Professional Documents
Culture Documents
30 Superlift
30.1 General
665--1300--041_en 1/85
30
6
7
Z 30 428
2/85 665--1300--041_en
Superlift 30
30.2 Components
(Z 30 428)
665--1300--041_en 3/85
30
1S
1
Z 30 429
4/85 665--1300--041_en
Superlift 30
Since the crane may not be driven on public roads with the Super-
lift attached, the Superlift must be transported separately on a
low--loader.
665--1300--041_en 5/85
30
Z 26 185
6/85 665--1300--041_en
Superlift 30
665--1300--041_en 7/85
30
Z 30 430
9a
Z 30 431
8/85 665--1300--041_en
Superlift 30
30.5 Attachment
(Z 30 430, Z 30 431)
(Z 30 431)
2. Fasten bracing rods (9a) with pins onto the foot section of the
main boom base section, and secure with fore locks.
In both cases, insert pins from the outside inwards, and se-
cure with fore locks so that the bracing support does not
damage the pin head when being lowered.
665--1300--041_en 9/85
30
19
Z 30 449 Z 30 450
10/85 665--1300--041_en
Superlift 30
(Z 30 449, Z 30 450)
665--1300--041_en 11/85
30
”D”
”E”
1
13
”C”
3
”B”
”A”
Z 30 457
12/85 665--1300--041_en
Superlift 30
(Z 30 457)
665--1300--041_en 13/85
30
Z 30 432
Z 30 433
14/85 665--1300--041_en
Superlift 30
(Z 30 432, Z 30 433)
5. Attach auxiliary ropes to the 3 eyes provided on bracing sup-
port (4) and hook the ropes to the auxiliary crane.
665--1300--041_en 15/85
30
11
Z 30 434
Z 30 458
16/85 665--1300--041_en
Superlift 30
(Z 30 434, Z 30 458)
6. Raise the Superlift using auxiliary crane, position the bracing
support in the basic bolts (11) on the main boom base section
and insert and guard locking pins (Z 30 458).
665--1300--041_en 17/85
30
Z 30 460
”C”
Z 30 435
18/85 665--1300--041_en
Superlift 30
7. Lower bracing support onto the base section using the auxil-
iary crane.
(Z 30 435)
9. Disconnect drop--back retaining rope (3) at point ”C” on
deflection roller (1) and lower the latter onto the main boom.
Risk of falling
The drop--back retaining rope is to be disconnected from
the side using a ladder and/or lifting platform.
However, should this be carried out from the base sec-
tion, then the crane operator is to guard against falling
by wearing a safety harness, before the rope is discon-
nected from the deflection roller. Furthermore, there is
also a risk of stumbling on the thimble of the discon-
nected drop--back retaining rope.
Risk of crushing.
When lowering the deflection roller there is a risk that
people may be crushed between the deflection roller and
the base section. It is prohibited to remain in the danger
zone.
665--1300--041_en 19/85
30
13
Z 30 461
1 1
2 2
3
3
Z 30 436
20/85 665--1300--041_en
Superlift 30
(Z 30 461)
11. Disconnect the connecting brackets from their transport
position of deflection roller (1) by removing pins (13).
(Z 30 436)
12. Fasten connecting brackets (3) of the deflection roller to
shackles (2) of the third boom section using the pins which
have already been removed, and guard.
Pins (13) are inserted from the outside inwards, and secured
with fore locks.
Risk of falling.
The deflection rollers are to be pinned to shackles on the
3rd and/or 4th boom sections (main boom head). This is
to be carried out from the side using ladders and/or lift-
ing platforms.
665--1300--041_en 21/85
30
Z 30 437
Z 30 447
22/85 665--1300--041_en
Superlift 30
(Z 30 437, Z 30 447)
13. Disconnect the bracing support from deflection roller
(Z 30 437) and the main boom from deflection roller
(Z 30 447) by removing the pins.
The main boom and deflection roller (Z 30 447) are only con-
nected if the deflection roller has already been lowered onto the
main boom in the transport position.
665--1300--041_en 23/85
30
Q 38
S38
Z 30 438
24/85 665--1300--041_en
Superlift 30
Hydraulic Connections
(Z 30 438)
Electrical Connection
(Z 30 438)
The distribution box (”X 38”) on the bracing support must be con-
nected to the distribution box (”X 510”) on the base section of the
main boom Insert plug (”Q 38”) into socket (”Q 38A”) on distribu-
tion box (”X 38”).
665--1300--041_en 25/85
30
12
Z 32 812
AUF
ZU
Z 36 744
26/85 665--1300--041_en
Superlift 30
(Z 32 812)
14. Extend erection cylinder (8). For this to happen, there must
first be a supply of hydraulic oil. Position the two three--way
directional control valves (12) on the main boom base sec-
tion as shown. This position is marked I. Especially pay
attention that the marker notches at the square are posi-
tioned correctly.
15. Press button (79) in the crane operator’s cab when the su-
perstructure engine is running. The erection cylinder ex-
tends and thus raises the bracing support.
Raise the bracing support until the deflection roller(s) of the hoist
rope and/or the deflection roller for the rope of the Superlift brac-
ing winch on the head of the bracing support is at operating
height.
The rope must only be reeved when the Superlift is erected for
the first time. This rope then remains reeved. As a rule, this rope
is already reeved when delivered to the customer.
If the rope is reeved, then proceed with point ”17.”.
(Z 36 744)
16.1 Move shut--off valve (30) on the upper right rim of the
superstructure hydraulic block (behind the cap cover)
to the ”ZU” position, as shown. This results in the wind-
ing speed of the bracing winch being reduced, which
is only permissible for reeving the rope of the bracing
winch.
665--1300--041_en 27/85
30
12
1
7
13
11
14
2 10
5
Z 30 442
Z 36 745
28/85 665--1300--041_en
Superlift 30
(Z 30 442)
16.3 Reeve the bracing winch rope. The rope is unwound
from bracing winch (7) -- on the left hand side on the
foot of the bracing support -- and fed through to the fix-
ing point on the right hand side of the head of the brac-
ing winch, via deflection roller (5) in the head of the
bracing support and deflection roller (1) which is
mounted on the main boom.
Rope socket (11) is attached to the shackle there with
pin (12), using 2 supporting discs (13). It is then se-
cured using pin lock (14), which consists of a pipe with
screw and nut (countered or secured using Loctite).
(Z 36 745)
16.4 Once the rope of the bracing winch is reeved and se-
cured, move shut--off valve (30) to the position ”AUF”
as shown.
665--1300--041_en 29/85
30
12 ”B” ”C” 12
11 14
13 11
C
D
13
Z 30 445
13
12
16
15
Z 30 446
30/85 665--1300--041_en
Superlift 30
(Z 30 445, Z 30 446)
17. Connect bracing rods (15), which have already been se-
cured to the main boom (L = 6000 mm and L = 2510 mm) and
bracing rods (13, L = 4500 mm) and shackles (12), which are
in the transport position on the bracing support.
This connection must be made for the left and right hand bracing
rod strand.
(Z 30 445)
17.1 Release bracing rods (13) from their transport position,
by removing forelocks (11) and then the corresponding
shackle (12) and bracing rod (13) from pin (14).
Pins which are released are to be placed on the ap-
propriate plate at point ”D” and secured with fore locks.
(Z 30 446)
17.2 Fasten the free end of shackle (12) with the free end
of bracing rod (15) onto the main boom using pin (16)
and guard with fore locks.
If this is carried out on the left and right hand side, then both brac-
ing rod strands are closed.
Insert pins from the outside inwards and secure with fore
locks so that the bracing support does not damage the pin
cone when being lowered.
665--1300--041_en 31/85
30
5.2 5.1
5.1
29
28
Z 30 439 Z 30 440
32/85 665--1300--041_en
Superlift 30
(Z 30 439)
18. Fold deflection roller (5.1) and/or (5.2) into operating position
in order to reeve the hoist rope.
Pull out pin (28), fold deflection roller(s) up through 90° and
secure in this position again using pin (28). Secure pin with
fore lock.
Should the rope from hoist 1 ever be reeved, then only deflection
roller 5.1 need be used.
(Z 30 440)
19. Release rope run--off safety (29) from deflection roller (5.1).
20. Feed the hoist rope over deflection roller (5.1) to the main
boom head section, and reeve the hook block.
When the hoist rope is being drawn in and also when the
hook block is being reeved, there is a danger of items
being caught and dragged in at the deflection rollers and
at the hook block.
Proceed in an appropriately cautious manner and ensure
that safety guards, such as a run--in protection, are fitted.
22. Fully extend the erection cylinder. The angle of the bracing
support to the main boom is approximately 10°.
23. Now check that the proximity switch S 39.1 (bracing support
rests on erection cylinder) is correctly activated.
Press luminous pushbutton (82) ”Reel in bracing rope”. The
light in the button must illuminate and the bracing winch
draws the bracing rope taut.
Briefly press luminous pushbutton (81) , and thus activate
”Reel out bracing rope”.
Both movements must function correctly.
If this is not the case then the Superlift may not start to
be fitted. The error must first be amended.
665--1300--041_en 33/85
30
Z 30 437 Z 30 447
”B” ”D”
Z 30 455
34/85 665--1300--041_en
Superlift 30
665--1300--041_en 35/85
30
12
Z 30 462
36/85 665--1300--041_en
Superlift 30
(Z 30 462)
3. By pressing button (109) in the crane operator’s cab, unpin
telescopic section 2 and extend it using control lever (26) un-
til the bracing support just starts to lift away from erection cyl-
inder (8) (maximum 20 mm).
665--1300--041_en 37/85
30
38/85 665--1300--041_en
Superlift 30
The length of the main boom and the extent to which the tele-
scopic section has been extended are indicated on the ECIS con-
sole.
665--1300--041_en 39/85
30
”K”
Z 30 451
40/85 665--1300--041_en
Superlift 30
(Z 30 451)
7. Secure drop--back retaining rope (3) to point ”K” of the main
boom base section with pins, and guard.
Risk of falling.
The drop--back retaining rope is to be pin locked to the
main boom from the side using ladders and/or lifting
platforms.
However, should this be carried out from the main boom,
the crane operator is to guard against falling by wearing
a safety harness before the rope is fastened to the main
boom.
665--1300--041_en 41/85
30
1
”A” ”B”
Z 30 454
42/85 665--1300--041_en
Superlift 30
(Z 30 454)
When operating the Superlift on the main boom, deflection roller
(1) of the bracing rope is to be pinned to the head of the 3rd tele-
scopic section (”A”).
Before operation with the Superlift, the brake disc of the bracing
winch is to be checked for clogging. Clean the disc with wire wool
if necessary.
665--1300--041_en 43/85
30
44/85 665--1300--041_en
Superlift 30
The code number and length code must be set according to the
crane configuration and the desired main boom length.
Make sure that the bracing rods are not taut once the unlock-
ing has taken place.
If they are taut, however, the boom MUST be retracted by a
minimal amount so that the bracing rods hang down slightly.
Only then may the bracing winch be switched to wind in and
the telescoping out procedure thus continued.
665--1300--041_en 45/85
30
46/85 665--1300--041_en
Superlift 30
665--1300--041_en 47/85
30
Z 30 453
48/85 665--1300--041_en
Superlift 30
(Z 30 453)
5. When the main boom has been extended to its final operat-
ing length and pin locked, retract all the telescopic sections
together to the stop.
This prevents overloading of the telescope cylinders and set-
tling movements of the boom sections when the load is
picked up.
(Z 30 453)
6. Check to see that the rope of the bracing winch (2) rope and
the bracing rods (9) are not sagging and move the main
boom using the luffing gear into its operating position.
Should the rope have visible slack, i.e. bracing rope (2) by
more than 100 mm, bracing rods (9) by more than 50 mm,
then the system is to be pretensioned again by gently tele-
scoping in, and then back out again.
Please refer to Section 30.7.3 ”Checking the Main Boom
Bracing”.
665--1300--041_en 49/85
30
50/85 665--1300--041_en
Superlift 30
30.7.2.2 Telescoping In
The code number and length code must be set according to the
crane configuration and the desired main boom length.
665--1300--041_en 51/85
30
52/85 665--1300--041_en
Superlift 30
When telescoping in, the bracing support rests against the rope
of the fall--back safety device.
665--1300--041_en 53/85
30
Z 30 453
54/85 665--1300--041_en
Superlift 30
(Z 30 453)
5. When the main boom has been extended to its final operat-
ing length and pin locked, retract all the telescopic sections
together to the stop.
This prevents overloading of the telescopic cylinders and
settling movements of the boom sections when the load is
picked up.
6. Check to see that bracing winch (2) and bracing rods (9) are
not sagging, and move the main boom into its operating posi-
tion using the luffing cylinder.
If the rope of the bracing winch and bracing rods show vis-
ible signs of slack, i.e. bracing rope (2) more than 100 mm,
bracing rods (9) more than 50 mm, then the system is to be
pretensioned by telescoping in slightly and then telescoping
out again.
Please refer to Section 30.7.3 ”Checking the Main Boom
Bracing”.
665--1300--041_en 55/85
30
56/85 665--1300--041_en
Superlift 30
Before placing the crane under load in Superlift mode, the boom
bracing must be checked for proper pretension. If the bracing
rope is visibly sagging, by more than 100 mm, and the bracing
rods by more than 50 mm, -- then the boom bracing must be re-
tensioned by telescoping out the main boom.
Proceed as follows:
665--1300--041_en 57/85
30
Z 30 453
58/85 665--1300--041_en
Superlift 30
(Z 30 453)
8. Check to see if the rope of bracing winch (2) and bracing rods
(9) are showing any signs of slack.
By doing this it is possible to determine whether the prelimi-
nary tension in this position is correct. Bracing rope (2) and
bracing rods (9) must be slightly taut.
If there are visible signs of slack, i.e. bracing rope (2) by more
than 100 mm, bracing rods (9) by more than 50 mm, then the
tensioning procedure described must be repeated once
again.
If, after a Superlift hoist, this pretension has changed and the
main boom angle has remained the same, the function of the
band brake of the bracing winch must be checked. Call the
service department at ”MANNESMANN DEMAG Fördertech-
nik, Mobile Cranes” to carry out this check.
665--1300--041_en 59/85
30
60/85 665--1300--041_en
Superlift 30
The details needed for reeving the hoist rope and/or for guiding
the hoist rope can be found in Section 17 ”Reeving” and in Sec-
tion 18 ”Main boom extension”.
Before the bracing support is erected, the fixed fly jib must al-
ready be attached to the main boom head. Please refer to Sec-
tion 20 ”Fixed fly jib”.
The details needed for reeving the hoist rope and/or guiding the
hoist rope can be found in Section 17 ”Reeving” and in Section
20 ”Fixed fly jib”.
665--1300--041_en 61/85
30
62/85 665--1300--041_en
Superlift 30
The procedures for attaching and erecting the luffing fly jib with
the Superlift are described in Section 27 ”luffing fly jib with Super-
lift”.
The details needed for reeving the hoist rope and/or guiding the
hoist rope can be found in Section 17 ”Reeving” and Section 27
”Luffing fly jib with Superlift”.
665--1300--041_en 63/85
30
64/85 665--1300--041_en
Superlift 30
Check the main boom length and angle on the ECIS display.
665--1300--041_en 65/85
30
66/85 665--1300--041_en
Superlift 30
665--1300--041_en 67/85
30
”K”
Z 30 451
68/85 665--1300--041_en
Superlift 30
(Z 30 451, Z 30 455)
4. Release drop--back retaining rope (3) at point ”K” on the
main boom.
Risk of falling.
The drop--back retaining rope on the main boom is to be
released from the side using ladders and/or lifting plat-
forms.
However, should this be carried out from the main boom,
then the crane operator is to guard against falling by
wearing a safety harness, before the rope on the main
boom is released.
665--1300--041_en 69/85
30
12
Z 30 462
Z 30 456 Z 30 460
70/85 665--1300--041_en
Superlift 30
(Z 30 462)
5. Now check whether erection cylinder (8) is completely ex-
tended.
If not, press pushbutton (79) in the crane operator’s cab to
fully extend the erection cylinder.
RISK OF ACCIDENTS!
When the erection cylinder is retracted, there is a risk,
with certain angle ratios, of the bracing support falling
through unchecked.
8. Lower the hook block onto the ground and slacken the hoist
rope by operating the hoist gear.
665--1300--041_en 71/85
30
13
12
16
15
Z 30 446
12 ”B” ”C” 12
11 14
13 11
C
D
13
Z 30 445
72/85 665--1300--041_en
Superlift 30
(Z 30 446)
10. Release the connection of shackles (12) to bracing rod (15)
by removing pins (16).
(Z 30 445)
11. Remove pins (14) from transport position at ”D”, move to
bracing support (”C”), fit each shackle (12), and secure with
fore locks.
This must be done for the left and right hand bracing rod strand.
The weight of one bracing rod (L = 4500 mm) is approximately
54 kg.
665--1300--041_en 73/85
30
5.2 5.1
5.1
29
28
Z 30 440 Z 30 439
”B” ”A”
Z 30 455 Z 30 437
74/85 665--1300--041_en
Superlift 30
(Z 30 440)
12. Remove rope run--off safety (29) for reeved deflection roller
(5.1).
13. Retract erection cylinder and at the same time unreel the
rope of the bracing winch slightly by actuating pushbutton
(81) in the crane operator’s cab.
(Z 30 439)
14. Unreeve hoist rope from deflection roller (5.1), and set down
between both deflection roller (5.1) and (5.2). When the rope
has been unreeved, attach rope run--off safety (29) again,
fold deflection roller(s) in transport position, insert pin (28)
and guard.
(Z 30 455)
15. Connect the free end of the drop--back retaining rope (3) to
the bracing support at point ”A” (transport support) by insert-
ing and guarding pin(s).
(Z 30 437)
17. Fully telescope in main boom and when the exact pin locking
position has been reached, connect the bracing support and
deflection roller by inserting pins.
Insert pins from outside inwards and secure with fore locks.
665--1300--041_en 75/85
30
1 1
2 2
3
3
Z 30 436
13
Z 30 461
76/85 665--1300--041_en
Superlift 30
(Z 30 436)
18. Remove the shackles (3) which connect the deflection roller
to the main boom by withdrawing the pins on shackles (2) of
the 3rd telescopic section or the pins on shackles (1) of the
main boom head.
(Z 30 461)
19. Move the deflection roller’s connecting brackets to transport
position, insert pins (13) and guard.
20. The rope of the bracing winch remains reeved and does not
need any additional safety locks.
The Superlift can now either be removed from the crane (Sec-
tion 30.9 ”Removing the Superlift”) or secured on the main boom
base section in transport position, e.g. for technical driveability
(Section 30.10, ”Superlift Remaining on the Main Boom”).
665--1300--041_en 77/85
30
Q 38
S 38
Z 30 438
78/85 665--1300--041_en
Superlift 30
When the bracing support has been lowered, the Superlift can be
removed from the crane as follows.
1. Unreeve the hook block and wind the hoist rope onto the
drum.
(Z 30 438)
2. Disconnect the hydraulic lines between superstructure and
bracing support, and seal the connections with protection
caps.
665--1300--041_en 79/85
30
1
”C”
3
Z 30 435
Z 30 432
15
Z 30 463
80/85 665--1300--041_en
Superlift 30
(Z 30 435)
4. Raise deflection roller (1) using an auxiliary crane and pin
drop--back retaining rope (3) at point ”C” on the deflection
roller.
(Z 30 432)
5. Disconnect the auxiliary crane from deflection roller, and at-
tach the lifting ropes to the 3 eyes provided on bracing sup-
port (4). Attach the ropes to the auxiliary crane and draw the
ropes taut.
(Z 30 463)
6. Disconnect bracing support from the superstructure by re-
moving pins (15).
665--1300--041_en 81/85
30
1 S
Z 30 429
19
Z 30 449 Z 30 431
82/85 665--1300--041_en
Superlift 30
7. Lift the Superlift off the main boom using the auxiliary crane
and lower onto a transport vehicle or to the ground.
(Z 30 449, Z 30 431)
8. Bracing rods (L = 6000 mm) and (L = 2510 mm) can:
− remain on the main boom, in which case they need to be
secured in their transport position using pins (19,Z 30 449).
or
665--1300--041_en 83/85
30
a
a
9
11
b
Z 30 459
Z 30 447
84/85 665--1300--041_en
Superlift 30
With the Superlift resting on the main boom, the axle loads
are over 12 t.
Not suitable for road transport.
When the bracing support has been lowered (Section 30.8), the
Superlift can be secured in transport position.
-- Bracing rod strands (9) must rest in retainers (11) on the main
boom base section.
-- Both rope guide rollers (13) can be detached and placed in
transport holders (14) on the bracing support in order to be
able to clear the maximum height clearances (up to max.
4000 mm)
Risk of falling.
This work is to be carried out from the side using ladders
and/or lifting platforms.
However, should this work be carried out from the base
section, then the crane operator is to guard against fal-
ling by wearing a safety harness.
(Z 30 447)
-- In addition to the bracing support connection, the deflection
roller of the bracing support must also be pinned to the main
boom base section and secured.
665--1300--041_en 85/85