You are on page 1of 2

16'-613

16", TYP.
TO
FOUNDATION ELEVATION & LOCATION SCHEDULE

T O /1 6
TO P/

P/ " B
SL

-2

-2
SL E L
P/ AB

3/1
SL HIGH POINT ELEVATION NORTHING EASTING

AB O

-2

6"
AB

"B

BE
(CTR.OF TANK / CTR. OF SLAB) (CTR.OF TANK / CTR. OF SLAB) (CTR.OF TANK / CTR. OF SLAB)

EL

LO
OW
W

W
SL
PAYNE & DOLAN

SL

SL
KUESTER 1284' - 6 15/16" N1302'-4 3/16" E2284'-4"

AB
AB

AB
HI
HI

HI
INCORPORATED

GH
GH

GH
MIHM 709' - 3 15/16" N1169'-10 15/16" E1675'-8 3/4"

PO
PO

PO
A WALBEC GROUP COMPANY

IN
IN

INT
T
T
W6380 Design Drive | Greenville, Wisconsin 54942
TEL 920.757.7550 | FAX 920.757.2906
www.payneanddolan.com

PLAN NOTES

TO " BE
1. FINISH SLAB CONTOUR TO MATCH CONTOUR OF CONICAL TANK BOTTOM.

P/ LO
-2

SL W
2. SLAB LOCATION AND ORIENTATION PER UMERC PLANS K-SF148 AND M-SF148.

AB S
3. SLAB ELEVATIONS PER WITHERUP FABRICATION DRAWING 17586, SHEET 1, REV.
A, 02/01/2018 WITH BMCD# 97179-5.2970-08496 COMMENTS, AND PAYNE & DOLAN WITHERUP

LA
B
EMAIL CORRESPONDENCE TO WITHERUP FABRICATION ON 3/15/2018.
FABRICATION AND

HI
GH
PO
TOP/SLAB ERECTION, INC.

IN
T
-2" BELOW SLAB HIGH POINT
CLIENT
TO 3/16
P/ " B
-2

SL EL
AB O
W
SL

NOT FOR
AB

#5 REBAR @ 12" O.C., EA. WAY


HI
GH

SLAB REINFORCING CONSTRUCTION


PO

REF. 1/F101, TYP.


IN
T

TO
-2

P/
3/1

SL
6"

AB
35'-0" DIA. FIRE WATER

UMERC F.D. KUESTER GENERATING STATION


BE
STORAGE TANK LO

UMERC A.J. MIHM GENERATING STATION


W
SL
AB
EQUAL, TYP.

STORAGE TANK
HI
G H

SLOPE 1" V : 10'-0" H


PO

REF. PLAN NOTE 1

FIRE WATER
CTR. OF TANK / CTR. FOUNDATION IN
HIGH POINT OF SLAB T
REF. FOUNDATION ELEVATION
& LOCATION SCHEDULE
1 1
TYP. F101 F101
TOP/SLAB TOP/SLAB
40'-0"

SLOPE 1" V : 10'-0" H SLOPE 1" V : 10'-0" H


-2" BELOW SLAB HIGH POINT REF. PLAN NOTE 1 REF. PLAN NOTE 1 -2" BELOW SLAB HIGH POINT

SLOPE 1" V : 10'-0" H


REF. PLAN NOTE 1
STAGGER LAP SPLICES
@ ADJACENT BARS, TYP.
EQUAL, TYP.

BOTTOM BARS
135

REF. 1/F101, TYP.


°, TY
P.

TO
P/
SL

-2

3-16-2018 UPDATED PER BMCD COMMENTS


NT

AB

3 /16
I
PO

"B
GH

DESCRIPTION
EL
OW
HI
AB

SL

1-24-2018 ISSUED FOR APPROVAL


REVISION SCHEDULE
SL

AB
W
6" B

HI
LO
3/1 /SLA

GH
BE
P

PO
TO

IN
2'-4" LAP @ BOTTOM BARS, TYP.

T
-2

TO
-2
"B

P/
SL
EL

AB
OW
T
IN

SL
PO

AB
GH

HI
GH
HI

DATE
AB

PO
EL LAB
SL

IN
T
OW
S
P/
TO
"B

NO.
PERIMETER BARS
-2

A
B
REF. 1/F101, TYP.
TO 3/16

STATE OF MICHIGAN
-2" BELOW SLAB HIGH POINT

P/ " B
-2

DATE: 1/24/2018
SL E

PROFESSIONAL ENGINEER
AB LO
T
IN

ENGINEER: DAN KLEIN


PO

DRAWN BY: DAN KLEIN


GH

W
HI

CHECKED BY: JARED MARUGG


SL
AB

AB
SL

SCALE: AS NOTED
HI
W
B

GH
LO
3/1 /SLA

PROJECT NUMBER:
TOP/SLAB
BE

PO
P
6"

IN
TO

T
-2

40'-0" REF. SHT. F101 FOR FOUNDATION


DESIGN AND
CONSTRUCTION PLAN
FOUNDATION PLAN 1 SPECIFICATIONS

FIRE WATER STORAGE TANK F100 DANIEL M. KLEIN


SCALE: 3/8" = 1'-0" LICENSE # 6201056325 F100
FOUNDATION DESIGN CRITERIA CONCRETE - GENERAL

1. DESIGN BASIS - BMCD SPECIFICATION 2970 FOR PROJECT 97179, AUGUST 29, 2017 AND REVISED REFERENCE DRAWINGS RECEIVED 1. CONCRETE CONSTRUCTION SHALL CONFORM TO THE LATEST EDITION OF ACI 301, ACI 318, 302.1, AND THESE PLANS, DETAILS AND
VIA EMAIL ON JANUARY 23, 2018. ALL MATERIALS AND CONSTRUCTION SHALL MEET THE REQUIREMENTS OF THESE DOCUMENTS, SPECIFICATIONS.
AND THE REFERENCE DOCUMENTS AND SPECIFICATIONS. 2. COLD WEATHER CONCRETING SHALL MEET THE REQUIREMENTS OF “STANDARD SPECIFICATION FOR COLD WEATHER
2. FOUNDATION LOADS - WITHERUP FABRICATION AND ERECTION, INC. TANK DESIGN DRAWING S1, REV. 0, 1/4/2018. CONCRETING”, ACI 306.1, LATEST EDITION.
3. FOUNDATION ELEVATIONS - WITHERUP FABRICATION DRAWING 17586, REV. A, SHEET 1, 02/01/18 WITH BMCD# 3. HOT WEATHER CONCRETING SHALL MEET THE REQUIREMENTS OF “SPECIFICATION FOR HOT WEATHER
CONCRETING”, ACI 305.1, LATEST EDITION.
PAYNE & DOLAN
97179-5.2970-08496 COMMENTS. PAYNE & DOLAN EMAIL CORRESPONDENCE TO WITHERUP FABRICATION ON 3/15/2018. INCORPORATED
4. FOUNDATION LOCATIONS AND ORIENTATION - BMCD DRAWINGS K-SF148, REV 0 AND M-SF148, REV 0. A WALBEC GROUP COMPANY
5. GEOTECHNICAL DESIGN - COLEMAN ENGINEERING REPORT OF GEOTECHNICAL INVESTIGATION FOR KUESTER GENERATING STATION, BASE SLAB
W6380 Design Drive | Greenville, Wisconsin 54942
JULY, 2017 AND COLEMAN ENGINEERING REPORT OF GEOTECHNICAL INVESTIGATION FOR MIHM GENERATING STATION, ADDENDUM TEL 920.757.7550 | FAX 920.757.2906
#1, SEPTEMBER 12, 2017. 1. TANK BOTTOM CUSHION SHALL BE PROVIDED BY TANK MANUFACTURER IN ACCORDANCE WITH AWWA D100, SECTION 12.6. www.payneanddolan.com

6. TANK GENERAL ARRANGEMENT - WITHERUP FABRICATION AND ERECTION, INC. TANK DESIGN DRAWING S1, REV. 0, 1/4/2018. 2. TOLERANCES ON SLAB FINISH SHALL BE IN ACCARDANCE WITH AWWA D100, SECTION 12.6.2.
7. SLAB EMBEDDED ITEMS - NONE. 3. BASE SLAB SHALL BE POURED MONOLITHICALLY
8. TANK BASE INSTALLATION DETAILS BY OTHERS. 4. REBAR BENDING SHALL BE PERFORMED IN ACCORDANCE WITH THE LATEST EDITIONS OF ACI 315, ACI 318, AND CRSI “MANUAL OF
9. MECHANICAL ANCHORAGE OF TANK IS NOT REQUIRED PER THE APPROVED TANK DESIGN. CONCRETE PRACTICE”.
10.DESIGN AND INSTALLATION OF TANK GROUNDING BY OTHERS. FOUNDATION CONTRACTOR TO COORDINATE GROUNDING SYSTEM 5. VIBRATE CONCRETE AS NECESSARY TO CONSOLIDATE CONCRETE AROUND REBAR AND PREVENT VOIDS.
6. REBAR SPLICES SHALL BE CLASS B LAP SPLICES.
INSTALLATION WITH OWNER PRIOR TO COMMENCING FOUNDATION CONSTRUCTION.
7. LAP SPLICES OF ADJACENT BARS SHALL BE STAGGERED SO THAT ADJACENT BAR SPLICES DO NOT OVERLAP. STAGGER LENGTH SHALL WITHERUP
GENERAL SPECIFICATIONS BE NOT LESS THAN THE LAP LENGTH SPECIFIED BELOW. FABRICATION AND
8. MINIMUM REBAR LAP SPLICE LENGTHS: #5 REBAR - 2'-0”.
1. THE SCOPE OF THIS PLAN AND SPECIFICATION IS FOR THE GEOSTRUCTURAL AND STRUCTURAL DESIGN AND CONSTRUCTION OF THE #6 REBAR - SEE PLAN. ERECTION, INC.
TANK FOUNDATION ONLY. 9. SLAB SHALL BE FINISHED FLAT AND LEVEL UNLESS OTHERWISE NOTED ON THE PLANS.
2. OBTAIN ALL REQUIRED PERMITS AND APPROVALS PRIOR TO MATERIAL PROCUREMENT AND CONSTRUCTION. 10.SLAB SHALL BE MAGNESIUM TROWEL FINISHED. CLIENT
3. THE CONTRACTOR SHALL FIELD VERIFY ALL ELEVATIONS AND DIMENSIONS PRIOR TO CONSTRUCTION. 11.CHAMFER EXPOSED CONCRETE EDGES ¾” X 45 DEGREES.
4. THE CONTRACTOR SHALL COMPLY WITH ALL FEDERAL AND STATE REQUIREMENTS FOR CONSTRUCTION SAFETY, CONSTRUCTION 12.DO NOT LOAD SLAB UNTIL THE SPECIFIED DESIGN COMPRESSIVE STRENGTH OF THE CONCRETE IS ACHIEVED.
PERSONNEL SAFETY, MAINTENANCE PERSONNEL SAFETY AND GENERAL PUBLIC SAFETY.
5. COORDINATE RELOCATION OF EXISTING UTILITIES AS REQUIRED WITH OWNER PRIOR TO CONSTRUCTION. USE OF DOCUMENTS
6. THE CONTRACTOR SHALL PROTECT ALL STRUCTURES, EQUIPMENT, PIPING AND ELECTRICAL SYSTEMS AND SITE IMPROVEMENTS
DURING CONSTRUCTION. 1. THE USE OF THESE PLANS, DETAILS OR SPECIFICATIONS FOR OTHER LOADING CONDITIONS OR OTHER PROJECTS IS PROHIBITED NOT FOR
WITHOUT THE WRITTEN CONSENT OF PAYNE & DOLAN, INC.
7. THE OWNER SHALL IDENTIFY TO THE CONTRACTOR THE LOCATION OF ALL UNDERGROUND UTILITIES AND UNDERGROUND
STRUCTURES IN THE VICINITY OF AND BELOW THE PROPOSED BASE SLABS, EXCAVATIONS AND GRADING PRIOR TO CONSTRUCTION.
CONSTRUCTION
8. THE OWNER IS RESPONSIBLE FOR IDENTIFICATION OF POTENTIAL ENVIRONMENTAL AND PERSONNEL SAFETY HAZARDS TO THE
CONTRACTOR PRIOR TO CONSTRUCTION.
9. HANDLING AND DISPOSAL OF POTENTIAL ENVIRONMENTAL HAZARDS SHALL BE IN ACCORDANCE WITH ALL STATE AND FEDERAL

UMERC F.D. KUESTER GENERATING STATION


REQUIREMENTS.
10.THE FOUNDATION SHALL BE PLACED USING METHODS THAT WILL NOT DAMAGE EXISTING FACILITIES.

UMERC A.J. MIHM GENERATING STATION


11.CONTACT THE ENGINEER FOR DIRECTION IF FIELD CONDITIONS DO NOT AGREE WITH THE PLANS AND SPECIFICATIONS.

STORAGE TANK
REFERENCE SPECIFICATIONS 10'-0" MIN.

VARIES, SEE PLAN

FIRE WATER
3
4"x45° CHAMFER

SEE PLAN
1. MICHIGAN BUILDING CODE, 2015 EDITION.

VARIES
2. AWWA D100-11 - “WELDED CARBON STEEL TANKS FOR WATER STORAGE”. #5 REBAR @ 12" O.C. EA. WAY
3. ASCE 7-10 - “MINIMUM DESIGN LOADS FOR BUILDINGS AND OTHER STRUCTURES”. (3) - #6 PERIMETER BARS
@ EQ. SPACING SLOPE 1" V : 10'-0" H
4. ACI 318-14 - “BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE”

41 2" CLR.
TOP/SLAB
SEE PLAN
SUBMITTALS
FIN. GRADE
1. SUBMIT REBAR SHOP DETAIL AND PLACEMENT DRAWINGS TO THE DESIGN ENGINEER FOR REVIEW AND APPROVAL PRIOR TO SLOPE 8% REF. SECTION NOTE 1
FABRICATING REBAR.
PER

1'-10"
FINISH GRADE

1'-8"
4" CLR.
INSPECTIONS AND TESTING ICATIONS 4" 1
UMERC SPECIF
1. INSPECTIONS AND MATERIAL TESTING SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT. 1.5
2. SUBGRADE AND FOUNDATION FILL COMPACTION TESTING SHALL BE AS SPECIFIED IN THE COLEMAN GEOTECHNICAL REPORTS.
3. ALL INSPECTION REPORTS AND TEST RESULTS SHALL BE SUBMITTED TO THE OWNER FOR REVIEW AND APPROVAL.

MATERIALS 4" CLR.


(5) - #6 REBAR @ EQ. SPACING
1. STRUCTURAL FILL BELOW THE BASE SLAB SHALL BE A NON FROST SUSCEPTIBLE MATERIAL CONFORMING TO MDOT CLASS IIA SAND CONTINUOUS, BOTTOM

3'-2" MIN.
OR EQUAL. 2" MUD SLAB
2. MINIMUM REQUIRED BEARING CAPACITY FOR STRUCTURAL FILL IS 2,500 PSF. NON FROST SUSCEPTIBLE
3. REBAR - ASTM A615 GR. 60. STRUCTURAL FILL
4. CONCRETE FOR BASE SLAB: MDOT CLASS IIA SAND
A. f'c=4,500 PSI MIN. COMPRESSIVE STRENGTH AT 28 DAYS. (OR EQUAL)
B. CONCRETE MIX SHALL BE PROPORTIONED BASED ON THE FOLLOWING EXPOSURE CATEGORIES AND CLASSES REFERENCING ACI

3-16-2018 UPDATED PER BMCD COMMENTS


318-14, SECTION 19.3.1:
I. FREEZING AND THAWING - F1 SECTION NOTES

DESCRIPTION
II. SULFATE - S0 3'-6" 5'-4"
III. IN CONTACT WITH WATER - W0 1. REF. BURNS & MCDONNELL PLANS FOR FINISH GRADE ELEVATION.

1-24-2018 ISSUED FOR APPROVAL


REVISION SCHEDULE
IV. CORROSION - C1 2. FIRE WATER STORAGE TANK NOT SHOWN.
C. CONCRETE SLUMP - MAXIMUM CONCRETE SLUMP IS 4” AT TIME OF PLACEMENT.
D. CONCRETE MIXTURES SHALL COMPLY WITH THE REQUIREMENTS OF ACI 318-14, SECTION 19.3.2.
E. CAST IN PLACE CONCRETE SHALL BE IN CONFORMANCE WITH BMCD SPECIFICATION 2970 FOR PROJECT 97179, AUGUST 29, 2017, TYP. FOUNDATION SECTION 1
SECTION 03 30 00.
FIRE WATER STORAGE TANK F100
EARTHWORK SCALE: 3/4" = 1'-0"

1. EROSION CONTROL MEASURES SHALL BE PROVIDED IN ACCORDANCE WITH STATE OF MICHIGAN REQUIREMENTS AND BEST
PRACTICE RECOMMENDATIONS.
2. OWNER TO LOCATE AND MARK ALL UNDERGROUND UTILITIES AND STRUCTURES WITHIN THE CONSTRUCTION BOUNDARY PRIOR TO

DATE
CONSTRUCTION.
3. THE CONTRACTOR SHALL CONTACT DIGGERS HOTLINE TO MARK UNDERGROUND UTILITIES PRIOR TO CONSTRUCTION.
4. CONTACT THE ENGINEER FOR DIRECTION IF GROUNDWATER IS ENCOUNTERED IN THE EXCAVATIONS.
5. THE CONTRACTOR SHALL KEEP EXCAVATIONS DRY DURING CONSTRUCTION.

NO.
6. STOCKPILED FILL MATERIALS SHALL BE KEPT DRY DURING CONSTRUCTION.

A
B
7. NO HOLES, TRENCHES, OR DISTURBANCES OF THE SOIL SHALL BE ALLOWED WITHIN THE VOLUME
DESCRIBED BY 45 DEGREE LINES SLOPING FROM THE BOTTOM EDGE OF THE EXISTING FOUNDATIONS. STATE OF MICHIGAN
DATE: 1/24/2018
DO NOT UNDERMINE EXISTING SLABS OR FOUNDATIONS. PROFESSIONAL ENGINEER
8. REMOVE ALL TOPSOIL, UNSUITABLE SOILS, ORGANIC MATERIALS, DEBRIS, ETC. BELOW THE OPEN GRADED STRUCTURAL FILL. ENGINEER: DAN KLEIN
9. COMPACT THE SUB-GRADE PRIOR TO PLACEMENT OF STRUCTURAL FILL. DRAWN BY: DAN KLEIN
10.MINIMUM REQUIRED SUBGRADE BEARING CAPACITY FOR SLAB CONSTRUCTION IS 2,500 PSF. VERIFY THE SUB-GRADE BEARING CHECKED BY: JARED MARUGG
CAPACITY PRIOR TO PLACEMENT OF STRUCTURAL FILL. IF THE SUB-GRADE BEARING CAPACITY BELOW THE STRUCTURAL SLAB IS LESS SCALE: AS NOTED
THAN 2,500 PSF, NOTIFY THE ENGINEER FOR DIRECTION BEFORE PROCEEDING WITH FOUNDATION CONSTRUCTION.
PROJECT NUMBER:
11.DO NOT PLACE FILL MATERIALS OR CONCRETE ON FROZEN GROUND, ICE OR SNOW.
12.ALL BEDDING AND FILL MATERIALS SHALL BE CLEAN, INORGANIC GRANULAR MATERIAL, FREE OF ICE, SNOW, DEBRIS AND LARGE
ROCKS. REF. SHT. F100 FOR SPECIFICATIONS
13.STRUCTURAL FILL SHALL BE PLACED IN LIFTS NOT EXCEEDING 12" IN LOOSE THICKNESS. EACH LIFT SHALL BE COMPACTED TO A FOUNDATION PLAN FOR FOUNDATION
MINIMUM OF 98% OF STANDARD PROCTOR (ASTM D-698) MAXIMUM DRY DENSITY.
14.PLACE MUD SLAB IMMEDIATELY AFTER PLACEMENT OF STRUCTURAL FILL. DESIGN &
15.CONCRETE FOR MUD SLAB SHALL BE f'c = 2000 PSI.
CONSTRUCTION
DANIEL M. KLEIN
LICENSE # 6201056325 F101

You might also like