Project : S S GAS LAB ASIA PVT LTD. - AE1BP3X160 / HIVER Aircon Pvt Ltd
Date: 25/04/20
- HX - CHILLER UNITS // QAP V 1.0
Activity (Visual & Type of Acceptance Inspection
Sr. No. Characteristic Rejection criteria
dimensional inspection) Inspection criteria Hiver Client
Evaporator Model Shell If does not match
As per drawing &
1 and Tube type Dimensions as per drawing 100% visual with drawing &
test certificate
(U Stamped) physical damage
If does not match
Condenser Model Dx Coil As per drawing &
2 Dimensions as per drawing 100% visual with drawing &
type test certificate
physical damage
Compressor Model Screw If does not match
As per drawing &
3 type Dimensions as per drawing 100% visual with drawing &
test certificate
(Make :Bitzer ) physical damage
If does not match
Condenser Fan Model As per drawing &
4 Dimensions as per drawing 100% visual with drawing &
Axial type test certificate
physical damage
If does not match
Electrical Junction Box
5 Dimensions as per drawing 100% visual As per drawing with drawing &
duly wired
physical damage
Voltage, Ampere, Coil, If does not match
100% visual As per Manual N/A
frequency with manual
6 Contactor Model Coil continuity, holding
contact & Auxiliary contact 100% visual Continuity Open N/A
continuity
Page 1 of 4
Rated current, Breaking If does not match
7 MCCB Model 100% visual Manual N/A
Capacity with manual
Current range, Frequency,
100% visual Manual If does not match N/A
8 Overload relay Model Voltage
with manual
Continuity of 3 phase 100% visual Continuity Open N/A
Input 3Phase 415V and
Single phase Preventer
9 remove one phase, signal 100% visual signal No signal N/A
Model
should blink under voltage
Supply live current from
current transformer and
10 Current Transformer 100% visual mV No signal N/A
output from s1 and s2 should
give mV
live supply of 3 phase input ,
11 Energy meter 100% visual Show readings N/A
check CT ratio setting No readings
Coil continuity, holding
12 PLA relay 100% visual Continuity N/A
contact Open
13 MCB KA, Volts, Amps, frequency 100% visual Manual If does not match N/A
with manual
14 Continuity of meter 100% visual Continuity Open N/A
Input 230V and Output No output / higher
15 SMPS 100% visual Output 24VDC N/A
24VDC output
proper ports as per
Pco5+ Controller and
16 Ports & physical 100% visual maual & no Damage and less N/A
accessories
damage ports
Manual &Test If does not match
17 H.M.I Physical damage 100% visual N/A
certificate with manual
Discharge pressure
18 Continuity 100% visual Continuity N/A
transducer Open
Suction pressure
19 Continuity 100% visual Continuity N/A
transducer Open
20 Pressure transducer cable Continuity and no. of cores 100% visual Continuity Open N/A
Page 2 of 4
Suction Refrigerant temp Give temperature and output No output / higher
21 100% visual mV N/A
sensor mV output
Discharge Refrigerant Give temperature and output No output / higher
22 100% visual mV N/A
temp sensor mV output
Give temperature and output No output / higher
23 Water temp sensor 100% visual mV N/A
mV output
Physical damage & If does not match
24 Filter shell 100% visual Manual
connections with manual
Physical damage & If does not match
25 Filter core 100% visual Manual
connections with manual
If does not match the
26 Copper pipes Dimensions as per drawing 100% visual Drawings dimensions of
drawings
27 Water flow switch Continuity of NC 100% visual Continuity Open N/A
if does not match the
28 Thermowell Dimensions as per drawing 100% visual Drawing dimensions of
drawings
If does not match
29 Pressure relief valve Dimensions as per drawing 100% visual Manual N/A
with manual
30 Angle valve physical damage 100% visual Connection size Size does not match
If does not match
31 Expansion valve Dimensions 100% visual Manual
with manual
If does not match the
32 Sheet metal Dimensions as per drawing 100% visual Drawings dimensions of
drawings
Page 3 of 4
If does not match the
3) Total frame dimension As per
Dimension dimensions of
after welding drawing
drawings
No crack and no
4) Weld inspection 100% visual
burrs Cracks and burrs
Painting 7 Tank Processing and final
34 DFT meter 70 ± 2 DFT
RAL7035 Epoxy coating Less then 68 DFT