Professional Documents
Culture Documents
Haarika Reddy K
RICS – CPM (Batch 04)
SWOT analysis
Strength Weakness
Approvals have been applied for already. Finance is not in place on account of
Land is in the possession of the Builder non-availability of statutory approvals.
though Registration is not done. Timely completion of the project on
account of various hurdles enumerated.
Opportunities Threats
Expediting the project could save 1.5 Effect of RERA on the project.
lakhs per flat per month. Cost overruns on account of severe
There is no penalty for late completion of shortage of electric power and water.
the club house. Cost implication in the form of penalty if
HT pylon affects only the periphery. project is not completed on time.
Environment impact due to existence of
100 trees in the site.
Strengths can to be used with a systematic risk mitigation approach to overcome the
weaknesses.
Opportunities have to be used and more may be created in due course to tackle the threats.
Diagrammatic Technique
Approvals Finance
Local statutory
approvals Delay in approvals
Inability to meet
project time lines
Shifting of HT Pylon
Shifting cost
Local statutory
Approvals Penalty due to delay
Shifting cost Shifting cost
Cost
overruns
Shortage of Water
Shifting the Cost for alternate
Line cost arrangements
Electricity shortage
Delay in Approvals
Environmental Existence of about 100 trees in the proposed site may pose
Risks: objections/ retaliation from the Environmentalists and local bodies.
Financial Risks: Non-availability of funding for the project till the time of obtaining
clearances would impact the project commencement date resulting
in the delayed handing over dates and penalties
Organisational These risks may be identified in detail once the project approvals
Risks: are obtained.
Project These risks may be identified in detail once the project approvals
Management are obtained.
Risks:
Risk Matrix:
Risk Risk Description Probability Impact
Number
R1 Failure to complete the project within 3 years Very high Severe
(December 2019)
R2 Failure to obtain the expected regulatory approvals Low Severe
in the initial phases
R3 Failure to achieve local authorities’ timely Moderate Tolerable
involvement to shift the existing systems (Sewer
line, HT pylon)
R4 Failure to go with the initial plan/ layout of the project Very Low Catastrophic
R5 Failure to supply timely power and water for the Very High Tolerable
project
R6 Failure to obtain permanent connections for water High Severe
and electric power supply by project completion
Consequences/ Impact
Very High R5 R1
High R6
Probability
Moderate R3
Low R2
Very Low R4
The above Risk matrix indicates the following major risks to be handled to help in achieving
the major project objectives:
R1 Completion date
R5 Alternative arrangements
R6 Avoid contractual implications / maximize profit or reduce losses
Risk Mitigation Plan:
Note: Reference is drawn to the Risk number given in the Risk Matrix above.
Expedite the process for Registration of the Land on the Builders name or Risk
Avoidance by entering into a legal agreement from the land owner such that the
builder does not have to register the land on the his name and still can take up the
project – all in compliance with the laws as devised in Indian Contract Act and
regulations of RERA.
Risk Mitigation by keeping the financers apprised of the present scenario and being
finance ready by the time statutory approvals are obtained.
This is a Construction Risk which is a result of External Risk and has an impact on the
Finances and Commercials of the project. The Risk mitigation plan for the same would be by
the following activities:
Risk Retention by providing additional funds and resources to supply electric power
and water to the construction site with the help of Diesel Generators, water tankers,
etc.
Risk Mitigation by planning the required finances and resources to supply alternate
means of electric power and water to the construction site with the help of solar
power, bore well supply, etc.
Risk Avoidance by entering into Contract/ Agreement with local authorities to obtain
minimum reserved/ fixed supply for the Contract period. This may involve additional
terms and conditions put forth by the authorities in the form of transferring solar
power generated at a later date to the EB grid/ develop additional low income
housing in the vicinity of this project/ developing green belt in the surrounding areas
etc. A cost-profit analysis for the same needs to be done.
R6 - Failure to obtain permanent connections for water and electric power supply by project
completion
Risk in this scenario might not be possible to be avoided hence Risk Retention is the only
possible outcome. However, efforts can be made by implementing the below mitigation plan
to reduce the impact of probable loss:
Risk Mitigation can be done by expediting the project activities and devising a
payment strategy which could reduce external funding and increase the funding from
the customers.
This risk being majorly of External Risk nature it is proposed that the Risk may be mitigated
by implementing a Risk transfer strategy as proposed at R1 above or Risk Retention/
acceptance is the possible option. However, this does not absolve the Builder completely of
the Risk. Cogency of this risk is upto project commencement.
R3 - Failure to achieve local authorities’ timely involvement to shift the existing systems
(Sewer line, HT pylon)
This risk arises at the Construction phase and the same is of moderate probability and
impact. This risk may be regarded as Passive tolerance nature and can be dealt during the
Construction phase.
The probability of this risk is low; however, the occurrence of this could be catastrophic as
the entire project planning could go on disruption. This can be dealt with ensuring the initial
layout or planning is done in line with the RERA and other applicable local guidelines with
the help of experienced Consultants to ensure the approvals are not delayed due to lack of
detail or erroneous planning.