You are on page 1of 6

JINDAL POWER LIMITED

6 X 135 MW ANGUL CAPTIVE POWER PLANT

ACID CLEANING

COLD WATER FLUSHING


DATE TIME ACTIVITY

Boiler water filling started and leakage found at ring header temporary
29/11/2010 14.15 Hrs.
pipe,system was drained for attend leakage.

30/11/2010 All leakage attended and Hot generator pipe line connection given.

Boiler water filling started. And Hydro test of boiler and temporary pipe
08.00Hrs. was done at 09.00 Kg/cm2.

16.30Hrs. Boiler drain completed.


1/12/2010
16.45Hrs. Again boiler filling started.
22.15 Hrs. Filling completed and water recirculation started.
04.00Hrs. Water drained.

HOT WATER FLUSHING

DATE TIME ACTIVITY

12.30Hrs. Water heating started through heat generator.


3/12/2010
Water temperature maintained 45-53 °C.
24.10Hrs. Hot water drained.
4/12/2010
24.30Hrs. Super heater drained.

SUPER HEATER BACK FILLING

DATE TIME ACTIVITY


Super heater back filling started with Hydrazine 200 PPM & Ammonia to
06.40Hrs.
maintain a pH of 10.
(Chemical use 35.00 ltrs.. Hydrazine & 20.00ltrs. Ammonia)
17.30Hrs. Super heater back filling completed.
5/12/2010
18.00Hrs. Boiler Economizer and water wall filling started.
23.00Hrs. Water filling completed. And recirculation started.
23.00Hrs. Heat generator started for water heating.
Page 1/5

JINDAL POWER LIMITED


6 X 135 MW ANGUL CAPTIVE POWER PLANT
ACID CLEANING

ALKALI FLUSHING

DATE TIME ACTIVITY


07.45Hrs. Boiler water temperature reached 38.0°C.
6/12/2010 19.00Hrs. Boiler water temperature reached 45.0°C.
24.00Hrs. Boiler water temperature reached 49.0°C.
4.00Hrs. Boiler water temperature reached 51-52.0°C.
04.15Hrs. TSP,NaOH & Surfactant dosing started
(TSP = 475.0 Kg, NaOH = 100.0 Kg, Teepol = 3.5 ltrs.
7/12/2010
05.30Hrs. Dosing completed & Recirculation started.
13.25Hrs. Draining started.
19.30Hrs. Draining completed.

COLD WATER RINSING

DATE TIME ACTIVITY

17.45Hrs. Boiler filling started.


7/12/2010
24.30Hrs. Filling completed & recirculation started.
01.30Hrs. Recirculation stop & Draining started.
03.15 Hrs. Draining completed.
03.20 Hrs. Again boiler filling started.
07.35 Hrs. Filling completed & recirculation started.
08.35 Hrs. Water draining started.
8/12/2010
(sample checked and found pH = 10.3
12.40 Hrs. Draining completed.
12.50 Hrs. 3rd Time filling started.
20.40 Hrs. Draining started.
20.45 Hrs. Again boiler filling started.
9/12/2010 05.30 Hrs. Filling and draining continue (sample checked :- pH = 8.5)
Page 2/5

JINDAL POWER LIMITED


6 X 135 MW ANGUL CAPTIVE POWER PLANT
ACID CLEANING

ACID CLEANING
DATE TIME ACTIVITY

01.02 Hrs. Boiler Light-up


02.08 Hrs. Boiler water temperature reached 100 °C.
02.10 Hrs. Boiler burner stopped.
10.45 Hrs. HCl Addition in water started at 62-63°C.
HCl Concentration 4.4 % maintained
10/12/2010 (HC L= 20 .00MT , Inhibitor = 360.00 ltrs. & Ammonium Bi-
flouried = 350 Kg.)
12.30 Hrs. Acid dosing completed. And chemical put into recirculation.
16.00 Hrs. Acid draining started through Nitrogen caping to the nutralization pit.
18.30 Hrs. Draining completed.
19.30 Hrs. DM water filling started.
00.35 Hrs. DM water filling completed.
02.00 Hrs. Draining started.
04.05 Hrs. Draining completed through Nitrogen caping.
11/12/2010
04.30 Hrs. DM water again filling satrted.
10.20 Hrs. Filling completed.
( Sample checked:- pH = 6.2, Fe = 8.5 ppm.)

CITRIC ACID RINSING

DATE TIME ACTIVITY

18.43 Hrs. Boiler light-up.


19.30 Hrs. Boiler water temperature 67 ° C.
19.40 Hrs. Boiler burner stopped.
Citric acid and Ammonia dosing started.
11/12/2010
(Citric acid = 350 kg. Ammonia = 50 ltrs.)
Sample checked:- pH = 3.8 , Fe = 22.1 ppm
22.30 Hrs. Boiler draining started with Nitrogen caping.
11/12/2010

23.50 Hrs. Boiler draiuning completed.


00.10 Hrs. DM water filling started.
12/12/2010
04.35 Hrs. DM water filling completed.
Page 3/5

JINDAL POWER LIMITED


6 X 135 MW ANGUL CAPTIVE POWER PLANT
ACID CLEANING

SODA ASH NUTRALISATION

DATE TIME ACTIVITY

05.40 Hrs. Boiler light-up.


06.34 Hrs. Boiler burner stopped. And water temperature 75.0 °C.
06.45 Hrs. Soda ash dosing started.
07.30 Hrs. Dosing completed & recirculation started.
(Soda ash = 450 kg, pH maintain 11.8 & Fe = 11 ppm)
12/12/2010
12.30 Hrs. Recirculation stopped and draining started.
14.55 Hrs. Draining completed.
15.00 Hrs. DM water filling started.
20.00 Hrs. Boiler once through draining started.
20.45 Hrs. Once through draining stopped With pH = 9.8

PASSIVATION

DATE TIME ACTIVITY

22.55 Hrs. Boiler light-up & Chemical dosing started.


12/12/2010
(Hydrazine = 185 ltrs. Ammonia = 105 ltrs.)
00.24 Hrs. Boiler burner stopped at water temperature 90 ° C.
13/12/2010 00.30 Hrs. Boiler re-circulation started.
20.00 Hrs. Recirculation stopped & water drained.
Page 4/5

JINDAL POWER LIMITED


6 X 135 MW ANGUL CAPTIVE POWER PLANT
ACID CLEANING

INSPECTION

Before starting the chemical cleaning five pieces of sample were hanged inside the drum.

After completion of chemical cleaning of bioler - on inspection it was found that drum and tube
were free from scales and smooth coated with a thin blackish layer of Magnetite. All the
chemical cleaning found completed successfully and satisfactorily.

CONCLUSION

After completion of all the processes and joint inspection it was found that the test pieces of
water wall and drum were free from scales and coated with a thin layer of magnetite.

As per the analysis during the Acid Cleaning and Citric Acid rinsing the total Iron removed from
the system is as follows:-

The total Iron removed from the system was 848.742 Kg.(approx)

Test coupon corrosion rate = 13.84 g/m2 hrs.

SIGNATURE

Commissioning Mechanical (Boiler) SEC/TEPC


Page 5/5