You are on page 1of 1

KD5 :Final Feasibility Consultancy Services for Preparation of Feasibility Report for Construction of Bridges including

Report including Schedules Approaches on Tamu – Kyigone – Kalewa Road Section from km 0.00 to km 149.70 in Myanmar

8.6 CROSS DRAINAGE STRUCTURES


The construction of bridges and culverts are assessed on proposed length and the earthwork,
pavement and shoulders for bridge approaches have been included as appropriate roadwork items.
The other items like RCC and PCC work of bridges and culverts are calculated as per design and
drawings.
8.7 DRAINAGE AND PROTECTIVE WORKS
Drainage and protective works provides for the roadside drains in the plain, rolling and hilly
terrain, drainage chutes and crash barriers for the embankments more than 3.0 m high and
retaining and breast walls where necessary.
8.8 ROAD FURNITURE AND SAFETY WORKS
Provisions for road safety measures road signs, markings, road appurtenant have been made.

The cost estimate for works item are presented in Table 8.1.

Table 8.1: Project Cost Estimate


Bill
Description of Item Amount
No.
1 Site Clearance 33704059
2 Earth Work 99741706
3 Sub-Base And Base Courses 338453038
4 Bituminous Works 249567085
5 Culverts 36677715
6 Road Markings & Sign Boards 26893765
7 Drainage And Protection Works 345384839
8 Bridges 1530507777
9 Miscellaneous 141124915
Sub Total 2802054898

MEA 8-2

You might also like