This document provides budget information for PT "ABC" including quarterly production budgets and realizations, budgeted and realized raw material and direct labor costs per unit, and total annual budgets and realizations. It asks to prepare a raw material cost budget, direct labor cost budget, and variance analysis for raw material and direct labor costs.
This document provides budget information for PT "ABC" including quarterly production budgets and realizations, budgeted and realized raw material and direct labor costs per unit, and total annual budgets and realizations. It asks to prepare a raw material cost budget, direct labor cost budget, and variance analysis for raw material and direct labor costs.
This document provides budget information for PT "ABC" including quarterly production budgets and realizations, budgeted and realized raw material and direct labor costs per unit, and total annual budgets and realizations. It asks to prepare a raw material cost budget, direct labor cost budget, and variance analysis for raw material and direct labor costs.
a. Raw Material and Direct Labour Cost : Period Production Production Budget Realization Budget Realization Budget Realization SUR Raw Material Direct Labour Hour per unit product per unit product
Q1 200,000 180,000 2 3 4 3
Q2 225,000 200,000 2 3 4 3
Q3 250,000 275,000 2 3 4 3
Q4 275,000 300,000 2 3 4 3
Total 950,000 955,000
Budget Realization Budget Realization
Price per unit Direct Labour Hour Raw Material (IDR) Cost per DLH
2,500 2,000 1,500 1,750
Prepare: a. Raw Material Cost Budget b. Direct Labour Cost Budget c. Prepare Variance Analysis for Raw Material Cost and Direct Labour Cost