Review Technique A Simple Guide to Network Models Program Evaluation & Review Technique
• Based on the assumption that an activity’s
duration follows a probability distribution instead of being a single value
• Three times estimates are required to
compute the parameters of an activity’s duration distribution Program Evaluation & Review Technique • Tries to account for the uncertainty in task durations
• A stochastic approach which considers the
uncertain nature of the project activities by estimating the expected duration of each activity and its corresponding variance
• Key question: What is the probability of
completing the project by a given deadline? optimistic time (a) = shortest possible time in which activity could possibly be completed
Most likely time (m) = means the time required if the
execution is normal
Pessimistic time (b) = longest time the activity could
ever require Program Evaluation & Review Technique
1. Draw the network diagram.
2. Find critical path. 3. The length of critical path is the mean of the project duration probability distribution assumed to be normal. 4. Compute for the standard deviation by adding all variances of the critical path and obtain the square root of the sum. 5. Compute for the probability. Program Evaluation & Review Technique Shopping Mall Renovation Activity Description IP Optimistic Most likely Pessimistic A Prepare initial design - 1 3 5 B Identify new potential clients - 4 5 12 Develop prospectus for C tenants A 2 3 10
D Prepare final design A 1 8 9
E Obtain planning permission D 1 2 3 F Obtain finance from bank E 1 3 5 G Select contractor D 2 4 6 H Construction G, F 10 17 18 I Finalize tenants contracts B, C, E 6 13 14 J Tenants move in I, H 1 2 3 Shopping Mall Renovation
1. Draw the Network Diagram
2. What is the critical path? 3. What is the total duration of the project? 4. What is the probability that the project will be done in 36 weeks?