
712
3
431
31
1210
392
2356
795
1201
760
350
2850
3274
4839
8986
5202
5430
6164
9639
13288
7697
5850
17153
26723
13467
18817
: Project
ORIENTAL GARDENS MAKATI (LILAC TOWER)
: Chino
Location
Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivered Grade 60
Supplier : Pagasa Steel Works, Inc.
As of : August 25, 2012
GMQ : 1,662,811.240
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivered Grade 40
Supplier : Capitol Steel Corporation
As of : September 29, 2012
301,557.16
323,619.83
343,657.43
365,809.43
386,150.32
406,478.32
430,010.75
486,710.75
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivered Grade 40
Supplier : Pagasa Steel Works, Inc.
As of : August 25, 2012
GMQ : 495,799.795
(0.017)
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (28th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 98,883.71
98,883.71
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (29th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 101,695.54
101,695.54
Total KGS
Delivered
49,282.67
57,178.76
62,506.76
62,506.76
62,506.76
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 (30th Priority)
(To be delivered @ Kakarong Staging Area)
Grade 60 0.00
Grade 40 4,043.42
4,043.42
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 to complete the delivery
(To be delivered @ Kakarong Staging Area)
\
Grade 60 0.00
Grade 40 28,496.16
28,496.16
Project : ORIENTAL GARDENS MAKATI (LILAC TOWER)
Location : Chino Roces Ave. corner Urban Ave., Makati City
Subject : Rebar Delivery Schedule Grade 40 to complete the delivery
(To be delivered @ Kakarong Staging Area)
\
Grade 60 0.00
Grade 40 17,245.54
17,245.54