Professional Documents
Culture Documents
Everyone hates it, but one logical place to start is with overtime. If people
work more hours, they can get more work done in the same amount of
calendar time. Overtime may be the best option if you're close to the end of
the project and just need a final push to get everything done on schedule. If
you're toward the end of the project, you also may be able to issue comp time
after the project is completed. If you're still early in the project, there are
probably more effective strategies. This option may also have cost
implications if you need to have contract resources work overtime.
Remember that the activities on the critical path are key. You may have
options to assign a more productive resource to those activities, while
reassigning a less productive resource to noncritical path activities. If the
activities off the critical path are delayed, you may still be okay in terms of
meeting your overall project deadline.
In another example, if two people can complete the work in six days, you will
have accelerated the schedule at an incremental cost of two workdays (two
people for six days vs. the original 10-day estimate). In this example, you
could further crash the schedule by applying three resources. Perhaps then
the activity would take four days, or four and a half days. Typically, the more
resources you throw on an activity, the more the incremental cost will be and
the less incremental timesavings you will receive.
The additional resources may come from within the project team or they may
be loaned temporarily from outside the team. One of the goals of crashing the
schedule is to minimize the incremental cost. However, crashing -- in
exchange for completing some work ahead of schedule -- usually leads to
some incremental cost increase to the project. If cost is not as important as
the deadline, crashing a set of activities can result in accelerating the
schedule.
Determining priorities
I've pointed out 10 areas to examine if you're behind schedule. Obviously, one
solution is just to deliver the work at a later date. In some cases, that may be
perfectly acceptable. However, the assumption here is that the scheduled
completion date is important to the client. Some of these techniques don't
require any incremental budget. You should look at them first, if possible.
Other techniques to accelerate the schedule will result in increased cost to the
project. If the deadline date is more important than costs, these techniques
should be applied next.
If the deadline date is extremely important and you can't move the schedule or
the budget, there may be options associated with scaling back the scope of
work. Usually you can complete less work faster. Once you know the cause of
the problem and your budget flexibility, you can determine the best actions to
undertake to get you back on track to hit your deadline.
A construction project is a manufacturing process with many more variables than most
manufacturers face and a delay in any one of those variables can delay a project in
varying degrees. A good quality project begins with a quality design. If the
designers/engineers/architects have limited knowledge of the details of construction
material, methods, actual conditions of the site etc. they will make assumptions. If
those assumptions don't turn out to be accurate, they usually don't become apparent
until the reality of construction brings them out and the craft has to go find something
else to do while the engineers figure out a solution. Experienced contractors can catch
some design errors and bring them to the attention of the A/E before they create a delay
to the project. A&Es need to be sure they are designing in the light rather than making
assumptions because they don't have the budget to actually investigate a site, for
example. If A/Es don't make the time to coordinate between mechanical/electrical/civil
and structural subconsultant designs, clashes will inevitably occur causing delays. A/Es
are also famous for taking more than their allotted time designing the project and,
thereby, delay the construction process.
If contractors or their subcontractors don't have sufficient experience in the scope of
work contemplated in the design, they are going to make mistakes that will require
rework and delay. If they don't order material far enough ahead of time, it will not arrive
on schedule and delay the project. If they order inferior material, it will be rejected and
delay the project. If errors or ommissions in the design are not brought to the designers
attention and answered soon enough they will delay the project.
External forces can also delay a project such as weather, strikes, governmental or
owner interference. Untimely payment for work installed may force the contractor to
reduce his forces thus slowing the progress of the work. Theft or damage from
accidents may cause a delay.
The best way to reduce the risk of delays is to have owner operations and construction
contractor input into the design at the beginning. Make sure the design is well
coordinated and is constructable. Be sure the general and subcontractors are
experienced and financially strong enough to accomplish the work.
It is critical that at least a conceptual CPM schedule be created at the beginning of the
design phase that includes design, procurement, permitting and construction durations
so that when delays occur, it can be determined who caused the delays and what the
impact to the project is projected to be. Once more detail is available, the summary
schedule can be expanded to a more detailed schedule, hopefully containing
reasonable logic and durations provided by those contractually responsible to
accomplish the tasks. A CPM schedule is important because it is probably the best tool
available to alert the project team of a possible threat to timely completion of the work
far enough in advance to reduce or eliminate its impact to the project. Overcoming
delays may be possible by adding more labor, working longer hours, resequencing the
work or making design changes for example. The sooner the flag is raised that a risk
of delay has increased, the wider the window will be to overcome its impact. Having a
responsibility based CPM schedule also makes it possible to assign the liability for the
delay to the party causing it.
As with a design, a CPM schedule has its flaws. It is only as good as the
reasonableness of the assumptions that go into its creation plus the diligence and
integrity with which it is updated and maintained. I have been involved with millions of
dollars of disputes and invariably a CPM schedule has been the measuring stick to
show which parties were responsible for the project impacts and what degree that
impact had, often leading to how much the delaying party must pay the damaged party
for the action or inaction that caused the impact.
A good CPM is an early warning system about a projects' likely success. If you don't
manage it well, however, it will become the stick that the damaged party will use to beat
you.