4G RF Optimization

Ilma Pratidina
Trainer (From Project Side)
IMPLEMENTATION PROCESS AND
OPTIMIZATION ACTIVITY
 Planning Checklist: NODIN, GCell and Master Site
1. Preparation Phase
2. Execution Phase
3. Post Execution
 Drive Test Acceptance
 Performance Report
 Analysis and Troubleshooting
PREPARATION-EXECUTION-POST
EXECUTION
Preparation Phase
DT Cluster Before
Execution Phase
KPI Formula Mapping
BTS OA
KPI BaseLine Cluster Post Execution
Final Adjx Concheck
JDSU Test Cross Feeder verification
Alarm Clearance
LAC-CI Core Lock Value
Functionality test
Vlan Tagging &
Connectivity Lacima Netact Update
Feature Mapping Declare swap Finish
Parameter Mapping
Datafill PES & Transmisi
Database Downloading
Database Concheck
CONSISTENCY CHECK

 Database check based on parameter and feature

Example LTE SMART LAYERING:


 IncomingLTEISHO
 LTECellReselection
 AbsPrioCellReselec
 Sprioritysearch1
 Sprioritysearch2
 Threshservlow
 SmartLTELayeringEnabled
 SmartLTELayeringRSCP
Drive Test Report
BSS Network 4G Swap Cluster Acceptance

CLUSTER KPI REPORT

BSC BSCN_BJM1

Cluster Name Cluster_06

Regional KALIMANTAN
Cluster :
Cluster_06
Name
Start date : 23-Apr-2017
Finish date : 23-Apr-2017
Configuration:
Cluster Name : SWAP Cluster_06 EXISTING Cluster_06 Total
Macro Sites : 12 0 12
IBS Site : 0 0 0
Total Sites : 12 0 12

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Network Kalimantan Cluster Overview
Cluster_06 Overview as below Map:

Figure 1. Site Map Cluster_06

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Clustering Implementation site list

NO CLUSTER NE ID SITE NAME BAND SOW


1 Cluster_06 BJM047 S_BJM047MW1_BUMI_LINGKAR L1800 Swap BTS
2 Cluster_06 BJM054 S_BJM054MW1_JEMBATAN_BASIRIH L1800 Swap BTS
3 Cluster_06 BJM070 S_BJM070MW1_TB_SEPAKAT_RT7 L1800 Swap BTS
4 Cluster_06 BJM090 S_BJM090MW1_PT_SEPAKAT L1800 Swap BTS
5 Cluster_06 BJM134 S_BJM134MW1_MT_KELAYAN_BANJARMASIN L1800 Swap BTS
6 Cluster_06 BJM764 S_BJM764MW1_TB_BANJAR_INDAH2 L1800 Swap BTS
7 Cluster_06 BJM002 S_BJM002MW1_STO_ULIN L1800 Swap BTS
8 Cluster_06 BJM012 S_BJM012MW1_PEKAPURAN L1800 Swap BTS
9 Cluster_06 BJM041 S_BJM041MW1_GATOT_SUBROTO L1800 Swap BTS
10 Cluster_06 BJM049 S_BJM049MW1_BANJAR_INDAH L1800 Swap BTS
11 Cluster_06 BJM088 S_BJM088MW1_PT_GATOT_SUBROTO2 L1800 Swap BTS
12 Cluster_06 BJM770 S_BJM770MW1_TB_KOMPLEK_BUMI_INDAH L1800 Swap BTS

Table 1.Clustering Site List


South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Cluster Drive Test KPI
Cluster Drive Test KPI : Cluster_06
DT BEFORE DT AFTER
Count of Count of Comment
Event Event
Event Event
Tput DL 1.66 Mbps Tput DL 20.58 Mbps Improved
Bad Spot 16 Bad Spot 12 Improved
PS Dropped 21 PS Dropped 17 Improved
Handover 346 Handover 614 Improved
Handover Handover
6 2 Improved
Failure Failure
RSRP Avg -90.61 RSRP Avg -95.38 Degraded
SNR Avg 5.56 SNR Avg 6.31 Improved
Table 3. Comparison Before – After Event Cluster_6
Remarks:
Action taken:
1. Consistency check power (Pmax) parameter
2. Consistency check MME and X2
3. Consistency check LNCEL parameter, included LNBTS and SBTS parameter
4. Consistency check ADJL 3G to 4G, included WCEL parameter and LTE Smart Layering parameter
5. Follow up alarm at site that impact to KPI
6. RSRP degradation will be followed up by site audit (azimuth and tilting)

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
4G Modernization Sites Map
Route and Coverage Prediction shows sites for BSS Network 4G Modernization Implementation

Figure 2. 4G Modernization DT route for Cluster_06

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Cluster Drive Test Verification Plot – Cluster_06
RSRP – Idle Mode

Idle RSRP Measurement (Before) Idle By RSRP Measurement (After)

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Cluster Drive Test Verification Plot – Cluster_06
SNR – Dedicated Mode
Dedicated SNR Measurement (Before) Dedicated By SNR Measurement (After)

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Cluster Drive Test Verification Plot – Cluster_06
RSRQ – Idle Mode

Idle By RSRQ Measurement (Before) Idle By RSRQ Measurement (After)

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Cluster Drive Test Verification Plot – Cluster_06
PDCP DL – Dedicated Mode

Dedicated By PDCP DL Measurement (Before) Dedicated By PDCP DL Measurement (After)

South Kalimantan Swap Modernization Project © 2017 Nokia . All rights reserved.
Implementation Report
Implementation Chronology

1. Total xx sites (xx NE) already executed successfully on 20 April 2017, 14.00 WITA
2. Functionality test call Drive test verification started parallel in all sites swapped no issues
observed.
3. Database after upload completed by 02.00 WITA
4. Database consistency & discrepancy checking done for eNode-B Objects 04.00 WITA
5. Update adjacencies by 03.30 WITA and still continue monitoring
6. Check Alarm : done
7. Check zero payload : done and continue monitoring
8. Initial tuning, solving worst performance contributor site on progress (discrepancies for LNREL &
LNRELW are completed)
Sites Implementation Data & Map Location - sample
Total site swapped 4G (Plan/OA/Not Yet OA) : 10/9/1

- Site OA :
1. N_BJM129ML1_MT_BANJARINDAHPERMAI
2. N_BJM265ML1_MT_KUINSELATAN2
3. N_BJM297ML1_MC_CEMPAKABESAR
4. N_BJM300ML1_MC_VETERAN3BANJARMASIN
5. N_BJM320ML1_MC_RUKOAYANIKM1
6. N_BJM321ML1_TB_BULANMAS
7. N_BJM327ML1_MT_SKPERMAIANTASAN
8. N_BJM426ML1_PT_GANGMANUNGGAL
9. N_BJM981ML1_PT_HKSNPERDAGANGAN

Note : 9 sites already OA with BW 15 MHz


Executive Summary - sample
4G
KPI KPI BEFORE AFTER IMPROVEMENT REMARK
E-UTRAN RRC CONN SETUP SR (%) 99.93 99.97 56.84% Improve
Accessibility E-RAB SETUP SR (%) 99.83 99.83 1.55% Maintain
CSSR (%) 99.92 99.78 -169.46% Degrade
Retainability SERVICES DROP RATE (%) 0.17 0.25 -52.56% Degrade
Mobility IFHO SR (%) 99.37 99.49 19.49% Improve
Payload 4G TOTAL PAYLOAD (MB) 25846.38 10022.00 -61.22% Degrade

• The statistic comparison is between


• Before : 13 - 18 September 2016
• After : 20 - 25 September 2016

Action Plan: Action Done:


 Need crosscheck worst cell contributor and do Action Date Cell Number
improvement on several KPI which degraded ANR Checking
Idle mode parameter
 Monitoring BTS / cell performance for improvement all KPIs
Dedicated mode parameter - Inter RAT
performance
CSFB
KPI Performance
Availability & Accessibility

• Radio Network Availability degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance
already improve
• RRC Setup SR degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already
improve
• E-RAB Setup SR degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already
improve
• Call Setup SR degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already
Retainability

• Service Drop degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already
improve
Mobility

• IFHO SR degradation contribute by MTP101 due to transmission problem (unproper transmission port), now the performance already improve
• CSFB Prep SR degradation contribute by MTP101 due to transmission problem (unproper transmission port), now the performance already
improve
Payload

• DL Payload degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already improve
• UL Payload degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already improve
Throughput

Average Throughput shown slight improvement, Maximum Throughput shown maintain performance
PRB Utilization

• Service Drop degradation contribute by MTP101 due to transmission problem (inproper transmission port), now the performance already
improve
X2 Performance

X2 Handover is working on LTE Pilot MTP101 & MTP 136


WPC E-RAB SR - sample

tchblockingnum [#] Before After


BSCName SegmentName 9/18/2016 9/25/2016 Remark
BSCN_FBGNISLAM2 MERTASARIMD2 0 2394 Alarm TRX Faulty starts 25-Sep-2016 10.00 AM
BSCN_FBTUBAN2 TELEVISIKTHMD3 6 628 Alarm TRX Operation Degraded flicker
BSCN_FBSERIRIT2 PEMUTERANMD2 41 594 Spike only on 25-Sep-2016 1.00 PM
BSCN_FBTJBENOA2 TJBENOAMD2 0 424 Alarm TRX Faulty many TRXs, RSSI detected
BSCN_FBTABANAN2 GAJAHSURAMD2 0 304 Alarm TRX Faulty starts 22-Sep-2016 10.00 PM

TCH BLOCK degraded if comparing with the same day on last week,
contributed by worst cells in BSCN_FBGNISLAM2, BSCN_FBTUBAN2,
BSCN_FBTJBENOA2, and BSCN_FBTABANAN2 due to availability
degradation/alarm, need to check onsite
WPC Service Drop Rate - sample

tchblockingnum [#] Before After


BSCName SegmentName 9/18/2016 9/25/2016 Remark
BSCN_FBGNISLAM2 MERTASARIMD2 0 2394 Alarm TRX Faulty starts 25-Sep-2016 10.00 AM
BSCN_FBTUBAN2 TELEVISIKTHMD3 6 628 Alarm TRX Operation Degraded flicker
BSCN_FBSERIRIT2 PEMUTERANMD2 41 594 Spike only on 25-Sep-2016 1.00 PM
BSCN_FBTJBENOA2 TJBENOAMD2 0 424 Alarm TRX Faulty many TRXs, RSSI detected
BSCN_FBTABANAN2 GAJAHSURAMD2 0 304 Alarm TRX Faulty starts 22-Sep-2016 10.00 PM

TCH BLOCK degraded if comparing with the same day on last week,
contributed by worst cells in BSCN_FBGNISLAM2, BSCN_FBTUBAN2,
BSCN_FBTJBENOA2, and BSCN_FBTABANAN2 due to availability
degradation/alarm, need to check onsite
WPC CSFB Preparation SR - sample

tchblockingnum [#] Before After


BSCName SegmentName 9/18/2016 9/25/2016 Remark
BSCN_FBGNISLAM2 MERTASARIMD2 0 2394 Alarm TRX Faulty starts 25-Sep-2016 10.00 AM
BSCN_FBTUBAN2 TELEVISIKTHMD3 6 628 Alarm TRX Operation Degraded flicker
BSCN_FBSERIRIT2 PEMUTERANMD2 41 594 Spike only on 25-Sep-2016 1.00 PM
BSCN_FBTJBENOA2 TJBENOAMD2 0 424 Alarm TRX Faulty many TRXs, RSSI detected
BSCN_FBTABANAN2 GAJAHSURAMD2 0 304 Alarm TRX Faulty starts 22-Sep-2016 10.00 PM

TCH BLOCK degraded if comparing with the same day on last week,
contributed by worst cells in BSCN_FBGNISLAM2, BSCN_FBTUBAN2,
BSCN_FBTJBENOA2, and BSCN_FBTABANAN2 due to availability
degradation/alarm, need to check onsite
REFERENCE

 4G Daily Performance SWAP_New Site OA


 LTE16 KPI NGTINEM