RESOURCE (MAN) MANHOURS RESOURCE (EQPT)

AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR

Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
1 IWR/BT3/2019/057 6''-PL-294053-1101A-NI PIPE REPLACEMENT & PAINTING
1 1-Pre Execution Material delivery INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Material inspection by AIMD Inspector INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Spool fabrication, NDT Inspection by AIMD at workshop HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Perform HT and Withness by AIMD Inspector INSP 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Perform blasting and painting on new spool HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Painting inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 1-Pre Execution Erect external scaffolding HRSB 0 0 0 0 0 0 0 0 0 0 0 0
8 1-Pre Execution Remove insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0

2-Execution 1.0 Piping replacement HRSB 0 0 0 0 0 0 0 0 0 0 0 0


9 2-Execution Blinding as per EIS (above to 12" Nom Bore) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Blinding as per EIS (above to 4" Nom Bore) HRSB 2 4.2 2 1 12.6 0 8.4 0 4.2 0 0 0 0 0 0 12.6
11 2-Execution Blinding as per EIS (up to 4" Nom Bore) HRSB 2 2.3 1 1 4.6 0 2.3 0 2.3 0 0 0 0 0 0 4.6
12 2-Execution Setup preparation and marking the cutting point HRSB 0.5 1 1 1 0 0 0.5 0.5 0 0 0 0 0 0 1
13 2-Execution Drill Pilot Hole for gas test by Operation HRSB 0.5 1 1 1 0 0 0.5 0 0 0 0.5 0 0 0 1
14 2-Execution Open flange at TP-08 & TP-01 HRSB 1 1.2 1 1 2.4 0 1.2 0 1.2 0 0 0 0 0 0 2.4
15 2-Execution Cutting, bevel and remove defect flange/pipe 2'' sch40 HRSB 1 0.9 1 1 1 2.7 0 0 0.9 0.9 0 0 0.9 0 0 0 2.7
16 2-Execution Lift down existing pipe (manual lifting) HRSB 1 0.5 1 1 1 1.5 0 0.5 0 0.5 0.5 0 0 0 0 0 1.5
17 2-Execution DPT on existing pipe HRSB 1 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
18 2-Execution Perform visual inspection HRSB 1 0.5 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up new pipe (manual lifting) HRSB 1 0.5 1 1 1 1.5 0 0.5 0 0.5 0.5 0 0 0 0 0 1.5
20 2-Execution Fit-up weld the new fitting 2'' sch40 (BW) - TP 06 HRSB 1 0.5 1 1 1 1 2 0 0 0.5 0.5 0 0 0.5 0.5 0 0 2
21 2-Execution Fit-up inspection HRSB 1 0.5 0 0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Perform full weld as per PPTSB requirement HRSB 1 0.9 1 1 1 2.7 0 0 0 0.9 0 0 0.9 0.9 0 0 2.7
23 2-Execution Perform DPT inspection HRSB 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
24 2-Execution Visual inspection by PPTSB rep HRSB 0.5 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Perform RT 1 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Cutting, bevel and remove defect pipe 3/4'' sch xxs 1 0.4 1 1 1 1.2 0 0 0.4 0.4 0 0 0.4 0 0 0 1.2
27 2-Execution Lift down existing pipe (manual lifting) 0.5 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution DPT on existing pipe 1 0.5 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Perform visual inspection 1 0.5 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Lift up new pipe (manual lifting 0.5 0 0 0 0 0 0 0 0 0 0 0 0
3/4'' sch xxs (SW) - TP 05
31 2-Execution Fit-up weld the new fitting 1 0.2 1 1 1 1 0.8 0 0 0.2 0.2 0 0 0.2 0.2 0 0 0.8
32 2-Execution Fit-up inspection 1 0.5 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Perform full weld as per PPTSB requirement 1 0.36 1 1 1 1.08 0 0 0 0.36 0 0 0.36 0.36 0 0 1.08
34 2-Execution Perform DPT inspection 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
35 2-Execution Visual inspection by PPTSB rep 0.5 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Hydrotest - Water filling 1 1 1 0 0 0 1 0 0 0 0 0 0 1
37 2-Execution Hydrotest - Set up & testing as per procedure HRSB 4 2 1 12 0 8 0 4 0 0 0 0 0 0 12
38 2-Execution Final inspection for HT 0.5 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Drain water 1 1 1 0 0 0 1 0 0 0 0 0 0 1
40 2-Execution Remove Fitting HT 0.5 2 1 1.5 0 1 0 0.5 0 0 0 0 0 0 1.5
41 2-Execution Surface preparation, power tool and clean the surface. HRSB 0.02 0.04 1 1 1 0.12 0 0.04 0 0.04 0 0 0.04 0 0 0 0.12
42 2-Execution Surface preparation inspection HRSB 0.02 1 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Apply 1st coat (touch up) HRSB 0.02 0.03 1 1 0.06 0 0 0 0.03 0 0 0 0 0.03 0 0.06
44 2-Execution Curing HRSB 0.02 8 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution 1st coat inspection HRSB 0.02 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution Apply 2nd coat (touch up) HRSB 0.02 0.02 1 1 0.04 0 0 0 0.02 0 0 0 0 0.02 0 0.04
47 2-Execution Curing HRSB 0.02 4 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution 2nd coat inspection HRSB 0.02 1 0 0 0 0 0 0 0 0 0 0 0 0
49 2-Execution Apply final coat (touch up) HRSB 0.02 0.02 1 1 0.04 0 0 0 0.02 0 0 0 0 0.02 0 0.04
50 2-Execution Curing HRSB 0.02 4 0 0 0 0 0 0 0 0 0 0 0 0
51 2-Execution Final inspection HRSB 0.02 1 0 0 0 0 0 0 0 0 0 0 0 0
52 2-Execution Box up flange TP-08 & TP-01 HRSB 1 1.3 1 1 2.6 0 1.3 0 1.3 0 0 0 0 0 0 2.6
53 2-Execution Deblinding as per EIS (above to 12" Nom Bore) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
54 2-Execution Deblinding as per EIS (above to 4" Nom Bore) HRSB 2 4.6 2 1 13.8 0 9.2 0 4.6 0 0 0 0 0 0 13.8
55 2-Execution Deblinding as per EIS (up to 4" Nom Bore) HRSB 2 2.6 1 1 5.2 0 2.6 0 2.6 0 0 0 0 0 0 5.2
56 2-Execution Housekeeping HRSB 1 1 1 0 0 0 1 0 0 0 0 0 0 1

2-Execution 2.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0


57 2-Execution Site preparation HRSB 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
58 2-Execution Surface preparation (Power tool) HRSB 21.44 42.88 1 1 1 128.64 0 42.88 0 42.88 0 0 42.88 0 0 0 128.64
59 2-Execution Inspection surface preparation by AIMD HRSB 21.44 1 0 0 0 0 0 0 0 0 0 0 0 0
60 2-Execution Painting 1st coat HRSB 21.44 32.16 1 1 64.32 0 0 0 32.16 0 0 0 0 32.16 0 64.32
61 2-Execution Overcoating interval HRSB 21.44 8 0 0 0 0 0 0 0 0 0 0 0 0
62 2-Execution 1st coat inspection by AIMD HRSB 21.44 1 0 0 0 0 0 0 0 0 0 0 0 0
63 2-Execution Painting 2nd coat HRSB 21.44 21.44 1 1 42.88 0 0 0 21.44 0 0 0 0 21.44 0 42.88
64 2-Execution Overcoating interval HRSB 21.44 4 0 0 0 0 0 0 0 0 0 0 0 0
65 2-Execution 2nd coat inspection by AIMD HRSB 21.44 1 0 0 0 0 0 0 0 0 0 0 0 0
66 2-Execution Painting final coat HRSB 21.44 21.44 1 1 42.88 0 0 0 21.44 0 0 0 0 21.44 0 42.88
67 2-Execution Overcoating interval HRSB 21.44 4 0 0 0 0 0 0 0 0 0 0 0 0
68 2-Execution Final coat inspection by AIMD HRSB 21.44 1 0 0 0 0 0 0 0 0 0 0 0 0

69 2-Execution 3.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0


70 2-Execution 10 3.3 1 1
Lift up pipe & support pipe using wooden block (1st side ) HRSB 6.6 0 3.3 0 3.3 0 0 0 0 0 0 6.6
71 2-Execution Surface preparation (Power tool) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
72 2-Execution Inspection surface preparation by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
73 2-Execution Painting 1st coat HRSB 0 0 0 0 0 0 0 0 0 0 0 0
74 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
75 2-Execution 1st coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
76 2-Execution Painting 2nd coat HRSB 0 0 0 0 0 0 0 0 0 0 0 0
77 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
78 2-Execution 2nd coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
79 2-Execution Painting final coat HRSB 0 0 0 0 0 0 0 0 0 0 0 0
80 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
81 2-Execution Final coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
82 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) HRSB 10 3.3 1 1 6.6 0 3.3 0 3.3 0 0 0 0 0 0 6.6
83 2-Execution Surface preparation (Power tool) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
84 2-Execution Inspection surface preparation by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
85 2-Execution Painting 1st coat INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
86 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
87 2-Execution 1st coat inspection by AIMD INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
88 2-Execution Painting 2nd coat INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
89 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
90 2-Execution 2nd coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
91 2-Execution Painting final coat INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
92 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
93 2-Execution Final coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
94 2-Execution Lift up pipe,remove wooden block & lift down pipe INSP HRSB 10 3.3 1 1 6.6 0 3.3 0 3.3 0 0 0 0 0 0 6.6
95 2-Execution Housekeeping HRSB 1 1 1 0 0 0 1 0 0 0 0 0 0 1

96 3-Post Execution Re instate Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0


97 3-Post Execution Dismantle External Scaffolding HRSB 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
206.39 376.5 0 88.82 3 158.39 2.5 0 46.68 1.96 75.11 0 376.46

Open
REMAKS

Open
REMAKS

Open
REMAKS

Open
EIS (above to 12" Nom Bore) DURATION HRS
BLIND NO SIZE RATING BLINDING DE.BLIND FIL HLP
0.00 0.00 2 1
0.00 0.00 2 1
TOTAL 0.0 0.0

EIS (above to 4" Nom Bore) DURATION HRS


BLIND NO SIZE RATING BLINDING DE.BLIND FIT HLP
1 6 150 1.40 1.54 2 1
2 6 150 1.40 1.54 2 1
6 150 1.40 1.54 2 1
0.00 0.00 2 1
TOTAL 4.2 4.6

EIS (up to 4" Nom Bore) DURATION HRS


BLIND NO SIZE RATING BLINDING DE.BLIND FIT HLP
3 2 150 0.63 0.70 1 1
4 3/4 150 0.57 0.62 1 1
3/4 150 0.57 0.62 1 1
3/4 150 0.57 0.62 1 1
0.00 0.00 1 1
TOTAL 2.3 2.6

DURATION HRS
qty
piping
cutting/
weld type SIZE sch fit up weld
bevel
BW 2 40 0.9 0.50 0.9 1
SW 3/4 xxs 0.4 0.20 0.6 1

TOTAL 1.30

life up pipe support DURATION HRS


step qty pipe support lift duration FIT S.S
1st side 10 0.33 3.33 1 1
2nd site 10 0.33 3.33 1 1
lift down 10 0.33 3.33 1 1
TOTAL 1.00 10.00

welding DURATION HRS


QTY SIZE RATING REMOVE INSTALL FIT HLP
1 0.00 0.00 2 1
0.00 0.00 2 1
TOTAL 0.00 0.00

painting DURATION HRS Minimum Resources

duration
QTY xtvt vol.m2 TOTAL SS FW
(hrs)
DURATION
Site pre 1 1
Surface prep 21.44 2 42.88 1 1
SP Insp. 21.44 1 21.44
1st coat 21.44 1.5 32.16 1
curing 21.44 8 171.52
1st coat Insp 21.44 1 21.44
2nd coat 21.44 1 21.44 1
curing 21.44 4 85.76
2nd coat Insp 21.44 1 21.44
Final coat 21.44 1 21.44 1
curing 21.44 4 85.76
Final coat Insp 21.44 1 21.44
TOTAL 0.00 0.00

NOZZLE UNLOAD DURATION HRS


QTY SIZE RATING REMOVE INSTALL FIT HLP
0.00 0.00 1 1
0.00 0.00 1 1
0.00 0.00 1 1
0.00 0.00 1 1
TOTAL 0.00 0.00

CLEANING FORMULA
ID H π D
SHELL 4.88 28.4 3.142 4.88
SHELL 3 20.315 4.142 3
ELLIP TOP 3 1 1.084 3
ELLIP BOTTOM 4.88 1 1.084 4.88

D
ELLIP SHELL bottom 4.942 1 1.084
1.084 0
CLEANING LGHT ID π TOTAL QTY PLATE
PERIMETER

WELDMENT SHELL 28.4 4.942 3.142 15.53 6.47


WELDMENT SHELL 20.315 3 4.142 12.43 5.18
WELDMENT ELLIP top 1 3 3.142 9.43 3.93
WELDMENT ELLIP bottom 1 4.942 3.142 15.53 6.47
3.142 0.00 0.00

CLEANING FORMULA
ID H π D
TRAY 4.942 3.142 4.942
TRAY 3 3.142 3

D
1.084 0
1.084 0

NDT
NO TYPE QTY DURATION TOTAL DUR
1 BORO 0.083 0.0
2 IRIS 0.367 0.0
3 RFET 0.083 0.0
TOTAL (HR) 0.53 0.0

INT.SCAFFOLDING DURATION
L W H M3 ERECT DISMANTLE
5 5 4 100 25 25 bottom
5 5 2.5 63 16 16 tray 35#
0 0 0
TOTAL 163 41 41

unloading & loading FORMULA


ID H π D
unloading 3.142 0
loading 3.142 0
remove tray
tray no bolt nut qty tray total bolt nut
MH 1A - Tray #64,63 and 61 322 24 966
MH 1B - Tray #58,57,55,54,52,51 and 49 322 56 2254
MH 1C - Tray #46,45,43,42,40,38 and 37 322 56 2254
MH 1D - Tray #33,32,30,29,27 and 26 322 96 1932
MH 1E - Tray #23,22,20,19,17,16 and 14 322 112 2254
MH 1F - Tray #11,10,8,7,5,4 and 2. 322 112 2254
total 1932 456 11914
RIG
1
1

RIG
Spec
Spec
spec -point for HT

open flange (up to 4" Nom Bore) DURATION HRS


RIG TP No SIZE RATING BLINDING
Spade TP-08 2 150 0.63
Spec TP-01 3/4 150 0.57
Spade-point for HT
Spade-point for HT
0.00
TOTAL 1.2

HRS FOR
WELD
ONLY

0.9
0.36 FCTOR 0.6

RIG

RIG
1
1

TOUCH UP

Fitter Painter Ins xtvt

1 Site pre
1 Surface prep
1 SP Insp.
1 1st coat
curing
1 1st coat Insp
1 2nd coat
curing
1 2nd coat Insp
1 Final coat
curing
1 Final coat Insp

RIG

ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
28.4 435.46 217.73 145.15 72.58
20.32 252.43 126.22 84.14 42.07
1 3.25 1.63 1.08 0.54
1 5.29 2.64 1.76 0.88

D
0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 696.43 348.22 232.14 73.46

DURATION
TOTAL
WELMENT QTY PLATE TOTAL
TOP ELLIP VESSEL WELDMENT POWER BRUSH
& LENGTH
BOTTOM
ELLIP
15.53 23.67 582.29 97.0
12.43 16.93 340.39 56.7
9.43 0.83 61.27 10.2
15.53 0.83 100.93 16.8
0.00 0.00 0.00 0.0
TOTAL 271.22 45.2 25% TOTAL WELDMENT

ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
0 124.22 62.11 41.41 20.70
0 61.27 30.63 20.42 10.21

D
0 0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 185.49 92.75 61.83 30.92

ORMULA QTY DURATION


M3
H DRUM manual crane
0 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
remove install
80.5 80.5
187.83 187.83
187.83 187.83
161.00 161.00
187.83 187.83
187.83 187.83
992.83333 992.83333
DURATION HRS
DE.BLIND FIT HLP
0.70 1 1
0.62 1 1

0.00 1 1
1.3
DURATION HRS
Total
duration
vol.m2 duration
(hrs)
(hrs)
1 1
0.02 2 0.04
0.02 1 0.02
0.02 1.5 0.03
0.02 8 0.16
0.02 1 0.02
0.02 1 0.02
0.02 4 0.08
0.02 1 0.02
0.02 1 0.02
0.02 4 0.08
0.02 1 0.02
TOTAL 0.11

flushing
TOTAL WELDMENT

FIT HLP RIG

4 4 1
2 2 1
PCOGD SDN BHD TURNAROUND 2019

SUMMARY DEFECT AREA BUTANOL

NO WORK ID LINE NO JOINT SIZE SCH WELD TYPE FW/SW F/U V/I DPI RT RT 1 HT PAINTING REMARKS

6''-PL-294053-1101A-NI
1 6''-PL-294053-1101A-NI 1 2 40 BW FW
6''-PL-294053-1101A-NI 2 0.75 120 BW SW 3/4 @ 0.75
6''-PL-294053-1101A-NI 3 0.75 120 SW SW 3/4 @ 0.75
6''-PL-294053-1101A-NI 4 0.75 120 SW FW 3/4 @ 0.75

Joint Dia inch PAINTING


Fit-up Joint Dia inch Fit-up DPI Done RT Done Ht Done
Welded Weld Done
0 0 0 0 0 0 0 0
WORK REQUERST
TOTAL
SHOP FIELD SHOP FIELD JOINT TOTAL DIA
(Overall) INCH (Overall)
SW BW SW BW TH TH
JOINT 1 1 1 1 0 0 4
DIA INCH 0.75 0.75 0.75 2 0 0 4.25
TOTAL JT 2 TOTAL JT 2
TOTAL Ø INCH 1.5 TOTAL Ø 2.75 RT (total) RT (SHOP) RT (FIELD)
INCH
JOINT SW TOTAL JOINT SHOP/FIELD 4 2 1 1
AND BW DIA INCH JOINT SHOP/FIELD 4.25

Socket Weld Butt weld


Fit-up RT
Qty Dia Inch Qty Dia Inch
Current 0 0 0 0 0 0
Progress workshop Total 2 1 0.75 1 0.75 29
Current 0 0 0 0 0 0
Progress Site Total 2 1 0.75 1 2 17
1.0 Table for piping painting
system 1c
PIPE SIZE od (mm) radius (m) circumference(m)lght (M) qty m2 1st coat(L)
1/2 21.3 0.01065 0.07 0.00 0.00
3/4 26.7 0.01335 0.08 0.05 1 0.01 0.00
1 33.4 0.0167 0.10 0.00 0.00
1.5 48.3 0.02415 0.15 0.00 0.00
2 60.3 0.03015 0.19 0.05 1 0.01 0.00
2.5 73 0.0365 0.23 0.00 0.00
3 88.9 0.04445 0.28 0.00 0.00
4 114.3 0.05715 0.36 0.00 0.00
5 141.3 0.07065 0.44 0.00 0.00
6 168.3 0.08415 0.53 0.00 0.00
8 219.1 0.10955 0.69 0.00 0.00
10 273.1 0.13655 0.86 0.00 0.00
12 323.9 0.16195 1.02 0.00 0.00
14 343 0.1715 1.08 0.00 0.00
16 392 0.196 1.23 0.00 0.00
18 441 0.2205 1.39 0.00 0.00
20 490 0.245 1.54 0.00 0.00
22 539 0.2695 1.69 0.00 0.00
24 588 0.294 1.85 0.00 0.00
26 637 0.3185 2.00 0.00 0.00
28 686 0.343 2.16 0.00 0.00
30 735 0.3675 2.31 0.00 0.00
32 784 0.392 2.46 0.00 0.00
34 833 0.4165 2.62 0.00 0.00
36 882 0.441 2.77 0.00 0.00
system 1c UNIT RATE (RM) REVENUE MPWR
2nd coat(L) 3rd coat(L) 1st coat(L) 2nd coat(L) 3rd coat(L)
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
0.00 0.00 RM0.00
MATERIAL CONSUM TOTAL COST SITE MARGIN

#DIV/0!
MTO

Sch/
Item Qty Unit Size Description Rate (RM)
Rating
1 PIPE
2 0.2 m 3/4'' S/XXS API5LGr.B, SMLS, PE
3
4
5 Flange
6 1 ea 3/4'' 150# WN-RF : A105, S/XXS
7 1 ea 2'' 150# WN-RF : A105, S/40
8
9
10 Gasket
11 1 ea 3/4'' 150# S.P.W 4.5mm thk
12 1 ea 2'' 150# S.P.W 4.5mm thk
13
14
15 Bolt & Nut : ASTM A193GR-B7/ A194GR-2H
16 1 ea 3/4'' 1/2''Ø X 65mm LG
17 1 ea 2'' 1/2''Ø X 70mm LG
18
19
20 Valve
21 1 ea 3/4'' 800# GATE : A105 / 13CR, BB.OS&Y, SW
Total (RM)