Professional Documents
Culture Documents
CAPITAL BUDGETING
CAPITAL BUDGETING
Capital budgeting is the process used to take investment decision. It is a process of planning whether an
organization’s long term investments such as new machinery, replacement machinery, new plants, new
products, and research development projects are worth the funding of cash through the firm’s
capitalization structure (debt, equity or retained earnings). It is the process of allocating resources for
major capital, or investment, expenditures. One of the primary goals of capital budgeting investments is
to increase the value of the firm to the shareholders. A collection of capital budgeting techniques
allowing the manager to choose among a variety of investment projects.
METHODS:
1. Payback
2. Discounted payback
3. Internal Rate of Return
4. Net Present Value
5. Profitability Index
PAYBACK PERIOD (PBP) is the time it takes to recover the initial cost of the investment. Payback is
usually measured in years.
Decision rule: Take the project with the shortest payback period.
Disadvantages:
• It ignores time value of money.
• It ignores risk
• It ignores cash inflows beyond the cutoff point.
42
PBP = 3+ (40.67/100) = 3.41 Years
Ranking:
1. Project B: 2.49 years
2. Project C: 3.41 years
3. Project A: 3.83 years
All three projects are viable, but project B is the first to recover its initial cost.
DISCOUNTED PAYBACK PERIOD (DPBP) is the time it takes to recover the initial cost of the
investment. Payback uses nominal CF; DPBP uses discounted CF.
Decision rule: Take the project with the shortest discounted payback period.
The calculation of discounted payback is exactly the same as that of payback, except that instead of using
nominal cash flow, we use present values.
INTERNAL RATE OF RETURN (IRR) is the discount rate that makes the present value of the project
equal to its initial cost.
Decision rule: Take the project if the IRR exceeds the required rate of return.
Disadvantages:
• Reinvestment rate assumption is unrealistic
43
• Multiple IRR
• IRR cannot rank mutually exclusive projects
IRR Calculation:
Project A:
Set: Initial cost (A) = PV (project A):
$5,045 = $400/(1+IRR) + $1,250/(1+IRR)2 + $900/(+IRR)3 + $3,000/(1+IRR)4 + $1,000/(1+IRR)5
IRR(A) = 8%
Since IRR (A) > 7.7%, accept project (A)
Project B:
$490.67 = $100/(1+IRR) + $400/(1+IRR)2 + $150/(1+IRR)3 + $100/(1+IRR)4 + $50/(1+IRR)5
IRR (B) = 8%
Since IRR (B) > 3%, accept project B
Project C:
$9,687.23 = $5,200/(1+IRR) + $4,000/(1+IRR)2 + $1,000/(1+IRR)3 + $200/(1+IRR)4 + $100/(1+IRR)5
IRR(C) = 5%.
Since IRR(C) < 6%, reject project C
NET PRESENT VALUE (NPV) is the difference between the present value of a project and its initial cost.
Disadvantages: Very complex analysis, too many variables to forecast, as it will be seen later.
NPV Calculation:
In order to calculate NPV, we must first estimate the PV of total cash flows; then we subtract the initial
cost of the project.
Project A:
PV (A) =$400/(1.077) + $1,250/(1.077)2 + $900/(1.077)3 + $3,000/(1.077)4 + $1,000/(1.077)5
Initial cost (A) = $5,045
NPV (A) = $44.36
Project B:
PV (B) =$100/(1.03) + $400/(1.03)2 + $150/(1.03)3 + $100/(1.03)4 + $50/(1.03)5
Initial cost (B) = $490.67
NPV (B) = $64.2
Project C:
PV(C) =$5,200/(1.06) + $4,000/(1.06)2 + $1,000/(1.06)3 + $200/(1.06)4 + $100/(1.06)5
Initial cost (C) = $9,687.23
NPV (C) = -$148.81
44
NPV (B) = $100/(1.08) + $400/(1.08)2 + $150/(1.08)3 + $100/(1.08)4 + $50/(1.08)5 - $490.67
NPV (B) = 0
When the discount rate equals 5%:
NPV(C) = $5,200/ (1.05) + $4,000/(1.05)2 + $1,000/(1.05)3 + $200/(1.05)4 + $100/(1.05)5 - $9,687.23
NPV(C) = 0
PI = PV/Initial cost
PI Calculation:
Project A:
PI (A) = PV (A)/Initial cost = 5,089.36/$5,045
PI (A) = $400/ (1.077) + $1,250/ (1.077)2 + $900/(1.077)3 + $3,000/(1.077)4 + 1,000/(1.077)5/$5,045
PI (A) = 1.0088
Project B:
PI (B) = $100/ (1.03) + $400/(1.03)2 + $150/(1.03)3 + $100/(1.03)4 + $50/(1.03)5 /$490.67
PI (B) = 1.131
Project C:
PI(C) = $5,200/(1.06) + $4,000/(1.06)2 + $1,000/(1.06)3 + $200/(1.06)4 + $100/(1.06)5 /$9,687.23
PI(C) = 0.9846
In project valuation, measures of absolute wealth are more appropriate than measures of relative
efficiency.
Mutually exclusive projects are projects in which acceptance of one project excludes the others from
consideration. In such a scenario the best project is accepted. NPV and IRR conflict, which can sometimes
arise in case of mutually exclusive projects, becomes critical. The conflict either arises due to the relative
size of the project or due to the different cash flow distribution of the projects.
45
Since NPV is an absolute measure, it will rank a project adding more dollar value higher regardless of
the original investment required. IRR is a relative measure, and it will rank projects offering best
investment return higher regardless of the total value added.
Example:
Project A requires $10 million investments and generates $10 million each in year 1 and year 2. It has
NPV of $7.4 million @ 10% discount rate and IRR of 61.8%. Project B requires $1 million investment and
generates $2 million in Year 1 and $1 million in Year 2. Its NPV @ 10% and IRR turn out to be $1.6 million
and 141.4%. Based on NPV one would conclude that Project A is better, but IRR offers a contradictory
view. This conflict arose mainly due to the size of the project.
Whenever there is a conflict in ranking of projects based on NPV and IRR, it is safer to always prefer the
NPV ranking. This is due to the realistic assumption and theoretical soundness of the method.
However, IRR is a great complement to NPV. It helps see a more complete picture.
ILLUSTRATIONS
Question – 1:
The following cash flows are for two different investments. Given that the discount rate for both the
projects are 12.5%. Calculate the a) Payback and b) Discounted payback for both the cash flows.
Project A Project B
PBP =3+(51.87/62.43) PBP = 4+ (46.74/166.48)
= 3.83 yrs = 4.28 yrs
Question – 2:
Ms Granger has been offered to invest $ 100,000 in a new project that her friend has undertaken. The
friend has offered that as a return to her investment today, she will receive $ 27,500 each year for the next
5 years. If Ms Granger’s required rate of return is 18%, should she invest in the project? (Find NPV)
Solution – 2:
NPV = - 100,000 + 27500/1.18 +27500/1.18^2 +27500/1.18^3 + 27500/1.18^4 + 27500/1.18^5
46
= - 100,000 +23,305 +19750 +16737+14184 +12021
= - 100,000+ 85997
= - 14,003
She should not invest as NPV is negative. [Annuity can also be used as all the cash flows are same]
Question – 3:
Bingley Company is considering acquiring a certain machine costing $22,000 which will save $ 8500 in
cash every year up to its 4 year life. The machine will have no value at the end of 4 years. Should the
company buy the machine if the cost of capital is 16%?
Solution – 3:
NPV = - 52,000 + 8500/1.16 +8500/1.16^2 +8500/1.16^3 + 8500/1.16^4
= - 52,000 +7328 + 6317+5446 +4694
= - 22,000+ 23,785
= 1785
Question – 4:
Your boss has asked you to evaluate a project with the following cash flows. He wants to know the rate
of return (IRR) the company can earn from investing in this project. The hurdle rate for the company is
10%. Should the investment be made?
Solution – 4:
0 1 2 3 4
Interpolation:
.10 110945
IRR 100000
.20 90607
47
110945 – 90607 = 20338
IRR - 0.10 = 10945
x/0.10 = 10945/20338
x = 0.0538 + 0.10
= 0.1538
IRR = 15.38%
Question – 5:
Your boss has asked you to evaluate a project with the following cash flows. He wants to know the rate
of return (IRR) the company can earn from investing in this project. The hurdle rate for the company is
10%. Should the investment be made?
Solution – 5:
0 1 2 3
Interpolation:
.10 106935
IRR 100000
.15 98179
48
ON CAMPUS TASK
Ronald wants to buy a new showroom which he wants to use for a commercial purpose. He wants to
rent out the showroom. He has two options. He can buy Showroom A requiring an investment of $1600
and will generate $ 400 each starting from the third year. This is because showroom A is still under
construction and will not be ready to rent out before year 3. If he buys Showroom B it can be rented out
from year 1. However, if he buys showroom A , he can rent it till the 6th year and will sell it in the 7 th
year for $400. On the other hand, he can rent showroom B for 4 years and then sell it on the 5 th year for
$50.
a) Determine the cash flows for each project and show it in a table.
Periods Cash flow A ($) Cash flow B ($)
0
1
2
3
4
5
6
7
b) PBP
Period Cash flow A Left to recover Cash flow B Left to recover
0
1
2
3
4
5
6
PBP
d) NPV ___________________________________________________________________________________
e) IRR _____________________________________________________________________________________
f) PI _____________________________________________________________________________________
g) If the projects are mutually exclusive, which one should Ronald invest in?
_________________________________________________________________________________________
_______________________________________________________________________________________
49
EXERCISES
1. Calculate the NPV for the following projects with a discount rate of 12%:
Project 1 costs $100,000 and earns $50,000 each year for three years.
Project 2 costs $200,000 and earns $150,000 in the first year, and then $75,000 for each of the next
two years.
Project 3 costs $25,000 and earns $20,000 each year for three years.
a) 0 1 2 3 4 5 6 7 8
− $86,890 $106,474 $91,612 $84,801 $84,801 $75,400 $66,000 $92,400
$404,424
What is the project’s net present value if the required rate of return is 14 percent?
b) Is the project acceptable?
50